MONTHYEARML20211H4441999-08-27027 August 1999 Notification of Significant Meeting with Util on 990916 & 17 in Arlington,Tx to Improve Utility & NRC Understanding of Industry & Regulatory Perspectives on Current Issues ML20211E1491999-08-23023 August 1999 Notification of Licensee Meeting with Util on 990830 to Discuss Recent Refueling Maint Outage ML20209G2421999-07-14014 July 1999 Notification of 990722 Meeting with License in Rockville, MD to Discuss Changes in EOI Licensing Organization Including Division of Responsibilities within New EOI Corporate Licensing Group ML20209F6111999-07-12012 July 1999 Revised Notification of 990805 Meeting with Util to Discuss Radiation Protection Issues Identified in NRC Insps Repts 50-458/98-10 & 50-458/99-04 ML20209D8271999-07-0707 July 1999 Notification of 990719 Licensee Meeting in Arlington,Tx to Discuss Failed Fuel Recovery Project ML20196G0321999-06-24024 June 1999 Notification of 990726 Meeting with Util to Discuss Radiation Protection Issues ML20195F8811999-06-10010 June 1999 Notification of 990622 Meeting with Util in Rockville,Md to Discuss Related Issues Associated with Fuel Integrity Problems Experienced During Recent Cycle 8 Operation ML20207G3761999-06-0202 June 1999 Revised Notification of 990611 Meeting with EOI in Rockville,Maryland to Discuss Issues Associated with Fuel Integrity Problems Experienced During Recent Cycle 8 Operation.Meeting Cancelled ML20207E9231999-06-0202 June 1999 Notification of 990611 Meeting with EOI in Rockville, Maryland to Be Briefed by EOI & to Discuss Related Issues Associated with Fuel Integrity Problems Experienced During Recent Cycle 8 Operation DD-99-05, Forwards Monthly Rept on Status of 10CFR2.206 Petition as of 990331.During March,Director'S Decision (DD-99-06) on Browns Ferry & DD on Army Corps of Engineers Was Issued & (DD-99-05) on Diablo Canyon Became Final Agency Action1999-04-20020 April 1999 Forwards Monthly Rept on Status of 10CFR2.206 Petition as of 990331.During March,Director'S Decision (DD-99-06) on Browns Ferry & DD on Army Corps of Engineers Was Issued & (DD-99-05) on Diablo Canyon Became Final Agency Action ML20205R8871999-04-20020 April 1999 Notification of 990504 Meeting with Util in Rockville,Md to Discuss Proposal to Submit Consolidated Security Plan for Util Sites ML20196K9471999-04-0606 April 1999 Notification of Significant Licensee Meeting with Util on 990420 to Discuss Results of Most Recent NRC Plant Performance Review IR 05000458/19993011999-03-29029 March 1999 Forwards NRC Operator Licensing Exam Rept 50-458/99-301 (Including Completed & Graded Tests) for Tests Administered on 990222-0303 ML20205C4481999-03-29029 March 1999 Forwards NRC Approved Operator Licensing Exam (Facility Outline & Initial Exam Submittal & as-given Operating Exam) for Tests Administered on 990222-0303 ML20207K9161999-03-11011 March 1999 Notification of Significant Licensee Meeting with Util on 990325 to Discuss River Bend Station Engineering Program & Performance with Project,Maintenance & Engineering Branch Personnel ML20199L0511999-01-21021 January 1999 Notification of 990222 Meeting with Util in Rockville,Md for Ucs to Present Addl Info & Clarify Issues Raised in Two 10CFR2.206 Petitions Re River Bend Station & Perry Nuclear Power Plant ML20195G1121998-11-17017 November 1998 Notification of 981201-02 Meeting with Entergy Operations in Taft,Louisianna to Conduct Joint Workshop for Licensing Personnel from Entergy & Nrc,Project Directorate IV-1 ML20195F1691998-11-12012 November 1998 Notification of 981123 Meeting with Entergy Operations,Inc in Arlington,Tx to Discuss Apparent Inoperability of Divs I & II Emergency DGs ML20151U7971998-09-0808 September 1998 Notifies of 980929 Meeting with Util in Rockville,Md to Discuss Level of Instructions & Details for Transferring Quality Assurance Plan Details from Current Program Plans at Four Sites to Std Quality Assurance Program Plan ML20153H6671998-09-0808 September 1998 Revised Notification of 981007 Meeting with Util to Discuss Level of Instructions & Details for Transferring QA Plan Details from Current Program Plans at Four Sites to Std Program Plan at All Sites.Originally Scheduled for 980929 ML20151T6141998-09-0303 September 1998 Notification of Licensee Meeting W/Util on 980910 in Arlington,Tx to Discuss Plant Performance W/Regional Administrator & Division Directors ML20238F5861998-08-28028 August 1998 Notification of 980909 Meeting w/BWR/6S:EOI & Listed Utils in Rockville,Md to Discuss W/Nrc Planned Applications by Licensees to Reduce Operability Requirements During Refueling Outages ML20237A2811998-08-12012 August 1998 Notification of 980827 Meeting W/Nrc & Util in Rockville,Md to Discuss Level of Instructions & Details for Transferring QA Plan Details from Current Program Plans at Four Sites ML20236Q9371998-07-13013 July 1998 Notification of Licensee Meeting W/Entergy Operations,Inc on 980729 in Arlington,Tx to Discuss Results of Plant Fire Protection Functional Insp ML20249A2101998-06-11011 June 1998 Notification of 980702 Meeting W/Util in Rockville,Md to Discuss Level of Instructions & Details for Transferring Quality Assurance Plan Details from Current Program Plans at Four Sites to Std Quality Assurance Program Plan for Site ML20248M1961998-06-0808 June 1998 Notification of Significant Licensee Meeting W/Util on 980626 in Arlington,Tx Re Predecisional EC to Discuss Apparent Violation of 10CFR50.9 ML20216D6351998-04-13013 April 1998 Notification of 980416 Meeting W/Util in Rockville,Md to Discuss Entergy Operations,Inc Initial Proposal to Standardize Security Plans for Listed Plants ML20217E8471998-03-26026 March 1998 Notification of Significant Licensee Meeting W/Util on 980402 to Discuss Entergy Operations,Inc Annual Performance Assessment ML20216B1391998-03-10010 March 1998 Notification of Significant Licensee Meeting W/Util on 980324 to Consider Licensee Assessment of Performance Since Feb 1997 & to Discuss Design Basis of Standby Gas Treatment Sys & Effect on Operator Access to Reactor Bldg ML20197B8721998-03-0505 March 1998 Notification of 980401 Meeting W/Util in Jackson,Ms to Discuss Licensing Issues & Regulatory Performance Efficiencies W/Licensing Staff for Plants.Meeting Agenda Encl ML20203B4131998-02-0505 February 1998 Notification of 980319 Meeting W/Entergy Operations,Inc,In Rockville,Md to Discuss Level of Instructions & Details of Transferring QA Plan Details from Current Program Plans at Four Sites to Standard QA Program Plan for Use at All Sites ML20198M8351998-01-12012 January 1998 Notification of 980122 Meeting W/Util in Rockville,Md to Discuss Site Licensing Status for Listed Plants & to Explore Ways to Standardize Licensing Submittals & Issuances ML20202G1561997-12-0303 December 1997 Forwards Facility Submitted Outline,Initial Exam Submittal & as Given Operating Exam,Administered on 970728-0801 at Plant,Unit 1 ML20202G1681997-12-0303 December 1997 Forwards SRO Exam Rept Key for Exams Administered on 970728-0801 at Plant ML20199E6851997-11-18018 November 1997 Notification of Licensee Meeting W/Util on 971202 to Discuss Circumstances Surrounding Two Incidents on 970913 & 971004 ML20198K0791997-10-15015 October 1997 Notification of 971022 Meeting W/Entergy Operations,Inc in Rockville,Md Re Standard Quality Assurance Manual for Entergy Sites ML20141H8111997-07-31031 July 1997 Notification of 970819 Meeting W/Entergy Operations,Inc in Rockville,Md to Discuss Open Issues from Fire Protection Functional Insp Conducted at River Bend Station During July 1997.Meeting Agenda Attached ML20141H2321997-05-20020 May 1997 Revised Notification of 970717 Licensee Meeting W/Util in Arlington,Tx to Discuss Long Term Performance Improvement Plan.Date Changed from 970522 ML20141A7191997-05-12012 May 1997 Notification of 970520 Meeting W/Util in Rockville,Md to Discuss Proposed Removal of Leakage Control Sys on Main Steam Lines & Other Penetrations & to Increase Allowable Leak Rate for MSIVs ML20141B9371997-05-0808 May 1997 Forwards NRC Approved Operator Licensing Exam (Facility Outline & Initial Exam Submittal & as-given Operating Exam) for Tests Administered on 970127-0214 ML20138K0821997-05-0808 May 1997 Notification of Licensee Meeting W/Util on 970522 in Arlington,Tx to Discuss Long Term Performance Improvement Plan ML20203C0921997-04-23023 April 1997 Discusses Initiation of OI Rept 4-97-003 Re Falsification of Fire Watch logs.EA-97-184 Assigned to Track Case.Viewgraphs from 970602 Predecisional Enforcement Conference Encl ML20137W6841997-04-15015 April 1997 Notification of 970502 Meeting W/Listed Attendees in Jackson,Mi.Meeting Agenda Encl ML20203C0871997-04-15015 April 1997 Requests Review of OI Rept 4-97-003 Issued 970411.OI Has Concluded That Deliberate Violation of Requirements Occurred ML20137K5231997-04-0101 April 1997 Notification of 970414 Meeting W/Util in Arlington,Tx to Introduce Entergy Mgt ML20147H4131997-03-31031 March 1997 Forwards SE Accepting Proposed P-T Limits for Heatup, Cooldown,Inservice Leak & Hydrostatic Testing & Core Criticality Acceptable to 12 Efpy.Salp Input Also Encl ML20137C9201997-03-20020 March 1997 Forwards Documentation of Meeting Conducted in Region 4 Office on 970225 to Discuss NRC Enforcement Policy as Applied to Nonescalated Enforcement ML20136D5531997-03-10010 March 1997 Notification of 970313 Meeting W/Util in Rockville,Md to Discuss Proposed Program & Design for ECCS Strainers for Plant,In Response to NRC Bulletin 96-003, Potential Plugging of ECCS Strainers by Debris in Bwrs ML20134P2231997-02-20020 February 1997 Discusses Ti 2515/122 Evaluation or Rosemount Pressure Transmitter Performance & Licensee Enhanced Surveillance Programs multi-plant Action B-122 ML20134M2471997-02-14014 February 1997 Submits List of Plants Not Meeting Selection Criteria for Ti 2515/118 Insp on Basis of Factors Such as SWS Operating Experience,Contribution of SWS to Plant Risk Assessment, Licensee Programs in Response to GL-89-13 1999-08-27
[Table view] Category:MEMORANDUMS-CORRESPONDENCE
MONTHYEARML20211H4441999-08-27027 August 1999 Notification of Significant Meeting with Util on 990916 & 17 in Arlington,Tx to Improve Utility & NRC Understanding of Industry & Regulatory Perspectives on Current Issues ML20211E1491999-08-23023 August 1999 Notification of Licensee Meeting with Util on 990830 to Discuss Recent Refueling Maint Outage ML20209G2421999-07-14014 July 1999 Notification of 990722 Meeting with License in Rockville, MD to Discuss Changes in EOI Licensing Organization Including Division of Responsibilities within New EOI Corporate Licensing Group ML20209F6111999-07-12012 July 1999 Revised Notification of 990805 Meeting with Util to Discuss Radiation Protection Issues Identified in NRC Insps Repts 50-458/98-10 & 50-458/99-04 ML20209D8271999-07-0707 July 1999 Notification of 990719 Licensee Meeting in Arlington,Tx to Discuss Failed Fuel Recovery Project ML20196G0321999-06-24024 June 1999 Notification of 990726 Meeting with Util to Discuss Radiation Protection Issues ML20195F8811999-06-10010 June 1999 Notification of 990622 Meeting with Util in Rockville,Md to Discuss Related Issues Associated with Fuel Integrity Problems Experienced During Recent Cycle 8 Operation ML20207G3761999-06-0202 June 1999 Revised Notification of 990611 Meeting with EOI in Rockville,Maryland to Discuss Issues Associated with Fuel Integrity Problems Experienced During Recent Cycle 8 Operation.Meeting Cancelled ML20207E9231999-06-0202 June 1999 Notification of 990611 Meeting with EOI in Rockville, Maryland to Be Briefed by EOI & to Discuss Related Issues Associated with Fuel Integrity Problems Experienced During Recent Cycle 8 Operation DD-99-05, Forwards Monthly Rept on Status of 10CFR2.206 Petition as of 990331.During March,Director'S Decision (DD-99-06) on Browns Ferry & DD on Army Corps of Engineers Was Issued & (DD-99-05) on Diablo Canyon Became Final Agency Action1999-04-20020 April 1999 Forwards Monthly Rept on Status of 10CFR2.206 Petition as of 990331.During March,Director'S Decision (DD-99-06) on Browns Ferry & DD on Army Corps of Engineers Was Issued & (DD-99-05) on Diablo Canyon Became Final Agency Action ML20205R8871999-04-20020 April 1999 Notification of 990504 Meeting with Util in Rockville,Md to Discuss Proposal to Submit Consolidated Security Plan for Util Sites ML20196K9471999-04-0606 April 1999 Notification of Significant Licensee Meeting with Util on 990420 to Discuss Results of Most Recent NRC Plant Performance Review IR 05000458/19993011999-03-29029 March 1999 Forwards NRC Operator Licensing Exam Rept 50-458/99-301 (Including Completed & Graded Tests) for Tests Administered on 990222-0303 ML20205C4481999-03-29029 March 1999 Forwards NRC Approved Operator Licensing Exam (Facility Outline & Initial Exam Submittal & as-given Operating Exam) for Tests Administered on 990222-0303 ML20207K9161999-03-11011 March 1999 Notification of Significant Licensee Meeting with Util on 990325 to Discuss River Bend Station Engineering Program & Performance with Project,Maintenance & Engineering Branch Personnel ML20199L0511999-01-21021 January 1999 Notification of 990222 Meeting with Util in Rockville,Md for Ucs to Present Addl Info & Clarify Issues Raised in Two 10CFR2.206 Petitions Re River Bend Station & Perry Nuclear Power Plant ML20195G1121998-11-17017 November 1998 Notification of 981201-02 Meeting with Entergy Operations in Taft,Louisianna to Conduct Joint Workshop for Licensing Personnel from Entergy & Nrc,Project Directorate IV-1 ML20195F1691998-11-12012 November 1998 Notification of 981123 Meeting with Entergy Operations,Inc in Arlington,Tx to Discuss Apparent Inoperability of Divs I & II Emergency DGs ML20151U7971998-09-0808 September 1998 Notifies of 980929 Meeting with Util in Rockville,Md to Discuss Level of Instructions & Details for Transferring Quality Assurance Plan Details from Current Program Plans at Four Sites to Std Quality Assurance Program Plan ML20153H6671998-09-0808 September 1998 Revised Notification of 981007 Meeting with Util to Discuss Level of Instructions & Details for Transferring QA Plan Details from Current Program Plans at Four Sites to Std Program Plan at All Sites.Originally Scheduled for 980929 ML20151T6141998-09-0303 September 1998 Notification of Licensee Meeting W/Util on 980910 in Arlington,Tx to Discuss Plant Performance W/Regional Administrator & Division Directors ML20238F5861998-08-28028 August 1998 Notification of 980909 Meeting w/BWR/6S:EOI & Listed Utils in Rockville,Md to Discuss W/Nrc Planned Applications by Licensees to Reduce Operability Requirements During Refueling Outages ML20237A2811998-08-12012 August 1998 Notification of 980827 Meeting W/Nrc & Util in Rockville,Md to Discuss Level of Instructions & Details for Transferring QA Plan Details from Current Program Plans at Four Sites ML20236Q9371998-07-13013 July 1998 Notification of Licensee Meeting W/Entergy Operations,Inc on 980729 in Arlington,Tx to Discuss Results of Plant Fire Protection Functional Insp ML20249A2101998-06-11011 June 1998 Notification of 980702 Meeting W/Util in Rockville,Md to Discuss Level of Instructions & Details for Transferring Quality Assurance Plan Details from Current Program Plans at Four Sites to Std Quality Assurance Program Plan for Site ML20248M1961998-06-0808 June 1998 Notification of Significant Licensee Meeting W/Util on 980626 in Arlington,Tx Re Predecisional EC to Discuss Apparent Violation of 10CFR50.9 ML20216D6351998-04-13013 April 1998 Notification of 980416 Meeting W/Util in Rockville,Md to Discuss Entergy Operations,Inc Initial Proposal to Standardize Security Plans for Listed Plants ML20217E8471998-03-26026 March 1998 Notification of Significant Licensee Meeting W/Util on 980402 to Discuss Entergy Operations,Inc Annual Performance Assessment ML20216B1391998-03-10010 March 1998 Notification of Significant Licensee Meeting W/Util on 980324 to Consider Licensee Assessment of Performance Since Feb 1997 & to Discuss Design Basis of Standby Gas Treatment Sys & Effect on Operator Access to Reactor Bldg ML20197B8721998-03-0505 March 1998 Notification of 980401 Meeting W/Util in Jackson,Ms to Discuss Licensing Issues & Regulatory Performance Efficiencies W/Licensing Staff for Plants.Meeting Agenda Encl ML20203B4131998-02-0505 February 1998 Notification of 980319 Meeting W/Entergy Operations,Inc,In Rockville,Md to Discuss Level of Instructions & Details of Transferring QA Plan Details from Current Program Plans at Four Sites to Standard QA Program Plan for Use at All Sites ML20198M8351998-01-12012 January 1998 Notification of 980122 Meeting W/Util in Rockville,Md to Discuss Site Licensing Status for Listed Plants & to Explore Ways to Standardize Licensing Submittals & Issuances ML20202G1681997-12-0303 December 1997 Forwards SRO Exam Rept Key for Exams Administered on 970728-0801 at Plant ML20202G1561997-12-0303 December 1997 Forwards Facility Submitted Outline,Initial Exam Submittal & as Given Operating Exam,Administered on 970728-0801 at Plant,Unit 1 ML20199E6851997-11-18018 November 1997 Notification of Licensee Meeting W/Util on 971202 to Discuss Circumstances Surrounding Two Incidents on 970913 & 971004 ML20198K0791997-10-15015 October 1997 Notification of 971022 Meeting W/Entergy Operations,Inc in Rockville,Md Re Standard Quality Assurance Manual for Entergy Sites ML20141H8111997-07-31031 July 1997 Notification of 970819 Meeting W/Entergy Operations,Inc in Rockville,Md to Discuss Open Issues from Fire Protection Functional Insp Conducted at River Bend Station During July 1997.Meeting Agenda Attached ML20141H2321997-05-20020 May 1997 Revised Notification of 970717 Licensee Meeting W/Util in Arlington,Tx to Discuss Long Term Performance Improvement Plan.Date Changed from 970522 ML20141A7191997-05-12012 May 1997 Notification of 970520 Meeting W/Util in Rockville,Md to Discuss Proposed Removal of Leakage Control Sys on Main Steam Lines & Other Penetrations & to Increase Allowable Leak Rate for MSIVs ML20138K0821997-05-0808 May 1997 Notification of Licensee Meeting W/Util on 970522 in Arlington,Tx to Discuss Long Term Performance Improvement Plan ML20141B9371997-05-0808 May 1997 Forwards NRC Approved Operator Licensing Exam (Facility Outline & Initial Exam Submittal & as-given Operating Exam) for Tests Administered on 970127-0214 ML20203C0921997-04-23023 April 1997 Discusses Initiation of OI Rept 4-97-003 Re Falsification of Fire Watch logs.EA-97-184 Assigned to Track Case.Viewgraphs from 970602 Predecisional Enforcement Conference Encl ML20137W6841997-04-15015 April 1997 Notification of 970502 Meeting W/Listed Attendees in Jackson,Mi.Meeting Agenda Encl ML20203C0871997-04-15015 April 1997 Requests Review of OI Rept 4-97-003 Issued 970411.OI Has Concluded That Deliberate Violation of Requirements Occurred ML20137K5231997-04-0101 April 1997 Notification of 970414 Meeting W/Util in Arlington,Tx to Introduce Entergy Mgt ML20147H4131997-03-31031 March 1997 Forwards SE Accepting Proposed P-T Limits for Heatup, Cooldown,Inservice Leak & Hydrostatic Testing & Core Criticality Acceptable to 12 Efpy.Salp Input Also Encl ML20137C9201997-03-20020 March 1997 Forwards Documentation of Meeting Conducted in Region 4 Office on 970225 to Discuss NRC Enforcement Policy as Applied to Nonescalated Enforcement ML20136D5531997-03-10010 March 1997 Notification of 970313 Meeting W/Util in Rockville,Md to Discuss Proposed Program & Design for ECCS Strainers for Plant,In Response to NRC Bulletin 96-003, Potential Plugging of ECCS Strainers by Debris in Bwrs ML20134P2231997-02-20020 February 1997 Discusses Ti 2515/122 Evaluation or Rosemount Pressure Transmitter Performance & Licensee Enhanced Surveillance Programs multi-plant Action B-122 ML20134M2471997-02-14014 February 1997 Submits List of Plants Not Meeting Selection Criteria for Ti 2515/118 Insp on Basis of Factors Such as SWS Operating Experience,Contribution of SWS to Plant Risk Assessment, Licensee Programs in Response to GL-89-13 1999-08-27
[Table view] |
Text
_ -_
JUL 2 21985 MEMORANDUM FOR: Hugh L. Thompson, Jr. , Director, Division of Licensing, Office of Nuclear Reactor Regulation FROM: Richard P. Denise, Director, Division of Reactor Safety and Projects, Region IV
SUBJECT:
STATUS OF FACILITY COMPLETION FOR RIVER BEND STATION DOCKET NO. 50-458, REVISION 4 This forwards the status of facility completion report for the River Bend Station in accordance with Inspection Procedure 943008. It is the fourth revision of this report. ,
The licensae's projected fuel load date is July 1985. Monitoring of licensee progress toward the completion of items indicates that this date will more i likely be early August 1985. The reasons for schedule slippage include the j clearing of items on the licensee's master list, the completion of system i turnover, and the completion of building turnover.
The licensee has closed 33,082 open items, but there are still 4,471 open. Of the total open, 821 are work items and 3,650 are paper items. In addition, there are 9 (of 27) safety-related areas not yet turned over to the licensee.
As these safety-related areas are turned over to the licensee, resulting open items from them are incorporated in the master list. Thus, the master list overall closure rate appears less than that indicated by the number of items closed daily. All open items on the master list will be resolved to the satisfaction of Region IV prior to fuel load. Resolved means that an item is l cleared, determined to have no safety significance, or determined to have no effect prior to exceeding 5% power.
There are no outstanding escalated enforcement issues at this time.
If there are questions, please contact either Johns Jaudon (FTS 728-8140)or myself.
C:v .-! Sa dc By:
e a rm .n R. P. Denise, Director Division of Reactor Safety and Projects
Enclosures:
(cont. on next page)
RPB1/A RPB1 h DRSP JPJaudon/lk EHJohnson RPDenise q /tt / 1/gp/85 /p5 G707080393 870512 PDR FOIA J g h
GRADERB7-279 PDR
{:
Enclosures:
- 1. Items to be Completed Prior to Fuel Load
- 2. Preoperational Test Status
- 3. Construction Status
- 4. Status of Inspections Required by MC 2512, MC 2513, and MC 2514
- 5. Status of Allegations
- 6. Status of SER Open and Confirmatory Items Affecting Region IV cc w/ enclosures:
R. Martin, RIV J. Taylor, IE S. Stern, NRR K. Kniel, NRR R. Bangart, RIV E. Johnson, RIV J. Jaudon, RIV !
R. Taylor, RIV !
R. Bennett, RIV D. Chamberlain, SRI bec w/ enclosures: l RPB RSB RIV Official Reading File I
l 1
1 I
ENCLOSURE 1 ITEMS TO BE COMPLETED PRIOR TO FUEL LOADING I. The licensee has demonstrated to the satisfaction of Region IV that management attention has been directed to those areas identified in the last SALP report as requiring either specific or general improvement.
Region IV will continue to monitor these areas by means of the inspection program.
Previous SALP Evaluations latest Previous Performance Category Performance Category Functional Area (8/1/83 to 12/31/84) (9/1/82 to-7/31/83)
A. Soils and Founda- Not Assessed (NA) NA tions B. Containment and 1 2 Other Safety-Related Structures )
l C. Fiping Systems and 2 2 Support D. Support Systems 2 2 E. Electrical Power and 2 2 Supply and Distribution F. Instrumentation and 2 2 Control Systems G. Safety-Related 2 2 Components H. Corrective Action and 1 2 I Reporting .
I. Quality Assurance 2 2 (Construction J. Quality Assurance 2 6 (Operations)
K. Design Control 2 1 i
L. Preoperational Testing 2 NA B10
i I
j Latest l
Previous l Performance Category Perfonnance Category ,
Functional Area (8/1/83 to 12/31/84) (9/1/82 to-7/31/83) j M. Plant Operations 2 NA Preparation I N. Emergency Preparedness 2 NA
- 0. Radiological Controls 2 NA P. Security 2 NA Q. Training 2 NA R. Management Control 1 1 S. Licensing Activity 2 2 II. Region IV will verify licensee implementation of applicable bulletins.
Thirteen bulletins remain to be verified.
III. NRC Region IV has reviewed action of Construction Deficiency Reports (10 CFR Part 50.55(e)) and Part 21 items. The licensee has reported 317 items. Of those remaining open, the status is as follows:
o Number of reportable items reported as " Ready 0 to Close" by the licensee o Number of items determined by the licensee to 0 be nonreportable and which the Region has not i yet reviewed o Number of items not reported either " Ready to 15 Close" or determined to be not reportable by the licensee i TOTAL OPEN 15 l
IV. The licensee must resolve, to the satisfaction of Region IV, the open violations, deviations, unresolved and open items which affect fuel load. A summary of these is provided in Appendix A to this enclosure.
V. Compliance to Appendix R requirements was inspected by a team during the week of April 1,1985. The most significant inspection finding was that the licensee had not analyzed effects of fire induced spurious signals outside the control room. This analysis has now been completed. A followup inspection by Region IV has verified the completion of fire stops. The licensee has requested deferral on some cable wraps until prior to exceeding 5% power.
1
I
{
{
1 VI. Regional followup to CAT and IDI inspections has been made. ;
VII. The final draft of Technical Specifications was checked against installed equipment by a Region IV inspection team April 29-May 3,1985. This i inspection found that many licensee procedures to implement Technical Specifications were not completed or had errors in.them. A reinspection is scheduled to commence July 22, 1985.
I i
I
l 1
. . I I
Open Inspection Items Affecting fuel Load i
l Type Item Subject {
(
Open Regiological Controls and Chemistry. There are several '
open items in these areas. The principal reason that there are open items in these areas is that the ;
licensee had not completed comitments or issued j procedures. The next inspection of this area will comence July 22, 1985. These are fuel load items.
Open Technical Specifications Implementing Procedures for Surveillance Testing. There are many open items q regarding procedures for the conduct of surveillance .
testing. The next inspection of this area is scheduled to commence on July 22, 1985. These are fuel load items.
1 Open Emergency Preparedness. There are several open items j resulting from the emergency preparedness appraisal and exercise. All items affecting fuel load should be closed by July 19, 1985.
Violations There are 11 open violations. These are fuel load ;
items. I Deviations There is one open deviation. It is the Region's judgement that this item needs to be resolved prior to exceeding 5% power.
l1 Open Quality Assurance Implementation. There are several I open items concerning implementation of the quality assurance program for operations. These are fuel load items.
Open Appendix R Implementation. There are four open items I concerning Appendix R implementation. The licensee is committed to complete resolution of these prior to !
exceeding 5% power.
Open Construction Program. There are a few miscellaneous open items from the construction inspection program.
These are fuel load items.
Open Preoperation Test and 0)erational Readiness. There are a few open items from t1e 2513 program. These are fuel load items pending additional review.
4
ENCLOSURE 2 PRE 0PERATIONAL TESTING STATUS The status of the licensee's preoperational tests is as follows:
Total number of tests 106 Number of tests completed and reviewed 99 Number of tests completed but not 2 reviewed Number of tests completed 5 Number of tests not started 0 i
l
.. . 1
)
ENCLOSURE 3 CONSTRUCTION STATUS i
As of May 17, 1985, construction was approximately 98 percent completed. The licensee has been releasing equipment by " Boundary Identification Packages" (BIPs) to the plant staff. Review of the current status by whole systems, 1 instead of BIPs, indicate that out of 113 systems identified by the licensee as needed to :epport a license to load fuel, 5 remain to be turned over to the plant staff as of this report. However, BIPs which contain portions of other required systems have been turned over also.
Of the 41 systems requiring N5 stamp certification, all have completed the approval process as of July 11, 1985.
1 ENCLOSURE 4 STATUS OF INSPECTIONS REQUIRED BY MC 2512, MC 2513, AND MC 2514 The MC 2512 inspection program has been completed.
The status of MC 2513 inspections is as follows: j Module Number Description Percent Complete 70325 Reactor Prot Sys-Test Evaluation 0%
70323 ILRT-Test Evaluation 30%
70552 Remote Reactor SD-Evaluation 90%
35742 QA Program-Document Control 50%* f 35743 QA program-Maintenance 50%*
35744 QA Program-Design Changes 50%*
35745 QA Program-Surveillance Test 50%* -
35750 QA Program MT&E 50%* I 42450 Operations Procedures 90%
71301 Technical Specifications Review 90%
79501 LWR Chem. Cont. 80%
79502 Plant System Affecting Chem. 80%
83522 Rad Protection-Preoperational 90%
j 83523 Rad Protection-Preoperational 90%
84522 Solid Wastes 80%
84523 Liquids and Liquid Waste 80%
84524 Gaseous Waste System 80%
84525 Radiological and Chemical Confirm Meas. 90%
81018 Management Effectiveness 0%**
81038 Records and Reports 0%**
81042 Testing and Maintenance OS*
81046 Locks, Keys, Combinations 0%**
Module Number Description Percent Complete 81054 Physical Barriers 0%**
81058 Security System Power Supply 0%**
81064 Compensatory Measures 0%**
81072 Access Control Packages 0%**
81074 Access Control-Vehicles 0%**
81080 Detection Aids 0%**
81084 Alarm Stations 0%**
81088 Comunications 0%**
81810 Physical Protection, S/G Info. 0%**
- The remaining 50% of these QA modules are done after implementation (i.e.,
after licensing).
- Preliminary inspections of security have been completed; however, modules are carried at 0% complete pending lock down. Lock down occurred on July 12, 1985. Final inspection of these modules commenced July 15, 1985.
The status of MC 2514 inspections is as follows:
Module Number Description Percent Complete 35501 QA for SU Test Program 0%
72400 Overall Startup Test Log 0%
72500 Initial Fuel Loading Procedures Review 0%
72524 Initial Fuel Loading-Witness 0%
83521 Rad Protection-SU 0%
84521 Radwaste-SU 0%
72502 Int. Crit-Procedures Review 0%
72504 Heatup Phase Procedure Review 0%
72508 Power Assession Procedure Review (A) 0%
72509 Power Assession Procedure Review (B) 0%
72510 Power Assession Procedure Review (C) 0%
72512 SU Test Procedure Review (B) 0%
72514 SU Test Procedure Review (A&B) 0%
72516 SU Test Procedure Review (A) 0%
{
72517 SU Test Procedure Review (A&B) 0%
I' l
Module Number Description Percent Complete ;
72518 SU Test Procedure Review 0% !
72526 Initial Criticality-Witness 0%
72532 Power Level Data Review & Evaluation 0%
TI2514-01 Lonfirmation of TMI Items 50%*
]
TI2500-11 Emergency Preparedness 80%
TI2513/55 Emergency Preparedness 90%* 3 ATWS 0% !
TI2515-64(Rev 1) 1 1
1
- All fuel load items requiring inspection are completed.
I i
I i
ENCLOSURE 5 STATUS OF ALLEGATIONS RECEIVED BY NRC FOR RIVER BEND A total of 35 allegations have been received. Twenty-six of these have been closed and nine are still open. The status of the nine open allegations is as follows:
Subject Source Status
- 1. Sensitive 01 lead
- 2. Sensitive OI lead
- 3. Ccble Trays Anonymous RIV lead; violations issued. Will close in IR 85-09
- 4. Harrassment of Eng. Anonymous GSU lead; RIV monitor.
Steff (S&W) Will close in IR 85-43
- 5. Control Room Circuitry Craft Worker GSU lead; RIV monitor.
Problems to GSU Will close in IR 85-41
- 6. Drug Usage Anonymous GSU lead; RIV monitor
- 7. Drug Usage Anonymous GSU lead; RIV monitor
- 8. Construction Practices Interested RIV lead for that part Citizen concerning RIV
- 9. Sensitive 01 and Region reviewing {
issues l
l l
ENCLOSURE 6 STAT'JS OF SER OPEN AND CONFIRMATORY ITEMS
)
AFFECT 1NG REGION IV The licensee has completed to the satisfaction of Region IV all of the SER confirmatory action assigned to RIV for closure, r