ML20204D816
| ML20204D816 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 03/12/1999 |
| From: | Dapas M NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Reddemann M WISCONSIN ELECTRIC POWER CO. |
| Shared Package | |
| ML20204D820 | List: |
| References | |
| 50-266-99-04, 50-266-99-4, EA-99-002, EA-99-2, NUDOCS 9903240290 | |
| Download: ML20204D816 (4) | |
See also: IR 05000266/1999004
Text
.
-
--
.-
-
-
- - _ _ -
.
'e
s
W E84
UNITED STATES
p
9
f
%,
NUCLEAR REGULATORY COMMISSION
'
REGION til
-#
o
5
E
801 WARRENVfLLE ROAD
"
lisle. ILLINOIS 60532-4351
49*****
March 12, 1999
EA 99-002
Mr. M. E. Reddemann
Site Vice President
Point Beach Nuclear Plant
.
6610 Nuclear Road
Two Rivers, WI 54241
SUBJECT:
POINT BEACH INSPECTION REPORT 50-266/99004(DRP)
Dear Mr. Reddemann:
On February 22,1999, the NRC completed a specialinspection at your Point Beach Unit i
reactor facility. The purpose of the inspection was to examine the circumstances associated
with the identification of an ice-induced flow blockage in the normal minimum flow path for the
two safety injection (SI) pumps. The enclosed inspection report presents the results of that
inspection.
On January 5,1999, the NRC identified that SI system operability could be affected by a
degraded material condition in the facade freeze protection (FF) system for which your staff had
initiated a work order on December 22,1998. Your staff followed up on this concern and
identified that the normal minimum flow recirculation line from the discharge of thf., two SI
pumps to the refueling water storage tank was blocked. Following the identification of the flow
blockage, your staff's short- and intermediate-term corrective actions were generally considered
appropriate, with one exception described below. As the result of detailed tests and evaluations
performed subsequent to this event, your staff determined that the SI system was not rendered
inoperable by the ice blockage. However, your staff's operability conclusion was based upon
the structural failure of low pressure system boundary valves that were not designed to fail.
The design and licensing basis does not credit the structural failure of low pressure system
boundary valves to ensure that an emergency core cooling system is operable.
On January 8,1999, the NRC identified that your staff response to another FF system alarm
was focused on the wrong pipe, in discussing this issue with your staff, the inspectors were
informed that the FF system operating procedure was known to contain inaccurate and
incomplete information, in part because of the failure to update the procedure following a FF
system modification. Only after discussion with the inspectors did your staff update the FF
system operating procedure to more accurately reflect the known discrepancies.
Numerous other program and performance weakness were identified by the NRC inspectors.
These findings were consistent with the preliminary findings of your event investigation team.
Examples of the weaknesses included the failure to adequately maintain the material condition
9903240290 990312
ADOCK 05000266
G
y
,
'
_s'
9'
o
' M. Reddemann
-2-
,
of the FF system, the failure to provide adequate engineering design and installation drawings
for the FF system, and the failure to establish minimum operability criteria for the FF system
prior to the' onset of cold weather,
Based on the results of this inspection, the -NRC has determined that one violation of NRC
_
requirements occurred.' This violation is being treated as a Non-Cited Violation, consistent with
-- Appendix _C of the Enforcement Policy. The NCV is described in the subject inspection report.
If you contest the violation or severity level of the NCV, you should provide a response within.
30 days of the date of this inspection report, with the basis for your denial, to the Nuclear
Regulatory Commission, ATTN: Document Control Desk, Washington D.C. 20555-0001, with
.
l
copies to the Regional Administrator, Region Ill, and the Director, Office of Enforcement, United
States Nuclear Regulatory Commission, Washington, D.C. 20555-0001
In addition, one apparent violation was identified and is being considered for escalated
enforcement action in accordance with the " General Statement of Policy and Procedure for
NRC Enforcement Actions"(Enforcement Policy), NUREG-1600. This apparent violation
. involves the failure of your staff to take prompt corrective action on December 22,1998, when
they received an alarm indicating that a safety-related pipe was at a temperature near freezing.
As described above, the potential safety significance of this condition was not recognized until
' the NRC intervention on January 5,1999. Accordingly, no Notice of Violation is presently being
issued for this inspection finding. In addition, please be advised that the number and
characterization of the apparent violation described in the enclosed inspection report may
change as a result of further NRC review.
An open predecisional enforcament conference to discuss this apparent violation has been
scheduled for March 26,1999, at 9:00 a.m. (CST), in the NRC Region ill Office in Lisle, Illinois.
The decision to hold a predecisional enforcement conference does not mean that the NRC has
determined that a violation has occurred or that enforcement action will be taken. This
-l
conference is being held to obtain information to enable the NRC to make an enforcement
decision, such as a common understanding of the facts, root causes, missed opportunities to
identify the apparent violation sooner, corrective actions,' significance of the issues and the
need for lasting and effective corrective action. In particular, we expect you to discuss: 1) tne
test on the diaphragm valve, including the methodology used and why the test is bounding,
from which you concluded that the safety injection system' remained operable,2) operator
performance, including the decision-making process, involved with the response to the low
temperature alarm on December 22,1998, and 3) the process used to classify the freeze
protection system as nonsafety-related and to establish the maintenance and operational
controls (e.g.,' how are failures evaluated for the effect on safety-related components / systems).
-in addition, this is an opportunity for you to point out any errors in our inspection report and for
you to provide any information conceming your perspectives on: 1) the severity of the violation,
2) the application of the factors that the NRC considers when it determines the amount of a civil
penalty that may be assessed in accordance with Section VI.B.2 of the Enforcement Policy, and
3) any other application of the Enforcement Policy to this case !ncluding the exercise of
discretion in accordance with Section Vll.
-
__
..
. - .
..
.
-
--
-
-
- - ~
.
.
.
M. Reddemann
-3-
You will be advised by separate correspondence of the results of our deliberations on this
matter. No response regarding the apparent violation is required at this time.
In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice,' a copy of this letter and its
enclosure will be placed in the NRC Public Document Room.
Sincerely,
/s/ Marc L. Dapas
Marc L. Dapas, Deputy Director
Division of Reactor Projects
a
I
Docket No.: 50-266
License No.: DPR-24
'
Enclosure:
Inspection Report 50-266/99004(DRP)
cc w/ encl:
R. Grigg, President and Chief
Operating Officer, WEPCO
M. Sellman, Chief Nuclear Officer
R. Mende, Plant Manager
J. O'Neill, Jr., Shaw, Pittman,
Potts & Trowbridge
K. Duveneck, Town Chairman
Town of Two Creeks
B. Burks, P.E., Director
"
Bureau of Field Operations
J. Mettner, Chairman, Wisconsin
Public Service Commission
S. Jenkins, Electric Division
Wisconsin Public Service Commission
State Liaison Officer
i
DOCUMENT NAME: G:\\POIN\\ pol 99004.DRP
- See previous concurrences
To receive a copy of this document, indicde in the box: "C" = Copy w/o attach /enci"E" = Copy w/ attach /enci"N" = No copy
OFFICE
- Rill:DRP
lE
- Rill:DRP
lE
Rlli:DRP
}
l
NAME
Kunowski/kjc/co,
Lanksbury RnP_
Dapas#JP(/
DATE
03/11/99
F
03/t L /99
03// 2 /99
OFFICIAL RECORD COPY
._.
.
.
. _ _ . _ _ _ _ _ _ _ _ . _ _ _ _ _ _ . _
_ _ _ _ _ _ . . _
. . _ .
_ _
_ _ _ _ _
l
.. . +
,
M. Reddemann
4-
l
l-
i
l
Distribution:
.
'
CAC (E-Mail)
RPC (E-Mail)
J. Lieberman, OE w/enci
J. Goldberg, OGC w/enci
R. Zimmerman, NRR w/ encl
Project Mgr., NRR w/ encl
J. Caldwell, Rlli w/enct
B. Clayton, R!ll w/ enc!
SRI Point Beach w/enct
DRP w/enci
DRS (2) w/ enc!
Rill PRR w/ encl
PUBLIC IE-01 w/ encl
Docket File w/enci
GREENS
LEO (E-Mail)
DOCDESA (E-Mail)
4
I
l
\\
!
U
l
240003
l
l*
._