ML20149F929

From kanterella
Jump to navigation Jump to search
Insp Repts 50-413/97-08 & 50-414/97-08 on 970427-0607. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support
ML20149F929
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 07/07/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20149F893 List:
References
50-413-97-08, 50-413-97-8, 50-414-97-08, 50-414-97-8, NUDOCS 9707220372
Download: ML20149F929 (31)


See also: IR 05000413/1997008

Text

..

.- __ _- .

.

._.

.

.- . . _ . , _ _ . . ~ _ _ _ _ . _ . _ . _ _ . - . _ .

_ .

-_

!-

l

I-

U.S. NUCLEAR REGULATORY' COMMISSION

r-

REGION II'

L

Docket Nos:

50-413, 50-414

.

License Nos:

NPF-35, NPF-52

l

Report Nos.

50-413/97-08, 50-414/97-08

i

licensee:

Duke Power Company

Facility:

Catawba Nuclear Station. Units 1 and 2

l

Location:

422 South Church Street

Charlotte, NC. 28242

~ Dates:

April 27 - June 7, 1997

Inspectors:

R. J. Freudenberger, Senior-Resident Inspector

'

J. Zeiler. Acting Senior Resident. Inspector

P.

A.' Balmain. Resident-Inspector

R. L. Franovich, Resident' Inspector

,

N. Economos. Region II Inspector (Sections M1.3)'

'

b

H. L. Whitener, Region II Inspector (Sections M1.4)

Approved by:

-S. M. Shaeffer Acting Chief

Reactor Projects Branch 1

Division of Reactor Projects

l

(

l

i

i

.

.

Enclosure 2

! M{g

"

PDR

-

-

- . -

-

- . - -

.

.

-

,

, .

- .

i

EXECUTIVE SUMMARY

Catawba Nuclear Station. Units 1 & 2

NRC Inspection Report 50-413/97-08. 50-414/97-08

4

This integrated inspection included aspects of licensee operations.

maintenance, engineering, and plant support.

The report covers a 6-week

period of resident ins]ection: in addition, it includes the results of

announced inspections ]y Regional reactor safety and inspectors.

Doerations

A Violation was identified for inadequate and untimely corrective

e

actions to determine operability of a Main Feedwater Containment

Isolation Valve (1CF-51) following control room indication of low

nitrogen actuator pressure.

Contributing to this was an inadequate

.

alarm response which failed to specify the alarm setpoint range or

require actions to be completed within the safety significance and

Technical Specification (TS) allowed action timeframe for an inoperable

valve (Section 01.2).

The cuality of licensee's containment cleanliness inspections following

the lnit 2 End-of-Cycle 9 (2EOC9) refueling outage was poor and had

declined from previous outages.

However, the debris identified in the

i

Unit 2 lower containment would not have readily transported to the

Emergency Core Cooling System (ECCS) sump screens or impacted ECCS

performance. Appropriate corrective action to reinspect and remove all

debris from containment was performed (Section 01.3).

On May 9. a rapid power reduction from 100 percent power to 67 percent

e

power was implemented on Unit 2 as a result of a significant main

turbine hydraulic oil leak.

Identification of the oil leak by a non-

licensed operator was an example of good attention to detail.

Operations adequately controlled the power maneuver and activities to

repair the hydraulic oil leak were accomplished without incident

(Section 01.4).

A Non-Cited Violation (NCV) was identified for an isolated instance

where excessive overtime was not authorized. The overtime control

program was generally ef fective; however, several weaknesses were

identi fied.

For example, the absence of timesheet audits to determine

if unauthorized overtime in excess of Technical S]ecification guidelines

was being worked was considered a limitation of t1e licensee's overtime

control program.

No formal record. independent of payroll timesheets.

,

existed for monitoring hours worked.

As a result, no alternative means

for verifying that overtime (specifically excessive overtime worked by

exempt personnel who may perform safety-related functions) was being

provided.

(Section 06.1).

l

Enclosure 2

l

!

U

2

Maintenance

A NCV was identified for an inadequate procedure which resulted in the

e

inadvertent autostart of Nuclear Service Water (NSW) pumps.

An IFI was

identified regarding reportability of NSW system actuations (Section

M1.2).

The high number of equipment motor failures experienced over the last

e

couple of years was attributed in part, to organizational changes.

programmatic deficiencies, inadequate resources, high work loads and

management's failure to take a proactive role in this area. A NCV was

identified regarding these previous problems which was related to the

lack of procedures to control preventive maintenance, storage and

transportation of motors.

Following the completion of Self-Assessment-

and Root Cause Analysis inspections, necessary steps _to establish a more

o

comprehensive preventive maintenance program for electric motors were

established.

The present program provides-for adequate inspections.

testing, and trending of motors in storage and in use.

Procedures to

control receiving, storage and. transporting of motors within and out of

,

the_ Duke system have been established, . At the present time, engineering

and-technical resources in charge of the electric motor maintenance

i

program appear to be adequate (Section M1.3).

Management focus on air operated valve maintenance has .resulted in

e

improved performance. Air operated valve program elements were in place

and an Engineering Directive was in development. Observed maintenance

was performed well with good management involveme'nt (Section M1.4).

Enaineerina

The licensee's pursuit and resolution of a small nonconservative thermal

e

power calculation error identified in the new plant computers was an

example of good questioning attitude (Section E1.1).

,

The licensee's initial evaluation of a potential vulnerability involving

e

air entrainment in the suction aiping of the Auxiliary Feedwater System

and subsequent air binding of t1e pumps was prompt and conservative.

Effective interim compensatory actions were implemented to ensure

Auxiliary Feedwater System operability until completion of the

evaluation. An Unresolved Item was identified regarding a potential for

1

air binding the Auxiliary Feedwater pumps (Section E2.1).

Plant Sucoort

Overall, radiation control practices were found to be proper.

In one

e

instance (i.e;. higher than normal radiation background in the men's

auxiliary building change facility), radiation protection personnel did

not demonstrate a questioning attitude and initiate appropriate actions

until questioned by the inspector (Sections R1 and R2)

'

The licensee's performance during the annual emergency exercise was

e

considered appropriate.

Particularly good performance by personnel in

the Operations Support Center was noted (Section P1).

Enclosure 2

i

_ - -

. . _ ,

_

, _ ,

_

,_

.

.

,.

3

Maintenance of the protected area perimeter fence and conduct of

e

security and safeguards activities were found to be appropriate (Section

S1).

l

Enclosure 2

..

.

.

.

--

.

. .

!

Report Details

!

Summary of Plant Status

Unit 1 operated at or near 100% power during the inspection period.

Unit 2 was shut down for a refueling outage at the beginning of the inspection

report period.

The Unit entered Mode 2 (Startup) on May 1 and reached full

power on May 8.

On May 9. power was reduced on Unit 2 to 67% in order to

repair a main turbine hydraulic oil leak.

Unit 2 operated at or near 100%

power for the remainder of the inspection period.

Review of Uodated Final Safety Analysis Reoort (UFSAR) Commitments

While performing inspections discussed in this report, the inspector reviewed

the applicable portions of the UFSAR that were related to the areas inspected'.

The inspector verified that the UFSAR wording was consistent with the observed

plant practices, procedures, and/or parameters.

I. Doerations

01

Conduct of Operations

01.1 General Comments (71707)

The inspector conducted frequent control room tours to verify proper

staffing, operator attentiveness and communications, and adherence to

approved procedures.

The inspector attended daily operations turnover

and Site Direction meetings to maintain awareness of overall plant

operations.

Operator logs were reviewed to verify operational safety

,

and compliance with Technical Specifications (TS).

Instrumentation,

computer indications, and safety system lineups were periodically

reviewed from the Control Room to assess operability.

Frequent plant

tours were conducted to observe equipment status and housekeeping.

Problem Identification Process (PIP) reports were routinely reviewed to

assure that potential safety concerns and equipment problems were

reported and resolved.

In general, the conduct of operations was professional and safety-

conscious.

Good plant equipment material conditions and housekeeping

was noted throughout the report period.

S)ecific events and noteworthy

observations are detailed in the sections Jelow.

01.2 Inocerable Main Feedwater Containment Isolation Valve (71707)

l

a.

Insoection Scooe

The inspector reviewed the licensee's failure to promptly determine the

operability of Unit 1

"C" Main Feedwater Containment Isolation Valve

,

'

(CFCIV) ICF-51 following receipt of a control room alarm indicating low

valve actuator pr' essure.

Seventeen hours following receipt of the

alarm, actions were completed to measure actuator accumulator pressure.

At that time it was determined that pressure was below the setpoint for

valve o)erability. The licensee determined the valve had been

inoperaale since the alarm was received, resulting in a failure to meet

Enclosure 2

i

.

-

. - - . - . - . - - - - - - -

.. - . - -

.. - . . .

- -

w

,

m

i

2

,

j

the allowable action times of TS 3.6.3 for an inoperable containment

isolation valve. .The inspector discussed the incident with operations.

,

l

engineering. and safety assurance personnel, as well as reviewed

associated alarm responses and PIP 1-C97-1037 involving this incident.

r

,

.

.

b.

Observations and Findinas

.

On -April 3,1997, at 6:08 a.m. . 'the Unit 1 Control Room operators

'

received a computer alarm indicating low pressure in the accumulator

.

-that-supplies nitrogen to the actuator which closes the "C" CFCIV. ICF-

['

51; A work request was initiated for maintenance personnel to determine

the actual pressure in the accumulator.

Following shift turnover,'the

j

L

work request was assigned to the Single Point of Contact (SPOC)

l

l

maintenance staff.

However. instead of working this job during day-

shift, operations directed SPOC to work planned activities on the

Component Cooling Water System associated with the entry of.both units

in a 72-hour TS action statement.

At 7:00 p.m.

when the on-coming

night shift returned. it was realized that accumulator pressure had

still not been checked.

At 11:18 p.m., after resolving problems in

locating the necessary pressure instrumentation. SP0C personnel

installed local pressure gauges and measured 2000~psig in the

accumulator. The required pressure necessary to ensure the valve would

close was 2050^psig.

The accumulator was recharged to its normal

'l

pressure of 2780 psig. .The licensee initiated PIP 1-C97-1037 to address

the potential past inoperability of the valve and the reason why the

pressure measurement was not performed until more than 17 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br />

following receipt of the alarm. This inadequate and untimely response

is considered a violation of 10 CFR 50. Appendix B. Criterion XVI for

inadequate corrective actions

On May 8. the licensee determined that ICF-51 had been inoperable during

the aeriod that accumulator pressure was below 2050 psig. This pressure

was )ased on the valve vendor's calculated pressure for ensuring that

there was sufficient nitrogen pressure to close the valve. Since the

,

exact time that pressure decreased below this setpoint could not be

conclusively determined the time used was based on when the alarm first

annunciated.

The inspector reviewed the actions required by the computer alarm

response for low CFCIV accumulator nitrogen pressure. .The actions

required operations to contact the Operations Work Manager and initiate

a work request for maintenance to determine operability (via checking

the accumulator pressure) and recharge the accumulator. The alarm

response procedure was determined to be inadequate, in that, it failed

to provide the actual alarm setpoint range (2050 - 2150 psig) or provide

actions for checking nitrogen pressure commensurate with the timeframe

allowed by TS 3.6.3 for a potentially inoperable CFCIV. This is

considered a violation of TS 6.8.1.

The operators had believed that the

setpoint was 2100 psig and were unaware that the pressure switch for the

alarm could have been set anywhere between 2050 and 2150 psig. This

misunderstanding resulted in lower priority being placed on ensuring

actions to check nitrogen pressure were accomplished within a reasonable

.timeframe. The inspector also noted that the associated work request

Enclosure 2

I

1

.

_ - . . . . . . _ _ _ .

_

. . . _

_ _ _ . _. _ . _ _ . _ . _ _ . ... _ .. _ _ _

,

3

was given a priority of "I" indicating routine scheduling and not "E"

(emergent) for high priority work having potential operability or TS

consequences.

The ins)ector reviewed the safety consequences of the valve being

,

inopera)le during the period. The main feedwater system would have

still been capable of performing its safety function even if 1CF-51 had

failed to close. The safety function of 1CF-51 is to terminate

,

feedwater flow in both directions in order to prevent excessive forward

feedwater flow and/or steam generator blowdown during various design

basis accidents. The valve closes automatically on Phase A Containment

Isolation and Feedwater Isolation signals. The prevention of excessive

-forward feedwater flow would have been mitigated by main feedwater pump

trip functions and isolation of the feedwater flow control valve which

,

also receives a feedwater isolation signal.

Steam generator blowdown

isolation would have been accomplished via the feedwater isolation check

valve located directly upstream of 1CF-51.

TS 3.6.3 states that if a containment isolation valve is inoperable the

valve shall be restored to operable within four hours or closed or

otherwise be in Hot Standby in the following six hours.

Since the valve

was potentially inoperable for-17 hours and 10 minutes, the licensee had-

failed to meet the action requirements of.TS 3.6.3.

c.

Conclusions

The inspector determined that operations staff actions for a control

room alarm indicating potential inoperability of CFCIV 1CF-51 were

inadecuate and untimely.

Contributing to the lack of work priority

placec on determining valve operability was an inadequate alarm response

which failed to specify the alarm setpoint range or require actions to

be completed within the safety significance and TS allowed action

timeframe for an inoperable CFCIV.

This issue was identified as a

violation of TS 6.8.1 and 10 CFR 50. Appendix B. Criterion XVI

(Violation 50-413/97-08-01:

Inadequate Alarm Response Results in

. Inadequate and Untimely Corrective Actions for Valve Operability

Determination.)

<

01.3 Unit 2 Containment-Cleanliness Walkdowns (71707. 61726. 62707)

a.

Inspection Scooe

On April 28. the inspector identified several small items of trash and

debris inside the Unit 2 containment building during routine walkdowns

performed following the Unit'2 refueling outage. The inspector reviewed

l

the' licensee's corrective actions to perform additional inspections of

i

the containment and PIP 2-C97-1453

i

!=

b.

Observations and Findinas

The walkdown was performed during Mode 3 prior to the unit startup from

,

i'

refueling outage 2EOC9 after the licensee had completed TS recuired

containment cleanliness inspections. The inspector identifiec. debris

Enclosure .2

.-.

--

..

- - - .

.

-..

.

.

..

-

.

.

- - -

l

!

l

4

l

and trash, including a plastic face shield, a watch discarded tie

wraps. nuts and bolts.

The inspector observed that cleariliness

standards had declined from observations made during previous outages.

The licensee initiated a PIP and performed additional inspections of

lower containment. Approximately 15 pounds of additional debris were

removed by the licensee following these inspections. The debris was

found mainly inside the crane wall area in lower containment which is

not directly adjacent to the Emergency Core Cooling System (ECCS) sump

screens.

Debris is not easily transportable to the ECCS sump screens

from these areas and would not have adversely impacted ECCS performance.

l

l

The inspector found acceptable conditions in the pipe chase areas

directly adjacent to the ECCS sump screens. These areas were in much

better condition than those located inside the crane wall.

'

c.

Conclusions

The quality of licensee's containment cleanliness inspections following

the Unit 2 End-of-Cycle 9 (2E0C9) refueling outage was poor and had

declined from previous outages.

However, the debris identified in the

Unit 2 lower containment would not have readily transported to the ECCS

. sump screens or impacted ECCS performance.

The licensee took

appropriate actions to reinspect and remove all debris from containment.

01.4 Unit 2 Main Turbine Hydraulic Oil Leak and Power Reduction (71707.

62707)

a.

Insoection Scope

On May 9 the licensee performed a rapid power reduction of Unit 2 from

100 percent power to 67 percent power as a result of a significant main

turbine hydraulic oil leak.

The inspector observed control room

activities during the

aow(r reduction and reviewed the licensee's

'

actions to repair the lydraulic oil leak.

b.

Observations and Findinas

The hydraulic leak was discover J by a non-licensed operator who was

investigating an unusual odor in the Unit 2 turbine building. The leak

was caused by a failed 0-ring located on a solenoid valve (2LH-93)

associated with main turbine combined intercept vahe CIV-3. At the

time of discovery the leakrate was estimated at 2 gpm and approximately

75 gallons of hydraulic oil had been lost.

The licensee initiated the

power decrease of Unit 2 to less than the automatic reactor trip

permissive interlock power level for a main turbine trip. A main

turbine trip would have occurred if the hydraulic oil leak had

continued.

The inspector observed that control room activities were

well controlled during the power reduction.

The licensee was successful in reducing the leakage from a steady stream

of about 2 gpm to a leakrate of several drops per minute.

Inspections

l

of similar solenoid valves ce performed on both units and no other

'

instances of leaking valves were identified. After the leak was

Enclosure 2

.

.

.~.

. .

- . - - - -

- - . - - . -

- .

, . ~

,

5

stabilized and the main turb'ine hydraulic oil reservoir was replenished.

the licensee returned the unit to full power and initiated frequent

monitoring of the leak.

The licensee completed repairs on May 13 to

seal the leak-(Work Order 97040075-02),

c.

- Conclusions

identification of a main turbine hydraulic oil leak.by a non-licensed

operator was a good example of diligence and awareness of plant

equipment conditions which prevented a main turbine / reactor trip. The

control room staff performed well during the subsequent rapid power

-

reduction and licensee actions to repair the leak were appropriate.

06

Operations Organization and Administration

06.1 Control of Overtime (71707)

a.

Insoection Stone

The inspector performed an overtime audit:to determine if overtime hours

were worked in accordance with regulatory requirements and the

licensee's administrative controls during the most recent ~ Unit 2

refueling outage.

The inspector reviewed:

Catawba Technical

3

Specification 6.2.2. Unit Staff: NRC Generic Letter 82-12. Nuclear Plant

Staff Working Hours. and associated clarifying correspondence: NRC Generic Letter 83-14. Definition of " Key Maintenance Personnel:" and

Duke Power Nuclear Station Directive 200, Overtime Control.

'

b.

Observations and Findinas

Technical Specification 6.2.2.f 3rovides guidelines for limiting the

i

working hours of station staff w1o perform safety-related functions.

In

part, the guidelines state that:

(1) an individual should not be

permitted-to work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> straight, excluding shift turnover

time: and (2) an individual should not be' permitted to work more than'16

'

-hours in any 24-hour period, nor more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in any 48-hour

period., nor more than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in any 7-day period, all excluding shift

turnover time.

The TS also states that any deviation from the

,

guidelines shall be authorized by the Station Manager or his designee.

'

or higher levels of management. in accordance with established

procedures and with documentation of the basis for granting the

deviation.

4

l

Nuclear Site Directive (NSD) 200 Overtime Control, effective date

December 27, 1996, provides administrative guidance to limit the working

hours of peo)le who perform safety-related functions.

The NSD

,

l

recognizes tlat excessive working hours can impact an employee's fitness

i

for duty and states ~that employees working excessive hours will be

!

assessed for fitness for duty each day a limit is exceeded. The NSD

!

specifies that all work hours must be considered when calculating

i

overtime. delineates the guidelines in TS 6.2.2.f. and requires that

'

authorization to exceed-the guidelines be obtained from one member of

,

line supervision and the Station Manager or designee in advance.

'

Enclosure 2

t

,,-

y

g.

y

a--

-

e-1

,,

-+4--

3

-

q

,,.-

p

r

  • - + " " " * ' "

_.

.

._

__

_

..

_

__

_

_

. _ _

6

!

Authorization of overtime must be documented per NSD 200. Appendix A,

'

" Request for Work Hours Extension."

l

-The licensee routinely reviews work hour extension forms to determine if

they are being filled out completely and in accordance with NSD-200.

Station PIP 2-C97-1821 was initiated to document numerous violations of

i

NSD-200 that had occurred during the recent Unit 2 refueling outage and

l

were identified during the subsequent periodic review of the work hour

extension forms.

.

To determine if the licensee was controlling the use of overtime in

compliance with TS 6.2.2.f. the inspector obtained payroll timesheets

for a sample of exempt (salaried) and non-exemat (wage-earning) plant

workers.

The inspector identified instances w1ere the timesheets of

non-exempt plant workers indicated that overtime had exceeded TS limits.

The inspector requested copies of the completed " Request for Work Hours

Extension" forms for individuals who worked overtime in excess of

administrative and TS guidelines. The inspector received authorization

forms for the majority of instances where overtime was excessive.

For

i

specific instances, where authorization forms were not available, the

'

licensee explained that either the limits were exceeded by small amounts

of time that were considered " shift turnover" time, or the timesheets

inaccurately indicated that time was charged to work that was not

performed.

The latter explanation involves payment for work that was

scheduled. but postponed without sufficient prior notice.

Employees and

vendors were compensated for their scheduled time even though they were

'

not onsite.

The inspector identified one instance where an individual's

authorization for overtime was not available. A work hour extension

form was provided to verify that authorization had been given for the

individual's crew to perform critical outage support activities:

however, the supervisor failed to recognize that the individual's name

had.been inadvertently left off the list. The inspector considered this

oversight an isolated violation of the NSD-200 requirement that

excessive overtime be authorized. This isolated occurrence did not

indicate any programmatic failure to control overtime or pervasive non-

compliance with TS and administrative requirements. The inspector is

not aware of any adverse impact on plant equipment as a result of the

violation. Therefore, this violation, which is of minor safety

significance. is characterized as Non-Cited Violation (NCV) 50-414/97-

08-02: Failure to Authorize Overtime in Excess of Administrative Limits,

consistent with Section IV of the NRC Enforcement Policy.

The inspector asked the licensee if reviews of timesheets were performed

,

to determine if overtime hours are being worked without the required,

l

documented authorization. The licensee responded that the scope of

l

their audits is limited to administrative reviews to ensure that the

work hour extension forms that are filled out are done so correctly and

i

l

in accordance with NSD-200 requirements: they do not review timesheets

j

i

to determine if unauthorized overtime is being worked. The inspector

'

considered such audits to be potential performance measures for

determining the effectiveness of NSD-200 and the program it governs.

Enclosure 2

1

7

The absence of these audits .or some alternative process for measuring

the effectiveness of the program in controlling the use_of overtime was

considered a limitation of the program.

During'the course of the inspection the inspector identified a

discrepancy between one em)1oyee'.s timesheet and onsite/offsite data

provided to the-inspector-Jy the. security organization. The

' onsite/offsite data reflected the times that the employee arrived onsite

and left the site.

This data'was availabic only from A)ril 21 to April.

30. 'The timesheets indicated that the employee had worced 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> a

day every day during tha month of April.

However. the onsite/offsite

data indicated that, between April 21 and April 27. the.em)loyee worked-

between 13 and 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> a day.

The inspector determined tlat, although-

the employee in question did not typically perform safety-related

functions during the outage, other employees who did perform safety-

related functions potentially could engage in similar time-recording

practices if no administrative procedure or process prevented it.

The inspector asked if an alternative (to payroll timesheets) record for

documenting hours worked was required; the licensee res-)onded that the

NSD required the individual and supervisor to keep tract of hours

worked,-and that no formal process for performing this function was

required.

The inspector quastioned the licensee's ability to monitor

the use of overtime when an L curate and correct record of hours worked

was not maintained for all employees, particularly exempt, salaried

employees who may not be compensated for overtime and, therefore, may

not document it on a payroll timesheet.

The licensee reiterated that

supervisors and individuals were expected to monitor the use of

overtime.'and that this expectation was the mechanism by which overtime

was controlled. The ins)ector considered that the absence of a formal

and auditable record of lours worked was a shortcoming of the licensee's

program for verifying .that TS requirements are met.

The inspector examined the provisions in NSD-200 for assessing an

employee's fitness for duty. The NSD states that employees working

excessive hours will be assessed for fitness for duty each day a limit

is exceeded, and that the assessment must be performed shortly before

overtime is to occur; specifically within the same day or same shift.

This provision allowed assessments to be Jerformed as many as 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

before the overtime work was to begin. T1e inspector determined that

the NSD may not provide adequate direction to ensure that a' fitness for

duty assessment would be performed in sufficiently close proximity to

the overtime work to ensure that the assessment was valid at the

beginning of the work.

c.

Conclusions

.

The inspector concluded that the isolated instance where excessive

overtime was not authorized constituted a minor violation of NSD-200.

which was characterized as a Non-Cited Violation. The absence of

timesheet audits to determine if unauthorized overtime in excess of'TS

guidelines was being worked was considered a limitation of the

licensee's overtime control program.

No formal record, independent of-

payroll ~ timesheets, existed for monitoring hours worked. As a result,

Enclosure 2

_ _

_ _ _

. _ _ _ _ _ . - _ _ _ _ _ _

_ _ _ _ . .

~ < _ _ _ _ , . . _

8

no alternative means for verifying that overtime (specifically excessive

overtime worked by-exempt personnel who may perform safety-related

functions) was being provided. The inspector did not identify any-

.

adverse impact on safety-related equipment or plant operation as a

result of these programmatic issues.

Followup of the licensee's

1

programmatic controls will be tracked as Inspector Followup Item-(IFI)

50-413.414/97-08-03: Overtime Control Program Limitations. Aside from

the programmatic issues noted. the inspector concluded that the

licensee's overtime control program was generally effective.

08

Miscellaneous Operations Issues (92901)

08.1

(Closed) Licensee Event Reoort (LER) 50-413/96-001:

Unit Shutdown

Required By Tuchnical-Specifications

1

This event was also discussed in NRC Inspection Report 50-413.414/96-01.

The licensee complied with TS time limits for performing the unit

shutdown. Acceptance criteria provided in procedures for verifying main

- feedwater pump runback circuitry status during reactor tri) breaker

testing were conservative.

The purpose of the status chect was to

ensure a feedwater pump runback would not be initiated when the reactor

tria breaker testing was completed and the trip breakers were placed

bac( in service. The inspector reviewed the licensee's corrective

actions and verified procedure revisions were completed. The licensee

updated the LER (commitment change letter dated December 4. 1996) to

require installation of minor modifications CNCE-61214 and 61215 to

eliminate the need to perform this ) articular circuit status check. The

j

inspector verified by reviewing wor ( order documentation (Work Order 96055051) that the Unit 1 modification was implemented.

This event did

not constitute a violation of NRC requirements.

l

08.2 (Closed) LER 50-414/96-004:

Containment Floor and Equipment Sump Level

Alarm Inoperability due to an Operator Aid Computer Error

)

A random computer equiament error in the Unit 2 plant computer caused

the alarm function to 3e suppressed.

The Unit 1 computer had previously

been replaced in June 1996, with a computer that is not susceptible to

this type of error. The inspector verified by reviewing a sample of

completed datasheets that the licensee performed a periodic operability

verification of TS related Unit 2 computer points until the computer was

replaced in April 1997.

This LER was a minor issue and was closed based

on this review-.

II. Maintenance

1

M1

Conduct of Maintenance

M1.1 General Comments (61726 and 62707)

I

i

a.

Insoection Scope

1

The inspector observed all or portions of the following maintenance

i

related Work Orders (W0s) and reviewed the associated documentation:

Enclosure 2

l

_,

.

.

-

_

-

-

- - _

-

,

.

..

.

- . - . - . - - - .-

.

..

. , - - ... -..- - - -

,

.

.

'

9

-

WO~97040075-02

Repair Unit 2' Main Turbine-Hydraulic 011 Leak

-

WO 97037274-02

-Auxiliary Feedwater Turbine Motor Testing

IP/1/B/3030/09

SB System Turbine Bypass Valve Calibration

-

b.

Observations and Findinas

,

!

The inspector observed that these activities were performed by personnel

who were experienced and knowledgeable of their assigned tasks. Work'

)

3rocedures were present at the work location and being adhered to.

3rocedures provided sufficient detail and guidance for the intended

activities. Activities were properly authorized and coordinated with

operations prior to performance. Test equipment in use was calibrated.

.

!

procedure prerequisites were met, and system restoration was completed.

.l

l

c.

Conclusions

The inspector concluded that routine maintenance activities were

performed satisfactorily.

M1 2 Autostart of Nuclear Service Water Pumos Durina Maintenance (62707)

a.

Jnsoection Scool

On May 20, 1997. during maintenance on the Unit 1 125VDC/120VAC vital

instrument and control power system a low Nuclear Service Water (NSW)

Pit level signal was generated. All four NSW pumps received an

autostart signal and two idle pumps started. The unit operators entered

,

Abnormal Procedure AP/0/A/5500/20. Loss of NSW Case.2: Loss of NSW Pit

'

Level. to verify that the NSW system was not needed and secured the

unneeded NSW pumps. The inspector discussed the occurrence with

j

operations and regulatory compliance personnel; reviewed associated

i

operating and abnormal operating procedures; reviewed several station

1

PIPS and the facility's TS and FSAR: and reviewed NUREG-1022. Event

i

Reporting Guidelines for 10 CFR 50.72 and 10 CFR 50.73 reports.

'

L

b.

Observations and Findinas

j

In 1995, during a Unit 2 refueling outage the licensee identified a

power alignment where a vital AC bus could be powered from regulated

'

power for an extended period of time during refueling outages. This

,

L

alignment facilitated the conduct of outage-related maintenance. The

,

licensee recognized that when safety-related inverter 1EIA was removed

from service for maintenance, level transmitters 1RNLT7400 und

ORNLT7390 as well as the associated NSW Pit A and B level channels.

would be powered from a regulated power supply.

Similarly, when safety-

,

,

related inverter 2EIA was removed from service for maintenance, level

transmitter 2RNLT7400 and its associated NSW Pit level channel, would be

powered from a regulated power supply.

Because NSW Pit level

instruments were required during Modes 1-4 on the o)erating unit (at

!

that time. Unit 1). this alignment was allowed on tie operating unit for

no more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> before shutdown was required by TS 3.8.3.1.

The

Enclosure 2

I

-

_

.

-.

-

~.

._

10

licensee initiated PIP 0-C95-1809 to address the impact of this

alignment on safety-related equipment.

'

One of the corrective actions from PIP 0-C95-1809 was to revise

OP/1(2)/A/6350/08. Enclosure 4.9. 1EIA Shutdown and Return to Service.

I

and Enclosure 4.12. 1EID Shutdown and Return to Service, to direct

.

control. room operators to declare.the. associated NSW Pit level

instruments-inoperable when their power supply was placed on Regulated

Power. -This would allow maintenance to continue for longer than a 24-

hour period. Additionally, control room operators would refer to TS 3.3.2. Engineered Safety Features Actuation System Instrumentation, and

take appropriate action.

With one channel of NSW Pit level

instrumentation inoperable. TS 3.3.2 required that the inoperable

channel be placed in the tripped condition within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.

With more

than one channel inoperable. TS 3.3.2 required that the NSW system be

aligned for NSW Pond recirculation within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. The revised

procedure was approved on February 28, 1996.

Subsequent to the February 28. 1996, procedure revision. another change

to OP/1(2)/A/6350/08. Enclosures 4.9 and 4.12 was made to add the

appropriate model work order number (91002943).that would be issued to

support placing the NSW pit level channels in the tripped condition when

the associated inverter was removed from service and regulated power was

aligned to the distribution bus. The procedure change was made for both

units and was approved February 20. 1997.

Two out of three logic for low NSW pit level initiates the following'

)

actions: (1) swap of the NSW pump suction to the Nuclear Service Water

Pond (NSWP): and (2) an automatic start of the NSW pumps.

Inverter 2EIA

supplies vital power to one NSW Pit level. instrument: placing that

instrument channel in the tripped position would not satisfy the logic

for these two actions.

However, since inverter 1EIA supplies vital

. power to two NSW Pit level instruments, tripping those instrument-

channels would satisfy the logic for these two actions.

i

On May 20. 1997, during maintenance on the 125VDC/120VAC vital

instrument and control power system, a low Nuclear Service Water (NSW)

Jit signal was generated when the two channels powered from 1EIA. which

lad been removed from service for maintenance, were placed in the

tripped condition.

In response to this low level signal, all four NSW.

pumps received an autostart signal and started. This system response

was not anticipated, nor was it included in the scope of procedure

OP/1(2)/A/6350/08. Enclosure 4.9.

The licensee determined that an

Engineered Safety Features (ESF) had not occurred because the NSW system

was not defined in the FSAR as an ESF system.

The inspector questioned

this basis. since the NSW system does perform ar. ESF function (to

provide cooling water to the component cooling system heat exchangers

and, thereby, serve as the heat sink for containment cooling).

The

licensee generated PIP 0-C97-1715-to clarify what NSW system actuations

constitute an ESF Actuation.

This issue is characterized as IFI 50-

413.414/97-08-04: Reportability of NSW System Actuations.

For this

specific issue, the licensee reasoned that, since a safety injection

signal did.not initiate the NSW pump starts to mitigate an event that

Enclosure 2

11

required containment cooling, the pump start did not constitute an ESF

function and was not reportable.

The inspector agreed with this

conclusion.

The licensee determined that the root cause of the pump start was an

inadequate procedure. The procedure change records indicate that the TS

and FSAR chapter associated with Electric Power Systems were consulted.

As a result, the appropriate actions for TS 3.2.2 were not delineated in

the procedure, and the impact of trip]ing two channels of NSW Pit level

were not recognized.

The procedure clange to direct plant workers to

place NSW Pit level instrumentation in the tripped condition should have

a3 plied to and been made for Unit 2 procedures only since only one

clannel of NSW Pit level instrumentation was rendered inoperable by the

inverter maintenance.

The inspector concluded that the inadequate procedure was a violation of

TS 6.8.1. Procedures and Programs.

However, the impact on plant

,

equi] ment was of minor safety significance.

Therefore, this violation

is claracterized as NCV 50-413/97-08-05: Inadequate Procedure Results in

Autostart of the NSW Pumps, consistent with Section IV of the NRC

Enforcement Policy.

The inspector verified that, on May 21, 1997. OP/1/A/6350/08 was revised

to remove the reference to model work order 91002943 for tripping the

'

NSW Pit level instruments associated with inverters 1EIA and 1EID.

c.

Conclusions

A NCV was identified for inadequate procedure.

The inspector concluded

that a more thorough review of the FSAR and of the TS associated with

the ESF function of the NSW system may have revealed the

inappropriateness of tripping two channels of NSW Pit level

instrumentation.

The inadequate procedure did not pose a threat to

safety-related equipment or render a safety-related component

inoperable.

Corrective actions for the NCV were timely and appropriate.

'

An IFI was identified to further review NSW ESF reportability.

M1.3 Maintenance of Electric Motors (62700)

a.

Insoection Scooe

2

This inspection was performed to determine by document review, work

'

observation and interviews, the apparent cause for increased electric

motor failures over the past two year period.

1

b.

Observations e

Findinas

The inspector reviewed the following documentation to ascertain the

{

extent of the problem, the underlying reason (s) for these failures and

the corrective actions taken to prevent their recurrence:

e

Electric Motor Failures

Root Cause Analysis (11-21-96)

l

Enclosure 2

~ ~ - .

.

- -

-

. - .

.

- --.--._--_..-

.~..-

.

.

4

i

'12

'

e

CTS-09-96

Electric Motor PM Program (12-

2-96)

e

SA-97-61(CN)(SRG)~

Assessment of Warehouse

{

Material Control (5-21-97)

i

e

CNS Site Focus Issue

System Reliability'(6-2-97)

~ Initiative: NO. 17 Motors

e

SM/0/A/5130/001

Preventive Maintenance for

i

Medium Voltage Motors in

[

Storage

[

e

SM/0/A5130/002

Inspection and Testing of

i

Motors

'

'

Backaround

I

By review of the above documents and through discussions with the

licensee's component engineer in charge of electric motor maintenance.

the inspector ascertained that electric motor failures at Catawba

indicated an increasing trend since the fourth quarter.of 1994. Most of

these failures were evaluated as electrical in nature.

The licensee's

j.

Self-Assessment evaluated the failure rate and determined that it was

a) proximately double that of the industry.

The underlying reasons for

tieses. problems as determined by the licensee's Assessments and Root

Cause Analysis included _ human factors, organizational and management

deficiencies, personnel changes., programmatic deficiencies and a failure

to implement existing Technical Support Program (TSP) instructions.

Findinal

Prior to establishing the present organization with assignment of

. specific responsibilities towards maintenance of electric motors, the

responsibility for testing electric motors had been assigned to a group

out of the licensee's General Offices. As such, the program lacked good

coordination and communications between key individuals.

For example,

the site organization did not have easy access to test data feedback or

have control over the type of tests performed. This made tracking and

- trending motor performance difficult to implement.

Vendor Maintenance Monitoring - In reference to motor repair work

. performed by vendors, the-documents reviewed revealed that the

organizational structure and the program in place at the time did not

provide for good communications between Catawba Maintenance and the

vendor (s). As such, the licensee accepted repaired motors from the

vendor when these motors were not in a condition suitable for service.

This was evidenced by problems with the Unit 1 Heater Drain Tank C1

motor and Unit 2 Condensate Booster Pump C motor.

Technical Support Program - The TSP for small and medium size electric

motors was. established to provide guidance and information for

maintenance on electric motors and to establish certain goals for the

Enclosure 2

.

,

.

, - - -

,

.--

_.-

-

-,-

13

Preventive Maintenance (PM) program.

These goals were designed to

reduce failures of motors critical to )lant operation by trending

performance and repairs as required.

iowever, the documents reviewed

revealed that TSP recommendations for PM of small and medium motors were

essentially ignored by supervision.

In general. this was attribut

3 +o

changes in staffing due to the reorganization and management's app 6itat

lack of skills and knowledge to recognize the seriousness of the

problem.

Failure of the Unit 2 Cooling Tower Fan A7 and Instrument Air

Compressor D motors were examples of failures due to PM program

inadequacies and management's failure to take a proactive role in this

area.

PM of Flectric Motors in Storage - On or about September 10. 1996, the

licensee determined that the spare Containment Spray (NS) motor was

inadequately stored in the contaminated warehouse, in that the warehouse

heater was not energized. This problem was documented in PIP No. 0-C96-

2488.

In addition to this problem, the licensee's investigation

identified other large motors stored without heaters energized. The

latter were stored ir ?n "old" warehouse located outside of the

protected area. Th a oblem evaluation section of the PIP found motor

PM procedure IP/0/A/3851/03 to be inadequatc. in that it did not provide

instructions to ensure that motor heaters were energized as required and

that no a)propriate action was taken to repair broken heaters.

To

correct t11s problem the licensee generated modification CNCE8015.

Completion of the corrective action on this modification was scheduled

for June 30. 1997.

Assessment of Warehouse Material Control - Between April 23-28, 1997

the licensee performed an assessment of activities associated with

onsite receiving, storing. shipping and controlling of motors and other

equipment both onsite and offsite.

The assessment, which was documented

under Report Nos. SA-97-61(CN)(SRG). was conducted in response to

damages identified on a spare Nuclear Service Water (RN) Pump motor

while undergoing pre-installation testing following its release from

storage.

Details of the damages and repairs performed were documented

in PIP 2-C97-1166.

Findings, evaluation and corrective actions

associated with this assessment were documented in PIP 0-C97-1621. A

review and evaluation of the findings were as follows:

(1) there were

no procedures which adequately detailed the correct methods of

performing preventive maintenance, moving or shipping of motors, and

responsibilities applicable to each of these activities were not

assigned to any one individual or group; and (2) there were no

procedures to define the necessary controls for equipment loaned out to

other Divisions or companies to assure proper maintenance and

suitability for use upon their return.

In response to the )roblems described above, the licensee took specific

action to correct t1e immediate problems and generated a Nuclear Site

Directive (NSD). Storage and Handling of Motors. to address the issue on

a broader basis. Areas covered included:

receiving. storage, off- and

on-line testing, in-storage testing. issuing and transportation of

l

motors.

Enclosure 2

)

1

-l

14.

This licensee identified problem of a failure to provide adequate

procedures for handling and conducting preventive maintenance of motors

in storage was determined to' be a violation of 10 CFR 50. Appendix B.

Criterion V. " Procedures. "- This licensee identified and~ corrected

violation was treated as a NCV consistent with Section VII.B.1 of the

NRC Enforcement Policy.

This issue was identified as NCV 50-413.414/97-

08-06:

Inadequate Motor Preventive Maintenance and Control Procedures.

Work' Observation

As a followup to the aforementioned document review. the inspectors

observed preventive maintenance testing performed on the Auxiliary

Feedwater (CA) Pump Turbine. 2 Sump Pump Motor "B".

The testing was

performed'per procedure SM/0/A/5130/002. -Tests performed on this motor

included meggering, digital low chmmeter resistance polarization index.

visual and functional.

The testing was performed under Work Order No.

97037274-02. using a Baker Motor Analyzer. S/N016.

Test results

attained were well within acceptance criteria. All equipment used for

this test were properly identified and within designated calibration

timeframe.

Personnel involved in the test appeared knowledgeable, and

followed the above-mentioned procedure in executing their tasks.

1

Insoection of Motors in Storace

The inspector, accompanied by the responsible component engineer,

inspected small, medium and large motors stored in Warehouses No. 2 and

i

4.

Storage conditions appeared to be consistent with ANSI N45.2.2.

Level "B" requirements, including environmental control, protection

against physical damage and airborne contamination.

In Warehouse No. 4

the inspector noted that three pump motors associated with fuel pool

cooling, volume control and "C". heater-drain systems did not have their

heaters energized.

However, the com3onent engineer indicated that a

decision had been made to modify ratler than fix-the existing heaters

which did not work properly and could damage the motors if energized.

c.

Conclusions

This inspection revealed that electric motor failures had increased-

significantly over the last couple of years.

This increase of failures

was attributed in part to organizational changes, programmatic

deficiencies. human factors inadequate resources, high work loads, and

i

management's failure to take a proactive role in this area.

Following

completion of the Root Cause Analysis Report and Assessments on the

Electric Motor PM Program and Warehouse Material Control, the licensee

took appropriate measures to improve conditions in this area. An NCV

was identified regarding inadequate motor PM and control procedures.

M1.4 Review of Maintenance Activities Associated With Air Ooerated Valves

(62700)

,

a.

Insoection Scooe

During this report period, the inspector reviewed the licensee's

Enclosure 2

1

15

activiti.es for maintenance of Air Operated Valves (A0Vs). Areas

reviewed included, but was not limited to. A0V maintenance program

attributes including PM and Corrective Maintenance (CM). valve outage

assessments, maintenance rework program assessments, valve related PIPS.

and valve testing.-

b.

Observations and Findinas-

The-inspection'was a general look 'at various aspects of the = licensee's

A0V activities to determine.that Management had been actively focused on

maintaining A0Vs important to safe and reliable operation of the plant.

A0V Proaram Elements

A formal, structured program had not been implemented for A0Vs at this

time.

However, the elements of a program had been developed and

controlled by the engineering and maintenance groups. Control of these

elements were assigned to an engineering valve s)ecialist who was

responsible for the program and was involved wit1 problem resolutions.

The engineer had been tasked with development of an A0V program document

(i .e. . an engineering directive for A0Vs). This document was scheduled

on the management calendar to be completed by the end of 1997. The

document will be coordinated with all three Duke Power sites.

The. licensee had performed a review of the ADV and' solenoid valve

population and application. A population of 2.348 ADVs-had been

identified.

There were 169 active A0Vs identified in safety significant

systems.

From a review of the licensee *s documentation, the inspectors

noted the following program elements:

active valves were stroke time tested per ASME Code requirements

e

482 safety-related solenoid valves were maintained through the

e

. Environmental Quali.fication Program

I

'

e

50 of the most critical actuators / valves were scheduled for

rebuild / replacement under a recently initiated program (Model PM

-

work orders would be established to automatically perform this-

,

function at 8-10 year frequencies)

68 high energy, normally closed valves were monitored for leakage

e

using infrared techniques

diagnostic. testing was used in calibration and setup of control

e

valves using state of the. art equipment

.

A0Vs/ solenoid valves were trended in the Failure Analysis Trending

e

system

approximately 150 PMs had been developed based on an operating

e

experience database

,

i

Enclosure 2

16

procedures had been developed for the various aspects of

e

A0V/ solenoid valve maintenance

Positioner Calibration

The inspector witnessed the positioner calibration on A0V 1SB24 (Sir

. operated steam dump control valve).

The inspector observed the pre-job

'

briefing and reviewed the work order. procedure IP/1/B/3030/09 (SB

LSystem Turbine Bypass Valve Calibration) and the procedure's data sheet

results. The inspector also observed the work-in progress. An approved

arocedure was present and followed on the job: personnel were

(nowledgeable and skilled in the task: and an Instrumentation and

Electrical technician was present for on-the-job-training to expand

skills. The job was performed in a controlled and professional manner.

Instrument Air System

The licensee had previously noted high dew point temperatures and

excessive moisture in the instrument air s

-problems and a number _of system failures. ystem. resulting in valve

Modification CN 50431

replaced the three reciprocating air compressors with two centrifugal

compressors. and the refrigerant dryers with two heatless. air-purge

desiccant dryers.

The dew point was reduced from the 50-70 degree range

to minus 30 degrees.

System failures have trended down from a high of

16 in 1995 to none so far in 1997.

The inspector considered that this

was a positive step to improve system / plant performance and reliability.

MSIV Issue

The inspector reviewed the failure of Main Steam isolation Valve (MSIV)

,

1SM1 to close in the required stroke time on March 7. 1995, against the

~l

recommendations of NRC Information Notice (IEN) 87-28.-Air System

Problems At U.S. Light Water Reactors, and IEN 88-24. Failures of Air

Operated Valves Affecting Safety-Related Systems, to determine if the

failure of MSIV 1SM1 had been due to the causes discussed in IEN 88-24.

Licensee documentation confirmed they had reviewed the safety-related

solenoid valve a) plication with the vendors as a result of IEN 88-24 and

,

1

concluded that t1ese valves would operate against as high as 150 psi air

j

system pressures.

Maximum instrument air system pressure for Catawba

-

was 115 psi.

MSIV solenoid valves were missed in this survey, in that

they were supplied as a part of a whole manifold assembly.

Subsequent'

testing and re-evaluation of the 1SM1 past operability (PIP C96-0751)

indicated that the root cause of the failure was an intermittently

sticking solenoid valve, possibly in conjunction with marginal spring

force.

No other MSIV at Catawba or McGuire has had this problem.

To

reduce the possibility of future failures, the licensee installed

-

stronger springs in Units 1 and 2 MSIV solenoids. The inspector

concluded that failure of MSIV ISM 1 to meet its stroke time was an

isolated event.

Enclosure 2

.

.-

.-.

- -

--. .

. _

. - . - - -

. - . - . - .

. - . . - . . . - -

.

t

17

Self-Assessments

The . inspector reviewed outage critiques for U1EOC8, U1EOC9. and U2E0C7.

These critiques dealt largely with improving efficiency through better.

organization, planning and communication. One deficient area was valve

. maintenance rework.

Review of an assessment report on the Maintenance -

Rework Program (MNT 15-97) showed that the cause for maintenance rework

items fell into three general areas: Work Practices, Design / Equipment.

and Planning / Procedure / Training. Approximately 60% of rework items were

in the Work Practice area.

In the area of valves, a review of over

three years of data indicated a significant reduction in rework items.

-It appeared that management focus on reduction of rework items has shown

positive results,

c.

Conclusions

Management focus on Air Operated Valve maintenance has resulted in

improved performance.

Air operated valve program elements were in place

and an Engineering Directive was in development. Observed maintenance

was performed well with good management involvement.

h8

Miscellaneous Hafntenance Issues (92902)

M8.1- (Closed) Unresolved Item (URI) 50-413.414/96-16-02:

Nonconservative

RCS Controlled Leakage Test

Surveillance procedure PT/1(2)/A/4150/01. Reactor Coolant System

Controlled Leakage Verification, was not being performed to simulate the

system flowpath as it is described in the current TS basis. The TS

basis states that the controlled leakage limitation restricts operation

when the total flow supplied to the reactor coolant pump seals exceeds

40 gpm with the modulating valve in the supply.line (NV-294) fully open

at a nominal Reactor Coolant System pressure of 2235 )sig.

However, the

surveillance test had been performed with NV-294 in t1e normal

modulating position to control charging flow. This was not conservative

because the accident analysis assumes a station blackout concurrent with

a loss of coolant accident. and the valve fails to the open position on

a loss of power to ensure that adequate seal injection is provided.

The licensee initiated an appropriate procedure change to

PT/1(2)/A/4150/01 and determined that with the modulating valve fully

open, Reactor Coolant System Controlled Leakage was within allowable

limits. The inspector reviewed PIP 2-C97-1010, which documented the

results of subsequent surveillance tests that were performed from

October 10. 1996. through February 28. 1997.

The ins >ector determined

l

that total seal injection flows continued to fall wit

1in the acceptance

L

criterion of 40 gpm.

The inspector also reviewed the supporting

i

documentation associated with the Emergency Core Cooling Systems' past

operability evaluation and discussed the evaluation with engineering

,

!

personnel.

The analysis indicated that with modulating valve NV-294

fully open during a large break loss of coolant accident, flow to the

seals would not-have exceeded the limit assumed in the accident

L

. analysis, and sufficient flow would have been provided to the core.

The

Enclosure 2

t

-

-

~.

.

.

.

.

--.

.

_

18

inspector concluded that the Emergency Core Cooling Systems were past

operable.

This Unresolved Item is closed, as is associated LER

50-413/96-09. Inadequate Reactor Coolant Controlled Leakage Test.

I

M8.2 (Closed) LER 50-413/96-09:

Inadequate Reactor Coolant Controlled

Leakage Test

l

(Details pertaining to this item are discussed in Section M8.1)

III. Engineerina

El

Conduct of Engineering

E1.1 Nonconservative Thermal Power Calculation Error (71707. 37551)

a. Insoection Stone

On May 9. the licensee identified a small nonconservative error in the

o)erator aid computer thermal ]ower calculation.

The inspector reviewed

t1e licensee's evaluation of t1e significance of the error (PIP 0-C97-

1589) verified modifications were installed to correct the error, and

reviewed UFSAR commitments related to the accuracy of thermal power

measurements.

b. Observations and Findinas

The operator aid computer thermal power calculation is used by control

room operators as the primary indication to control the reactor thermal

power within the licensed power limit of 3411 megawatts-thermal.

During

the final stages of the Unit 2 power ascension testing following its

recent refueling outage, the licensee identified a small discrepancy

between the operator aid computer thermal power indication and the

measured main generator electrical output.

This discrepancy prompted c

detailed review of the thermal power calculation.

The licensee's reviEv

identified that an incorrect constant (coefficient of thermal expansion)

was used in the plant computer's thermal power calculation which

resulted in an error with a magnitude of 0.3 percent in the

nonconservative direction. This caused indicated power to read 0.3

percent below actual )ower. The licensee's review determined that the

error existed since tie new operator aid computers were placed inservice

(September 1996 for Unit 1 and April 1997 for Unit 2). The old and new

computer systems used different calculation techniques for generating

this constant which were not realized until the detailed review of the

l

thermal power calculation was performed. A power discreaancy was not

l

detected following the Unit 1 startup in September 1996 3ecause normal

l

process instrumentation uncertainty errors masked the 0.3 percent

'

calculation error.

The inspector reviewed UFSAR and safety analysis commitments for

uncertainties for the thermal power indication.

The UFSAR and safety

analysis assume an error of 2 percent for this parameter and use an

assumption of 102 percent rated thermal power as the initial condition

Enclosure 2

l

19

for accident analyses.

The licensee's General Office personnel

performed a review of the actual uncertainty of the thermal power

measurement and found, based an previous calculations, that the actual

uncertainty of the indication was 1.52 percent. An addition of 0.3

percent error caused by the incorrect constant resulted in a total

uncertainty of 1.82 percent, which is within the analyzed uncertainty.

Based on this, the inspector considered that the error resulting from

using the incorrect constant was of minor safety significance.

The

licensee revised the constant by performing a software change to both

unit's computers.

The inspector verified by reviewing Variation Notices

VN-CN-11329AS and VN-CN-21329Y that the constant was corrected. The

inspector also verified by reviewing o)erator aid computer group display

data printouts that this constant had Jeen input properly into the plant

computers.

The ins)ector reviewed the power history printouts for both units and

found tlat they were conservatively operated below 100 percent power.

Normally, thermal power was controlled at 99.8 percent to 99.9 percent

power based on a review of data for the 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> averaged thermal power

calculation.

There were no excursions above 100 percent power

identified during this review.

c. Conclusions

The licensee's pursuit and resolution of a small nonconservative thermal

power calculation error identified in the new plant computers was an

example of good questioning attitude. The error had minor safety

significance because of its small magnitude and did not result in

exceeding the 2 percent uncertainty required by the Updated Final Safety

Analysis Report and assumed in safety analyses.

E2

Engineering Support of Facilities and Equipment

E2.1 Potential Air Bindina of Auxiliarv Feedwater Pumos

a.

Insoection Scoce (37551)

During an auxiliary feedwater (CA) suction source reliability review at

the McGuire Nuclear Station, engineering personnel identified a

potential vulnerability of the CA system to air entrainment in the

suction piping to the CA pumps and subsequent air binding of the pumps.

The licensee determined that the potential vulnerability applied to the

Catawba Nuclear Station (CNS) as well.

The inspector discussed the

issue with Engineering personnel: reviewed the facility's TS and UFSAR:

reviewed station PIP 0-C97-1579 and a 10 CFR 50.72 notification of

potential inoperability of the CA system: reviewed information provided

from the pump vendor; assessed the appropriateness of compensatory

actions; and verified that compensatory actions had been effectively

implemented.

Enclosure 2

-- . . - -

20

b.

Observations and Findinas

Because they provide condensate quality water, the normal suction

sources for CA are the shared CA condensate storage tank (CACST). the

respective unit's upper surge tank (UST) and the respective unit's

condenser hotwell.

iowever, these sources do not meet seismic

requirements.

Therefore, the assured suction source for the CA system

is NSW which is not of condensate quality.

Unit 2 TS 3.7.1.5 requires

that the Condensate Storage System, which consists of the CACST. UST and

-Condenser Hotwell, be operable during Modes 1 through 3 with a contained

water volume of at least 225.000 gallons.

This TS requirement is not

applicable to Unit 1.

'

If the CA system automatically starts, a low CA pump suction pressure

will cause pump suction to swap to the Nuclear Service Water system.

Similarly, a low CACST level signal will cause pressure switch 0CSPS5030

to close CACST outlet valves 1/2CA-6 (if the control switch is in auto).

This automatic function prevents the introduction of air into the system

piping after the CACST has been depleted.

Control board switches also

enable a reactor operator to manually close the valves from the control

room.

The valves are powered from the Blackout Power System to ensure

that the CA pumps are protected from air binding during a station

blackout event.

On May 8. Catawba engineering personnel identified three mechanisms

whereby air entrainment in the suction piping to the CA pumps could

cause air-binding of all three CA pumps (2 motor-driven and 1 turbine-

driven).

The three issues were:

vortexing of _the CACST. vortexing_ of

the UST, and depletion of the CACST.

The licensee determined that

specific conditions were necessary to cause vortexing of the CA and the

UST.

Specifically, high CA system flow rates (e.g. . during a main

steamline break accident) and a small range of tank levels were required

for vortexing to occur.

Similarly, a dual unit loss of offsite power coincident with a main

steamline break on one unit is a condition necessary for CACST depletion

to cause air entrainment in the CA system piping. A second condition

necessary for CACST depletion to result in air entrainment is a negative

pressure (less that atmospheric 3ressure) at the junction of the CACST

and the UST discharge piping. T1is condition would essentially educt

air into the suction piping downstream of the junction.

The CA pump vendor was contacted to evaluate pump operability under the

postulated air entrainment scenarios. The vendor responded that the

,

length of aiping from the CACST to the CA pumps was sufficient to

preclude tie any generated vortex from reaching the suction of the

pumps.

Any small amount of air that might be entrained in the suction

line if the postulated vortex did not break up would be forced through

the pum) by the. inertia of the fluid in the piping without any

noticea31e affect on the pump.

The vendor was unable, however, to provide assurance that CACST

depletion, concurrent with UST supplying the CA pumps, would not cause

Enclosure 2

. _ .

. - .

21

pump damage as a result of air entrainment from the emptied CACST into

the suction piping to the Jumps. This scenario posed a real possibility

that sufficient air could )e drawn into the pump suction piping and to

the pump, to cause pump failure.

The failure mechanism is referred to

as a break in suction whereby air trapped in the pump casing would

,

preclude water from entering the pump.

The pump would run dry and be

severely damaged.

_

The vendor indicated that a small amount of air would be passed through

i

the pump without any noticeable affect whereas a large amount of air

would cause a suction pressure drop to the NSW auto swap to setpoint.

The vendor was unable to quantify the mid-range amount of air entrained

in the water that would cause this failure without extensive analysis

'

and modeling.

Engineering personnel have contracted a separate vendor

to quantify the air factor required to cause pump failure. The results

of their analysis and the associated past operability evaluation are not

formally completed.

This issue is characterized as URI 50-413.414/97-

08-07:

Potential Air Binding of Auxiliary Feedwater Pumps, pending the

completion of the hydraulic analysis and past operability evaluation.

The licensee submitted a 10 CFR 50.72 notification to the NRC regarding

the potential air binding problem.

The licensee also implemented

compensatory actions to protect the CA pumps from the postulated air

i

binding failure-until the analysis is completed.

Compensatory actions

consisted of: (1) closing ICA-6 and 2CA-6 to eliminate the potential for

'

air binding the CA pumps as a result of CACST depletion: (2) maintaining

each units UST full to minimize the risk of an autoswap to the NSW

system on low AFW pump suction pressure; and (3) implementing Abnormal

Procedure (AP)-06. Loss of Steam Generator Feedwater, upon any CA-

autostart. The inspector verified that these compensatory actions.

either had been taken or were communicated to the control room operators

'

via Operations Technical Memorandum #97-01.

The inspector also verified

that the requirements of Unit 2 TS 3.7.1.5 to maintain a volume of

225.000 gallons of water in the Condensate Storage System were being

met.

c.

Conclusions

The inspector concluded that the licensee's effo,ts to determine if the

concern identified at the McGuire Nuclear Station was applicable to

Catawba were prompt.

Consultation with off-site resources to determine

the amount of air that would cause pump failure was appropriate, and

compensatory actions to prevent air-binding of the CA pumps in the

interim were conservative. An Unresolved Item was identified regarding

the potential for air binding the Auxiliary Feedwater pumps.

.E8

Miscellaneous Engineering Issues (92903)

E8.1

(Closed) Acoarent Violation 50-41?.414/97-04-01: Auxiliary Feedwater

System Single Failure Design Deficiency

During an inspection conducted January 6 through 23, 1997, the NRC

examined the facts and circumstances associated with a licensee-

Enclosure 2

_.

.

-

-

22

identified design deficiency that rendered the auxiliary feedwater

system outside its design basis.

On January 9.1997, Licen.see Event

Report (LER) 50-413/96-012 was submitted to communicate this

determination. and on January 17 Revision 1 to the LER was submitted to

provide additional information and corrective actions.

The NRC's inspection findings associated with this issue were documented

in NRC Inspection Report 413.414/97-04.

The issue was characterized as

Apparent Violation (EEI) 50-413.414/97-04-01: Auxiliary Feedwater

System Single Failure Design Deficiency.

By letter dated February 18.

1997, the NRC notified the licensee of an exercise of discretion in

.

accordance with Section VII.B.3 of the Enforcement Policy.

The letter

documented the closure of the apparent violation and completed the NRC's

.

action on the issue.

Accordingly, the apparent violation is

administrative 1y closed.

IV. Plant Sucoort

,

P1

Conduct of Emergency Preparedness Activities

Pl.1 Emeraency Exercise (71750)

On May 7. the resident inspectors observed the licensee's annual

emergency exercise. The exercise was conducted from the training

"

simulator and included Technical Support Center. Operations Support

Center, and Emergency Operations Facility activation with limited

participation by offsite organizations.

Inspector observations included

simulator. Technical Support Center, and Operations Support Center

functions.

The inspectors noted particularly good performance by

personnel in the Operations Support Center to recognize that a field

team was to be dispatched with multiple tasks to be performed.

The

tasks were divided and more than one team was dispatched to perform the

tasks. The inspector observed the licensee's critique and noted that

i

discrepancies and strengths identified were appropriately characterized.

In general, the inspectors concluded that licensee performance during

the drill was appropriate.

R1

Radiological Protection and Chemistry Controls

R1.1 Tours of the Radioloqical Control Area (RCA) (71750)

The inspectors periodically toured the RCA during the inspection period.

Radiological control practices were observed and discussed with

radiological control personnel, including RCA entry ind exit, survey

postings, locked high radiation areas, and radiologicel area material

conditions.

The inspector concluded that radiation control practices

were proper.

-

Enclosure 2

. . -.

.. - - . . - - . _ - - - . - . - - - . - . - -

- - - - . . .

- - - - - -

1

y

,

23'

R2-

Status of Radiological Protection and Chemistry Facilities and Equipment

I

R2.1 Backaround Radiation Levels in the Vicinity of Whole Body Friskers

]

(71750)

,

During a plant tour on April 28. the inspector noted that two whole body

'

friskers located in the men's change facility (located in the Auxiliary

j

!

Building) were in an alarm condition that indicated high background

radiation levels. -One of the friskers had been removed from service.

the other appeared to be available for use. The inspector contacted

-

Radiation Protection Surveillance and Control and was informed that the

i

4

friskers had been checked and were acce) table for. use.

The inspector

also noted that hand held friskers in t1e area were reading a higher

radiation background than normal, but still within limits to perform an

acceptable survey.

The inspector questioned the cause for the higher than normal radiation

background with licensee radiation protection supervision. Apparently,

a waste system line in the vicinity of the change room has caused

~j

elevated background levels in the past. After questioning by the

inspector, the licensee initiated PIP C-97-1463 to address the issue.

The line was subsequently flushed and the background radiation levels

returned to normal

l,

The inspector noted that radiation protection personnel did not

demonstrate a questioning attitude and initiate appropriate actions.

including initiation of a PIP, until the ins)ector questioned the whole

~

body frisker alarms and the cause of the higler than normal background

radiation.

'.

S1

Conduct of Security and Safeguards Activities

S1.1 fgneral Comments (71750)

1

'

During the period, the inspectors toured the protected area and noted

that the perimeter fence was intact and not comaromised by erosion or

disrepair.

I:olation zones were maintained on Joth sides of the barrier

i

and were free.of objects which could shield or' conceal an individual.

The inspectors periodically observed personnel. packages, and vehicles

entering the protected area and verified that necessary searches,

visitor escorting, and special purpose detectors were used as applicable

prior to entry.

Lighting of the perimeter and of the protected area was

acceptable and met illumination requirements.

V. Manaaement Meetinas

X1

Exit Meeting Summary

The inspectors ) resented the inspection results to members of licensee

management at t1e conclusion of the inspection on June 12, 1997.

The licensee

acknowledged the findings presented.

No proprietary information was

identified.

Enclosure 2

24

PARTIAL LIST OF PERSONS CONTACTED

Licensee

Bhatnager. A.. Operations Su]erintendent

Birch. M.

Safety Assurance ianager

Coy. S... Radiation Protection Manager

Forbes. J., Engineering Manager

Harrall. T. , Instrument and Electrical Maintenance Superintendent

Kelly, C.. Maintenance Manager

Kimball. D., Safety Review Group Manager

!

Kitlan

M.. Regulatory Compliance Manager

McCollum. W., Catawba Site Vice-President

Nicholson, K., Compliance Specialist

Peterson. G.. Station Manager

1

Enclosure 2

_ _ _

25

INSPECTION PROCEDURES USED

'

IP 37551:

Onsite Engineering

IP 61726:

Surveillance Observation

IP 62700:

Maintenance Program Implementation

IP 62707:

Maintenance Observation

IP 71707:

Plant Operations

IP 71750:

Plant Support Activities

IP 92901:

Followup - Operations

IP 92902:

Followup - Maintenance

IP 92903:

Followup - Engineering

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

'

50-413/97-08-01

VIO

Inadequate Alarm Response Results in Inadequate

and Untimely Corrective Actions for Valve

Operability Determination (Section 01.2)

50-414/97-08-02

NCV

Failure to Authorize Overtime in Excess of

,

Administrative Limits (Section 06.1)

50-413.414/97-08-03

IFI

Overtime Control Program Limitations (Section

06.1)

'

50-413.414/97-08-04

IFI

Reportability of NSW System Actuations (Section

M1.2)

50-413/97-08-05

NCV

Inadequate Procedure Results in Autostart of the

NSW Pumps (Section M1.2)

50-413.414/97-08-06

NCV

Inadequate Motor Preventive Maintenance and

,

Control Procedures (Section M1.3)

50-413.414/97-08-07

URI

Potential Air Binding of Auxiliary Feedwater

Pumps (Section E2.1)

G_losed

l

50-413/96-001

LER

Unit Shutdown Required By Technical

Specifications (Section 08.1)

l

50-414/96-004

LER

Containment Floor and Equipment Sump Level Alarm

l

Inoperability due to an Operator Aid Computer

Error (Section 08.2)

l

Enclosure 2

l

26

50-413.414/96-16-02

URI

Nonconservative RCS Controlled Leakage Test

(Section M8.1)

50-413/96-09

LER

Inadequate Reactor Coolant Controlled Leakage

Test (Sections M8.1, M8.2)

50-413.414/97-04-01

EEI

Auxiliary Feedwater System Single Failure Design

Deficiency (Section E8.1).

List of Acronyms

!

AFWCST-

Auxiliary Feedwater System Condensate Storage Tank

ANSI

-

American Nuclear Standards Institute

A0V

-

Air Operated Valve

ASME -

American Society of Mechanical Engineers

CA

-

Auxiliary Feedwater System

CFIV -

Main Feedwater Containment Isolation Valve

CFR

Code of Federal Regulations

-

ECCS -

Emergency Core Cooling System

EEI

Apparent Violation

-

EOC

-

End of Cycle

ESF

-

Engineered Safeguards Feature

FSAR -

Final Safety Analysis Report

GL

-

Generic Letter

IFI

-

Inspector Followup Item

IN

-

Information Notice

IR

-

Inspection Report

MSIV -

Main Steam Isolation Valve

NCV

-

Non Cited Violation

NRC

-

Nuclear Regulatory Commission

NS

-

Containment Spray

NSD

-

Nuclear Site Directive

NSW

-

Nuclear Service Water

NSWP -

Nuclear Service Water Pond

PDR

-

Public Document Room

PIP

Problem Investigation Process

-

PM

-

Preventive Maintenance

psig -

Pounds Per Square Inch Gauge

QA

-

Quality Assurance

RCA

-

Radiologically Controlled Area

RCP

-

Reactor Coolant Pump

RCS

-

Reactor Coolant System

RG

-

Regulatory Guide

RP

-

Radiation Protection

SB

-

Main Steam System Bypass to Condenser

SI

-

Safety Injection

SLC

-

Select Licensee Commitments

SM

-

Main Steam System

SPOC -

Single Point of Contact

SRG

Safety Review Group

-

TS

-

Technical Specifications

Enclosure 2

.

27

UFSAR -

Updated Final Safety Analysis Report

i

URI

-

Unresolved Item

UST

-

Upper Surge Tank

Volts, alternating current

VAC

-

VDC

Volts, direct current

-

VIO

-

Violation

VN

-

Variation Notice

WO

-

Work Order

4

!

Enclosure 2