Intervenor Exhibit I-MOSBA-39A,consisting of Case Number 2-90-020R Re List of Exhibits
ML20100B760
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 10/11/1995
From:
AFFILIATION NOT ASSIGNED
To:
References
OLA-3-I-MOS-39A, NUDOCS 9601230115
Download: ML20100B760 (7)


Text

- . . _ _ _

///[)8/d A ' g g o NUCLEAR REGULATORY COMMISSION 8

Docket No. 50-424/425-OLA4 EXHIBITNO.1 'N/ ;

In the rnatter of Geors Power Co. et af, Voatie Unite t & 2 *

  • O 8ta" O Ap ant dintervc.w O Other b i

, Received O n+cted Reporter 5D DD Witnese LIST OF EXHIBITS

'95 0CI 26 P4 :38 Exhibit No. Descriotion .

g. ,

1 Request for Investigstfi6hi'dat'ed N05b$r 1.1990, from Stewart D.

EBNETER, Regional Administrator. Region II. NRC.

2 Addendum to Request for Investigation, with attachments, dated June 19. 1991. from Regional Administrator Region II. NRC.

3 Computer printout alleging false statements, by Georgia Power i Company (GPC) to NRC. regarding Emergency Diesel Generator testing, undated, prepared by Allen L. H05BAUGH. former Acting Assistant General Manager for Plant Support. Plant Vogtle GPC, and provided by NOSBAUGH to NRC on June 14. 1990, h Copy of NRC Letter, entitled

SUBJECT:

CONFIRMATION OF ACTION LETTER, to GPC (Hairston), dated March 23. 1990.

5 Transcripts of Interview of HOSBAUGH dated July 18 and 19,1990.  ;

6 Transcript of Interview of NOSBAUGH, dated November 4.1993.  ;

7 Copy of " Diesel Testing" transparency presented to NRC on April 9, 1990, by George BOCKHOLD. Jr.. former General Manager Plant Vogtle. GPC.

8 Copy of " Quarantined Components" transparency presented to NRC by BOCKHOLD on April 9. 1990, 9 Transcript of Interview of Jimmy Paul CASH, former Operations Supervisor. Plant Vogtle. GPC. dated August 14. 1990.

10 Transcript of Interview of CASH. dated June 14. 1993.

11 Copy of computer printout. undated, identified by CASH as being representative of his handwritten list of Diesel Start entries obtained from the Vogtle. Unit 1. Control Log and Shift Supervisor *s Log, which he provided to BOCKHOLD as part of BOCKHOLD's preparation for the April 9, 1990 presentation to NRC.

12 Transcript of Interview of BUCKHOLD. dated August 14. 1990.

13 Transcript of Interview of BOCKHOLD. dated June 22. 1993. with exhibits.

p 14 Transcript of Interview of Kenneth S. BURR. Senior Project Engineer.. Southern Nuclear Company (SNC), dated June 14. 1993, with exhibits. .

b, 15 Plant Vogtle. Unit 1. Control Log, for period March 20, 1990 -

April 9, 1990.

' 9601230115 951011 PDR ADOCK 05000424 C PDR ~ii -

Case No. 2 90 020R 105

-QhT k

l i

Exhibit '

No. Descriotion 16 Copies of DIESEL GENERATOR START LOG (from VEGP Procedure No.

55038 C). from train B. Unit 1. for the period 216 90 (Start No.

1-90 114) through 5 23 90 (Start No. 1 90 161).

17 Copies of Diesel Test COMPLETION SHEETS. (from VEGP Procedure No.

131451) for DG1B (Diesel Generator B. Unit 1), for the period 3-13 90 through 4 19 90.

18 Report of Interview of Stewart D. EBNETER. Regional Administrator (RA) Region II (RII). NRC. dated July 17, 1991.

19 Remrt of Interview of Stewart D. EBNETER RA. RII NRC, dated Fearuary 27, 1992.

20 Reports of Interview of Kenneth E. BROCKMAN. Branch Chief.

Incident Response Branch. Office of Analysis and Evaluation of Operational Data (AE00). NRC. formerly Section Chief. Vogtle Project. Division of Reactor Projects (DRP). RII. NRC' dated .

September 5. 1991, and August 23. 1993.

21 Report of Interview of Milton D. HUNT. Reactor Inspector.

Engineering Branch. Division of Reactor Safety (DRS) RII. NRC.

dated September 3, 1991.

22 Report of Interview of Peter A. TAYLORs Reactor Inspector.

Engineering Branch. DRS. RII. NRC dated September 4. 1991.

23 Report of Interview of David B. MATTHEWS Director. Project Directorate II 3 NRR. NRC. dated September 5. 1991.

24 Report of Interview of Leigh TROCINE', Resident Inspector. Turkey Point Nuclear Station. RII. NRC formerly a Project Engineer. RII.

NRC. dated August 30. 1991.

25 Report of Interview of Alfred E. CHAFF Branch. Office of Nuclear Reactor Regu'EE. Events Assessmentl Team Leader. Incident Investigation Team (IIT). NRC. for the Vogtle Site Area Emergency (SAE). dated August 28. 1991.

26 Report of Interview of Richard A. KENDALL. Senior General  ;

Engineer, Department of Energy Germantown. MD formerly Senior ~

Electrical Engineer. Events Assessment Branch, NRR. NRC dated August 28, 1991.

27 Copy of GPC Letter entitled V0GTLE ELECTRIC GENERATING PLAFT CONFIRMATION OF ACTION LETTER, to NRC (Ebneter), dated April 9.

1990. ,

28 Transcript of James A. BAILEY. Licensing Manager, Vogtle Project.

( SNC. dated June 23, 1993, with exhibits.

Case No. 2 90 020R 106

. _ __ -- = - - .

, , +

i I

Exhibit l No. Descriotion i 29 Transcript of C. Kenneth McC0Y, Vice-President Vogtle Project, SNC, and V-P, GPC, dated June 30, 1993, with exhibits. ,

30 Transcript of N. Jackson STRINGFELLOW, Project Licensing Engineer, SNC, dated June 21, 1993.

31 Transcript of W. George HAIRSTON, III. Executive Vice President, GPC: and Chief Operating Officer, SNC, dated June 25, 1993, with exhibits.

~

32 Copy of Draft, dated April 19, 1990, of GPC Licensee Event Report (LER) 90-06, pertaining to the Site Area Emergency at Plant Vogtle on March 20, 1990.

33 MOSBAUGH audio tape, dated April 19, 1990, #3 (NRC #57) 34 Transcript of MOSBAUGH audio tape (NRC #57) .

l 35 MOSBAUGH audio tape, dated April 19, 1990, #4, (NRC #58).

36 Transcript of MOSBAUGH audio tape (NRC #58).

37 Copy of GPC LER No. 90 06, entitled LOSS OF 0FFSITE POWER LEADS TO SITE AREA EMERGENCY, with transmittal letter, dated April 19, 1990.

38 Transcript of Interview of John G. AUFDENKAMPE, Manager, Hechanical Group. Vogtle Project. Southern Company Services (SCS)-

formerly Manager Technical Support Plant Vogtle, GPC, dated June 16, 1993, with exhibits.

39 Transcript of William B. SHIPMAN, General Manager, Plant Support.

2 Vogtle Project. SNC & GPC, dated June 11, 1993.

. 40 Transcript of Interview of Georgie R. FREDERICK, Manager, Maintenance, Plant Vogtle--formerly, Supervisor. Safety Audit and Engineering Review (SAER), Plant Vogtle, GPC, dated June 28, 1993, with exhibits.

41 Copy of Letter of Transmittal, dated June 29, 1990, to the first Revision to LER 90 06, addressed to the NRC Document Control Desk, from GPC (W. G. Hairston).

42 Transcript of Interview of Harry W. MAJORS, Licensing Project Engineer Vogtle Project, SNC dated June 29, 1993.

v 43 Copy of GPC SAER Audit of Diesel Generator Records, dated' June 29, 1990.

l Case No. 2 90 020R 107

e i I

i

. Exhibit No. Descriotion i i 44 Copy, dated August 22, 1990, of Response to NRC Ouestion ,

i Concerning Diesel Starts Reported on April 9, 1990 and in LER i 90 06. Revisions 0 and 1.

4 1 45 Copy of Letter from GPC (Hairston, signed by McCoy) to NRC (Ebneter), entitled V0GTLE ELECTRIC GENERATING PLANT CLARIFICATION 1

0F RESPONSE TO CONFIRMATION OF ACTION LETTER, with attachments.  ;

} dated August 30, 1990. >

46 Copy of marked up draft of GPC Letter to NRC, entitled V0GTLE ELECTRIC GENERATING PLANT CLARIFICATION OF RESPONSE TO ,

CONFIRMATION OF ACTION LETTER. dated August 28. 1990.  ;

L 47 Transcript of Interview of Thomas V. GREENE. Manager. Engineering  !

1 and Licensing Vogtle Project. SNC- formerly Assistant General l l Manager, Plant Support, Plant Vogtle, GPC, dated July 6, 1993.

i 48 Transcript of Interview of R. Patrick MCDONALD. Executive I

Director. Advanced Reactor Corporation formerly Executive Vice

President. GPC and Alabama Power Company, dated July 1. 1993.

49 Letter from B. LAVINE. attorney, Troutman Sanders Law Firm, to i

James Y. Vorse. Field Office Director. Atlanta Field Office of -

! Investigations. NRC, dated August 4. 1993, declining polygraph examinations on behalf of HAIRSTON. McC0Y. SHIPMAN. STRINGFELLOW,

BOCKHOLD. and AUFDENKAMPE.
50 Transcript of Interview of Kenneth R. HOLMES. Manager, Training

' and Emergency Preparedness VEGP GPC dated September 27, 1991.

with exhibits.  !

51 Report of Interview of Christopher C. ECKERT. Quality Assurance j Auditor. VEGP. GPC, dated November 3, 1993.

i- 52 Report of Interview of Paul M. K0CHERY. Engineering Supervisor.

Plant Hodifiestions. VEGP. GPC, dated November 3.1993, with exhibits.

53 Report of Interview of Charles L. COURSEY. Superintendent.
Maintenance Department VEGP, GPC. dated November 3, 1993.

54 Report of Interview of Kenneth C. STOKES, Senior Engineer, VEGP,

GPC, dated November 3, 1993.

3 55 Copy of Letter of Transmittal, signed by R. P. MCDONALD. and Page 3 Section III.3, of GPC's RESPONSE TO MOSBAUGH/ HOBBY 2.206 PETITION, dated April 1, 1991. .

i- 56 NRC Special Team Ins wetion Report, No.s 50 424.425/90 19 lt i

Supplement 1 dated November 1,1991.

Case No. 2-90 020R 108 i .

Exhibit

.,,, No . Qescriotion 57 Transcript of MOSBAUGH audio tape (NRC #187).

58 HOSBAUGH audio tape, dated August 15, 1990. #3 (NRC #253).

59 HOSBAUGH audio tape, undated (NRC #184).

60 Transcript of MOSBAUGH audio tape (NRC #184).

61 MOSBAUGH audio tape, dated April 11, 1990 (NRC #42).

62 Transcript of MOSBAUGH audio tape. (NRC #42).

63 MOSBAUGH audio tape. dated August 30, 1990 #2 (NRC #269).

64 Transcript of MOSBAUGH audio tape. (NRC #269).

65 MOSBAUGH audio tape, dated April 11. 1990. #1 (NRC #41).

66 Transcript of MOSBAUGH audio tape. (NRC #41).

67 HOSBAUGH audio tape. dated August 17, 1990. #1 (NRC #258).

68 Transcript of MOSBAUGH audio tape (NRC # 258). !

69 HOSBAUGH audio tape, dated March 23 24, 1990 (NRC #10).

70 Transcript of MOSBAUGH audio tape. (NRC #10).

71 MOSBAUGH audio tape dated June 29, 1990. #1 (NRC #186).

72 Transcript of MOSBAUGH audio tape (NRC #186).

73 H058AUGH audio tape, undated, with the word "McC0Y" written on it (NRC #99).

74 Transcript of MOSBAUGH audio tape (NRC #99).

75 HOSBAUGH audio tape, dated July 27, 1990. #1 (NRC #222).

76 Transcript of MOSBAUGH audio tape (NRC #222).

77 HOSBAUGH audio tape, dated August 13, 1990 #3 (NRC #247).

i 78 Transcript of MOSBAUGH audio tape (NRC #247).

79 HOSBAUGH audio tape, dated August 13, 1990. #2 (NRC #246).

80 Transcript of NOSBAUGH audio tape (NRC #246). -

( 81 MOSBAUGH audio tape, dated August 15, 1990. #4 (NRC #254).

l Case No. 2 90 020R 109

Exhibit No. Descr1Dtion 82 Transcript of MOSBAUGH audio tape (NRC #254).

83 MOSBAUGH audio tape, dated July 30, 1990, #2 (NRC #226).

84 Transcript of MOSBAUGH audio tape (NRC #226).

85 MOSBAUGH audio tape, dated July 30, 1990, #3 (NRC #227).

86 Transcript of MOSBAUGH audio tape (NRC #227).

87 HOSBAUGH audio tape, dated August 15, 1990, #3 (NRC #253).

_88, Transcript of MOSBAUGH audio tape (NRC #253).

89 MOSBAUGH audio tape, dated July 23, 1990, #2 (NRC #215).

90 Transcript of MOSBAUGH audio tape (NRC #215).

91 MOSBAUGH audio tape, dated August 29, 1990, #2, (NRC #267).

92 Transcript of MOSBAUGH audio tape (NRC #267).

93 MOSBAUGH audio tape, dated July 23, 1990, #1 (NRC #214). l 94 Transcript of MOSBAUGH audio tape (NRC #214).

95 Report of Interview of George BOCKHOLD, dated November 23, 1993.

96 MOSBAUGH audio tape, dated (NRC #187).

97 MOSBAUGH audio tape, dated June 12, 1990 (NRC #160).

98 Transcript of MOSBAUGH audio tape (NRC #160).

THE FOLLOWING EXHIBITS WERE SPECIFICALLY IDENTIFIED BY THE LAW FIRH OF TROUTHAN SANDERS, ON BEHALF 0F THEIR CLIENT, GEORGIA POWER COMPANY.

99 HOSBAUGH audio tape, dated March 24, 1990 (NRC #11). Note: there is no NRC transcript of this tape.

100 NRC Inspection Report No. 90 05, dated April 26, 1990.

101 NRC IIT transcript No. 147, dated March 30, 1990.

102 NRC IIT transcript No. 257, dated April 3, 1990. -

103 NRC IIT transcript No.1681, dated April 4,1990.

(.. .

Case No. 2 90 020R 110

Exhibit

  • No. Descriotion 104 NRC IIT transcript No. 200, dated April 5,1990.

105 NRC IIT transcript No. 212, dated April 10, 1990.

106 NRC IIT transcript No. 205, dated April 7.1990.

107 NRC IIT transcript No. 245, dated April 12, 1990.

108 MOSBAUGH audio tape, dated March 28, 1990, #1 (NRC #19). Note: No NRC transcript.

109 HOSBAUGH audio tape, dated April 10, 1990, #2 (NRC #40). Note: No NRC transcript.

110 MOSBAUGH audio tape, dated April 26,1990, #2 (NRC #69). Note: No NRC transcript.

111 MOSBAUGH audio tape, dated April 27,1990, il (NRC #71-). Note: No NRC transcript.

112 Copy of the minutes of Vogtle Plant Review Board (PRB) meeting.

No. 90 59, dated April 18, 1990. ,

~

113 Two folders of indexed documents, received from Troutman Sanders on October 7. 1993.

a i

r 1

a A .

Case No. 2 90-020R 111