Notice of Nonconformance from Insp on 871116-20. Nonconformance Noted:Inadequate Translation of App B Into QA Program & Inadequate Translation of Design Requirements Into Testing Parameter RequirementsML20148M669 |
Person / Time |
---|
Issue date: |
01/25/1988 |
---|
From: |
Office of Nuclear Reactor Regulation |
---|
To: |
|
---|
Shared Package |
---|
ML20148M621 |
List: |
---|
References |
---|
REF-QA-99900779 NUDOCS 8801280337 |
Download: ML20148M669 (6) |
|
|
---|
Category:NOTICE OF DEVIATION/NONCONFORMANCE FROM A REGULATORY
MONTHYEARML20059H8811993-10-28028 October 1993 Notice of Nonconformance from Insp on 930907-10. Nonconformance Noted:Changes Made to Computer Codes Redya, Odyna & Safer Not Being Documented & Verified in Formal Manner ML20057C0521993-09-16016 September 1993 Notice of Nonconformance from Insp on 930712-15. Nonconformance Noted:Licensee Failed to Maintain User Manual for SEISMIC4 Finite Element Analysis Program Under Formal Document Change Control ML20046C0171993-08-0202 August 1993 Notice of Nonconformance from Insp on 881025-26. Nonconformance Noted:Rec Failed to Produce Documented Evidence to Substatiate That Audits of Vendors Performed W/ Frequency Specified in Qam from Jan 1986 to Oct 1988 ML20056F2301993-07-16016 July 1993 Notice of Nonconformance from Insp on 930504-05 Nonconformance Noted:Qa Manual,Rev 10,dtd Dec 1992 Did Not Contain Provisions for Dedicating Items Purchased by Vendor as Commercial Grade ML20036C4601993-06-0808 June 1993 Notice of Nonconformance from Insp on 930413-16. Nonconformance Noted:Two Nuclear safety-related Suppliers Not Audited Since Oct of 1991 ML20035G0571993-04-0909 April 1993 Notice of Nonconformance from Insp on 930302-05. Nonconformance Noted:Cable in Cable Tray Ampacity Test Specimen Purcased by Omega Point Commercial Grade from Distributor & Not Thereafter Controlled as Safety Grade ML20062F7831990-11-0909 November 1990 Notice of Nonconformance from Insp on 900625-27. Nonconformance Noted:Licensee Sold Listed Items as Nuclear safety-related W/O Completely Evaluating Suitability for Use in Such Applications ML20062G3091990-11-0808 November 1990 Notice of Nonconformance from Insp on 901015-19. Nonconformance/Deviation Noted:Licensee Failed to Identify Excessive Raised Metal in Form of Burr Adjacent to One Grid Pad Bore Hole on Lower End Fitting ML20058F0131990-11-0202 November 1990 Notice of Nonconformance from Insp on 900423-27. Nonconformance Noted:Failure to Effectively Control Design Calculation Verification Process for Certain Piping & Pipe Support Stress Calculations Re Bulletin 79-14 ML20058D5821990-10-30030 October 1990 Notice of Nonconformance from Insp on 900716-18. Nonconformance Noted:Failure to Implement Program to Control Insp & Process Monitoring of Mfg of safety-related Structural Steel Tubing Sections ML20059L4661990-09-17017 September 1990 Notice of Nonconformance from Insp on 890515-18. Nonconformance Noted:Purchased Commercial Grade 5/16-18 Inches Hex Heavy Nuts from Uchimoto Mfg Co,Neither Approved Nor Qualified Vendor Licensee ML20059L4441990-09-13013 September 1990 Notice of Nonconformance from Insp on 880509-12. Nonconformance Noted:Licensee Could Not Produce Adequate Documentation to Substantiate Qualification of Insp & Auditing Staff ML20058M2681990-08-0707 August 1990 Notice of Nonconformance from Insp on 900312-15. Nonconformance Noted:Five of Six Employees That Perform Activities Affecting nuclear-related Sys & Components Not Indoctrinated in QA Program ML20056A5261990-08-0303 August 1990 Notice of Nonconformance from Insp on 900423-26. Nonconformance Noted:Licensee Failed to Establish Adequate Measures to Assure That Conditions Adverse to Quality Promptly Corrected ML20059P0411990-07-31031 July 1990 Notice of Nonconformance from Insp on 900730-31. Nonconformance Noted:Audit Repts for Abb,Seitz & Poppe & Potthoff Not Completed at Time of Insp & Audits Conducted 7 Months Prior to Insp Date ML20055F7311990-07-11011 July 1990 Notice of Nonconformance from Insp on 900205-08. Nonconformance Noted:Failure to Clearly Establish & Delineate in Writing Authority & Responsibility of Persons Affecting safety-related Function of Field Engineering ML20055D8121990-07-0202 July 1990 Notice of Nonconformance from Insp on 900510 & 11. Nonconformances Noted:Licensee Program to Assure Design Control & Equivalency to Original Part Supplied for safety- Related Spare & Replacement Part Orders,Inadequate ML20043G6481990-06-13013 June 1990 Notice of Nonconformance from Insp on 900129-0201. Nonconformance Noted:Qa Manual Does Not Require QA Requirements Received W/Customer Purchase Orders Be Imposed on Subvendors for Supply of Matls ML20043B9521990-05-23023 May 1990 Notice of Deviation from Insp on 900404-0502.Deviation Noted:Licensee Employee Holding Levels I-III Certifications from 1981-1987 Did Not Possess Either High School Diploma or General Educ Development Equivalent of High School Diploma ML20043B5211990-05-21021 May 1990 Notice of Nonconformance from Insp on 900312-15. Nonconformance Noted:Purchase Orders Indicated That Silicone Fluid Treatment for Which No Written Procedure Existed Applied to Certain safety-related Electrical Connectors ML20033E9951990-03-0808 March 1990 Notice of Deviation from Insp on 900122-0202.Deviations Noted:Lack of Written Procedures for Energizing & Changing Modes of Operation for Portions of Distributions Sys ML20006F7811990-02-0707 February 1990 Notice of Nonconformance from Insp on 890606-09. Nonconformance Noted:Licensee Failed to Invoke Quality Requirements to Extent Necessary for Matl Vendors in Listed safety-related Purchase Orders ML20006D1421990-01-31031 January 1990 Notice of Nonconformance from Insp on 881003-07. Nonconformance Noted:Failure of Program for Dedication & Qualification of Commercial Grade Circuit Breakers to Provide Adequate Dedication Basis W/O Having Traceability ML20011E0271990-01-30030 January 1990 Notice of Nonconformance from Insp on 891002-03. Nonconformances Noted:Issuance of Purchase Orders to Vendors W/O Assurance That Vendors Capable of Mfg Products in Conformance W/Procurement Documents & Unclear Quality Plan ML18033B1411990-01-18018 January 1990 Notice of Deviation from Insp on 891115-1218.Deviation Noted:Failure to Submit Special Rept to NRC on Licensee Reviews of Initiating Conditions ML20011D1861989-12-14014 December 1989 Notice of Nonconformance from Insp on 890207-10. Nonconformance Noted:Hardware Specialty Co Certified Matl Test Repts Did Not Provide Impact Test Results on ASME SA-193,Grade B7 1 1/16-inch Diameter Fasteners ML18033B0731989-12-0707 December 1989 Notice of Deviation from Insp on 891016-1115.Deviation Noted:Failure to Notify Nrc,Within Reasonable Time,Prior to or After Senior Mgt Changes ML19332D6191989-11-28028 November 1989 Notice of Nonconformance from Insp on 890905-08. Nonconformance Noted:Failure to Establish & Delineate in Writing,Authority & Duties of Persons Performing Activities Affecting safety-related Functions of Components ML19325C7981989-10-13013 October 1989 Notice of Nonconformance from Insp on 890912-13. Nonconformances Noted:Failure of Rotork Personnel to Route Nonstandard Product Request Forms 916 & 1087 to QA Manager for Review & Approval & Lack of Documented Instructions ML18033A8851989-08-0404 August 1989 Notice of Deviation from Insp on 890508-19.Deviation Noted: as of 890510,167 Mod Engineers Had Not Completed Orientation Phase Training or Been Granted Waivers within Time Limits Established in Commitments & Implementing Procedures ML20247F2931989-07-21021 July 1989 Notice of Nonconformance from Insp on 881102-04 & 890201-03. Nonconformance Noted:Licensee Certified & Supplied Stock Matl W/O Testing Each Piece of Stock Matl & All Nuclear Sales Order Folders Not Color Coded ML20246F0761989-07-10010 July 1989 Notice of Nonconformance from Insp on 890508-11. Nonconformances Noted:Failure to Test Latest Rev of Replacement Circuit Boards at Battery Charger Final Acceptance Test to Verify That Charger Output within Specs ML18041A2021989-07-10010 July 1989 Notice of Nonconformance from Insp on 890313-23. Nonconformances Noted:Safety Function & Critical Characteristics of Dedication Packages Not Documented in Design Record File or Other Equivalent Documents ML20245D2171989-04-25025 April 1989 Notice of Nonconformance from Insp on 890206-10. Nonconformance Noted:Nuclear Safety Subcommittee Not Convened to Evaluate Problems Identified in Repair for safety-related Type Pressure Signal Limiter Circuit Boards ML20248K4551989-04-0707 April 1989 Notice of Nonconformance from Insp on 890123-27. Nonconformances Noted:Company Shipped Ductwork w/3/16 Inch by 2 Inch Welds Attaching Stiffeners to Ducts Which Were Spaced More than 8 Inch Apart ML20247J8781989-03-31031 March 1989 Notice of Nonconformance from Insp on 890123-27. Nonconformance Noted:Vendor Initiated 35 Purchase Orders for safety-related Electrical Matl W/Gismo Co W/O Supplier Listed on Ebasco Waterford 3 Approved Supplier List ML20155E4151988-10-0707 October 1988 Notice of Nonconformance from Insp on 880801-05. Nonconformance Noted:Nuclear Raw Matl Stored in Hold Area W/Govt Level 1 Matl & Lack of Evidence That Spherical & Cylindrical Stds Used to Calibr Optical Compactor ML20154H0351988-09-14014 September 1988 Notice of Nonconformance from Insp on 880627-0701. Nonconformance Noted:Qa Dept Director Does Not Rept to Mgt Level Which Provides Adequate Independence from Cost & Schedule When Opposed to Safety Considerations ML20153H4561988-09-0202 September 1988 Notice of Nonconformance from Insp on 880711-15. Nonconformance Noted:Licensee Did Not Include Chemical Product Analysis Performed by Schevers Labs on CMTRs ML20151U9401988-08-12012 August 1988 Notice of Nonconformance from Insp on 880627-29. Nonconformance Noted:Requirement for Vendor to Have Approved QA Program Not Stated on Purchase Orders & Lack of Documentation Re Certification of Two Current Inspectors ML20207G9081988-08-0404 August 1988 Notice of Nonconformance from Insp on 880201-10. Nonconformance Noted:Ge Responsible Engineer Procured 100 Replacement Metric Phillips Flat Head Screws W/O Purchase Documents Being Processed & Verification of Matl Quality ML20151S3301988-08-0404 August 1988 Notice of Nonconformance from Insp on 880411-13. Nonconformance Noted:Code Sponsor for Gt Strudl Computer Program Failed to Perform Actions on Error Notices Sent by Control Data Corp from Jan 1985 to Present ML20151R5991988-08-0202 August 1988 Notice of Nonconformance from Insp on 880524-26. Nonconformance Noted:Eight Radioactive Matls Packages Did Not Contain Foam & One Package Contained Rubber Instead of Foam & Records of Fabrication & Use Not Kept ML20151S2191988-08-0101 August 1988 Notice of Nonconformance from Insp on 880502-06. Nonconformance Noted:Measures to Ensure That Shaft Keys & Terminal Blocks Procured from Commercial Subvendors Per Applicable Design Requirements Not Established ML20151Q3331988-07-26026 July 1988 Notice of Nonconformance from Insp on 880418-22. Nonconformance Noted.Major Areas Inspected:Evaluation & Records Re Several Recent Events at Westinghouse PWR-type Nucelar Power Plants ML20155D2981988-06-0303 June 1988 Notice of Nonconformance from Insp on 880125-28. Nonconformances Noted:Failure to Clearly Establish Duties & Authorities of Engineering Personnel to Ensure safety- Related Design & Engineering Activities Performed ML20151V6071988-04-21021 April 1988 Notice of Nonconformance from Insp on 880216-19. Nonconformance Noted:Trent Tube Facility Did Not Include Chemical Product Analyses Performed by Steel Mfgs &/Or Lab on Listed Certified Matl Test Repts for Nuclear Orders ML20151F8731988-04-15015 April 1988 Notice of Nonconformance from Insp on 880307-11. Nonconformance Noted:Matl Being Upgraded for Westinghouse Purchase Orders Lacked Required Number of Tensile Tests Needed to Meet ASME Boiler & Pressure Vessel Code ML20148H3051988-03-22022 March 1988 Notice of Nonconformance from Insp on 871207-11. Nonconformance Noted:Failure to Establish Adequate QA Program to Control safety-related Activities Re Fire Damper Design & QA Monitoring Design Areas ML20149M2211988-02-22022 February 1988 Notice of Nonconformance from Insp on 880111-14. Nonconformance Noted:Matl Not Purchased to Astm/Asme Spec, Chemical Composition Limits Incomplete & Actual Mechanical Property Limits Missing 1993-09-16
[Table view]Some use of "" in your query was not closed by a matching "". Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARML20138H3031996-02-29029 February 1996 Notice of Violation from Insp on 961005-1113.Violation Noted:Alert for Loss of Annunciator Event Was Not Promptly Declared as Required by Ecg, Introduction & References, Section ML20149H4691994-11-15015 November 1994 Notice of Violation from Insp on 930201-0308 & Investigation Conducted Between Feb 1990 & Nov 1993.Violation Noted: Licensee Quality Implementation Procedure Not Adequately Established IR 05000528/19942011994-04-0606 April 1994 Insp Repts 50-528/94-201,50-529/94-201,50-530/94-201 on 940406.No Violations Noted.Major Areas Inspected:Plant Programs,Procedures,Training,Equipment,Sys & Documents for Implementation of SBO Rule Per 10CFR50.63 ML20059H3401994-01-11011 January 1994 Insp Rept 99900786/93-01 on 930826-27 & 30-31.No Violations Noted.Major Areas inspected:RMS-9 Overcurrent Trip Devices, Thmthjk & Tjj molded-case Circuit breakers,CR124 Overload Relays & Certain Other Issues ML17158A0781993-12-29029 December 1993 Notice of Violation from Insp on 931108-12.Violation Noted: Contrary to TS 6.12.1 on 931101 High Radiation Area Barricade Was Found Down & High Radiation Area Sign Was Missing ML20059K8641993-12-27027 December 1993 Exam Rept 50-002/OL-93-04 on 931207-08.Exam Results: One RO & Two Sroi Were Administered Exam & Operating Test. All Candidates Passed ML20059K8901993-12-23023 December 1993 Exam Rept 50-097/OL-93-02 & 50-157/OL-93-02 on 931004-06. Exam Results:Three SRO Passed Exams IR 05000387/19930211993-12-21021 December 1993 Insp Repts 50-387/93-21 & 50-388/93-21 on 931108-12. Violations Noted.Major Areas Inspected:Review of Audits & Assessments,Outage Organization & Contractor Training & Review of Outage Maintenance Work HP Coverage IR 05000317/19930261993-12-17017 December 1993 Insp Repts 50-317/93-26 & 50-318/93-26 on 931026-28.No Overall Exercise Strengths or Weaknesses Identified ML20059G3171993-12-0909 December 1993 Exam Rept 50-128/OL-93-03 on Stated Date.Exam Results: Candidate Successfully Passed SRO Upgrade Exam ML20058K0871993-11-30030 November 1993 Exam Rept 50-284/OL-93-01 on 931025-27.Exam Results:Reactor Operator Operating Test Retake Applicant Failed Exam.All Other Applicants Passed Exams ML20058A8161993-11-18018 November 1993 Notice of Nonconformance from Insp on 930809-13. Nonconformance Noted:Tracg Input Decks Used to Model Gist Facility Not Independently Verified to Be Correct ML20058D6691993-11-15015 November 1993 Exam Rept 50-020/OL-93-01 on 930913-15.Exam Results:All Applicants Passed Exams & Issued Appropriate License ML20059K9471993-11-10010 November 1993 Notice of Violation from Insp on 931006-08.Violation Noted: Licensee Alcohol Testing Procedures Did Not Address Those QCs Used to Ensure Test Results Were Valid ML20058A8251993-11-0404 November 1993 Insp Rept 99900403/93-01 on 930809-13.Nonconformances Noted. Major Areas Inspected:Review Input Modeling of Tragg Computer Code for Gist Facility ML20058A5411993-11-0404 November 1993 Insp Rept 99901268/93-01 on 931018-21.No Violations Noted. Major Areas Inspected: QA Program Implementations in Areas of Matl & Svc & Controls for Subsuppliers,Matl Control Insps & ASME Code Certification ML20059H8811993-10-28028 October 1993 Notice of Nonconformance from Insp on 930907-10. Nonconformance Noted:Changes Made to Computer Codes Redya, Odyna & Safer Not Being Documented & Verified in Formal Manner ML20059H8961993-10-26026 October 1993 Insp Rept 99900403/93-02 on 930907-10.Nonconformance Noted.Major Areas Inspected:Quality Activities of Design of Advanced BWR IR 05000327/19932011993-10-13013 October 1993 Insp Repts 50-327/93-201 & 50-328/93-201 on 930823-930902. Several Deficiencies Noted.Major Areas Inspected:Plant Operations,Maint,Engineering & Quality Programs ML20059G1471993-10-0808 October 1993 Initial Exam Rept 50-134/OL-93-03 Administered During Wk of 930913.Candidates Administered Retake Exam Passed Applicable Portion of Exam ML20057G2431993-09-28028 September 1993 Exam Rept 50-113/OL-93-01 on 930823-24.Exam Results:Both SROs Passed Exam ML20057F0861993-09-24024 September 1993 Exam Rept 50-027/OL-93-02 on 930816-17.Exam Results:Initial Written Exam & Operating Tests Administered to One RO Applicant.Operating Tests Also Adminsitered to One SRO Applicant.All Applicants Passed Exam & Issued Licenses ML20057D8761993-09-24024 September 1993 Exam Rept 50-027/OL-93-03 on 930816-17.Exam Results:One SRO Administered Written & Operating Requalification Exam,Passed Exam ML20057D1921993-09-23023 September 1993 Exam Rept 50-166/OL-93-02 on 930909.Exam Results:Ro Passed Retake of Section C of Written Exam ML20057E6741993-09-23023 September 1993 Insp Rept 99900404/93-01 on 930816-17.No Violations or Deviations Noted.Major Areas Inspected:Control of Activities Re re-manufacture of X-ray & Other Components Installed in DB & Dhp Type 480 Volts Breakers ML20057C0521993-09-16016 September 1993 Notice of Nonconformance from Insp on 930712-15. Nonconformance Noted:Licensee Failed to Maintain User Manual for SEISMIC4 Finite Element Analysis Program Under Formal Document Change Control ML20057C0501993-09-16016 September 1993 Notice of Violation from Insp on 930712-15.Violations Noted: Licensee Failed to Appropriate Procedures to Implement Provisions of 10CFR21 ML20057C0531993-09-0202 September 1993 Insp Rept 99900105/93-01 on 930712-15.Violations & Noncompliance Noted.Major Areas Inspected:Qa program,10CFR21 Program & follow-up on Concern Re Licensee Valve Assembly Seismic Stress Calculations ML20056G0581993-08-12012 August 1993 Exam Rept 50-186/OL-93-01 on 930726-27.Exam Results: Candidate Passed Written & Operating Portions of Exam ML20056D4851993-08-0404 August 1993 Exam Rept 50-150/OL-93-01 on 930628.Exam Results:Two Operator Requalification Retake Exams Administered.Both Operators Passed Exams ML20046C0171993-08-0202 August 1993 Notice of Nonconformance from Insp on 881025-26. Nonconformance Noted:Rec Failed to Produce Documented Evidence to Substatiate That Audits of Vendors Performed W/ Frequency Specified in Qam from Jan 1986 to Oct 1988 ML20046C0101993-08-0202 August 1993 Notice of Violation from Insp on 881025-26.Violation Noted: REC Corp Had Not Posted Any of Required Documents & Had Not Developed Procedures to Either Evaluate Deviations & Failures to Comply or Inform Licensee of Deviation ML20056E4431993-07-26026 July 1993 Exam Rept 50-184/OL-93-01 on 930713.Exam Results:Applicant Passed Both Portions of Licensing Exam ML20056F2301993-07-16016 July 1993 Notice of Nonconformance from Insp on 930504-05 Nonconformance Noted:Qa Manual,Rev 10,dtd Dec 1992 Did Not Contain Provisions for Dedicating Items Purchased by Vendor as Commercial Grade ML20056F2181993-07-16016 July 1993 Notice of Violation from Insp Rept on 930504-05.Violation Noted:Qa Manual,Rev 10,dtd Dec 1992 for Implementing 10CFR21 Inadequate Due to Listed Reasons ML20056D4061993-07-0808 July 1993 Exam Rept 50-116/OL-93-01 on 930623.Exam Results:All Three Candidates Passed Their Respective Portion of Exams & Issued Appropriate License ML20056F2361993-07-0101 July 1993 Insp Rept 99901265/93-01 on 930504-05 & 0604.Violation & Nonconformances Noted.Insp Conducted to Determine Whether Tests Conducted by Vendor in Accordance W/Approved App B QA Program & Applicable Purchase Order Requirements ML20056D8781993-06-28028 June 1993 Notice of Violation from Insp on 930510-14.Violation Noted:Failed to Complete Evaluation & Revise Procedure ML20056D9661993-06-21021 June 1993 Insp Rept 99901266/93-01 on 930602-03.No Violations or Deviations/Noncompliance Noted.Major Areas Inspected: Licensee Purchase Orders,Related Records & Associated Activities of Huron Industries,Inc ML20046D3891993-06-18018 June 1993 Insp Rept 99901264/93-01 on 930413-15.Violations & Nonconformance Noted.Major Areas Inspected:Implementation of Vendor QA Program for Supplying Nuclear safety-related Equipment W/Emphasis on Calibr of Flowmeters ML20036C4561993-06-0808 June 1993 Notice of Violation from Insp on 930413-16.Violation Noted: Procedures Not Revised to Address Substantive Revs to 10CFR21 That Became Effective on 911029 & Current Copies of 10CFR21 Not Posted as Required ML20036C4601993-06-0808 June 1993 Notice of Nonconformance from Insp on 930413-16. Nonconformance Noted:Two Nuclear safety-related Suppliers Not Audited Since Oct of 1991 ML20056C4571993-06-0707 June 1993 Exam Rept 50-128/OL-93-02 on 930518.Exam Results:Applicant Passed Both Written Exam & Operating Evaluation ML20036C4621993-06-0303 June 1993 Insp Rept 99901256/93-01 on 930413-16.Violations & Nonconformance Noted.Major Areas Inspected:Circuit Breaker div,10CFR21 Program & QA Program & Implementation in Providing Items for safety-related Use,Per App B to 10CFR50 ML20045C8851993-05-28028 May 1993 Initial Exam Repts 50-151/OL-93-01 & 50-356/OL-93-01 During Wk of 930519-20.Exam Results:Both Applicants Failed Written Exam IR 05000298/19932011993-05-27027 May 1993 Insp Rept 50-298/93-201 on 930301-05 & 0408-16.No Violations Noted.Major Areas Inspected:Quality & Implementation of Licensee Outage Planning W/Regard to Minimizing Risk of Accident Sequences During Shutdown Conditions ML20056D8901993-05-27027 May 1993 Insp Rept 99900100/93-01 on 930510-14.Violations Noted: Failed to Complete Evaluation & Revise Procedures.Major Areas Inspected:Mfg & Engineering Programs for safety-related Items IR 05000324/19932011993-05-21021 May 1993 Insp Rept 50-324/93-201 on 930329-0409.No Violations Noted. Major Areas Inspected:Assessment of Readiness of Mgt Control,Programs,Operations,Maintenance,Surveillanece & Testing.App a Re Summary of Deficiencies Encl ML20045E6751993-05-11011 May 1993 Exam Rept 50-134/OL-93-01 on 930419-21.Exam Results:Sro Passed Exams ML20036B2691993-05-0707 May 1993 Exam Rept 50-188/OL-93-02 on 930429.Exam Results:All Applicants Passed Exam & Have Been Issued Appropriate Licenses 1996-02-29
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
_
ll.
APPENDIX A Nutherm International Incorporated Docket No. 99900779/87-01 NOTICE OF NONCONFORMANCE-This NRC inspection was performed as a result of allegations received by the J
NRC in regard to disregard of the NRC quality assurance (QA) program require-L ments by Nutherm International Incorporated (NI). Based on the results of this inspection conducted on November 16-20, 1987, it appears that certain of your activities were not conducted in accordance with NRC requirements. These items are set forth below and have been identified and classified in accordance with the requirements of Appendix B to 10 CFR Part 50.
1.
Criterion II, "Quality Assurance Program" of Appendix B to 10 CFR Part 50 requires, in part, that the applicant [or designee] shall establish a quality assurance program which complies with the NRC requirements.
j Contrary to the above, the following examples were noted where NI did not adequately translate the requirements of Appendix B into its QA program.
(a) Section 10, "Inspection," of the NI QA manual (QAM) does not prohibit a person from inspecting their own work; (b) Section 10. "Inspection," of the NI QAM, as written, does not require QA inspection / monitoring activities in the NI equipment testing lab facility; and (c) NI has not established procedures to control its periodic use of rented measuring and test equipment. Examples of typical rental equipment are as follows:
(1 NI #158, Bechman voltage meter; (2
NI #313, Waltow meter; (3
NI f103, Meghom meter; and (4
NI #315, B&K Scope 2.
Criterion III, "Design Control," of Appendix B to 10 CFP Part 50 requires, in part, that measures shall be established to assure that the specified d
design bases are correctly translated into procedures and instructions to assure that appropriate quality standards are specified and included.
Design control shall also provide measures for verifying or checking the adequacy of design, such as by the performance of design reviews.
Criterion VI, "Document Control," of Appendix B to 10 CFR Part 50 requires, in part, that measures shall be established to control issuance of documents and assure that documents are reviewed for adequacy and approved for release by authorized personnel.
8801280337 880125 00h [ E Q
. Section 5 of the NI QAM, dated June 18, 1986, requires, in part, that:
(1) The project engineer shall be responsible for generating the project instructions, procedures and drawings necessary; (2) the QA manager shall be responsible for verifying that activities affecting quality are implemented in accordance with instruction; and (3) the engineering manager shall be responsible for review of all instructions, procedures and drawings that are generated.
Section 3 of the NI QAM, dated June 18, 1986, requires in part, that:
(1) the QA manager shall be responsible for verifying the implementation of an effective design control program; (2) the engineering manager shall be responsible for ensuring that the designers, engineers, analysts and verifiers are in confomance with the design control program; (3) design control measures shall be implemented to verify the adequacy of the design; and (4) verifying or checking the design consists of, at least, a fomal review of the design, spot checking of calculations / analyses, and assessing the results against the original design basis.
Section 4 of the previous revision nf the NI QAM, dated January 30, 1985, requires, in part, that:
(1) the engineering design document review and approval shall be performed by qualified design engineers; and (2) the QA manager shall review procedures to assure that they include appropriate acceptance criteria and test prerequisites.
Paragraph 4.6 of NI QA procedure QAP No. 3.0.00, from revision 0, dated February 16, 1985 through revision 2 dated November 17, 1986, requires, in part, that once a project manager has completed a design drawing, in accordance with the required procedures, they shall submit it to the engineering manager for approval.
Contrary to the above, the following items were noted:
(a) The below listed NI "Qualification Results Index" (QRI) fons, which are used as specific hardware instruction riders to NI's generic functional and test procedures that delineate the design parameters for testing, do not correctly and/or fully translate the design requirements into testing parameter requirements and quality standards, and do not indicate that an independent technical review was perfon'ad by qualified personnel.
QRI Number Prepared by/ Title Approved by/ Title Hardware (1)#1494,12/85 SDJ/ Design Engineer BE/QA Engineer Rotary Relay (GPU-1759 (2)#1495,12/85 SDJ/ Design Engineer BE/QA Engineer Control Switch
- GPU-1759 (3) #1403, 10/85 SS/ Engineer JH/Vice President Switch
- NMP-1841 (4)#1467,3/86 PB/EQ Secretary None Seleci.or Switch
- NMP-1841
- ORI Number Prepared by/ Title Approved by/ Title Hardware (5)#1759,1/86 SDJ/ Design Engineer None Control Switch iGPU-1759 (6)#1514,12/85 GH/ Metallurgist None Rotary Relay
- GPU-1759 (7)#1579,1/86 PB/EQ Secretary None Thyrite Secondary f
GPU-1897 Protector (8)#1526,1/86 GH/ Metallurgist None Current Alann AE/EQ Secretary J
(9)#1570,3/86 SDJ/ Design Engineer None Signal Isolator i1759-63 (10) #1540, 1/86 DW/ Technical Asst.
None OSA Relay
- FPL-1676 (b) Thefollowinglistedequipmentqualification(EQ)proceduresand functional test procedures did rot indicate that an independent technical review was performed to verify the adequacy of the design requirements for testing:
Procedure Title / Number Prepared by/ Title Approved by/ Title (1) Operations Aging for PB/EQ Secretary RH/QA Manager Thyrite Protector,
- 9.7.10.30, 5/86 (2) Baseline Test for PB/EQ Secretary RH/QA Manager Cycle Duration of Thyrite Protector,
- 9.7.10.29,5/86 (3) Baseline Testing of LH/ President RH/QA Manager So11 tech Controllers,
- 9.7.10.22, 12/85 (4) Procedure for Mechanical MAM/QA Assistant RH/QA Manager Cycle Aging Airflow Switches, #9.7.10.17, 11/85 (5) Baseline Testing of MAM/QA Assistant RH/QA Manager Disconnect Switches,
- 9.7.10.6,11/85 (6) Operational Aging of PB/EQ Secretary RH/QA Manager Push button Selector Switches, #9.7.10.10, 4/86
l l
. Procedure Title / Number Prepared by/ Title Approved by/ Title (7) Function Test for AC HB/ Project Manager RH/QA Manager Transformers, #9.7.10.39, 9/29/86 i
(8) Baseline Testing for SDJ/Desiga Engineer RH/QA Manager Voltage Relays, #9.7.10.26, 1/86 q
(9)FunctionalTestingfor BE/QA Engineer RH/QA Manager Temperature Controllers,
- 7.2.07, 2/85 (10)FunctionalTestingfor SDJ/ Design Engineer RH/QA Manager Analog and Digital Meters
- 7.2.0.6,3/86 (11) Functional Testing of SDJ/ Design Engineer RH/QA Manager Solid State Power Controllers, #7.2.13, 10/86 (c) Several design drawings in the pre-1986 time period indicated that the engineering manager did not perfom the required design verifi-cation activit]. Specifically:
(1 Dwg. f7023-56767-53, 11/12/85. GPU-1759 (2
Dwg. #7013-55215-53, 12/13/85, C-1167 Dwg. f5001-54983-43, 4/27/83, BE-1214 Dwg. #7023-56994-33, 8/21/86, GPU-2169 Dwg. f4033-56689-33, 10/3/85, GPU-1712 i
(6 Dwg. #1023-55953-33, 10/30/84, TVA-1497 3.
Criterion X, "Inspection," of Appendix B to 10 CFR Part 50 requires, in part, that inspection activities to verify the quality of the work shall be performed by persons other than those who performed the activity being inspected and that such persons shall not report directly to the immediate supervisors who are responsible for the work being inspected, Additionally, if direct inspection is disadvantageous, indirect control by monitoring of the processing methods and personnel shall be provided.
j Contrary to the above, the following areas were identified where NI is not providing adequate QA inspection / verification controls of its quality related activities. Specifically:
(a) HI has not implemented its program for the inspection or monitoring of activities affecting quality for any of the work activities that are perfomed in its.equiptreqt testing laboratory, except for its annually scheduled QA audit;
~
.. (b) Discussions with NI lab personnel and a review of several of NI's current typical "functional test result" (FTR) foms for completed tests which had been verified by QA revealed that management is allowing the lab technicians that perfomed the work to sign the FTR form in the "QA inspector approval" block. Therefore, a review of a completed form would lead one to believe that QA had monitored and approved the testing results; however, in practice, the lab tech-nician is signing for the testing results that he has perfonned; and (c) Discussions with NI personnel and a review of records indicated that on the previous revision of the FTR foms, the testing lab supervisor used the "QA approval" block for his signature. Therefore, a review of these FTR foms would also appear to indicate that a QA approval had been obtained. However, in practice, the lab supervisor was i
inserting his signature in the QA approval block.
4.
Criterion XI, "Test Control," of Appendix B to 10 CFR Part 50, requires, in part, that a test program be established to assure that all of the required testing is performed in accordance with procedures / instructions which incor-porate the requirements and acceptance limits contained in applicable design documents. Additionally, the program requires that the procedures include provisions for ensuring that all prerequisites for the given test have been met, that adequate test instrumentation is used, and that the test results are documented and evaluated to assure that test requirements have been satisfied, j
Contrary to the above, the following items were noted during NRC inspections of the current in-house work activities being performed in the NI testing /
EQ area:
(a) During testing activities of an undervoltage relay device for NI project iTVA-2605, it was observed that the device was being tested with an electrical current value that was approximately 2.5 times less than required by the manufacturer's technical specification for the inductive load application of the relay; (b) During testing activities of an AC contactor device for NI project
- 8PC-2475, it was observed that a resistive load was being used in lieu of the required inductive load, and that the required adjustable AC power supply was not being used; (c) A review of test results for NI project f1841, in conjunction with discussions with NI personnel, detemined that the voltage meter that was recorded as being used has a maximum readout capability of 10 airperes, but the test results indicated that the total load of the perfomed test was 11 amperes; (d) Procedure 9.7.6,03, "Procedure for Issuing an Equipment Qualification Procedure or Report," does not reference or indicate that the IEEE-323 EQ report format requirements are necessary to prepare and establish NI's EQ reports; and
l
'. ' (e) Even though typical NI procedures such as 9.7.10.10. "Operational Aging of Push Button and Selector Switches," require that the technician record the indicated voltage and current following each operation (cycle), it was revealed that this is typically not per-formed.
An extreme example was noted where the lab technician recorded two out of 6000 cycles. One reading was the starting value and the other was the last cycle value.
5.
Criterion XVII, "Quality Assurance Records," of Appendix B to 10 CFR c
Part 50 requires, in part, that sufficient records shall be maintained to furnish evidence of activities affecting quality and shall include at least: results of reviews, inspections, tests, audits, monitoring of work perfortnance, and closely related data such as qualifications of personnel.
Contrary to the above, it was found that the NI personnel records did not indicate adequate evidence of qualifications for several current and past NI ernployees. The following NI employee files were found to be either incomplete, incorrect, or indeterminate as to the relevant job experience and education. The initials of the applicable personnel are: HB, CG, GW, SS DW, GJ, SDJ, LH, and PB.
6.
Criterion XVIII, "Audits," of Appendix B to 10 CFR Part 50, requires, in part, that the audits be performed by personnel not having direct responsi-bilities in the areas being audited.
Section 4.4 of NI's QAP #18.10.00 "Auditor Training Program," requires, in part, that all personnel conducting an audit shall be independent of any direct responsibilities for performance of the activities which they audit.
Contrary to the above, NI management allowed a QA inspector, who had direct QA department responsibilities, to be the lead auditor for the last two QA department annual audits. The report numbers are QA-86-AE, dated 12/23/86, and QA-85, dated 12/6/85.