Comments on Proposed Rule 10CFR50 Re Monitoring Effectiveness of Maint at Nuclear Power Plants.Util Is in Total Agreement with NEI Comments
ML20198A203
Person / Time
Site: Hatch, Vogtle, Farley  Southern Nuclear icon.png
Issue date: 12/14/1998
From: Sumner H
SOUTHERN NUCLEAR OPERATING CO.
To: Hoyle J
NRC OFFICE OF THE SECRETARY (SECY)
References
FRN-63FR52201, RULE-PR-50-6FR52201 63FR52201-00007, 63FR52201-7, HL-5715, LCV-1287, NUDOCS 9812160179
Download: ML20198A203 (2)


Text

DEC.14.1998 7: 31 Af1' SCUTHERN huCLEAR ~C205)S92 6108' N0.833 P.2/3 towie Sameer Southem helear 7 Vice President Operstme Conspesy, lac.

Hatch Project Support sainvemes: Parkway D0CFETED Post Office Box 1295 i :g' .: a g

[lirmingham, Alabams 35201

Tal 205.992.7279 l

lex 20sss2a1 98 DEC 14 P1 :47 M V1:

..1,KEf NUMBER Oi m'

'ROPOSED RULEhh, skt snounranu~

50 ,_)

(&3FR50aot December 14, 1998 Docket Nos. 50-348 l 50-321 50-424 HL.5715 50-364 50-366 50-425 LCV-1287 l

Mr. John C. Hoyle, Secretary U. S. Nuclear Regulatory Commission ATTN: Rulemakings and Adjudication's Staff Washington, D. C. 20555-0001 Comments on the Proposed Rule,

" Monitoring the: Effectiveness of Maintenance at Nuclear Power Plants" (63 Federal Register 52201 dated September 30,1998)

Dear Ladies and Gentlemen:

Southem Nuclear Operatidg Company (Southem Nuclear; has reviewed the proposed mie,

" Monitoring the Effectiveness of Maintenance at Nuclear Power Plants," published in the Federal Register on Septe6ber 30,1998. In accordance with request for comments, Southern Nuclear is in total agreement with the NEI comments which are to be provided to the NRC.

Respectfully submitted, r .

H. L. Sumner HLS/JDB

\

D l

l l

l l

9812160179 981214 ,

PDR PR 50 6FRS2201 PDR 1v- ,

^

@@r.14.a@@@~ Ti3@M ' ? @ouTNEAN rOCL.EC i205)992 6108 ~ ~ ~ ' ~ tii.833~ p.'3/3

~ ~ ^

g O

, U. S. Nuclear Regulatory Commission Page Two cc: Southern Nuclest Operating Company Mr. M. L. Stinson, General Manager - Plant Farley Mr. P. H. Wells,? General Manager Plant Hatch Mr. J. T. Gasser, General Manager - Vogtle Electric Generating Plant Mr. D. N. Morey, Vice President - Plant Farley Mr. J. B. Beasley, Vice President - Plant Vogtle U. S. Nuclear Regulatory Commission, Washington, DC Mr. J. I. Z.mmennan, Licensing Project Manager - Farley Mr. L. N. Olshan, Project Manager - Hatch '

Mr. D. H. Jaffe, Senior Project Manager - Vogtle

_U_. S. Nuclear Regulatory Commission, Region II Mr. L. A. Reyes, llegional Administrator Mr. T. P. Johnson, Senior Resident Inspector - Farley Mr. J. T. Munday, Senior Resident Inspector - Hatch Mr. J. Zeiler, Senior Resident Inspector - Vogtle HL-5715 LCV-1287 i