Similar Documents at Fermi |
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217N4261999-10-25025 October 1999 Forwards Amend 17 to License DPR-9 & Safety Evaluation. Amend Revises TS by Deleting SR D.3.c,which Required Weekly Observation of Nitrogen Cover Gas Pressure within Sodium Storage Tanks Located in Sodium Building NRC-99-0085, Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl1999-10-22022 October 1999 Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl NRC-99-0094, Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed1999-10-22022 October 1999 Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed ML20217P1661999-10-21021 October 1999 Forwards Insp Rept 50-341/99-17 on 990927-1005.No Violations Noted ML20217M0771999-10-19019 October 1999 Confirms Discussion Between GL Shear,M Mitchell,E Kosky, D Williams,B Rumins,D Harmon & W Rutenberg in Public Meeting on 990923.Purpose of Meeting Was to Discuss Current Status RP Program at Enrico Fermi 2 ML20217N9231999-10-15015 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 40 ML20217E5671999-10-14014 October 1999 First Partial Response to FOIA Request for Documents.Records in App a Already Available in Pdr.App B Records Encl & Being Released in Entirety NRC-99-0087, Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons1999-10-12012 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons NRC-99-0083, Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-10-0707 October 1999 Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal ML20217D5331999-10-0707 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 39 ML20217F5931999-10-0707 October 1999 Forwards Insp Rept 50-341/99-11 on 990724-0908.Two Violations Re Failure to Follow Procedures While Sampling Standby Liquid Control Tank & Wear Dosimetry Properly Being Treated as Noncited Violations ML20217B8261999-10-0404 October 1999 Forwards Summary of Decommissioning Insp Plan for Fy 2000. Plan Will Be Updated Annually & May Be Revised at Any Time Based Upon Future Insp Findings,Events & Resource Availability ML20212J8121999-10-0101 October 1999 Discusses Plant,Unit 2 Completion of Licensing Action for GL 98-01 & Suppl 1, Y2K Readiness of Computer Sys at Npps. Ack Efforts That Licensee Have Completed to Date in Preparing Plant for Y2K Transition ML20212K8881999-09-30030 September 1999 Refers to 990928 Meeting Conducted at Fermi Unit 2 to Discuss Initiatives in Risk Area & to Establish Dialog Between SRAs & PSA Staff ML20217A3261999-09-30030 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 38 NRC-99-0091, Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations1999-09-27027 September 1999 Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations ML20212J8331999-09-27027 September 1999 Responds to Licensee 990924 Request That NRC Exercise Discretion Not to Enforce Compliance with Actions Required in TS 3/4.6.1.8.Ltr Documents 990923 Telcon with Util in Which NRC Orally Issued NOED ML20216G9791999-09-24024 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 37 NRC-99-0092, Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys1999-09-24024 September 1999 Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys ML20216H3561999-09-23023 September 1999 Informs That During 990914 Telcon,L Sanders & M Bielby Made Arrangements with NRC to Inspect Licensed Operator Requalification Program at Fermi Nuclear Station for Week of 991129 Which Coincides with Util Regularly Scheduled Exam ML20216H4541999-09-23023 September 1999 Informs That During 990914 Telcon L Sanders & M Bielby Made Arrangements for Administration of Licensing Exams at Fermi Nuclear Station for Week of Jan 31,2000.NRC Will Make Exam Validation Visit to Facility During Week of Jan 10,2000 ML20212F3241999-09-20020 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 36 NRC-99-0081, Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public1999-09-17017 September 1999 Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public ML20217A9421999-09-0909 September 1999 Informs That NRC Plan to Conduct Addl Resident Insps Beyond Core Insp Program Over Next 6 Months to Assess Improvements in Areas of Procedural Compliance & Quality of Work. Historical Listing of Plant Issues Encl NRC-99-0079, Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-09-0808 September 1999 Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20211Q0991999-09-0303 September 1999 Forwards Rev 35 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0090, Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld1999-09-0303 September 1999 Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld NRC-99-0066, Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d)1999-08-30030 August 1999 Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d) ML20211G4951999-08-24024 August 1999 Forwards Rev 34 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0055, Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval1999-08-19019 August 1999 Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval IR 05000341/19990131999-08-19019 August 1999 Discusses Insp Rept 50-341/99-13 & OI Rept 3-98-039 Conducted Into Potential Misconduct of Operator Formerly Employed by De.Nrc Determined That Violation of NRC Regulations Occurred.Synopsis of IO Rept Encl NRC-99-0056, Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation1999-08-19019 August 1999 Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation ML20211C0521999-08-17017 August 1999 Forwards Tables for Sections 3.6 & 3.7 of Draft Safety Evaluation of Proposed Conversion of Current TS to Improved Standard TS NRC-99-0089, Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-08-17017 August 1999 Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20217E6181999-08-13013 August 1999 FOIA Request for Documents Re Implementing Regulations in 10CFR & Requesting That Region III Task Interface Agreement (TIA) Related to Fermi 2 Plant Be Made Available IR 05000341/19990011999-08-10010 August 1999 Forwards Insp Rept 50-341/99-01 on 990619-0723 & Nov. Violation of Concern Because Operators Did Not Understand License Requirements & Placed Plant in Configuration Where EDG 11 Was Removed from Service IR 05000341/19990121999-08-0606 August 1999 Forwards Insp Rept 50-341/99-12 on 990712-0716.No Violations Noted.Insp Focused on Implementation of Plant Chemistry & Radiological Environ Monitoring Programs & Operation of post-accident Sampling Sys ML20211C4761999-08-0606 August 1999 Forwards Draft Safety Evaluation Re Proposed Conversion of Current TS to Improved Standard TS NRC-99-0057, Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS1999-08-0404 August 1999 Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS ML20210N5451999-08-0303 August 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 33 NRC-99-0077, Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS1999-07-26026 July 1999 Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS ML20210J2121999-07-23023 July 1999 Discusses NRC OI Investigation Rept 3-98-039 Completed on 990524 & Forwards Notice of Violation NRC-99-0053, Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl1999-07-15015 July 1999 Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl ML20209H7211999-07-14014 July 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 32 NRC-99-0054, Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal1999-07-13013 July 1999 Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal ML20209F6571999-07-12012 July 1999 Forwards Insp Rept 50-341/99-09 on 990516-0618.No Violations Noted.Weak Procedural Guidance,Communications Issues & Configuration Control Weaknessess Were Evident NRC-99-0052, Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions1999-07-0707 July 1999 Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions ML20196J5511999-07-0202 July 1999 Discusses GL 92-01,Rev 1,Supp 1, Rv Integrity, Issued by NRC on 950519 & DE Responses & 980729 for Fermi 2.Informs That Staff Revised Info in Rvid & Released Info as Rvid Version 2 as Result of Review of Responses ML20209C6141999-07-0101 July 1999 Rev 31 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0076, Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included1999-06-30030 June 1999 Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included 1999-09-09
[Table view] Category:ENGINEERING/CONSTRUCTION/CONSULTING FIRM TO NRC
MONTHYEARML20247P9411989-05-17017 May 1989 FOIA Request for Final Open Item Transmittal Ltrs Per NRC Insp Procedure 94300B for Listed Plants ML20235A1251987-12-16016 December 1987 Forwards Info Re Resource Technical Svcs,Inc,Including Summary of NRC Contract Work,Nrc Form 26 for Three Existing Contracts,Audit Info,Work History & Lists of Expertise Available for Special Insps & of Current Resource Svcs ML20215L9971987-05-0101 May 1987 Forwards Final EGG-NTA-7205, Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components,Enrico Fermi-2, Informal Rept. Plant Conforms to Generic Ltr on Item ML20214R7141987-03-26026 March 1987 Forwards EGG-NTA-7574, Conformance to Generic Ltr 83-28, Item 2.2.2 - Vendor Interface Programs for All Other Safety- Related Components:Fermi-2, Final Informal Rept.Plant Conforms to Generic Ltr on Item ML20214Q2731986-09-11011 September 1986 Provides Results of Author 860903-05 & 09-12 Investigation of Whether Cracks in Base Mat Pose Safety or Operational Hazards.Base Mat Will Safely Carry Design Static & Seismic Loads & Exfiltration of Water to Ground Is Impossible ML20154K3631986-02-26026 February 1986 Forwards Listed Documents Containing Discussions of Embedment Plate Issue,In Response to 860221 Telephone Request.Addl Documents May Be Stored in Warehouse.W/O Encls ML20137P4581986-01-31031 January 1986 Forwards Rept on 860124 Site Visit W/J Kudrick & a Notafrancesco to Meet W/Util Representatives Re Fairbanks Morse Model 38TD8-1/8 Opposed Piston Engines.Statement for Work & Visit Also Encl ML20127M9561985-05-17017 May 1985 Forwards Responses to Re Questions & Comments on Final Idvp Rept ML20127M2791985-05-15015 May 1985 Grants Permission to Microfiche Proprietary Info Submitted in Support of Facility License Application ML20100D7411984-11-30030 November 1984 Forwards Revised Pages to Section 8.0 W/Instruction Sheet for Insertion Into Idvp Final Rept,In Response to 841126 Telcon.Exhibit 8.2.2-1 & Section 8.2.1 Revised to Assign Valid Design Control Observation to Root Cause ML20099E2431984-11-16016 November 1984 Responds to NRC 841105 Request for Info Re Generation of Potential Finding Rept Resulting from Annulus Pressurization Review Question.Cygna Expects NRC & Util to Resolve Annulus Pressurization W/O Addl Idvp Review ML20106D2351984-10-19019 October 1984 Forwards Section 8.0 to Rev 2 to TR-83021-1, Fermi 2 Idvp Final Rept, in Response to Bj Youngblood 840327 Request. Info Re Freezing in RHR Complex Included ML20084C2431984-04-20020 April 1984 Notifies of 840430 Meeting W/Util & NRC at Sargent & Lundy Ofcs to Discuss Idvp Structural Review Activities in Preparation for Response to Item 3 of NRC ML20082F0831983-11-14014 November 1983 Forwards Vol 4 to Idvp, Suppl to Final Rept ML20077F7051983-07-29029 July 1983 Advises That Suppl to Final Rept for Independent Design Verification Program Will Be Provided by 831014.Suppl Based on Util Comments & Specific NRC Comments at 830615 Meeting & in 830617 Telcon.Completion Schedule Encl ML20023B3841983-05-0303 May 1983 Forwards Pages 2.20-2.32 Inadvertently Omitted from Independent Design Verification Program Final Rept. ML20069M0511983-04-29029 April 1983 Forwards Independent Design Verification Program,Final Rept, Vols 1,2 & 3.Rept Presents Results & Conclusions of Review Conducted Per 821216 Independent Design Verification Program Plan ML20076A7011978-11-0101 November 1978 Forwards Errata to Subj Facil FSAR Amend 16 Which Was Recently Submitted to NRC ML20210E0611973-09-24024 September 1973 Forwards Description of Retirement Plan for Facility, Expanding on Plan Submitted w/730119 Ltr.Details Re Disposition of Sodium & Blanket Matls Unknown.Sodium May Be Shipped to Hanford & Blanket Matl to Savannah River ML20210E0061973-01-19019 January 1973 Forwards Retirement Plan for Facility.Early Approval of Proposed Blanket & Sodium Onsite Storage Requested.Fully Detailed Retirement Plan Cannot Be Developed Until Questions Re Blanket & Sodium Storage Settled ML20210D9711972-04-28028 April 1972 Submits Info Re Decommissioning of Facility,Per AEC 720331 Request.Major Activities of Decommissioning Plan Listed. Bases,Schedule & Cost Estimates for Decommissioning Encl 1989-05-17
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARNRC-99-0094, Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed1999-10-22022 October 1999 Forwards Safeguards Event Rept 99-S01-00 for Reportable Event That Occurred on 990922.Commitments Made by Util Listed NRC-99-0085, Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl1999-10-22022 October 1999 Forwards Rev 15 to Fermi 2 Security Personnel Training & Qualification Plan, IAW 10CFR50.54(p)(2).Without Encl ML20217N9231999-10-15015 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 40 NRC-99-0087, Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons1999-10-12012 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-341/99-10.Licensee Contests Subject Violation,Due to Listed Reasons NRC-99-0083, Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal1999-10-0707 October 1999 Submits Requested Response to GL 99-02, Laboratory Testing of Nuclear-Grade Activated Charcoal ML20217D5331999-10-0707 October 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 39 ML20217A3261999-09-30030 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 38 NRC-99-0091, Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations1999-09-27027 September 1999 Forwards NRC Form 536,in Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations ML20216G9791999-09-24024 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 37 NRC-99-0092, Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys1999-09-24024 September 1999 Documents Util Request for Enforcement Discretion with Respect to Requirements of TS 3/4.6.1.8 Re Drywell & Suppression Chamber Purge Sys ML20212F3241999-09-20020 September 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 36 NRC-99-0081, Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public1999-09-17017 September 1999 Submits Eight Relief Requests Associated with Containment Inservice Exam Program for Fermi 2 Plant,Per Provisions of 10CFR50.55a(g)(5)(iv).Requested Relief Does Not Adversely Affect Health & Safety of Public NRC-99-0079, Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-09-0808 September 1999 Forwards Rev 15 to Fermi 2 ITS Submittal,Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev NRC-99-0090, Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld1999-09-0303 September 1999 Forwards Proprietary Operator License Renewal Application, NRC Forms 398 & 396 for SW Burt,License SOP-30199-3. Proprietary Encls Withheld ML20211Q0991999-09-0303 September 1999 Forwards Rev 35 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0066, Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d)1999-08-30030 August 1999 Forwards semi-annual fitness-for-duty Rept for Fermi 2 for Period of 990101-0630,IAW 10CFR26.71(d) ML20211G4951999-08-24024 August 1999 Forwards Rev 34 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0056, Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation1999-08-19019 August 1999 Forwards Rev 2,change 0 to ISI-Nondestructive Exam (ISI-NDE) Program (Plan) for Piping,Components & Integral Attachments, for Second ten-year Interval of Fermi 2 Plant Operation NRC-99-0055, Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval1999-08-19019 August 1999 Forwards Rev 5 to Inservice Testing Program for Pumps & Valves for Fermi 2 Second 10-Year Interval, Per Provisions of 10CFR50.55a(f)(5)(iv).Rev Includes Four Pump Relief Requests & Ten Valve Relief Requests Requiring NRC Approval NRC-99-0089, Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev1999-08-17017 August 1999 Forwards Rev 13 to Fermi 2 ITS Submittal Dtd 980403.Rev Provide Update for Remaining Open Issues Associated with NRC Review of ITS Submittal.Attachment 1 Contains Brief Abstract of Changes Included in Rev ML20217E6181999-08-13013 August 1999 FOIA Request for Documents Re Implementing Regulations in 10CFR & Requesting That Region III Task Interface Agreement (TIA) Related to Fermi 2 Plant Be Made Available NRC-99-0057, Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS1999-08-0404 August 1999 Forwards Rev 12 to ITS 980403 Submittal,Providing Update to Submittal for ITS Section 3.3,including Changes Associated with NRC Review of Rev 6 ITS ML20210N5451999-08-0303 August 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 33 NRC-99-0077, Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS1999-07-26026 July 1999 Forwards Rev 11 to Fermi ITS Submittal,Dtd 980403,providing Update to Submittal for ITS Sections 3.5,3.6 & 3.8.Update Includes Changes Associated with NRC Review of Util Transmittals of Revs 5,5a & 7 to ITS NRC-99-0053, Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl1999-07-15015 July 1999 Forwards Rev 14 to Fermi 2 Security Personnel Training & Qualification Plan, Per 10CFR50.54(p)(2).Changes Do Not Decrease Effectiveness of Plan.Summary of Changes Also Encl ML20209H7211999-07-14014 July 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 32 NRC-99-0054, Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal1999-07-13013 July 1999 Forwards Rev 10 to Fermi 2 ITS Submittal, , Providing Update to Submittal for ITS Section 3.4,RCS.Update Includes Changes Associated with NRC Review of Util Transmittal of Rev 4 to ITS Submittal NRC-99-0052, Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions1999-07-0707 July 1999 Forwards Rev 9 to Fermi 2 ITS Submittal,Dtd 980403. Attachment 1 Contains Brief Abstract of Changes Included in Rev.Attachment 2 Contains Revised Pages for Submittal Along with Rev Instructions ML20209C6141999-07-0101 July 1999 Rev 31 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0049, Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Disclosure Encl1999-06-30030 June 1999 Submits Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. Disclosure Encl NRC-99-0076, Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included1999-06-30030 June 1999 Forwards Rev 8 to ITS Submittal to Provide Update to ITS Submittal for ITS Section 3.7.Brief Abstract of Changes Included ML20209C1081999-06-29029 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section), Rev 30 NRC-99-0050, Forwards Rev 7 to ITS Submittal of 980403,to Provide Remaining Responses to NRC RAIs Re ITS Sections 3.5 & 3.8. Revision Instructions Included1999-06-24024 June 1999 Forwards Rev 7 to ITS Submittal of 980403,to Provide Remaining Responses to NRC RAIs Re ITS Sections 3.5 & 3.8. Revision Instructions Included NRC-99-0075, Forwards Operator License Renewal Application,Nrc Forms 398 & 396 for CR Effan,License SOP-30186-3.Encl Withheld1999-06-22022 June 1999 Forwards Operator License Renewal Application,Nrc Forms 398 & 396 for CR Effan,License SOP-30186-3.Encl Withheld ML20212J3861999-06-18018 June 1999 Forwards Rev 29 to Approved UFSAR LCR That Have Not Been Incorporated Into UFSAR Hardcopy (Sorted by Section) NRC-99-0047, Responds to NRC 990513 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Revised Design Calculation DC-5957, GL 96-06 Calculations, Encl1999-06-0909 June 1999 Responds to NRC 990513 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design- Basis Accident Conditions. Revised Design Calculation DC-5957, GL 96-06 Calculations, Encl ML20195G2001999-06-0808 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 28 ML20195E7391999-06-0303 June 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 27 NRC-99-0046, Forwards Rev 6 to Fermi 2 ITS Submittal ,to Provide Remaining Responses to NRC RAI Re ITS Section 3.3, & Update ITS Submittal to Reflect Responses.Brief Abstract of Changes Contained in Attachment 11999-06-0202 June 1999 Forwards Rev 6 to Fermi 2 ITS Submittal ,to Provide Remaining Responses to NRC RAI Re ITS Section 3.3, & Update ITS Submittal to Reflect Responses.Brief Abstract of Changes Contained in Attachment 1 ML20207D9631999-05-26026 May 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section) ML20195B3381999-05-19019 May 1999 Forwards Rev 25 to Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section) NRC-99-0040, Requests NRC Approval of Revs to Weld Tables of Encl Relief Requests RR-A21,rev 1 & RR-A22,rev 1.Revs Do Not Impact Basis for Original Requests for Relief Because There Is No Change to Technical Basis or Proposed Alternative1999-05-14014 May 1999 Requests NRC Approval of Revs to Weld Tables of Encl Relief Requests RR-A21,rev 1 & RR-A22,rev 1.Revs Do Not Impact Basis for Original Requests for Relief Because There Is No Change to Technical Basis or Proposed Alternative NRC-99-0039, Requests Relief from ASME Section XI Requirement to Examine Essentially 100% of Selected Category B-J Pipe Welds,Per 10CFR50.55a(g)(5)(iii).Relief Request RR-A23,encl1999-05-14014 May 1999 Requests Relief from ASME Section XI Requirement to Examine Essentially 100% of Selected Category B-J Pipe Welds,Per 10CFR50.55a(g)(5)(iii).Relief Request RR-A23,encl NRC-99-0041, Requests Relief from ASME Section XI Requirements to Examine Essentially 100% of Accessible Category B-D Nozzle Welds,Per 10CFR50.55a(g)(5)(iii).Rev 1 to Relief Request RR-A6,encl1999-05-14014 May 1999 Requests Relief from ASME Section XI Requirements to Examine Essentially 100% of Accessible Category B-D Nozzle Welds,Per 10CFR50.55a(g)(5)(iii).Rev 1 to Relief Request RR-A6,encl NRC-99-0038, Requests Relief from ASME Section XI 1980 Requirement to Examine Essentially 100% If Category B-A RPV Shell Weld Lengths,Per 10CFR50.55a(g)(5)(iii)1999-05-14014 May 1999 Requests Relief from ASME Section XI 1980 Requirement to Examine Essentially 100% If Category B-A RPV Shell Weld Lengths,Per 10CFR50.55a(g)(5)(iii) NRC-99-0045, Forwards Rev 5a to Fermi 980403 Submittal,Converting TS to Its.Encl Rev Provides Remaining Responses to NRC RAIs Re ITS Section 3.6 Contained in NRC 990211 Rai.Brief Abstract of Changes & Responses to Rai,Encl1999-05-0707 May 1999 Forwards Rev 5a to Fermi 980403 Submittal,Converting TS to Its.Encl Rev Provides Remaining Responses to NRC RAIs Re ITS Section 3.6 Contained in NRC 990211 Rai.Brief Abstract of Changes & Responses to Rai,Encl NRC-99-0044, Forwards Rev 5 to ITS to Provide Responses to RAI Re ITS Section 3.6 (Except ITS Section 3.6.1.3) Contained in & Update in ITS Submittal to Reflect Responses1999-04-30030 April 1999 Forwards Rev 5 to ITS to Provide Responses to RAI Re ITS Section 3.6 (Except ITS Section 3.6.1.3) Contained in & Update in ITS Submittal to Reflect Responses NRC-99-0059, Provides Notification Required by 10CFR50.82(a)(7) of Changes to Fermi 1 Decommissioning Cost Estimate1999-04-29029 April 1999 Provides Notification Required by 10CFR50.82(a)(7) of Changes to Fermi 1 Decommissioning Cost Estimate ML20206E2941999-04-28028 April 1999 Forwards Approved UFSAR Lcrs That Have Not Been Incorporated Into UFSAR Hardcopy & Approved TRM Lcrs (Sorted by Section), Rev 24 NRC-99-0037, Forwards Rev 9 to Fermi 2 Ufsar,Per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of Changes to QA Program & Vol 1 of Technical Requirements Manual,Encl1999-04-26026 April 1999 Forwards Rev 9 to Fermi 2 Ufsar,Per 10CFR50.71(e) & 10CFR50.4(b)(6).Summary of Changes to QA Program & Vol 1 of Technical Requirements Manual,Encl 1999-09-08
[Table view] |
Text
_ - - - - - - - - - - - - -
U
~
POWER REACTOR DEVEIAPMENT COMPANY A^Z - 2 J SesteeggAgge.g 1911 FIRST STREET DETROIT, MICHIGAN 48226 EXHIBIT 4.5 l
woooWARD besSe September 24, 1973 Mr. L. Manning Muntzing Director of Regulation Office of Regulation U. S. Atomic Energy Coundesion Washington, D. C. 20545
Dear Mr. Huntzing:
Enclosed is a document describing the retirement program for the Fermi 1 facility. It is essentially an update and expansion of a similar document sent to you by letter dated January 19, 1973, before receipt of Mr. Skovholt's letter of January 22, 1973 prohibiting the permanent on-site storage of the blanket and radioactive sodium. which had previo; sly been contemplated by PRDC and which was reflected in the Januar 19, 1973 document. .
It is our understanding that, given the type of retirement contemplated by PRDC for the facility, it may be necessary upon comple-tion of retirement, to continue the Part 50 license with such modifica-tions in the license and technical specifications as necessary to reflect the retired status of the facility and post-retirement surveillance program. PRDC and The Detroit Edison Company anticipate that, upon completion of the retirement or before, application will be made by PRDC
' to transfer the residual license (whatever its form) to Edison which, upon such transfer taking place, would assume responsibility for the facility.
PRDC is continuing the retirement program expeditiously and would like to negotiate with The Detroit Edison Company as soon as possible the financial aspects of the contemplated transfer of responsi-bility, so that PRDC can better determine its financial requirements.
In order to do this PRDC needs and hereby requests action by your office-sufficient to provide PRDC and Edison assurance that the contemplated configuration for the retired facility and the post-retirement surveillance program is generally satisfactory in concept and scope. We recognize that approval in detail, as distinguished from assurance as to concept and scope, cannot be forthcoming until we have submitted the proposed final form of license and technical specifications covering the retired facility. ,
8609220091 860915 PDR ADOCK 05000016 P, PDR 4.21
_ - _ _ - - - - . - ~ - - . - -
PoirEn REACTOR DEVELOPMENT COMPANY '
Mr. L. Manning Muntaing September 24, 1973 Because PRDC's original plan for permanent on-site storage of E the blanket and radioactive sodium has not proved acceptable to your office, the revised retirement program, by requiring off-site disposition of these materials, will reduce the residual radioactivity on-site by about 40,000 curies, or about 90%, vis-a-vis the original plan. The residual on-site radioactivity will be in the order of 5000 curies, which is much less than that at other retired facilities such as Saxton. This residual radioactivity will be located in solid materials within several barriers, and be subject to the surveillance program. Access to the facility would be restricted, a status which reflects the fact that it is on land owned by The Detroit Edison Company, is within the exclusion area for at lesst two nuclear reactors programmed by the Company, and accordingly would not be available for general commercial, residential, recreational or conservation use even if reduced to unrestricted access status from a radiological point o'f view. .. Finally, no discharges to the environment, either radioactive or non-radioactive, are planned or anticipated from the retired facility.
l The attached document does not cover details of disposition of radioactive primary sodium and blanket materials since these are not yet known. It appears that we may be able to ship the sodium to Hanford with a .few months' delay, and ship the blanket material to Savannah River with a year or two delay. These must be done to complete retirement, with the h facility remaining in a semi-retired state from about year end 1973 until 3 the codium and blanket have been removed from the site.
Please let us know if you have any questions. E 1 Sincerely, J 7
, h{ . , 'N ~
Eldon L. Alexanderson l General Manager i ELA/dem Enclosure -
E E
4.22 E
FERMI 1 RETIREMENT PROGRAM r
This document describes the Fermi-1 retirement program and is an l
update and expansion of the retirement plan submitted to the AEC by letter dated January 19, 1973. The previous plan was ;.ased upon permanent on-site l
storage of the blankat subassemblies and radioactive sodium. Since that submission, the AEC has forbidden the permanent on-site storage of these materials. This new plan incorporates the changes resulting from that decision.
. The Detroit Edison Company plans to continue to use the Fermi-1 turbine for peaking power utilizing the fossil fueled boiler. In addition, Edison plans to install two'1100 he boiling water reactors on the site; one of these reactors is already under construction. The surveillance and access control programs associated with these other facilities provide added protection in assuring the containment of the small amount of residual radioactivity remaining upon completion of the Fermi-1 retirement program.
- 1. Present Status of the Facility The major retirement tasks which have been completed or started are as described below:
The core fuel sections of all 214 core A fuel subassemblies composed of 25.6% enriched uranium-molybdenum alloy have been shipped to the Savannah l
River Plant facilities of the U. S. Atomic Energy Commission for reprocessing.
The depleted uranium axial blanket sections and radial blanket subassemblies are i
currently stored in water pools located in the Fuel and Repair Building (FARB).
Enriched uranium cold scrap and plutonium-beryllium sources have all been returned .
to the AEC. With the exception of plutonium of very low density in the axial blankst sections and radial blanket subassemblies and seven fission counters, no special nuclear material is on the Fermi-1 site.
- 4. 23
ne reactor vessel has been drained of sodium as far as is possible usin2 the 30-inch outlet pipes. The r== minder of the system will be drained by using special syphoning piping. The additional volumes to be syphoned cret the 30-inch loops; the IHK secondary tube bundles; the reactor low pressure plenum; the remainder of the reactor vessel; the 1HX drain lines; and the overflow pump tank. All primary pump motors and pony motors have bsen removed from the pump shafts.
The primary system cold trap has been drained, shipped, and buried ct the Nuclear Engineering Company site at Beatty, Nevada. The primary system codium hot trap and -economiser have been removed for decontamination.
A sodium melting facility and a decontamination facility for sodium piping and other equipment are being fabricated in the FARB maintenance pit.
Secondary coolant system sodium was drained to the secondary sodium oterage tanks; a sodium barrelling facility was constructed adjacent to the codium service building; and the nonradioactive sodium has been barrelled and chipped off-site for sale. The secondary coolant lines in the sodium galleries hr.ve been cut and capped just outside the reactor building.
About 3000 pounds of 78% NaK are on-site. About 2500 pounds of the E
%. NaK have been drained from various systems to drums. This NaK is nonradioactive and will be sold to or disposed of by Mine Safety Appliance Company or others under contract to PRDC. The means of disposal of the radioactive NaK has not yat been determined.
The Auxiliary Fuel Storage Facility is being retired. The sodium in E the pots has been drained into the primary system. CO2e vill be added to the fccility and the tank will be sealed.
The gaseous fission product detector system has been dismantled. Many ,
of the parts which could not be decontaminated have been shipped for burial.
Th9 remainder of the system is being offered for sale.
4.24
~
g.. -
The emergency diesel generator has been disabled and avaits sale.
The fuel has been drained from the tank and the tank is filled with water.
- 2. Ramaining Retirement Tasks <
l E. remain:
he following sections describe the major retirement tasks which 2.1 Disposal of Radioactive Sodium An inventory and analysis of the radioactive sodium presently at the site are given in Table 1. This sodium is in storage tanks in the Sodium Storage Building, in the transfer tank in the FARB, and in the primary system in the Reactor Building. During the retirement task, all the sodium is to be placed in tanks and/or ' drums and shipped off-site for final disposal.
Sodium is transferred from one location to another by the technique E of adjusting cover gas pressures and syphoning rather than pumping.
2.2 Securing Reactor Building Penetrations j he Reactor Building penetrations can be broken down into three categories: electrical and instrumentation, piping and ventilation, and personnel and equipment.
The electrical and instrumentation penetrations will not be altered although many of the electrical lines will be cut adjacent to the penetrations.
After the primary system is drained, associated sodium and gas piping penetrations will be cut and capped inside or outside of the reactor building.
As previously stated, the secondary coolant lines have been cut and capped just outside the reactor building. One of the above-floor ventilation penetrations will be fitted with a filter and left open to permit the building to " breathe";
other ventilation pwnetrations will be capped.
At the completion of the retirement tasks in the Reactor Building, the access penetrations will be dealt with as follows: the equipment door, which 4.25
is operable only from the inside, will be bolted closed; the emergency and personnel airlocks will be locked on the outside.
2.3 Sealing the Primary System In its final configuration, the primary system will be a gas-tight !
cystem consisting of the reactor vessel and primary sodium piping plus the E, primary shield tank, the machinery done, and the primary sodium service and cecondary sodium system out to welded pipe caps. After the system is sealed, l it will be connected to a carbon dioxide supply and maintained at a slight positive pressure. (The CO slowly reacts with the residual sodium to form l
2 the inert solid compound Na CO ).
2 3 l The reactor vessel vill contain safety and control rods and stainless oteel thermal shield bars, but no fuel or blanket subassemblies. The activity levels associated with these components are shown in Table 2. As of June 1, 1973, the calculated totals are 1500 curies of co-60, 3500 curies of Fe-55, and 130 curies of other isotopes. These materials are nonvolatile and contained within the sealed reactor vessel. In addition, it is estimated that the primary system and overflow tank will contain a maximum of 1100 Kg of residual sodium. The
,' total activity of this soditan la 0.024 curies.
Note that the overflow tank will not be a part of this system. All lines to the tank will be cut and capped. CO will 2 be added to the tank atmos- l phere and the tank will be sealed.
2.4 Sodium Service System l This system consists of the cold trap, hot trap, economizer, and piping in the sodium service tunnel and cold trap room. As stated previously, the cold trap, hot trap, economizer, EM pump and much of the piping in the cold trap room have been dismantled and removed. At the completion of plant retirement, the cold trap room will be essentially empty. l
- 4. M
I The piping in the sodium service tunnel will be cut at each end of the tunnel, the ends will be covered, and the pipe will be flooded with CO 2
to passivate any residual sodium.
2.5 Disposal of Secondary Sodium <
and System Components Sodium for this nonradioactive system was drained to storage tanks from which it was loaded in 55-gallon drums, shipped off-site and sold. The L residual sodium in the piping and equipment external to the reactor building
~
vill be reacted with CO2 8 88 t Prevent any hazard from fire or from hydrogen formation. Components of the system can thec. be salvaged or scrapped as time permits and need for the space for other use arises.
The Detroit Edi, son Company is planning to provide No. I steam generator to the Central Research Institute of Electric Power Industry, of
- Japan. The steam generator will be shipped as a unit; a 2 psig nitrogen gas pressure will be maintained during shipment.
2.6 Disposal of Fuel Transfer and FARB Systems j The fuel transport facility consists of a cask car which shuttles between the reactor building and the FARB, two gripper casks, and two plug casks. This system will be cleaned of sodium, the car will be moved to the B reactor building, and the casks will remain in their storage locations.
1 Drainable pots used in fuel handling and storage will remain in the l transfer rotor or transfer tank. Non-drainable pots will be emptied, steam cleaned, and shipped off-site for disposal.
( The FARB transfer tank will be drained of sodium and deactivated by filling with CO . 2The two temporary storage tanks in the FARB sodium service -
system and the FARB cold trap will be removed, drained of sodium, and shipped 1
l
\ ..
4.27
r u-off-site for burial. The decontamination and sodium melting facilities in the FARB maintenance pit will be removed and the area decontaminated. The steam cleaning machine will be sealed in its room. Tae wasta liquid holdup tanks will be decontaminated.
Presently, the FARB pools are heir.g used to store radioactiva blanket subassemblies. When these are removed from a pool, the pool will be drained of water and decontaminated; the equipment associated with the pool will be dis-mantled, decontaminated, and sold.
- 2.7 Revised Site Boundary The retirement of Fermi-1 has now proceeded to the point where reactor i
operation is impossible; most of the radioactivity has been removed by shipping the fuel off-site, and activities are limited to dismantling, decontamination, and off-site shipments. At this point in the retirement program, no accident can be conceived which results in a discharge or distribution of radioactivity in sufficient quantity to be of danger to the health and safety of the public.
Consequently, a large exclusion area is no longer needed. A sufficient site is one which excludes public access to all radioactive components.
The boundary of the site will be revised as shown in Figure 1 to include only those areas containing radioactivity. Note that some building walls t
are used as part of the boundary; by the completion of the retirement program the building doors which now interrupt those walls will have been permanently closed.
2.8 Prevention of Access to Areas Containing Radioactivity
~
Those areas which will or may contain radioactive material or con-tamination are the reactor primary system, the auxiliary fuel storage facility (AFSF), the overflow tank and associated piping, the sodium service piping Complete decontamination of some of these components will not be practicable. In general, components for which decontamination is not successful will be shipped off-site for burial. When this is not feasible, the component will be sealed and access to the area will be restricted.
4.28
I .
~
in the tunnel, the primary sodium storage tanks in the sodium storage building, and the following areas in the FARB: transfer tank room, cold trap room, fue, decay and cut-up pools, steam cleaning room, and the wasta liquid and gas holdup areas. #
Access to the reactor building will be limited by the locked personnel doors. The primary system will be seal-welded and will be gastight. The AFSF
{ is located under a heavy five-foot thick,12 foot diameter shield plug. The overflow tank and piping are below-floor; unauthorized access to the below-floor area will be prevented by a locked cover or grating over the manhole.
After the primary sodium storage tanks are emptied, an attempt will be made to decontaminate them. If unsuccessful, the storage building will be l sealed by some means such as welding a plate over the door.
The piping in the sodium service tunnel can be reached only through l
l a manhole which will be locked or welded closed. (The total activity in this E
area will be in the order of 10 pCi.)
l Access to the FARB will be limited to one locked door; other doors
( wi11 be operable only from the inside. In the FARB, s'ccess to the transfer tank room and cold trap room will be prevented by a locked manhole cover. Doors 1
to the pool areas will be locked. Only single accesses to the waste tank area and steam-cleaning room exist and they will be blocked by heavy plugs.
2.9 Disposition of Miscellaneous E
, Equipment and Material PRDC intends to offer a number of components and materials for sale.
Major items include the two PRDC fuel shipping casks, the diesel electric generator, the three primary coolant pump main motors and pony motors, the plant ran.c d.t. - - s,.t... . d v.ri.. 1.c - c.1 s., ,.a,. tr.s, _ e,s. . d E ..
4.2, E -- - -- _. . _ _ . ._ -
compressors. The extent of sale will depend largely on economic feasibility.
Sale components will be checked for radioactive conta=fnation and cleaned when necessary.
Some radioactive components may also be offered for sale to those cuthorized by the AEC to receive them. Possible items are the vacuum pump and B compressor of the recirculating and waste gas systems, the fuel subassembly cut-up machine, and portions of the fission product detector system. Transfer of these items would be made pursuant to. applicable regulations of the AEC and the Department of Transportation.
2.10 Disposal of Blanket Elements +
l The blanket subassemblies are to remain in the FARB pool (s) until a nathod for disposal is agreed upon with the AEC. These subassemblies constitute e source of 52,000 Ci and contain 6.7 Kg Pu. The activity is primarily fission products contained in metallic uranium alloy rods encased in stainless steel tubes.
Since the uranium is depleted, criticality cannot be achieved in any configura-tion. The decay heat is sufficiently low that even if the pools should drain, no melting would result.
Consequently, it is incredible ,that this activity could cadanger the health and safety of any person at the revised site boundary.
} 2.11 Administrative and Technical Files Legally required and other significant files, drawings, and records are being consolidated and will be retained as long as required. The Detroit Edison Company is expected to be the file custodian once PRDC is dissolved.
These records will be maintained in the Fermi-1 office building or other suitable otorage.
- 3. Final Plant Configuration The final configuration of the facility resulting from accomplishment of the foregoing tasks will be as follows: '
4.30
L -
9 v.'
- a. As previously indicated, the facility would be redefined: its boundaries will be narrowed and demarked by a fence, as shown in Figure 1, through which there will be limited means of access by locked gates. All contaminated areas will he within this fence.
The facility will be within the large exclusion area owned by The Detroit Edison Conpany and associated with other reactors and generation facilities planned or operated by that company. Access and use limitations as may be imposed by that company will apply to this area.
- b. Within the facility as redefined, all areas having residual radio-E ' ctivity a will be sealed and/or secured as described in Section 2.
4 above.
- c. The amount of residual radioactivity in the primary system will be in the order of 5000 curies.
I d. The amount of residual radioactivity outside of the primary system
~
is estimated to be 5 to 10 curies.
- e. There will be no planned radioactive discharges from the facility as
( redefined above.
- 4. Post-retirement Surveillance i 4.1 Physical Barrier Inspection Visual inspection of the fence and buildings will be made monthly to 1
determine that the physical barriers are intact and the gates and doors are
! properly locked.
4.2 Cover Gas Pressure i
Carbon dioxide cover gas will be maintained over the primary system as described in Section 2.3. The cover gas pressure will be maintained at
~~
I 4.31 5
approximately 1 psig. A low pressure switch will energize a light located in a continuously manned room. The alarm system will be tested quarterly.
j 4.3 Water Seepage Detection Water detectors will be installed to detect seepage into the space between the biological shield and the reactor building and the primary sodium overflow tank pit. Alarms will be continuously monitored. The alarm systems l will be tested quarterly.
4.4 kadiation Surveys l
~
Surveys will be made to check for the presence of gsama radiation and transferable contamination on a quarterly basis. Gamma radiation measurements using portable survey instruments and contamination checks using smears will E be made of the following areas:
Containment Building
- 1. Exit port area N=
- 2. Machinery dome door and window seals
- 3. Operating ' floor E
- 4. Filter in breather pipe f Fuel and Repair Building
- 1. Cold trap room access plugs
- 2. Transfer tank exit port area
- 3. Pool areas While the blanket subassemblies r*= min on site, water samples from the storage pool (s) will be analyzed for radioactivity on a quarterly basis.
To verify that no detectable release of radioactive material has occurred, the radioactivity on the filter in the building breather pipe will be measured quarterly. This together with the above tests and the absence of l
4.32 5'
l
. . -n-l alarse from the water seepage monitors and the primary cover gas pressure l
monitor win verify the integrity of the primary system and other barriers.
l Detroit Edison's Fermi 2 enviran==ntal monitoring program will provide additional data on the retention of radioactivity.
4.5 Administrative Controls A person will be designated to control the keye to the locked gates l
and doors and to control authorized entry into restricted areas. The results l
of the radiation surveys together with a report on the statt.s of the deactivated facility win be submitted annually to the AEC. Unusual events win be reported to the AEC as requ' ired by license and by means of the annual reports. Records or logs will be kept witti respect to the radiation surveys, water seepage, q testing of the cover gas and water seepage alarm systems, inspection of the physical barriers and unusual events.
- 5. Licensing The land on which the facility is located is owned by The Detroit Edison Company. Some of the facility buildings are now own6d by that company; the others win be sold or otherwise transferred to it. Accordingly, upon completion of the retirement.or before, it is contemplated by The Detroit Edison Ccepany and PRDC that application will be made to the AEC for transfer of the residual license to the former, who would then assume responsibility for post-retirement surveillance of the facility. The Detroit Edison Company and PRDC 'have not yet entered into a definitive arrangement for this purpose and will not be able to do so until PRDC has received from the AEC sufficient indication of the accept-ability of the retirament and surveillance pisna to permit useful finaccial estimates to be made of the completion and surveillence costs.
,, 4.33
4 For purposes of the retirement tasks, PRDC plans to continue to request appropriate modifications to the technical specifications to permit these tasks to go forward efficiently. In due course, a wholly revised license and technical specification covering the retired facility and its surveillance will be submitted.
B.
R E-B B
B B
~
R 0
B EiI R, i 1
4.34 9-24-73 I
l -
.g u a xx xx xxxx x xx x x x xxx xxxx x x i i i I I I i I ! I f I I i i i l i i I : i i i ! t I i t i i f I'
. t
i l h FUEL 4 'h RE. PAIR .9 N.. HEALTH PHT'E.21CS ,
l OUILO b I"
? E.UlLDiMG L
x :
y GODlU M COLD gtqcto!; $
g STORAGE TRAP gg .. d.
- BLDS, ROOM O
M ytaT st. tsp AREA M OO M l
. 3 ; t--!:
8 l ,
WASTE INERT f.
GAS C,A6 -
?
~BLDC,. .',!
l .
? %
E U REACTOR ,
t x BUILDING $
. n x X :K g
OFFlCE J
E20\LDIRQ CONTROL GTEAM BUILDtNG GE14ERAioR E e,LDc, .
R
- THESE DOORS TO BE. LOCKED OR PERMAMENTLY CLOCE.D.
1 l FIG.1 REVISED 5ITE BOUNDART 4.35 ;
1 _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ -
. e TABLE 1 l RADICACTIVE SODIUM INVENTO R E[
B.
Trrsafer Prianry Er.e:gency Tank IHX Sodies Sedha __ Sodium Drain Total ,
e l
l Quantity, Ib '# 6,000 101,000 73,000 32,000 582,000 r s l
Measured Specific Activity tici/gm Na-22 0.02 0.G004 l'
Sr-90 0.0005 C.0C001 Cs-137 0_. 00J. _,
0.001 l; Total 0.022 0.00025 0.0014 0.00000 -
Total Activity ,ci 3.8 0.01 O.05 0.00000 3.9 1
B:
~
N 3
9- 4-73 l
. 3e g
. o TABLE 2 CALCULATED STAINLESS STREL ACTIVATION IN REA30R t'3SSEL
! 2, INEGLECTING BU_EET_ $~JhASSEMELIES) l (June 1,1973) w q Actig tlen Source, curies Comeonent Mi-63 Fe-55 Co.-_5 8 Co-60_ Total lj Control and Sa.fety Rod Channeln ,
C,d Portica is Core 2 76 21 9 108 Portion in Blanket L 22 1 9 32 Portion b'etween Blanket
~]
m and Holddown L -1 L 1 2 Holddown Machanism
~l Inner Region 4 152 L 158 314 d1 Outer Region (E741 cm) 1 54 L 70 125 n
Shield bars 22 795 12 105 935 Thermal Shield Lower 20 720 1 88 829 Upper .
2 76 L '9 87 Holddwn celunc L 22 L 3 25 Safety Rods - Poison Section Lwer L 1 L 1 2 Mid11e L 1 L 1 2 Upper L 1 L 1 2 Totating Plug L 1 L 1 2 Support ?lates 24 8K L 965 1849 Support Structure 7 259 L 35 301 Support Structure Shielding 8 259 L 35 312 71w Baffles L 10 L 2 12 Conicci F. low Guide L 1 L 1 2 Lever Rasetor Head Shielding 4 152 L 18 174 Transfer Rotor L 1 L 1 2 OHM 1 44 L 6 51 Reactor Vessel ::egligible Total 96 3515 35 1519 5168 L = Less than 1 curie This table has been v; dated since the January 19, 1973 eubmission. Activity due to Fe-55 and Ni-63 has been taken into account and that due to Fe-59 and Cr-51 < deleted since these nuclides constitute less than 2 curies total 4.37
___ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ - - - - - - - - - - - - - - - s