ML20211C065

From kanterella
Jump to navigation Jump to search
Describes Plans to Remove Temporary Wall Separating Unit 1 & 2 Control Room Areas.Wall Installed to Operate Unit 1 Prior to Unit 2 Completion.Operation of Unit 1 Control Room During Removal requested.W/10 Oversize Figures & Rev to Tech Spec
ML20211C065
Person / Time
Site: Beaver Valley
Issue date: 02/10/1987
From: Sieber J
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8702200005
Download: ML20211C065 (54)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - -

,e

'At3 Telephone (412) 393 6000 Nuclear Grouo P.O. Box 4 Shippingport, PA 15077-0004 February 10, 1987 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

Reference:

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 Control Room Wall Removal - Revision 1 Gentlemen:

This letter provides a description of our plans to remove the temporary wall separating the Unit 1 and Unit 2 control room areas.

The temporary wall was installed between the two control room areas in order to operate Unit 1 prior to Unit 2's completion. The wall served as an interim pressure boundary as well as a fire and security barrier. As a result of the temporary wall removal, the capacity of the Unit 1 Control Room Emergency Ventilation System (CREVS) must be increased. The current design of the Unit 1 CREVS only provides for pressurization of the Unit 1 control room envelope (CRE).

It is our request that Unit 1 be permitted to continue to operate while this temporary wall is removed and the Unit 1 CREVS equipment is being modified. This wall needs to be removed prior to fuel load on Unit 2 to permit full access of the Unit 2 operators to the communications console for Emergency Preparedness purposes and to monitor shared non-safety related auxiliary systems.

Additionally, during the period when the Unit 1 CREVS is out of service for the necessary modifications, control room habitability will be ensured by maintaining the Unit 2 CREVS operable. The Unit 2 CREVS is sized to service both Unit 1 and Unit 2 control room areas.

Technical Specification Change Request No. 134 has been submitted to allow continued operation of Unit 1 while the Unit 1 Control Room Emergency Ventilation System (CREVS) is out of service for equipment design modification. When Unit 1 CREVS modifications are complete

'" and the system is verified operable, the temporary technical specification presented in Change Request No. 134 will expire. At this time, we will request NRC approval of Technical Specification Change Request No. 126 which implements the surveillance requirements for the modified Unit 1 CREVS.

8702200005 870210 6g\ g,gl .

PDR ADOCK05000g4 .

g P

Q g

<c

B$avar Valley' Power Station, Unit No. 1 Docket No. 50-334,.Licensa No. DPR-66 Control Room Removal - Revision 1 Page 2 A Control Room Habitability Implementation Program (CHIP) has been developed to ensure operability of the Unit 2 equipment and support systems that are required to provide a safe and habitable

. environment- in- the combined control room while the Unit 1 CREVS is being modified. The CHIP (provided as Attachment 1) includes a summary of planned actions, Unit 2 equipment requirements, fire protection requirements and security measures.

In the event any Unit 2 equipment supporting Unit 1 operations

should become inoperable, this would mean Unit 1 would not be able to a demonstrate operability of both control room emergency habitability j systems. In this case, Unit 1 would follow the required action statement of Technical Specification 3.7.7.1 which requires the inoperable system be restored to operable status within 7 days or be j in at least hot standby within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown i within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. The CHIP has been reviewed by both

! the OSC and ORC. Procedures controlling the-operability of equipment

! and changes to these procedures will be handled in accordance with existing administrative controls. Changes to the CHIP which i represent intent changes will be reviewed by the OSC.

Specific tasks involved with the removal of the temporary wall i include the following. Prior to removal of the wall separating the

two control rooms and modification of the Unit 1 CREVS, a repairable test penetration will be made through the gypsum portion of the i temporary wall. Testing will then be performed to verify Unit 2 l CREVS operability. This testing will ensure that Unit 2 CREVS can
perform the required functions necessary to maintain combined Unit l 1-Unit 2 control room area habitability under postulated accident conditions. Operation of the BV-2 CREVS would be accomplished
manually through the addition of tags on the BV-1 control board that I

would instruct operators to prepare BV-2 equipment for startup 60 minutes following initiation of control room pressurization. Current Emergency Operating Procedures require the BV-1 operators to manually initiate control room pressurization when the correct conditions exist. This tag will be placed on the indicating lights which provide indication that control room pressurization has been initiated.

It has been determined that the integrity of the Unit 1 control room pressure envelope will be degraded'for a period of up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> when the test penetration is created in the temporary wall and subsequent Unit 2 CREVS operability testing is performed. However, in the unlikely event that pressurization of the Unit 1 control room becomes necessary, the repairable penetration through the wall separating the two control rooms will be isolated.

After the Unit 2 CREVS is verified operable, removal of the temporary wall and modification of the Unit 1 CREVS may begin.

Behvcr Vallcy Powar Station, Unit No. 1 Dock t No. 50-334, Lic5nto No. DPR-66 Control Room Removal - Revision 1 Page 3 Temporary wall removal work is expected to begin as early as the last week of March, 1987.

If you have any questions regarding this matter, please contact Mr. Steve Sovick.

Very truly yours,

.S ice President, Nuclear Enclosure cc: w/o drawings Mr. W. M. Troskoski, Resident Inspector U. S. Nuclear Regulatory Commission Beaver Valley Power Station Shippingport, PA 15077 U. S. Nuclear Regulatory Commission Regional Administrator Region 1 631 Park Avenue King of Prussia, PA 19406 Mr. Thomas M. Gerusky, Director Bureau of Radiation Protection Pennsylvania Dept. of Environmental Resources P.O. Box 2063 Harrisburg, PA 17120 Mr. Peter S. Tam U. S. Nuclear Regulatory Commission Project Directorate No. 2 Division of PWR Licensing - A Washington, DC 20555

- Mail Stop 340 Addressee only w/ drawings Mr. Jack Hayes U. S. Nuclear Regulatory Commission Project Directorate No. 2 Division of PWR Licensing - A Washington, DC 20555

- Mail Stop 416 -

ATTACHMENT 1 Control Room Habitability Implementation Program (CHIP)

TABLE OF CONTENTS Page I. Summary of Planned Actions A. Diagrams and Description of Wall 2 Figure 1 3 Figure 2 4 B. Activity Summary 5 II. Control Room Habitability l

A. Unit 1 Systems Expected to be Out of Service 8

B. Systems Necessary to Support Unit 2 control Room Emergency Habitability Systems 9 C. Unit 2 Equipment Operability and Fire Protection Requirements 10 D. Unit 2 Procedure Requirements 11 E. Unit 1 Emergency Operating Procedure 11 Requirements F. Control Room Pressure Boundary Management 12 i III. Security Measures 12 IV. Fire Protection Measures 12 i

Appendix A Unit 2 equipment operability and fire protection requirements.

^

ATTACHMENT 1 (cont.)

I.

SUMMARY

OF PLANNED ACTIONS A. Diagrams and Description of Temporary Control Room Wall The temporary control room wall is located in the main control room area for Unit 1 and Unit 2. Unit 1 control boards are on one side of the wall and Unit 2 control boards are on the other side as shown in Figure 1.

The wall is composed of 3/8" steel plate and several layers of gypsum board as shown in Figure 2. The largest steel plate is 4' x 10' and weighs approximately 612 pounds.

There are ten plates of this size and sixteen smaller plates. Gypsum board thickness ranges from 5/8 inch to 2 inches.

The steel plate functions as a security boundary between the two control rooms. It does not serve in any way as part of the Unit 1 control room pressure boundary. The layers of gypsum board form the Unit 1 control room pressure envelop.

l

_~

- p.y e

r, 3 l _ - 8:[

i_ m b E 43 g nnnn [O ~J .b_ ' , p y .:. l ~5 ems i-imizi:mm - i C

l di i)El ,

.w  : !_

u 1:

I c

=

= _Y ~

j ~

woe w o2 .

.N i 3 L.

~

-,? s.

/~' .

y .

p I

~

! II d)1

- l.

)

i -

8 5 3

$, j -

e J.A a -

! I t.

! } ] a .. '

. /

6 ,

i e J }.

I

% ) il OO c = m . . . . . . . . . . . .?. . . . . . . . . . _ . L . . ... . .

n. .c s.... ...m ,l a >

d i

5 i  ;

}"'~ j i

l1-l, .~ u i

.j'1 O -

y

+

li j:::j 6 u

k J'3 l NI =

I E 5' a

i: .

. 1

! s d i i is u

E 3

!e JA'.

- 3l I f

y'T"

) [W[~

px -

I aI 1} .. !p? i i

= "

LJ s ? J

[

] ..

w. . y i,-,--

4'

,f .sg-- 3 -p - - , , _ m

. + . - - . _ _ _ . _ --m_. -,

a. ,, - .

,~ ,

e S

9 9

Il:g -

as 38w

? *0 .f 19 .. I 8 i.

s- .

, g

    • 3

{j e3 -srs . f.'* . .I 8 8 2

\ \, . :il 6-2 a

_ ,, ,- \

1 4 - -I t p "3 6 -5 w -

w  ;

{ r 1

--- -- . 4 . 3 , gi

c y , ,
: )g, g t - - -

. . g e

er . >

$. 5 l

> / l- . b.t w

c .$3 . -: a

!! i 38 :s wt

/ . .

-Es e- .

O 1 I "2:

  • e I

11 s1 Q ,

e . 1 & g l

I e a

l i

. 3

    • . / . .

t*. .

8

. 4

. l

. -)

, a

> . . t-t-  ; .

8,s ~,

54

. ..s ,

  • N l.

- :q n ,s 22~

i: 1st*e* .s 3 - - l.

I *g 'e..{!

a y

.i -1: 1 ' .Q.

m i . , .1.g};1 sise

.. . ~s

{;,

s e-

=vle g ,

i* / e w.e *

/-I ,

I I *

. / / a

.,,/ X . ,

T . #'. .

  • e g

. 6

( .

. 's . . ,

... E 'a, -

i I2:

g9ee.,q I,." , . ..

j* I,

/ .

g /

I I~ hE h! (

  • I/ 1 st . .. . s - g p  : -

sf r 2: i  :

l . - . _

ATTACHMENT 1 (cont.)

B. ACTIVITY

SUMMARY

List of Activities to Support Control Room Wall Removal Required Equipment Activity Unit 1 Emergency la Unit 2 Emergency Ventilation Fan and Ventilation and Habitability System Test. Unit 2 to be Control Room Habit- placed in the recirculation Mode ability Equipment. (DCP-711).

lb Identify Unit 2 Systems and Components to support operation of Unit 1.

1c Verify Unit 2 Systems are incorporated into the OST program and necessary procedures are completed. (calibrations completed) ld Fire seals, doors and dampers operable for control room and all areas containing systems and components identified in Activity lb above.

le Security systems are operable or compensatory measures in place for control room and all areas containing systems and components identified in activity lb above.

If Provide administrative controls and pro-cedures to ensure Unit 2 equipment that is required to be operable remains operable. In addition, define line of authority and communication flow paths between Unit 1 and Unit 2.

2a Remove steel portion of control room wall except section to be used for CREBAPS duct support.

2b Develop Ventilation and CREBAPS test procedure for testing Unit 2 control room and combined Unit 1 and Unit 2 control room areas.

3a Pressure test Unit 2 area including shake

'./ space using fans.

2 T

._ , , . _ , _ _ . _ , . _ . , _ _ _ _ , . . _ ~ , _ . . . . _ . - , - - , , . . _ _ _ . _ _ , , . ..y_ , - _ . -_ _

ATTACHMENT 1 (cont.)

B. ACTIVITY

SUMMARY

(cont.)

Required

' Equipment Activity Unit 1 Emergency 3b Implement control room pressurization Ventilation and envelope control program.

Control Room Habit-ability Equipment 3c Documentation from Unit 2 to Unit 1 to continued operable. verify Unit 2 support-equipment operability.

3d Install new CREBAPS orifices, one at a time and perform flow test on first bottle and a system test when all orifices have been changed.

3e Unit 1 control boards appropriately tagged to require operation of Unit 2

-CREVS upon initiation of control room pressurization.

I 4 Cut repairable opening in gypsum wall.

Unit 2 Emergency 5 Operability testing of Unit 2 control Ventilation and Room Emergency Habitability Systems.

CREBAPS operable. (Emergency Ventilation and CREBAPS).

6 Documentation from Unit 2 to Unit 1 to verify Unit 2 ventilation equipment and y CREBAPS operability.

Unit 2 Emergency 7a Relocate CREBAPS 6tct and remove re-Ventilation System maining section of sucurity wall.

and CREBAPS; 60 day clock starts 7b Provide for personnel access between Unit 1 and Unit 2 for Unit 1 and Unit 2 operators to verify continued equipment operability.

8 Remove gypsum wall.

9 Install DCP-611, Unit 1 Control Room Emergency Habitability Systems Modifi-cation; de-energize control room air intake dampers in closed position.

10a Verify Unit 1 Emergency Ventilation y System operable.

~

ATTACHMENT 1 (cont.)

B. ACTIVITY

SUMMARY

(cont.)

Required Equipment Activity Unit 1 Emergency 10b Install new partition wall in control Ventilation and room.

CREBAPS operable.

l l

l 1

f f

I l

l 1

\

1 i

i

- . ~ . . _ . . . . , _ _ _ _ . . _ _ _ , _ , _ _ _ . _ . _. .._.._._ _ __. _ .,, . _. _ _ . . _ . _ . . _ _ . - _ _ _ . . - - - , . . _ _ , . .

ATTACHMENT 1 (cont.)

II. CONTROL ROOM HABITABILITY A. Unit 1 systems expected to be out of service.

The Unit 1 Control Room Emergency Ventilation System will be removed from service to increase the fan size, increase the size of supply and discharge ducting for the fans and filter, and provide larger duct heaters and dampers.

It has been determined that the integrity of the Unit 1 control room pressure envelope will be degraded for a period of up- to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> when the test penetration is created in the temporary wall and subsequent Unit 2 CREVS operability testing.is performed. However, in the unlikely event that pressurization of the Unit 1 control room becomes necessary, the repairable penetration through the wall separating the two control rooms will be isolated. Therefore, specification 3.0.3 will not be applied during this period of time.

Unit 1 Control Room Emergency Bottled Air Pressurization System (CREBAPS) will be modified by replacing the existing restricting orifices with larger restricting orifices to allow an increased flow rate to 200 cfm through each orifice (1,000 cfm total). One orifice will be replaced at a time, thus allowing continued CREBAPS availability since four out of five bottles will always be inservice. It has been estimated that all five orifices can be changed out in less than_ a day. In any event, we will follow the operability requirements of T.S. 3.7.7.1 during this work e,ffort.

During the period of time that the Unit 1 CREVS equipment is inoperable due to the planned modifications, the operability requirements of T.S. 3.7.7.1 will be modified as described in Technical Specification Change Request No. 134 when approved by the NRC. The change request consisted of the addition of the following note:

"This specification may be satisfied using the BV-2 control Room Area Emergency Habitability Systems during the period of time (60 days) when the BV-1 Control Room Emergency Ventilation System is out of service for equipment design modification. The NRC approved Control Room Habitability Implementation Program provides requirements to ensure BV-2 Control Room Emergency Habitability System Operability."

If at any time Unit 2 support components are determined inoperable based on the operability requirements provided in Appendix A, this would render one control room emergency habitability system inoperable. In this case, we would enter the action statement of T.S. 3.7.7.1 which would require the system to be restored to operable status within 7 days or be in at least hot standby within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown with the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

ATTACHMENT 1 (cont.)

II. CONTROL ROOM HABITABILITY (cont.)

B. Systems necessary to support Unit 2 Control Room Emergency Habitability Systems.

Applicable portions of the following Unit 2 systems will be maintained operable:

Emergency Diesel Generators Service Water Systems Station Batteries Electrical System 4KV Switchgear 480 V Substation 480 V Motor Control Centers 125 VDC Switchboard 125 VDC Distribution Panels 120 VAC Emergency Distribution Panels Administrative controls will be established to ensure general system arrangements (GSA) are in place. Specific components and the testing of these components will be defined in a Temporary Operating Procedure currently under development.

The GSA is as follows:

Unit 2 station service transformers 2C and 2D are energized System station service transformers 2A and 2B are energized (alternate supply to the normal 4KV buses).

Emergency buses 2AE, 2DF, 2N and 2P are properly aligned.

Diesel generator fuel oil storage tanks are filled above the minimum required 53,225 gallons.

Emergency diesel generator auxiliary day tanks are filled to greater than 16 inches and less than 44 inches above the tank bottom.

Emergency diesel generators are set up for automatic operation with load sequencing defeated.

Batteries 2-1 and 2-2 are charged, respective output breakers are shut and are capable of supplying power.

Control Room Outside Air Intake and Exhaust Dampers are closed and their supply breakers are off.

Control Room Emergency Supply Fans supply breakers are on and their control switches in auto-after-stop.

ATTACHMENT 1 (cont.)

II. CONTROL ROOM HABITABILITY (cont.)

Control Room Emergency Supply Fan Intake Dampers, Inlet Dampers, and Outlet Dampers are closed and aligned for automatic operation.

All zone and equipment rocm fire dampers are operable and open.

Service Water Pump (s) is operating and lined up to its respective header.

CO2 systems servicing specific areas are available.

Also included for your information is a set of Unit 2 drawings which have been marked to identify what portions of the Unit 2 systems will be required to support operation of Unit 1. If a drawing has no markings, then the drawing in its entirety is needed. The following is an index of those Unit 2 drawings for reference:

FSAR Fig. OM Figure Description 9.2-1 30-1 Service Water System - Main Headers 9.2-2 30-2 Service Water System - Intake Structure 9.2-4 30-4 System Primary and Secondary Heat Exchangers 9.5-7 36-9 Diesel Fuel Oil System 9.5-12 36-10 Diesel Air Intake, Exhaust and Vacuum 9.5-10 36-11 Diesel Air Starting System 9.5-8 36-12A Diesel Cooling Water System - Sheet 1 9.5-9 36-12B Diesel Cooling Water System - Sheet 2 9.5-11 36-13 Diesel Generator Lube Oil Systems 9.4-1 44A-2 Air Conditioning Control and Computer Room C. Unit 2 Equipment Operability and Fire Protection Requirements Applicable Unit 2 equipment operability and fire protection requirements are provided in Appendix A for information.

ATTACHMENT 1 (cont.)

II. CONTROL ROOM HABITABILITY (cont.)

Unit 2 equipment that is required to be operable will be verified operable in accordance with the requirements presented in Appendix A.

D. Unit 2 Procedures The Unit 2 Procedures used to demonstrate operability of required systems are listed below:

NUMBER TITLE FREQUENCY OST 2.36.7 Offsite to Onsite Power Distribution W System Breaker Alignment Verification OST 2.36.8 AC Power Source Weekly Breaker Alignment W Verification OST 2.36.9 AC Power Breaker Alignment Verification W During Shutdown OST 2.30.2 Service Water Pump (2SWS*P21A] Test M (STB)

OST 2.30.3 Service Water Pump (2SWS*P21B] Test M (STB)

OST 2.30.6 Service Water Pump (2SWS*P21C] Test M -

OST 2.44A.2 Control Room Ventilation System Test - M Train A OST 2.44A.3 control Room Ventilation System Test - M Train B OST 2.39.1A Weekly Station Battery Check, Battery W No. 2-1 OST 2.39.1B Weekly Station Battery Check, Battery W No. 2-2 OST 2.36.1 Emergency Diesel Generator (2EGS*EG2-1] M (STB)

Monthly Test OST 2.36.2 Emergency Diesel Generator (2EGS*EG2-2] M (STB)

Monthly Test E. Unit 1 Emergency Operating Procedure Rcquirements No special Emergency Operating Procedure (EOP) changes will be required during the period when the Unit 1 CREVS is out of service.

ATTACHMENT 1 (cont.)

II. CONTROL ROOM HABITABILITY (cont.)

After the Unit 1 CREVS modifications are complete, the Unit 1 EOP's will be revised to include a step to verify that one emergency ventilation fan is running 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> after initiation of the Control Room Emergency Bottled Air Pressurization System (CREBAPS).

F. Control Room Pressure Boundary Management Administrative controls will be established to maintain the integrity of the control room pressure boundary.

III. SECURITY MEASURES i

Physical protection of applicable Unit 2 areas will be provided in I accordance with the Beaver Valley Power Station Physical Security Plan which applies to both Unit 1 and Unit 2.

IV. FIRE PROTECTION MEASURES Fire protection will be provided for those systems or portions of systems that are required to be operable.

j

Appendix A 3/4.7 PLANT SYSTEMS 3/4.7 4 SERVICE WATER SYSTEM (SWS)

LIMITING CONDITION FOR OPERATION 3.7.4.1 At least two service water subsystems supplying safety related equipment shall be OPERABLE.

APPLICABILITY: MODES 1, 2, 3, and 4.

ACTION: With less than two SWS subsystems OPERABLE, restore at least two subsystems to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIREMENTS 4.7.4.1 At least two SWS subsystems shall be demonstrated OPERABLE:

a. Verify that each pump develops the required differential pressure and tiow rate when tested in accordance with the requirements of Section 4.0.5.
b. At least once per 31 days by verifying that each valve (manual, power operated, or automatic) servicing safety related equipment that is not locked, sealed, or otherwise secured in position, is in its correct position.
c. At least once per 18 months during shutdown, by cycling each power operated valve servicing safety related equipment that is not testable during plant operation, through at least one complete cycle of full travel.

"This specification applies to the components, systems or portions of systems identified in the Cor*rol room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and,4".

. 3/4 7 PLANT SYSTEMS 3/4.7.7 CONTROL ROOM EMERGENCY HABITABILITY SYSTEMS LIMITING CONDITION FOR OPERATION 3.7.7.1 The following control room emergency habitability systems shall be OPERABLE:

a. The emergency ventilation system, and
b. The bottled air pressurization system.

APPLICABILITY: MODES 1, 2, 3, and 4.

ACTION: With one control room emergency habitability system inoperable, restore the system to OPERABLE status within 7 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

SURVEILLANCE REQUIREMENTS 4.7.7.1 The emergency ventilation system shall be demonstrated OPERABLE:

a. At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying that the control room air temperature is less than or equal to 104*F.
b. At least once per 31 days by initiating flow through the HEPA filter and charcoal adsorber train and verifying that the train operates for 15 minutes,
c. At least once per 12 months and (1) after each complete or partial replacement of a HEPA filter or charcoal adsorber bank, or (2) after any structural maintenance on the HEPA filter or charcoal adsorber housings, or (3) following painting, fire, or chemical release in the vicinity of the control room outside air intake while tbo system is operating by:

1

1. Verifying that the charcoal adsorbers remove 1 99.95%

of a halogenated hydrocarbon refrigerant test gas when they are tested in-place in accordance with ANSI N510-1980 while operating the ventilation system at a flow rate of 800 - 1000 CFM i 10%.

2. Verifying that the HEPA filter banks remove 1 99.95% of the DOP when they are tested in-place in accordance with ANSI N510-1980 while operating the ventilation system at a flow rate of 800 - 1000 CFM i 10%.

"This specification applies to the components, systems,or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4". .

3/4.7 PLANT SYSTEMS 3/4.7.7 CONTROL ROOM EMERGENCY HABITABILITY SYSTEMS SURVEILLANCE REQUIREMENTS

3. Subjecting the carbon contained in at least one test canister or at least two carbon samples removed from one of the charcoal adsorbers to a laboratory carbon sample analysis and verifying a removal efficiency of 1 99% for radioactive methyl iodide at an air flow velocity of 0.7 ft/sec i 20% wigh an inlet methyl iodide concentration of 1.5 to 2.0 mg/m , 95% relative humidity, and 1176*F; other test conditions shall be in accordance with USAEC RDT Standard M-16-lT, June 1972. The carbon samples not obtained from test canisters shall be prepared by either:

a) Emptying one entire bed from a removed adsorber tray, mixing the absorbent thoroughly, and obtaining samples at least two inches in diameter and with a length equal to the thickness of the bed, or b) Emptying a longitudinal sample from an adsorber tray, mixing the adsorbent thoroughly, and obtaining samples at least two inches in diameter and with a length equal to the thickness of the bed.

4. Verifying a system flow rate of 800 - 1000 cfm i 10 percent during system operation.
d. At least once per 18 months by:
1. Verifying that the pressure drop across the combined HEPA filters and charcoal adsorber banks is less than 5.6 inches Water Gauge while operating the ventilation system at a flow rate of 800 - 1000 cfm i 10 percent.
2. Verifying that on a containment isolation signal, the system automatically starts in 60 minutes and supplies air to the control room through the HEPA filters and charcoal adsorber banks. ,
3. Verifying that the system maintains the control room at a positive pressure of greater than or equal to 1/8 inch Water Gauge relative to the outside atmosphere during system operation.

4.7.7.2 The bottled air pressurization system shall be demonstrated OPERABLE:

a. At least once per 31 days by verifying that the system contains a minimum of 10 bottles of air, each pressurized to at least 1825 psig.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

, '3/4.7 PLANT SYSTEMS 3/4.7.7 CONTROL ROOM EMERGENCY HABITABILITY SYSTEMS 4.7.7.2, (Cont'd) .

b. At least once per 18 months by verifying that the system will supply at least 800 cfm of air to maintain the control room at a positive pressure of greater than or equal to 1/8 inch Water Gauge rel'ative to the outside atmosphere during system operation.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

V 3/4.7 PLANT SYSTEMS

' 3/4.7.14 FIRE SUPPRESSION SYSTEMS FIRE SUPPRESSION WATER SYSTEM LIMITING CONDITION FOR OPERATION i

3.7.14.1 The fire suppression water system shall be OPERABLE

, with:

a. An OPERABLE flow path capable of taking suction from the Ohio River and transferring the water through distribution piping with OPERABLE sectionalizing control or isolation valves to the yard hydrant curb valves and the first valve ahead of-the water flow alarm device on each sprinkler, hose standpipe, or spray system riser required to be OPERABLE per Specifications 3.7.14.2 and 3.7.14.4.
b. The booster fire pump, with a capacity of 625 gym able to align its discharge to Unit 2 hose rack stations in the safety-related equipment areas.
c. An OPERABLE flow path capable of taking suction from the Service Water System and transferring the water through distribution piping to the first valve ahead of the water flow alarm device on each hose standpipe required to be OPERABLE per Specification 3.7.14.4.

APPLICABILITY: At all times.

ACTION: a. With the booster fire pump inoperable verify the operability of two 2500 gpm pumps, and restore the inoperable equipment to OPERABLE status within 7 days or, prepare and submit a Special Report to the Commission pursuant to Specification 6.9.2 within the next 30 days outlining the plans and procedures to be used to provide for the loss of redundancy in this ~

system. The provisions of Specifications 3.0.3 and 3.0.4 are not applicable.

i "This specification applies to the components, l

systems or portions of systems identified in i the Control room Habitability Implementation l

Program (CHIP) when BV-1 is in Modes 1, 2, 3 i and 4".

4

. 3/4.7 PLANT SYSTEMS 3/4.7.14 FIRE SUPPRESSION SYSTEMS - FIRE SUPPRESSION WATER SYSTEM LIMITING CONDITION FOR OPERATION

b. With the fire suppression water system otherwise inoperable:

+

1. Establish a backup fire suppression water system within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and,
2. Submit a special Report in accordance with Specification 6.9.2:

a) By telephone with 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, b) Confirmed by telegraph, mailgram or facsimile transmission no later than the first working day following the event, and c) In writing within 14 days following the event, outlining the action taken, the cause of the inoperability, and the plans and schedule for restoring the system to OPERABLE status.

SURVEILLANCE REQUIREMENTS 4.7.14.1.1 The fire suppression water system shall be demonstrated OPERABLE:

a. At least once per 31 days by starting the booster fire pump and operating it for at least 15 minutes.
b. At least once per 31 days by verifying that each valve

'(manual, power operated, or automatic) in the flow path is in its correct position.

c. At least once per 12 months by performance of a system flush to be performed in conjunction with the Unit 1 system flush, .

(Unit 1 Technical Specification Surveillance Requirement 4.7.14.1.1.c).

d. At least once per 12 months by cycling each testable valve in the flow path through at least one complete cycle of full travel.
e. At least once per 18 months by:
1. Verifying that the booster fire pump develops at least 625 gpm at a system head of 250 feet, "This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3

. and 4".

.3/4.7 PLANT SYSTEMS

~

3/4.7.14 FIRE SUPPRESSION SYSTEMS FIRE SUPPRESSION WATER SYSTEM SURVEILLANCE REQUIREMENTS

2. Cycling each valve in the flow path that is not testable during plant operation through at least one complete cycle of full travel, and
f. At least once per 3 years by performing a flow test of the system in accordance with Chapter 8, Section 16 of the Fire Protection Handbook, 15th Edition, published by the National Fire Protection Association.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

3 -

a

. 3/4.7 PLANT SYSTEMS 3/4.7.14 FIRE SUPPRESSION SYSTEMS - SPRAY SYSTEMS LIMITING CONDITION FOR OPERATION 3.7.14.2 The following spray systems shall be OPERABLE:

a. Auxiliary Feed Pumps; 2FWS*P22, P23A&B, Safeguards Building.
b. Component Cooling Pumps; 2CCP*P21A,B, and C, Auxiliary Building.
c. Residual Heat Removal Pumps; 2RHS*P21A and B, Reactor Containment.*
d. Charcoal Filters; 2HVS*FLTA 205A and B, 208A and B, Auxiliary Building.

APPLICABILITY: Whenever equipment protected by the spray system is required to be OPERABLE.

ACTION:

a. Wi*.h one or more of the above required spray systems inoperable, within one hour establish a roving fire watch with backup fire suppression equipment for those areas in which redundant systems

'or components could be damaged, such that the area is checked hourly when the system has to be operable. Restore the system to OPERABLE status within 14 days or, prepare and submit a Special' Report to the Commission pursuant to Specification 6.9.2 within the next 30 days outlining the action taken, the cause of the inoperability and the plans and schedule for restoring the system to OPERABLE status,

b. The provisions of specification 3.0.3 and 3.0.4 are not applicable.

SURVEILLANCE REQUIREMENTS 4.7.14.2 Each of the above required spray systems shall be demonstrated OPERABLE:

j a. At least once per 31 days by verifying that each valve (manual,

! power operated, or automatic) in the flow path accessible during plant operation is in its correct position.

! b. At least once per 12 months by cycling each testable valve in the flow path through at least one complete cycle of full travel.

"This specification applies to the components, l systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 l.

and 4".

I

s s-

. 3/4.7 PLANT SYSTEMS 3/4.7.14 FIRE SUPPRESSION SYSTEMS SPRAY CYSTEMS SURVEILLANCE REQUIREMENTS .

c. At least once per 18 months:
1. By performing a system functional test which includes simulated automatic actuation of the system, and:

a) Verifying that the automatic valves in the flow path actuate to their correct positions on a manual test l signal, and 1

b) Cycling each valve in the flow path that is not testable during plant operation through at least one complete cycle of full travel.

4 2. By a visual inspection of the dry pipe spray headers to verify their integrity, and

3. By a visual inspection of each nozzle's spray area to verify 4 the spray pattern is not obstructed.
d. At least once per 3 years by performing an airflow test through each open head spray header and verifying each open head spray nozzle is unobstructed.

2 "This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

I i

~9 --

-<-c -e .,--y.v.-- - - - - , - - , - , - ---.---,,--,-ny. .m,,4,m-.

3/4 7 PLANT SYSTEMS ,

3/4.7.14 FIRE SUPPRESSION SYSTEMS LOW PRESSURE CO2 SYSTEM LIMITING CONDITION FOR OPERATION 3.7.14.3 The 10 ton low pressure CO system serving the following areas shallbeOPERABbEwithaminimumlevel of 91 percent and a minimum pressure of 275 psig in the associated storage tank.

a. Cable Spreading Area (Control Building 725'6")
b. Instrumentation and Relay Room (Control Building 707'6")

' c. Relay Room (Cable Vault 755'6")

d. Emergency Diesel Generator Room (Orange, Purple)
e. Cable Tunnel Between Control and Auxilir y Buildings (712'6")
f. Cable Vault and Rod Control Areas (735'6" West, 735'6" East, 755'6)
g. Cable Spreading Area (Service Building 745'6") ,

APPLICABILITY:

Whenever equipment in the low pressure CO2 protected areas is required to be OPERABLE.

ACTION:

a. With the above required low pressure C07 system inoperable, establish a continuous fire watch wIth backup fire suppression equipment for the unprotected area (s) within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />; restore the system to OPERABLE status within 14 days or, prepare and submit a Special Report to the
  • Commission pursuant to Specification 6.9.2 within the next 30 days outlining the action taken, the cause of the inoperability and the plans and schedule for restoring the system to OPERABLE status.

i

b. The provisions of Specification 3.0.3 and 3.0.4 are not applicable.

l l "This specification applies to the components,

, systems or portions of systems identified in

! the Control room Habitability Implementation l Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

P I

t

. 3/4.7 PLANT SYSTEMS

~

3/4.7.14 FIRE SUPPRESSION SYSTEMS LOW PRESSURE CO2 SYSTEM SURVEILLANCE REQUIREMENTS . . . . ,

4.7.14.3 The above required low pressure CO2 system shall be demonstrated OPERABLE:

a. At least once per 7 days by verifying CO2 storage tank level and pressure, and
b. At least once per 18 months by verifying:
1. The system valves and associated ventilation dampers actuate manually and automatically, upon receipt of a simulated actuation signal, and ,

! 2. Flow from each nozzle during a." Puff Test".

1

?

k l

b i

"This specification applies to the components, systems or portions of systems identified in the control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

I

1. .. .- .

. 3/4.7 PLANT SYSTEMS 3/4.7.14 FIRE SUPPRESSION SYSTEMS FIRE HOSE STATIONS LIMITING CONDITION FOR OPERATION 3.7.14.4 The fire hose stations shown in Table 3.7-5 shall be OPERABLE.

APPLICABILITY:

! Whenever equipment in the areas protected by the fire hose stations is required to be OPERABLE.

ACTION:

a. With one or more of the fire hose stations shown in Table 3.7-5 inoperable, route an additional equivalent capacity fire hose to the unprotected area (s) from an OPERABLE hose station within one hour (4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for containment hose stations) if the inoperable fire hose is the primary means of fire suppression; otherwise, route the additional hose within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Restore the fire hose station to OPERABLE status within 14 days or submit a Special Report to the Commission pursuant to specification 6.9.2 within the next 30 days, outlining the action taken, the cause of the inoperability, and plans and schedule for restoring the station to OPERABLE status.
b. The provisions of Specifications 3.0.3 and 3.0.4 are not applicable.

SURVEILLANCE REQUIREMENTS _ _ _ _ - _ _ . _ _ _ _ _ - - _ -

4.7.14.4 Each of the above required fire hose stations shall be demonstrated OPERABLE:

~

a. At least once per 31 days by visual inspection of the fire hose stations accessible during plant operation to assure all required equipment is at the station.
b. At least one per 18 months by:
1. Visual inspection of the stations not accessible during plant operations to assure all required equipment is at the station.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

. 3/4.7 PLANT SYSTEMS 3/4.7.14 FIRE SUPPRESSION SYSTEMS LIMITING CONDITION FOR OPERATION _

4.7.14.4 (Cont'd)

2. Removing the hose for inspection and re-racking, and
3. Inspecting all gaskets and replacing any degraded gaskets in the couplings.
c. At least one per 3 years by:
1. Partially opening each hose station valve to verify valve OPERABILITY and no flow blockage.

i 2. Conducting a hose hydrostatic test at a pressure at least 50 psig above maximum fire main operating pressure.

l l "This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

l

TABLE 3.'7-5 FIRE HOSE STATIONS Isolating Hose Rack Location Valve No. Elevation Number Decon Bldg 182 735' 6" 201 Fuel Bldg 181 752' 5" 202 Fuel Bldg 180 752' 5" 203 Fuel Bldg 179 735' 6" 204 Diesel 2-2 Bldg 523 732' 6" 205 Diesel 2-1 Bldg 526 732' 6" 206 Cable Vault /Contig Area 566 718' 6" 207 Cable Vault /Contig Area 568 718' 6" 208 Cable Vault /Contig Area 558 735' 6" 209 Cable Vault /contig Area 564 735' 6" 210 Cable Vault /Contig Area 560 755' 6" 211 Cable Vault /contig Area 562 755' 6" 212 Cable Vault /Contig Area 570 773' 6" 213 Service Bldg 138 780' 6" 214 Service Bldg 137 760' 6" 215 Service Bldg 135 760' 6" 216 Service Bldg 139 745' 6" 217 Service Bldg 142 745' 6" 218 Service Bldg 144 730' 6" 219 Service Bldg 146 730' 6" 220 Auxiliary Bldg 195 710' 6" 241 Auxiliary Bldg 199 773' 6" 242 Auxiliary Bldg 316 755' 6" 243 3/4 7-39

1 TABLE 3.7-5 FIRE HOSE STATIONS (CONT'D.)

Isolating .

Hose Rack Location Valve No. Elevation Number Auxiliary Bldg 317 735' 6" 244 Auxiliary Bldg 320 718' 6" 245 Auxiliary Bldg 324 773' 6" 246 Auxiliary Bldg 325 755' 6" 247 Auxiliary Bldg 326 735' 6" 248 Auxiliary Bldg 327 718' 6" 249 Auxiliary Bldg 331 773' 6" 250 Auxiliary Bldg 332 755' 6" 251 Auxiliary Bldg 333 735' 6" 252 Auxiliary Bldg 340 718' 6" 253 containment 772 735' 6" 258 Containment 774 735' 6" 259 Containment 770 735' 6" 260 Containment 777 717' 0" 261 Containment 779- 717' 0" 262 Containment 776 717' 0" 263 _

Containment 783 692' 11" 264 Containment 785 '392' 11" 265 Containment 781 692' 11" 266 Containment 764 767' 10" 267 Containment 766 767' 10" 268 Containment 768 767' 10" 269 Auxiliary Bldg 577 712' 6" 270

TABLE 3.7-5 FIRE HOSE STATIONS (CONT'D.)

Isolating Hose Rack Location Valve No. Elevation Number Auxiliary Bldg 579 712' 6" 271 Cable Tunnel 575 735' 6" 272 Relay Room 573 735' 6" 273 control Bldg 549 7256" 274 Control Bldg 551 725' 6" 275 Control Bldg 553 712' 10" 276 Control Bldg 555 707' 6" 277 Control Bldg 545 712' 6" 278 Safeguards. Area 516 737' 6" 287 Safeguards Area 514 737' 6" 288 Safeguards Area 518 718' 6" 289 Safeguards Area 512 718' 6" 290

=

-3 -. .- , ...y.. -_7, ,mr--- -

y - - ,ey - **

o ,

. 3/4.7 PLANT SYSTEMS

-3/4.7.14 FIRE SUPPRESSION SYSTEMS HALON SYSTEMS LIMITING CONDITION FOR OPERATION 3.7.14.5 The following Halon systems shall be OPERABLE:

a. Control Building Computer Room
b. Cdntrol Building West Communications Room APPLICABILITY: Whenever equipment protected by the Halon system is required to be OPERABLE.

ACTION: a. With one or more of the above required Halon systems inoperable, within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> establish a continuous fire watch with backup fire suppression equipment for those areas in which redundant systems or components could be damaged. Restore the system to OPERABLE STATUS within 14 days or, prepare and submit a Special Report to the Commission pursuant to Specification 6.9.2, within the l next 30 days outlining the action taken, the cause of the inoperability and the plans and schedule for restoring the system ot OPERABLE status,

b. The provisions of Specifications 3.0.3 and 3.0.4 are not applicable. <

SURVEILLANCE REQUIREMENTS 4.7.14.5 Each of the above required Halon systems shall be demonstrated OPERABLE:

a. At least once per 31 days by verifying that each valve (manual, power operated, or automatic) in the flow path is in its correct position.

L

b. At least once per 6 months by verifying Halon storage tank -

, weight to be at least 95% of full charge weight (or level) and pressure to be at least 90% of full charge pressure.

l c. At least once per 18 months by:

I

l. Verifying the system, including the associated ,
ventilation dampers and fire door release mechanisms, i actuate manually and automatically upon receipt of a l simulated actuation signal.

I i

"This specification applies to the components, systems or portions of systems identified in I

the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 l and 4".

t T 8~ '

^r' " ~ ~

' ' ' " ' ~ ~ * " ' " ' ' ' ' " ' ' ' " " " ' ' ' ' ' ' " " ' ' ' ' ' '

~ " ~ ~ ' " ' ' " " " ' * ' ^

3/4.7 PLANT SYSTEMS 3/4.7.14 FIRE SUPPRESSION SYSTEMS HALON SYSTEMS LIMITING CONDITION FOR OPERATION

2. Visually inspect each header and nozzle to verify their integrity.
d. At least once per 36 months by performance of a flow test through headers and nozzles to assure no blockage.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

. 3/4.7- PLANT SYSTEMS 3/4.7.15 FIRE RATED ASSEMBLIES LIMITING CONDITION FOR OPERATION 3.7.15 All fire rated assemblies (walls, floor / ceilings, cable tray enclosures and other fire barriers) separating safety related fire areas or separating portions of redundant systems important to safe shutdown within a fire area and all sealing devices, in fire rated assembly penetrations (fire doors, fire windows, fire dampers, cable and piping penetration seals and ventilation seals) shall be OPERABLE.

APPLICABILITY: At all times.

ACTION:

a. With one or more of the above required fire rated assemblies and/or sealing devices inoperable, within one hour either establish a continuous fire watch on at least one side of the affected assembly, or verify the OPERABILITY of fire detectors on at least one side of the inoperable assembly and establish an hourly fire watch patrol until the functional capability of the barrier is restored. Restore the inoperable fire rated assembly and sealing device to OPERABLE status within 7 days, or prepare i and submit a Special Report to the Commission pursuant to Specification 6.9.2 within the next 30 days outlining the action taken, the cause of inoperability and the plans and schedule for restoring to OPERABLE status.

l b. The provisions of Specifications 3.0.3 and 3.0.4 are not applicable.

SURVEILLANCE REQUIREMENTS 4.7.15.1 At' least once per 18 months the above required fire rated F assemblies and penetration sealing devices shall be verified OPERABLE by: j

a. Performing a visual inspection of the exposed surfaces of each fire rated assembly,
b. Performing a visual inspection of each fire window / fire damper and associated hardware.

"This specification applies to the components, systems or portions of systems iden'tified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

  • 3/4.7 PLANT SYSTEMS

'3/4.7.15 FIRE RATED ASSEMBLIES SURVEILLANCE REQUIREMENTS

c. Performing a visual inspection of at'least 10 percent of each type of sealed penetration. If apparent changes in appearance or abnormal degradations are found, a visual inspection of an additional 10 percent of each type of sealed penetration shall be made. This inspection process shall continue until a 10 percent sample with no apparent changes in appearance or abnormal degradation is found.

4.7.15.2 Each of the above required fire doors

  • shall be verified OPERABLE by inspecting- the automatic hold open, release and closing mechanism and latches at least once per 6 months, and by verifying:

i

a. The position of each closed fire door at least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
b. That doors with automatic holdopen and release mechanisms are free of obstructions at least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
  • Security alarm fire doors are not included in the above j surveillance requirements, since they are checked per security

! requirements.

1 "This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 l and 4".

~ . - _

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES OPERATING LIMITING CONDITION FOR OPERATION 3.8.1.1 As a minimum, the following A.C. electrical power sources shall be OPERABLE: ,

a. Two physically independent circuits between the offsite transmission network and the onsite Class lE distribution system, and
b. Two separate and independent diesel generators each with:
1. A separate day tank containing a minimum of 222 gallons of fuel,
2. A separate fuel storage system containing a minimum of 53,225 gallons of fuel, and
3. A separate fuel transfer pump.

APPLICABILITY: MODEC 1, 2, 3, and 4.

ACTION:

a. With either an offsite circuit or diesel generator of the i above required A.C. electrical power sources inoperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.a.5 within one hour and at least once per 8 hcurs thereafter; restore at least two offsite circuits and two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
b. With one offsite circuit and one diesel generator of the '
above required A.C. electrical power sources incperable, demonstrate the OPERABILITY of the remaining A.C. sources by performing Surveillance Requirements 4.8.1.1.1.a and 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter; restore at least one of the inoperable sources

! to OPERABLE status within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Restore at least two offsite l circuits and two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from the time of initial loss or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

l .

-,, ,-----n- . - - .- . . - . , , - . . -

  • 3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C.' SOURCES LIMITING CONDITION FOR OPERATION
c. With two of. the above required offiste- A.C. circuits the OPERABILITY of two diesel inoperable, demonstrate generators by performing Surveillance Requirement 4.8.1.1.2.a.5 within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, unless the diesel generators are already operating; restore at least one of the inoperable offsite sources to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY within the next 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. With only one offsite source restored, restore at least two offsite circuits to OPERABLE status within.72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss or be in COLD SHUTDOWN within the next-36 hours,
d. With two of the above required diesel generators inoperable, demonstrate the OPERABILITY of two offsite A.C. circuits by performing Surveillance Requirement 4.8.1.1.1.a within one hour and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter, restore at i least one of the inoperable diesel generators to OPERABLE

, status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. Restore at least two diesel generators to OPERABLE status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> from time of initial loss or be in COLD SHUTDOWN within the next 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

SURVEILLANCE REQUIREMENTS 4.8.1.1 Two physically independent circuits between the offsite transmission network and the onsite Class lE distribution system shall be:

j

! a. Determined OPERABLE at least once per 7 days by verifying I correct breaker alignment, indicated power availability, and 1

j b. Demonstrated OPERABLE at least once per 18 months by ,

transferring (manually and automatically) unit power supply from the unit circuit to the system circuit.

4.8.1.1.2 Each diesel generator shall be demonstrated OPERABLE:

a. At least once per-31 days on a STAGGERED TEST BASIS by:
1. Verifying the fuel level in the day tank, "This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation l

Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES SURVEILLANCE REQUIREMENTS

~

2. Verifying the fuel level in the fuel storage tank,
3. Verifying that a sample of diesel fuel from the fuel storage tank is within the acceptable limits specified in Table 1 of ASTM D975-68 when checked for viscosity, water and sediment,
4. Verifying the fuel transfer pump can be started and transfers fuel from the storage system to the day tank,
5. Verifying the diesel starts from ambient condition,
6. Verifying the generator is synchronized, loaded to greater than or equal to 2,268 kW and operates for greater than or equal to 60 minutes, and
7. Verifying the diesel generator is aligned to provide standby power to the associated emergency busses,
b. At least once per 18 months during shutdown by:
1. Subjecting the diesel to an inspection in accordance with procedures prepared in conjunction with it's manufacturer's recommendations- for this class of standby service,
2. Verifying the generator capability to reject a load of greater than or equal to 825 kW (largest single emergency load, a standby service water pump) without tripping,
3. Simulating a loss of offsite power in conjunction with a safety injection signal, and:
a. Verifying de-energization of the emergency busses -

and load shedding from the emergency busses,

b. Verifying the diesel starts from ambient condition l

on the auto-start signal, energizes the emergency busses with permanently connected loads, energizes l

the auto-connected emergency loads through the load sequencer and operates for greater than or equal to 5 minutes while its generator is loaded with the emergency loads.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.1 A.C. SOURCES SURVEILLANCE REQUIREMENTS .

4. Verifying that on a loss of power to the emergency busses, all diesel generator trips, except engine overspeed, generator differential and overcurrent, are automatically disabled,
5. Verifying the diesel generator operates for 1 60 minutes while loaded to 1 4,238 kW,
6. Verifying that the auto-connected loads to each diesel

. generator do not exceed the 2000 hour rating of 4,535kW,

7. Verifying that the automatic load sequence timer is OPERABLE with each load sequence time within i 10 percent of its required value.

i I

"This specification applies to the components, systems or portions of systems identified in

! the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3

! and 4".

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.2 ONSITE POWER DISTRIBUTION SYSTEMS A.C. DISTRIBUTION - OPERATING LIMITING CONDITION FOR OPERATION .

3.8.2.1 The following A.C. electrical busses shall be OPERABLE and

. energized from sources of power other than the diesel generators with tie breakers open between redundant busses:

E 4160 volt Emergency Bus #2AE and 480 volt Emergency Bus #2N 4160 volt Emergency Bus #2DF and 480 volt Emergency Bus #2P 120 volt A.C. Vital Bus #I 120 volt A.C. Vital Bus #II 120 volt A.C. Vital Bus #III 120 volt A.C. Vital Bus #IV APPLICABILITY: MODES 1, 2, 3, and 4.

ACTION:

With less than the above complement of A.C. busses OPERABLE, restore the inoperable bus to OPERABLE status within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

4 1

SURVEILLANCE REQUIREMENTS .

I

! 4.8.2.1 The specified A.C. busses shall be determined OPERABLE and energized from A.C. sources other than the diesel generators at least once per 7 days by verifying correct breaker alignment and indicated power availability.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

m l

-- - -. -.- . . - . -. - - - _ . - - - . - . - . - - . ~ . _ _ - . .-

~

3'/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.2 ONSITE POWER DISTRIBUTION SYSTEMS D.C. DISTRIBUTION - OPERATING LIMITING CONDITION FOR OPERATION

~

3.8.2.3 The following D.C. bus trains shall be energized and OPERABLE.

TRAIN "A" (orange) consisting of 125-volt D.C. busses No. 2-1 &

2-3, 125-volt D.C. battery banks 2-1 & 2-3 & charger 2-1 & inverter 2-3.

TRAIN "B" (purple) consisting of 125-volt D.C. busses No. 2-2 &

2-4, 125-volt D.C. . battery banks 2-2 & 2-4 & charger 2-2 & inverter 2-4.

APPLICABILITY: MODES 1, 2, 3, and 4.

ACTION: a. With one of the required battery banks inoperable, restore the inoperable battery bank to OPERABLE status within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />,

b. With one of the required full capacity chargers inoperable, demonstrate the OPERABILITY of its asociated battery bank by performing Surveillance Requirement 4.8.2.3.2.a.1 within one hour, and at least once per 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> thereafter. If any category A limit in Table 3.8-1 is not met, declare the battery inoperable.

SURVEILLANCE REQUIREMENTS 4.8.2.3.1 Each D.C. bus train shall be determined OPERABLE and energized at least once per 7 days by verifying correct breaker alignment and indicated power availability.

4.8.2.3.2 Each 125-volt battery bank and charger shall be demonstrated OPERABLE:

a. At least once per 7 days by verifying that:
1. The parameters in Table 3.8-1 meet the Category A limits, and
2. The total' battery terminal voltage is greater than or equal to 127.8 - volts on float charge.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

l

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.2 ONSITE POWER DISTRIBUTION SYS'TEMS D.C. DISTRIBUTION - OPERATING SURVEILLANCE REQUIREMENTS

b. At least once per 92 days and within 7 days after a battery discharge with battery terminal voltage below 110 - volts, or battery overcharge with battery terminal voltage above 150 - volts, by verifying that:
1. The parameters in Table 3.8-1 meet the Category B limits.
2. There is no visible corrosion at either terminals or connectors, or the co islessthan150x10-gnectionresistanceoftheseitems ohms, and 4
3. The average electrolyte temperature of every tenth cell of connected cells is above 60*F.
c. At least once per 18 months by verifying that:
1. The cells, cell plates, and battery racks show no visual indication of physical damage or abnormal deterioration,
2. The cell-to-cell and terminal connections are clean, tight, and coated with anti-corrosion material,
3. The resistance of each cell-to-cell and terminag connection is less than or equal to 150 x 10-ohms; and
4. The battery charger will supply at least (100) amperes at 140-volts for at least (4) hours.
d. At least once per 18 months, during shutdown, by verifying that the battery capacity is adequate to supply and maintain .

in OPERABLE status all of the actual or simulated emergency loads for the 2-hour design duty cycle when the battery is subjected to a battery service test.

e. At least once per 60 months, during shutdown, by verifying that the battery capacity is at least 80 percent of the manufacturer's rating when subjected to a performance

! discharge test. Once per 60 month interval, this performance discharge test may be performed in lieu of the battery service test.

"This specification applies to the components, i systems or portions of systems identified in .

the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3

(

and 4".

l L ---

F- - - - - -.

3/4.8 ELECTRICAL POWER SYSTEMS 3/4.8.2 ONSITE POWER DISTRIBUTION SYSTEMS D.C. DISTRIBUTION - OPERATING

-SURhEILLANCE REQUIREMENTS

f. At least once per 18 months, during shutdown, performance discharge tests of battery capacity shall be given to any battery that shows signs of degradation or has reached 85 percent of the service life expected for the application.

Degradation is indicated when the battery capacity drops more than 10 percent of rated capacity from its average on previous performance tests, or is below 90 percent of the manufacturer's rating.

i i

l I

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

l L_ _.

TABLE 3.8-1 .

BATTERY SURVEILLANCE REQUIREMENTS

$'dih!!$!!

4 Li. CATEGORY A (1) CATEGORY B (2) -

niiiiii!!!!!Hiini!!!!!!!!!!!EiiNHiiiiiiiiiiiiME;;;;;;;;;;;;;;;;;;;;;;ii 1 Parameter Limits for each designated Limits for each connected Allowable (8) value pilot cell. cell. for each connected '3 cell.

Electrolyte > Minimum level indi- > Minimum level indication Above top of pla,tes, Level cation mark, and i 1/4" mark, and i 1/4" above and not overflowing.

above maximum level maximum level indication indication mark. mark. t Float > 2.13 volts > 2.13 volts (c) > 2,07 volts Voltage Not more that .020 below the average of

> 1.195 all connected cells.

specific > 1.200 (b) Average of all connected Average of all Gravity (a) cells > 1.205 connected cells 1 1.195(b).

(a) Corrected for electrolyte temperature and level.

(b) or battery charging current is less than (2) amps when on charge.

(c) Corrected for average electrolyte temperature.

, (1) For any Category A parameter (s) outside the limit (s) shown, the battery may be considered OPERABLE provided that within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> all the Category B measurements are taken and found to be within their allowable values, and provided all Category A and B parameter (s) are restored to within limits within the next 6 days.

(2) For a'ny Category B parameter (s) outside the limit (s) shown, the battery may be considered OPERABLE provided that the Category B parameters are within their allowable values and provided the Category B parameter (s) are restored to within limits within 7 days.

(3) Any Category B parameter not within its allowable value indicates an inoperable battery.

NOTE: Numbers in parentheses assume a manufacturer's recommended full' charge specific gravity of' 1.215.

"This specification applies to the components, systems or portions of systems identified in the Control room Habitability Implementation Program (CHIP) when BV-1 is in Modes 1, 2, 3 and 4".

OVERSIZE DOCUMENT PAGE PULLED SEE APERTURE CARDS NUMBER OF OVERSIZE PAGES FILMED ON APERTURE CARDS -LW APERTURE CARD /HARD COPY AVAILABLE FROM RECORD SERVICES BRANCH,TIDC FTs 4sa-sess 1

4

--'=wtt- = we e>* w ee - m w w m-e =r. - w .--~e---