IR 05000423/1985038

From kanterella
(Redirected from ML20137W538)
Jump to navigation Jump to search
Insp Rept 50-423/85-38 on 850715-19.No Violation Noted.Major Areas Inspected:Preoperational Test Program,Including Test Assessing,Emergency Diesel Generator Status,Esf Test Status, QA & QC
ML20137W538
Person / Time
Site: Millstone Dominion icon.png
Issue date: 09/12/1985
From: Eselgroth P, Vankessel H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20137W527 List:
References
50-423-85-38, NUDOCS 8510040335
Download: ML20137W538 (12)


Text

__ _ _ _ . _ _ _

,

.

.

4 U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report N Docket N License N CPPR-113 Category B Licensee: Northeast Nuclear Energy Company P. O. Box 270 Hartford, Connecticut 06101

Facility Name: Millstone Nuclear Power Station, Unit 3

]

Inspection At: Waterford, Connecticut Inspection Conducted: July 15-19, 1985 Inspectors-H'. F. Va'1 ssel," Reactor Engineer b/2- date 8[

Approved by: 9-//-TfE P. W. Ese}g oth, Chief, Test Programs date Sectio # 0B, DRS

!

l Inspection Sumnary: Inspection on July 15-19, 1985 (Inspection N /85-38}

I Areas Inspected: Routine unannounced inspection of the preoperational test

, program, inc1tding Test Assessing, Emergency Diesel Generator Status, ESF

Test Status, Quality Assurance and Quality Control, independent inspection and i

measurements associated with: valve stroke times for ESF related valves. The inspection involved 44 hours5.092593e-4 days <br />0.0122 hours <br />7.275132e-5 weeks <br />1.6742e-5 months <br /> on site by one NRC region based inspector.

!

.

l 8510040335 850917 PDR ADOCK 05000423  :'

G PEWt

.

r-- , w- wgr-1+te af- w w 9 4g- m- gr e=**r- 9-- "

9-WT '--'" ' " = = ' ' * ' ' ' P'-- +"-+ Mr'-- + - -N-

--P-----Hg+49e -- -

p e--" ' * 'Ww'-

.

.

.

OETAILS 1.0 Persons Contacted Northeast Nuclear Energy Company (NNECo)

A. Cardillo, Startup Engineer J. Dimarzo, Startup Engineer E. Fries, Startup Engineer M. Gentry, Assistant Startup Supervisor T.Lyons, Startup Engineer

  • 0. Miller, Jr. , Startup Manager D. Prawdzik, Startup Engineer
  • Rose, QA/QC Inspector
  • R. Thompson, QA/QC Inspector Northeast Utilities Service Company NUSCo)

"D. Blumenthal, QA Engineer R. Bradley, Instrument Technician B. Carlson, Project Engineer

  • J. LaWare, Engineering Technician
  • Orefice, Project Engineer Stone and Webster Engineering Corporation (SWEC)

W. Matejek, Project Advisory Engineer U.S. Nuclear Regulatory Commission (USNRC)

  • R. J. Summers, Project Engineer

2.0 Licensee Actions on Previous Inspection Findings 2.1 (Closed) Unresolved Item, " Vibration Induced Valve Failures" (423/85-10-01)

References:

(1) Interoffice memorardum, "IE Information Notice 83-70, Supplement 1",

from N. Barrett to W. Ramsden, dated April 2, 1985 (2) Problem Report Response (SWEC) PR-P-148, " Loose anti-rotation stem clamp device on Anchor / Darling Valves, dated Sept. 19, 1984

-

, __ _ _ - __ - _ . _ _ _ . _ _ _ . __ __ . _ . . _ _ _ _ . - - _ _ _ _ .

.

,

i 3

,

! (3) Problem Report Response (SWEC) PR-P-148, " Loose anti-rotation stem clamp device on Anchor / Darling Valves (interim response)",

dated May 16, 1984 (4) Interoffice Memorandum, " Problem Report PR-P-148, Loose Anti-rotation stem clamp device on Anchor / Darling valves,"

W. M. Eifert to Distribution, dated November 29, 198 (5) Letter Anchor / Darling Valve Company, to Stone and Webster Engineering Corp., "P.O. No. 310501 Shoreham Nuclear Power Station, Unit 1," dated April 5,1983, by J. D. Cartwright,

} letter attached to reference (4) abov Discussion The referenced correspondence shows that IE Notice 83-70 and its Sup-plement I have received adequate attention by the licensee over a two year period. While some of the problems, discovered by the Licensee in the course of the investigation, remain to be solved, the licensee's system for resolution of these remaining items appears adequate.

Unresolved Item (423/85-10-01) is hereby close .2 (Closed) Unresolved Item, " Vendor action on sheared pinion keys on i

Limitorque S8-0-25 operators for W-EMD motor operated valves",

(423/85-27-02)

i

!

i References

$

(1) Problem Report Response (SWEC), PR-P-129 (revised), " Repetitive failures of Limitorque operator SMB-4 motor to shaft key," dated j July, 1984

(2) Interoffice Memorandum, " Sheared pinion keys in Limitorque SB-0-25 Motor operators supplied on Westinghouse EMD valves",

j from W. M. Eifert to Distribution, dated April 12, 1984

]

'_ (3) Problem Report (SWEC), PR-P-150, " Sheared pinion keys in Limitorque S8_-0-25 motor operators supplied on Westinghouse EMD valves", from F. Sestak, Jr. , undated.

J j

(4) Problem Report Response (SWEC), PR-P-150, " Sheared pinion keys in Limitorque SB-0-25 motor operators supplied on Westinghouse

EMD valves" dated July 25, 1984

i l

)

. . - . . . . . . _ . . . _

. - . - . - - , , - - - - _ _ - _ - _ _ _ - _ _ - - - .-- . -.

.

.

(5) Letter from Westinghouse, Water Reactor Divisions, to NUSCo, Millstone 3, "Limitorque Motor Operators Sheared Pinion Keys",.

by R. L. Hoter, dated May 10, 1983 (6) Letter from NUCSo to USNRC, Region 1, " Reporting of Potential Significant Deficiencies in Design and Construction: Failure of Pinion Gear Shear Keys in Limitorque Model 880 (50-25)", by W. G. Council, dated June 10, 1983-Discussion The referenced correspondence indicates that the particular problem does not apply to any of the Limitorque motor operators used at Millstone-3. Westinghouse {W), however, went one step further towards safety by replacing the pinion keys in all SB-0-series motor operators on W-EMD manufactured valves (ref. 6). The inspector has no further questions on this outstanding item. Unresolved Item (423/85-27-02)

is hereby close .3 (0 pen) Unresolved Item, " Valve Position Indication Problems",

(423/85-02-01)

Reference (1) Status report (SWEC) " Valve Position indication Problems", dated July 17, 1985 Discussion i

The individual valve position indication problems are being resolved by the licensee. All of the identified problems are tracked by Design Deficiency Report (DDR), Unsats (UNS), Engineering and Design Change Request (E&DCR), etc, including the two new generic items: (6)

" Wrong description on control switch label" and (7) " Reach rod post-tion indicator not installed". The number of valves with incomplete .

!

information is being reduced. The inspector will continue to follow the licensee's corrective actions on this unresolved ite .0 Preoperational Test Program 3.1 Test witnessing Scope The inspector witnessed selected steps of the following Engineered Safety Feature (ESF) and Hot Functional Test (HFT) related tests:

i

. . - . - - . - . . . , - - - . , .. . - . - . ,, - - .. - - - - . .

-

. , . . _ _ _ _ . __ _ _ _ _ _ . . ._ ._ .. . - _ - - _ _ _.,

'

!

i i *

Low Pressure Safety Injection (T3307AP001)

4 *

High Pressure Safety Injection (T3308-P002) -

i *

Service Water (T3326-P)

}

Safety Injection Accumulator Test ( T3307 AP003)

Test witnessing by the inspector included observations of: '

Overall crew performance

1 *

Use of latest revised and approved procedure available and in j use by test personnel

Designation of one person in charge of conducting the tests

Availability of sufficient test personnel to perform the tests i

Coverage of test prerequisites

'

Use of acceptance criteria to evaluate test results

Verification that plant supporting systems are in service

Service status of calibrated special test equipm:nt required by j the test procedure

Adherence to the test requirements of the test procedure during the test

Timely and correct actions by test personnel during the performance of the tests

,

,

j Data collection for final analysis by proper personnel The inspector made independent measurements during the test (see j Section 5)

.

Discussion f The inspector witnessed stcps 7.1.22 through 7.1.34 of procedure T 3307 AP001. Rev 0, " Low Pressure Safety Injection (LPSI)". The j

objectives of this partial test are to verify the proper functioning of various control circuits of the LPSI system as observed on the ,

main control boards in the control room. The inspector noted that verification of valve closure in the field had been eliminated in

,

i

'

. . . . _ . _ , . _ _ _ . - . - - - - - - _ - - _ _ _ - - - - . _ . , - . . . _ . - -

--

. , , - . - - - - . . - _ , _ - . _ _

.

.

procedure change No. 3 The test engineer explained that these steps had been eliminated because the phase-1 tests for these valves had all been done, corrections had been made, and the valves were known to function well. Change No. 35 is expected to be approved by the Joint Test Group in the near future. Disapproval would mean re-petition of the tes It was also noted by the inspector that the test engineer was adhering strictly to the administrative requirement He assigned a number of "Unsats" and DDR The inspector witnessed the opening and closing of remotely operated valves in accordance with procedure T3308P002, Rev.0, "High Pressure Safety Injection, i.e. steps 7.10.4/5 and 7.11.1/ The inspector verified the open/close times of these steps to be 10.04, 10.02, 9.5 and 9.0 seconds respectively. The inspector also observed the opening and closing of valves 3SIH* MV8801 A and B (Steps 7.9 and 7) and 3SIH*CV 8871 and 8823 (Steps 7.99.26 and 14) upon receiving a simulated ESF signal. Annunciator 2-33 did not come on and GPII annunciator did not flash as required. "Unsats" were filled out against these failures. It was noted by the inspector that the valve open/

close time table, shown under the acceptance criteria in the proced-ure, indicated a different time of closure for MV8821 A and B, (i.e, 10 and 60 seconds, respectively). After further checking, the test engineer determined that this was a typographical error in the tabl Both values for opening and closing of these two valves should be 10 seconds. Appropriate action was taken to ensure that the table of the procedure would be correcte In the course of conducting the test of procedure T3308P002, several wire lifts or jumpers had to be installed temporarily to obtain the desired simulation ESF signals. The inspector closely followed the installation of these temporary changes in accordance with a sub-routine procedure, and their subsequent removal to restore initial conditions. The test engineer had good control over these restora-tion step The inspector witnessed testing of the logic of control circuits for the Service Water System, in connection with the ESF tests as perform-ed in accordance with steps 7.1.20 through 56 of procedure T3326-P, Rev. O. Simulation signals were introduced at the EDG Loading Se-quencer of train B to get the pump to start (step 7.1.20). Jumper installation was accomplished in accordance with the signal simulation procedures on form PU-590, Rev 0.

i

,

_, .. - -. .- .. - . _ _ . _ _ = _

.- - - - , - _ . - . - .

.

l 7 Again, as under procedure T3308-P002, the inspector closely followed the restoration steps which, in this procedure, followed immediately after accomplishing the subtask. The test engineer closely followed the requirements of the administrative procedures with respect to the

, verification of "Unsats", DDR's completion of form PU-590, observance of most recent test changes, et The time for the interlock action upon opening of motor operated valve MV-4 (step 7.1.22) was obtained two ways. The first method was to check the time at the main control board, the other method checked the time at the relay locatio The times were 10.0 and 12.04 seconds, respectivel The most conservative number (12.04) was noted in the procedure check lis It was noted by the test engineers that test change 13 forgot to put restoration steps in. The test

,

engineer will make another test change to have these steps included, i

For Step 7.1.26 the intent is to assure that manual cross connects with the other train (A) are closed to prevent water movements to.the i

other train. This check had been requested by the test engineer but i

the procedure as written will not accomplish that objective. Another test change will be necessar Some problems were experienced with test change No. 4 in the conduct i of step 7.1.30, 7.1.33 and 7.1.39, step 7.1.39. In step 7.1.39, a i

breaker did not close as expected. DDR541 was written to take care of the problem. The test was interrupted at this point to determine why the test steps did not track the existing logic of the control circuit as shown on logic diagram LSK9-10A (dwg No. 12179). The test was continued at step 7.1.40. The inspector noted that the test engineer re-established start conditions for the test as required after a test interruption. The performance of steps 7.1.40 and up established that the logics of LSK9-10A were satisfie It was noted by the inspector that the logics of the A and C pump were different from those of the B and D pump with respect to local operation. The ESF signal will not come through to the set of pumps put in the local mode of operation. This departure from normal logic

was introduced via a design modification intended to satisfy the fire protection requirements of Appendix R. These changes in ESF logic appear to.be acceptabl Several "Unsats" were identified in the course of conducting step 7.1.40 through 56.

j- For the partial test performed per procedure T3307AP003, Rev 0, the inspector witnessed steps 7.2.1 through 10. These steps involved, amongst others, the determination of the closure time for valves

,

CV8825, 8890A, 8880, and 88908 which were 3.3, 3.7, 5.2 and 3.3 L seconds, respectively.

i

!

i t

.

1 .- - _ . - . _ . - .- _ - - --. , . - _ - - _ . - _-

- _ , , _ _ - - . - . . . _ . - _ -_ --. - . _ . - . . - . - -

.

!

4 Findings

}

! Test results observed by the inspector indicated that acceptance criteria had been met for those portions of the test that had been i witnessed. No items of non-compliance were identified.

3.2 Emergency Diesel Generator (EDG) Status Fuel oil system flushing on EDG-A continued. Vendor requirements on the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> full load and overload (10%) test runs for EDG-8 were

,

j satisfie The licensee, however, wants to perform a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> test run (per procedure T3346 AP004) on EDG-8, prior to the ESF tests, without EDG trips. Such trips had been experienced in 3 prior

!

attempts as witnessed by the inspector. Low Jacket water pressure j

j was diagnosed to be the cause of at letst two of these trips.

Remedial action was thought to be easy to accomplish and, hence, the next attempt is expected to be successful. Unfortunately, EDG-8 '

received a batch of lubricating oil contaminated 'with pieces of rubber. Cleaning of the luue oil system was in progress. After the cleaning operatian EDG-B should be ready for the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ru .3 ESF Status

+

I It is presently anticipated by startup management that the ESF_ tests 3 INT-2003 and 3 INT 2004 can be started in early August (2 days later

than the current date for the previote inspection report 85-25). The j

same critical path items as reported in 423/85-25 persist. Further slippages in this schedule are anticipated.

l 4.0 QA/QC Interface

'

Scope

Since there are no hold points defined in any of the preoperational test i

procedures and there is no direct, in process, NUSCO quality control involvement, the inspector will closely follow the surveillance program executed by NUSCO-Q '

For additional background on NUSCO-QA involvement, see inspection report 423/85-03.

i  ;

) Discussion i

The inspector reviewed the NUSCo Quality Assurance Surveillance Reports j listed below.

i l

1 i

- . - ~ , _ . . , - - -- , ., r ,-, _ , . . . . - . . . - . , . _ . - ,. - . . . . , . -. ,

. - . - .

.

These surveillances are associated with the preoperational test of systems involved with the ESF tests 3 INT 2003 and 4 as pre-requisites. These surveillances are:

TC-3431, dated 3-11-85, " Containment B SI Accumulator", test procedure T3307AP00 ;

TC-3416, dated 3-6-85, "t ow Pressure Safety Injection System", test procedure T3307AP001 TC3416 shows NUSCO QA involvement in the process of developing test proce-dure changes. The problem identified by QA and the test engineer involves the lack of adjustment in the total developed head calculations for pumps for the position of the test gauges relative to the pump center lin For '

most. cases, these gauges are not located at the pump centerlin Follow-up on this item

  • '

appears to be adequat Findings t

No violations or non-compliances were -noted in the reviev of the.NUSCO *

QA Surveillance reports mentioned abov . Independent Inspection and Measurements Scope In parallel with the Tech. Spac. team efforts (Inspection Report 50-423/ j 85-37) in the area of valve open/close time requirements, the inspector '"

independently surveyed the a'ct' val values of open/close times for-the valves pertinent to the team's comparison effort Discussion The ' Tech. Spec; team had ' discovered some anomalies in open/close times of

, valves when comparing the values appearing in the FSAR table 6.2.65 with those of the Technical Specifications (table 6.2-2). The inspector was in

'

tne position to witness and independently measure the> stroking of some

valves pertinent to the team's findings. In addition, the inspector wit-l nessed and surveyed the stroking of other valves partinent to the team's

efforts. The results of the inspector's efforts are summarized in a table

in Attachment A. . The table identifies the valve stroke times measured in-j dependently by the inspector, f

1 * Findings-

'

\

j

The , inspector identified no-violations, deviations, or other noncompli-

,

ances within the scope of this independent inspectio !

p -

,

.

i

'

\! '

!! <t

3 -s l _

>

cv ,

.~

.

6.0 Technical Specification Team (TS Team) Assistance The inspector assisted the NRC's TS team during their second week at the site for the TS inspection. The inspector prepared the table in Attachment A in anticipation of the TS team's needs for the comparison effort on the valve stroke times identified in tables of the FSAR and the T.S. (see Section 5 above for details.)

The inspector participated in the exit interview conducted by the T.S. Team on July 19, 1985. A separate inspection report will be produced for the TS Team inspection (423/85-37).

7.0 Exit Interview At the conclusion of the site inspection on July 19, an exit meeting was conducted with the Licensee's Senior representative: (denoted in para-graph 1). The findings were identified and previous inspection items were discusse At no time during this inspection was written material provided to the licensee by the inspecto ~

_

-

,

,~ ,

.

,

6.0 Technical Specification Team (TS Team) Assistance The inspector assisted the NRC's TS team during their second week at the site for the TS inspection. The inspector prepared the table in i

-

Attachment A in anticipation of the TS team's needs for the comparison effort on the valve stroke times identified in tables of the FSAR and the T.S. (see Section 5 above for details.)

The inspector participated in the exit interview conducted by the T.S. Team on July 19, 1985. A separate inspection report will be produced for the TS Team inspection (423/85-37).

7.0 Exit Interview At the conclusion of the site inspection on July 19, an exit meeting was conducted with the Licensee's Senior representative: (denoted in para-graph 1). The findings were identified and previous inspection items were discusse At no time during this inspection was written material provided to the licensee by the inspecto "

.

.

ATTACHMENT A SAFETY INJECTION HIGH (SIH) SYSTEM VALVE OPEN/ CLOSURE TIME OPEN/ CLOSURE TIMES FOR VALVES, SE TYPE APP. A T3308 - P002 TEST OPER VALVE N OESCRIPTION FSAR TABLE 2.4 OPEN CLOSE CHG #4 MO 3STH*MV8806 Rust Supply Table s10/s10 1 .0 Yes M0 MV8801A Charg. Pump -/10 s60/s60 1 .8 Yes SI Header Isolation M0 MV88018 "A" Safety -/10 s60/s60 .02 Yes Inj. Pump to Hot Leg In M0 MV8802A SI Pump to -/10 s60/s60 1 .0 Yes Hot Leg In M0 MV8802B LP SI Char /10 s60/s60 1 .2 Yes M0 MV8807A Suction Cross None $10/s10 1 .0 Yes Connect

  1. MO MV88078 Suction Cross None s10/s10 10.01A Yes Connect

t MO MV8835 SI Cold Leg -/10.0 s60/s60 1 .0 Yes Master Isolation A0 CV8824 Test Line Iso. None NA/s10 -- N/A SI to 1/3 Hot Leg A0 CV8843 Charg. Pump NAi10.0 NA/s10 -- N/A Hdr. Cl A0 CV8823 Test Line NA/10.0 NA/s10 -- N/A Isol. SI to Cold Leg In M0 MV8920 "B" SI Pump None s22.6/ 20.08 18.08 Yes Miniflow Is s2 FM0 MV8821A "A Sa fety None s10/s10 1 .0 Yes Inj. Pump to Cold Leg In #MO MV8821B "B" Safety None s60/s60 1 .4 Yes Inj. Pump to Cold Leg In M0 MV8923A "A" Safety None s10/s10 1 .0 Yes Inj. Pump Suction Iso M0 MV89238 "B" Safety None 510/s10 1 .02A Yes Inj. Pump Suction Iso ,-

)

.

l TYPE APP. A T3308 - P002 TEST OPER VALVE N DESCRIPTION FSAR TABLE 2.4 OPEN CLOSE CHG #4 AMO MV8924 LPSI Chargng None s10/s10 9.06 7.02 Yes Change No. 4 is to allow separate sign-off and verification of functional and/or valve response timin # Independent measurement by HFV a UNSAT 4472 for exceeding 10.0, Was cleared by JT X Questioned by Mr. Beckman of TS Team