Forwards EGG-NTA-7574, Conformance to Generic Ltr 83-28, Item 2.2.2 - Vendor Interface Programs for All Other Safety- Related Components:Fermi-2, Final Informal Rept.Plant Conforms to Generic Ltr on Item
ML20214R714
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/26/1987
From: Roberts E
EG&G IDAHO, INC., IDAHO NATIONAL ENGINEERING & ENVIRONMENTAL LABORATORY
To: Carrington M
Office of Nuclear Reactor Regulation
Shared Package
ML20214R717 List:
References
CON-FIN-D-6002 EWR-60-87, GL-83-28, NUDOCS 8706080273
Download: ML20214R714 (1)


Text

. . foA

~

/NEA ideho Nedenel Enok,eerk,e Lahorerery March 26, 1987 ,

Mr. M. Carrirgton, Project Manager Office o' Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 TRANSMITTAL OF FINAL REPORT, "CONFORMANCE TO GENERIC LETTER 83-28, ITEM 2.2.2--VENDOR INTERFACE PROGRAMS FOR ALL OTHER SAFETY-RELATED COMP 0NENTS: FERMI-2," EGG-NTA-7574 MARCH 1987 (FIN D6002) - EWR-60-87 Ref: NRC Form 189, " Evaluation of Conformance to Generic Letter 83-28 For OLs (Project 2)" (06002)

Dear Mr. Carrington:

Transmitted herewith is the above subject report.

The report documents INEL's evaluation of the applicant actions in response to NRC Generic Letter 83-28, Item 2.2.2--Vendor Interface Programs for All Other Safety-Related Components. Based on the applicant submittals, we conclude that the plant conforms to the generic letter on this item.

Very truly yours,  !

C/ /

t/ ( cy>,b _ ]

E. W. Roberts, Manager NRC Headquarters Support ACU:gp

Enclosure:

As Stated cc: G. L. Jones, 00E-ID A Toalston, NRR-PAE! (2) ,