Letter Sequence Request |
---|
|
|
MONTHYEARML20059B0841993-12-22022 December 1993 Forwards RAI Re GL-92-08, Thermo-Lag 330-1 Fire Barriers, Per 10CFR50.54(f) for Plant.Requests Addl Info on Configurations & Amounts of Thermo-Lag Fire Barriers Installed in Plant & Cable Loadings Project stage: RAI ML20073R9971994-02-0909 February 1994 Forwards Response to NRC 931222 RAI Re GL 92-08, Thermo-Lag 330-1 Fire Barriers Project stage: Other ML20070G7081994-07-15015 July 1994 Responds to Request for Addl Info Re GL 92-08,Thermo-Lag 330-1 Fire Barriers,Issued on 941222 Project stage: Request ML20078S7891994-12-22022 December 1994 Responds to 940923 Request for Addl Info Re GL 92-08 Concerning Thermo-Lag Fire Barrier Protection Sys Project stage: Request ML20086A6481995-06-27027 June 1995 Forwards Suppl Response to NRC 941229 follow-up to RAI Re GL 92-08, Thermo-Lag 330-1 Fire Barriers & Rept from Nucon Intl,Inc, Pyrolysis Gas Chromatography Analysis of 5 Thermo-Lag Fire Barrier Samples Project stage: Other ML20137C2081997-03-20020 March 1997 Ack Completion of Licensing Action of GL 92-08, Thermo-Lag 330-1 Fire Barriers, & Requests to Retain All Documentation Related for Future NRC Audits & Insp Project stage: Other 1994-02-09
[Table View] |
|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEAR05000482/LER-1999-002, Forwards LER 99-002-00,re Identification of Surveillance Performed in Modes Other than Those Required by TS SR 4.6.3.2.a.Commitments Made by Util Are Encl1999-10-15015 October 1999 Forwards LER 99-002-00,re Identification of Surveillance Performed in Modes Other than Those Required by TS SR 4.6.3.2.a.Commitments Made by Util Are Encl 05000482/LER-1994-014, Forwards LER 94-014-00 Re Util Identification of Missed Surveillance Required by TS Prior to Changing Modes.List of Commitments Made by Licensee,Encl1999-10-15015 October 1999 Forwards LER 94-014-00 Re Util Identification of Missed Surveillance Required by TS Prior to Changing Modes.List of Commitments Made by Licensee,Encl ML20217F7481999-10-14014 October 1999 Informs That Based on Approval of Core Assessment Damage Guidance in WCAP-14696,rev 1 for Westinghouse Nuclear Power Plants,Licensee May Use WCAP-14696,rev 1 at Wolf Creek Generating Station ML20217F8701999-10-13013 October 1999 Provides Summary of Meeting on 991007 with Representatives of Wolf Creek Nuclear Station in Burlington,Kansas Re Status of Licensee Radiation Protection Program.List of Meeting Attendees & Licensee Presentation Encl ML20217C1721999-10-0707 October 1999 Forwards Insp Rept 50-482/99-09 on 990830-0903.No Violations Noted.Purpose of Insp to Perform Routine Operational Status Insp of Emergency Preparedness Program & to Resolve Questions Re Revised Emergency Plan ML20217A4881999-09-29029 September 1999 Forwards Changes to Plant Data Point Library,Iaw 10CFR50,App E,Section VI.3.a.ERDS Point Affected Is RDS0001 ML20216H9291999-09-29029 September 1999 Informs That Licensee Responses to GL 97-06, Degradation of Steam Generator Internals Acceptable & Did Not Identify Any New Concerns with Condition of SG Intervals at Plant ML20212G1681999-09-24024 September 1999 Notifies NRC of Change in Status of Licensed Individual at Plant,Per 10CFR50.74.RL Acree Holds License OP-42654 at Plant,But Has Been Permanently Reassigned from Position for Which Plant Has Certified Need for RO License ML20216F9591999-09-22022 September 1999 Forwards Withdrawal of Amend Request Re Ultimate Heat Sink Temp for Wolf Creek Generating Station ML20212G5641999-09-20020 September 1999 Forwards Insp Rept 50-482/99-13 on 990725-0904.Three Violations Being Treated as Noncited Violations 05000482/LER-1999-011, Forwards LER 99-011-00 Re Identification of Missed Surveillance Due to Exceeding Flow Rate Specified in TS for Ccps.List of Util Commitments Contained in Attachment I1999-09-17017 September 1999 Forwards LER 99-011-00 Re Identification of Missed Surveillance Due to Exceeding Flow Rate Specified in TS for Ccps.List of Util Commitments Contained in Attachment I 05000482/LER-1999-010, Forwards LER 99-010-00,re Failure to Correctly Perform TS Surveillance 4.3.3.6.Encl Identifies Actions Committed to by Util1999-09-16016 September 1999 Forwards LER 99-010-00,re Failure to Correctly Perform TS Surveillance 4.3.3.6.Encl Identifies Actions Committed to by Util ML20212D9381999-09-16016 September 1999 Informs That NRC Staff Completed Midcycle PPR of WCGS on 990818.Areas of EP & Engineering Warranted Increase in NRC Action.Nrc Plan to Conduct Add Insp Beyond Core Insp Program Over Next 7 Months to Address Listed Questions 05000482/LER-1999-006, Forwards LER 99-006-01,re Identification of Failure to Enter LCO for TS 3.6.1.1 While Taking Containment Atmosphere Samples During Power Operation.Commitments Made by Util Are Encl1999-09-15015 September 1999 Forwards LER 99-006-01,re Identification of Failure to Enter LCO for TS 3.6.1.1 While Taking Containment Atmosphere Samples During Power Operation.Commitments Made by Util Are Encl ML20212C9211999-09-15015 September 1999 Forwards NRC Form 536, Operating Licensing Examination Data, in Response to NRC Administrative Ltr 99-03 ML20216F1641999-09-14014 September 1999 Forwards Insp Rept 50-482/99-12 on 990816-20.No Violation Noted.Determined That Solid Radwaste Mgt & Radioactive Matls Transportation Programs Were Properly Implemented 05000482/LER-1999-009, Forwards LER 99-009-00 Re Util Identification of Fire Suppression Issue Affecting Safe Shutdown Components. Attachment I Identifies Actions Committed to by Licensee in Encl LER1999-09-10010 September 1999 Forwards LER 99-009-00 Re Util Identification of Fire Suppression Issue Affecting Safe Shutdown Components. Attachment I Identifies Actions Committed to by Licensee in Encl LER ML20212A5651999-09-10010 September 1999 Informs of Completion of Review of & Encl Objectives for Wolf Creek Generating Station 1999 Emergency Preparedness Exercise Scheduled for 991117.Determined Exercise Objectives Appropriate to Meet EP Requirements 05000482/LER-1999-008, Forwards LER 99-008-00,re Efsa at Plant.Attachment I Identifies Actions Committed to by Licensee in LER1999-09-0303 September 1999 Forwards LER 99-008-00,re Efsa at Plant.Attachment I Identifies Actions Committed to by Licensee in LER ML20211M7151999-09-0303 September 1999 Forwards Changes to Wolf Creek Generating Station Data Point Library.Emergency Response Data Sys Points Affected Are EJL0007 & EJL0008 ML20211N0081999-09-0202 September 1999 Informs That NRC Staff Has Reviewed Submittals & Concluded Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power- Operated Gate Valves ML20211K8301999-09-0202 September 1999 Forwards marked-up TS Page Deleting Inequality Signs from Trip Setpoints in SR 3.3.5.3 & Reflecting Info on Calibr Tolerance Band,Per 990708 Application to Amend License NPF-42 ML20211K1941999-08-31031 August 1999 Forwards Rev 31 to WCGS Physical Security Plan,Safeguards Contingency Plan & Training & Qualification Plan,Iaw 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 ML20211H1491999-08-26026 August 1999 Forwards Insp Rept 50-482/99-16 on 990809-13.No Violations Noted.Insp Focused on Low as Is Reasonably Achievable Program,Training Program for Contract Radiation Protection Personnel & Radiation Protection QA Program ML20211A8581999-08-18018 August 1999 Forwards Insp Rept 50-482/99-08 on 990316-0724.One Violation Being Treated as Noncited Violation ML20211G2201999-08-17017 August 1999 Forwards Exam Rept 50-482/99-301 on 990726-29.Exam Evaluated Six Applicants for SO Licenses & Three Applicants for RO Licenses ML20210U0991999-08-13013 August 1999 Forwards Insp Rept 50-482/99-11 on 990712-16.No Violations Noted.Insp Was to Review Radiological Environ Monitoring Program ML20210U9751999-08-13013 August 1999 Informs That Licensee Identified That Answer Key for One Question on 990720 Written Exam & Event Classification for on Job Performance Measure Required Mod.Description & Justification for Proposed Mod,Including Technical Ref,Encl ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210R5621999-08-12012 August 1999 Forwards Monthly Operating Rept for July 1999 for Wolf Creek Generating Station,Per TS 6.9.1.8 & GL 97-02.Revised Repts for Apr,May & June 1999,correcting Number of Hours Reactor Critical,Encl ML20210P7491999-08-0909 August 1999 Ack Receipt of ,Which Transmitted Wolf Creek Radiological Emergency Response Plan 06-002,Rev 0,under Provisions of 10CFR50,App E,Section V ML20210N0061999-08-0303 August 1999 Forwards Response to NRC 990401 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Motor-Operated Gate Valves ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML20210H2551999-07-29029 July 1999 Provides 180-day Response to NRC Request for Info Re GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal ML20210J1371999-07-29029 July 1999 Requests NRC Approval of Methodology for Determining RCS Pressure & Temp & Overpressure Mitigation Sys PORV Limits. Attachment I Provides Proposed Changes to Improved TS ML20210F5931999-07-27027 July 1999 Forwards semi-annual Fitness for Duty Performance Data Rept for Wcnoc,Per 10CFR26.71(d).Rept Covers Period of 990101- 0630 ML20210F5881999-07-23023 July 1999 Submits Response to Administrative Ltr 99-02, Operator Reactor Licensing Action Estimates, ML20210B8191999-07-20020 July 1999 Ack Receipt of ,Which Transmitted Wolf Creek EP Implementing Procedure 06-005,Rev 1.Implementation of Changes Will Be Subj to Insp to Confirm That Changes Does Not Decrease Effectiveness of EP ML20209H5411999-07-15015 July 1999 Forwards Insp Rept 50-482/99-07 on 990614-18.No Violations Noted.Insp Focused on Radiation Program During Normal Operating Conditions ML20209H0441999-07-14014 July 1999 Forwards Response to NRC 990326 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs. Summary of Util Commitments Provided in Attachment 2 ML20209H0751999-07-14014 July 1999 Forwards Monthly Operating Rept for June 1999 for Wolf Creek Generating Station,Per TS 6.9.1.8 & GL 97-02.Max Dependable Capacity Has Been Updated from 1163 to 1170,as Determined by Calculations Based on Capacity Test Results of July 1998 ML20209G9871999-07-14014 July 1999 Informs of Changes Affecting Wolf Creek Security Plan,Per 10CFR50.54(p)(2).Encl Provides Description of Changes & Justification for Changes ML20209E3581999-07-12012 July 1999 Discusses Util 980925 Response to GL 92-01,Rev 1,Suppl 1, Rv Structural Integrity, Issued on 950519 to Wolf Creek Generating Station ML20209E0611999-07-0808 July 1999 Forwards Addl Pages to Rev 12 of USAR & Commitment Changes, Inadvertently Omitted from 990311 Submittal ML20196K8231999-07-0606 July 1999 Submits Kansas Electric Power Cooperative,Inc Ltr Pursuant to Commission Direction in Memo & Order CLI-99-19.Addresses Disposition of Existing Antitrust Conditions Attached to License for Wolf Creek Unit 1 Re Proposed License Transfer ML20209C6031999-07-0606 July 1999 Provides Applicants View as Result of 990618 Memo & Order Directing Parties to Address Proper Disposition of Existing Antitrust License Condition Attached to OL for Facility Due to Planned Changes in Ownership of Facility.With Svc List ML20196K0501999-07-0202 July 1999 Forwards Insp Rept 50-482/99-06 on 990502-0612.Three Violations Occurred & Being Treated as Noncited Violations, Consistent with App C of Enforcement Policy ML20209B7131999-07-0101 July 1999 Submits Response to NRC Request for Info Re GL 98-01, Suppl 1, Y2K Readiness of Computer Sys at Npps. Response on Status of Facility Y2K Readiness Was Requested by 990701.Disclosure Encl ML20209A7461999-06-29029 June 1999 Informs of Changes in Project Mgt Staff Assigned to Wcgs. Effective 990628,J Donohew Will Assume PM Responsibilities ML20209B5151999-06-29029 June 1999 Informs That Util Completed Analyses & Modifications to Address Items Discussed in GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions 1999-09-03
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEAR05000482/LER-1994-014, Forwards LER 94-014-00 Re Util Identification of Missed Surveillance Required by TS Prior to Changing Modes.List of Commitments Made by Licensee,Encl1999-10-15015 October 1999 Forwards LER 94-014-00 Re Util Identification of Missed Surveillance Required by TS Prior to Changing Modes.List of Commitments Made by Licensee,Encl 05000482/LER-1999-002, Forwards LER 99-002-00,re Identification of Surveillance Performed in Modes Other than Those Required by TS SR 4.6.3.2.a.Commitments Made by Util Are Encl1999-10-15015 October 1999 Forwards LER 99-002-00,re Identification of Surveillance Performed in Modes Other than Those Required by TS SR 4.6.3.2.a.Commitments Made by Util Are Encl ML20217A4881999-09-29029 September 1999 Forwards Changes to Plant Data Point Library,Iaw 10CFR50,App E,Section VI.3.a.ERDS Point Affected Is RDS0001 ML20212G1681999-09-24024 September 1999 Notifies NRC of Change in Status of Licensed Individual at Plant,Per 10CFR50.74.RL Acree Holds License OP-42654 at Plant,But Has Been Permanently Reassigned from Position for Which Plant Has Certified Need for RO License 05000482/LER-1999-011, Forwards LER 99-011-00 Re Identification of Missed Surveillance Due to Exceeding Flow Rate Specified in TS for Ccps.List of Util Commitments Contained in Attachment I1999-09-17017 September 1999 Forwards LER 99-011-00 Re Identification of Missed Surveillance Due to Exceeding Flow Rate Specified in TS for Ccps.List of Util Commitments Contained in Attachment I 05000482/LER-1999-010, Forwards LER 99-010-00,re Failure to Correctly Perform TS Surveillance 4.3.3.6.Encl Identifies Actions Committed to by Util1999-09-16016 September 1999 Forwards LER 99-010-00,re Failure to Correctly Perform TS Surveillance 4.3.3.6.Encl Identifies Actions Committed to by Util 05000482/LER-1999-006, Forwards LER 99-006-01,re Identification of Failure to Enter LCO for TS 3.6.1.1 While Taking Containment Atmosphere Samples During Power Operation.Commitments Made by Util Are Encl1999-09-15015 September 1999 Forwards LER 99-006-01,re Identification of Failure to Enter LCO for TS 3.6.1.1 While Taking Containment Atmosphere Samples During Power Operation.Commitments Made by Util Are Encl ML20212C9211999-09-15015 September 1999 Forwards NRC Form 536, Operating Licensing Examination Data, in Response to NRC Administrative Ltr 99-03 05000482/LER-1999-009, Forwards LER 99-009-00 Re Util Identification of Fire Suppression Issue Affecting Safe Shutdown Components. Attachment I Identifies Actions Committed to by Licensee in Encl LER1999-09-10010 September 1999 Forwards LER 99-009-00 Re Util Identification of Fire Suppression Issue Affecting Safe Shutdown Components. Attachment I Identifies Actions Committed to by Licensee in Encl LER 05000482/LER-1999-008, Forwards LER 99-008-00,re Efsa at Plant.Attachment I Identifies Actions Committed to by Licensee in LER1999-09-0303 September 1999 Forwards LER 99-008-00,re Efsa at Plant.Attachment I Identifies Actions Committed to by Licensee in LER ML20211M7151999-09-0303 September 1999 Forwards Changes to Wolf Creek Generating Station Data Point Library.Emergency Response Data Sys Points Affected Are EJL0007 & EJL0008 ML20211K8301999-09-0202 September 1999 Forwards marked-up TS Page Deleting Inequality Signs from Trip Setpoints in SR 3.3.5.3 & Reflecting Info on Calibr Tolerance Band,Per 990708 Application to Amend License NPF-42 ML20211K1941999-08-31031 August 1999 Forwards Rev 31 to WCGS Physical Security Plan,Safeguards Contingency Plan & Training & Qualification Plan,Iaw 10CFR50.54(p).Encl Withheld,Per 10CFR73.21 ML20210U9751999-08-13013 August 1999 Informs That Licensee Identified That Answer Key for One Question on 990720 Written Exam & Event Classification for on Job Performance Measure Required Mod.Description & Justification for Proposed Mod,Including Technical Ref,Encl ML20210R5621999-08-12012 August 1999 Forwards Monthly Operating Rept for July 1999 for Wolf Creek Generating Station,Per TS 6.9.1.8 & GL 97-02.Revised Repts for Apr,May & June 1999,correcting Number of Hours Reactor Critical,Encl ML20210N0061999-08-0303 August 1999 Forwards Response to NRC 990401 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Motor-Operated Gate Valves ML20210J1371999-07-29029 July 1999 Requests NRC Approval of Methodology for Determining RCS Pressure & Temp & Overpressure Mitigation Sys PORV Limits. Attachment I Provides Proposed Changes to Improved TS ML20210H2551999-07-29029 July 1999 Provides 180-day Response to NRC Request for Info Re GL 99-02, Lab Testing of Nuclear-Grade Activated Charcoal ML20210F5931999-07-27027 July 1999 Forwards semi-annual Fitness for Duty Performance Data Rept for Wcnoc,Per 10CFR26.71(d).Rept Covers Period of 990101- 0630 ML20210F5881999-07-23023 July 1999 Submits Response to Administrative Ltr 99-02, Operator Reactor Licensing Action Estimates, ML20209G9871999-07-14014 July 1999 Informs of Changes Affecting Wolf Creek Security Plan,Per 10CFR50.54(p)(2).Encl Provides Description of Changes & Justification for Changes ML20209H0441999-07-14014 July 1999 Forwards Response to NRC 990326 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs. Summary of Util Commitments Provided in Attachment 2 ML20209H0751999-07-14014 July 1999 Forwards Monthly Operating Rept for June 1999 for Wolf Creek Generating Station,Per TS 6.9.1.8 & GL 97-02.Max Dependable Capacity Has Been Updated from 1163 to 1170,as Determined by Calculations Based on Capacity Test Results of July 1998 ML20209E0611999-07-0808 July 1999 Forwards Addl Pages to Rev 12 of USAR & Commitment Changes, Inadvertently Omitted from 990311 Submittal ML20209C6031999-07-0606 July 1999 Provides Applicants View as Result of 990618 Memo & Order Directing Parties to Address Proper Disposition of Existing Antitrust License Condition Attached to OL for Facility Due to Planned Changes in Ownership of Facility.With Svc List ML20196K8231999-07-0606 July 1999 Submits Kansas Electric Power Cooperative,Inc Ltr Pursuant to Commission Direction in Memo & Order CLI-99-19.Addresses Disposition of Existing Antitrust Conditions Attached to License for Wolf Creek Unit 1 Re Proposed License Transfer ML20209B7131999-07-0101 July 1999 Submits Response to NRC Request for Info Re GL 98-01, Suppl 1, Y2K Readiness of Computer Sys at Npps. Response on Status of Facility Y2K Readiness Was Requested by 990701.Disclosure Encl ML20209B5151999-06-29029 June 1999 Informs That Util Completed Analyses & Modifications to Address Items Discussed in GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions ML20196G9681999-06-22022 June 1999 Informs NRC That BC Ryan Will Be Leaving Ks State Univ for Position with Wolf Creek Nuclear Operating Corp,Effective 990701 05000482/LER-1999-007, Forwards LER 99-007-00,re Condition in Which Wolf Creek Generating Station TS 3.3.2 Was Not Met.Commitments Made by Util Also Encl1999-06-18018 June 1999 Forwards LER 99-007-00,re Condition in Which Wolf Creek Generating Station TS 3.3.2 Was Not Met.Commitments Made by Util Also Encl ML20196A0251999-06-17017 June 1999 Requests That Written Exams for Reactor Operator & SRO for Plant Be Administered Beginning Wk of 990719 & Followed by Operating Exam During Wk of 990726 to Personnel Listed in Attachment.Proprietary Info Encl.Proprietary Info Withheld ML20195K0641999-06-15015 June 1999 Forwards MOR for May 1999 for Wolf Creek Generating Station & Corrected Page 2 of 2 of Apr 1999 Mor,Adding That Unit Entered Intomode 5 for Restart During Month of Apr & Correcting Shutdown Duration Hours from 672 to 671 ML20195G4391999-06-11011 June 1999 Provides Details for Missed Rept Re 10CFR50.46 Thirty Day Rept of ECCS Model Revs.Attachment I Provides Summary of Commitments Made in Submittal 05000482/LER-1999-005, Forwards LER 99-005-00,re Esfa.Commitments Made by Util Are Encl1999-06-11011 June 1999 Forwards LER 99-005-00,re Esfa.Commitments Made by Util Are Encl 05000482/LER-1997-027, Forwards LER 97-027-00 Re Identification of Missed Surveillance Required by TS 4.3.3.5.2.Encl 1 Identifies Actions Committed to by Util1999-06-0404 June 1999 Forwards LER 97-027-00 Re Identification of Missed Surveillance Required by TS 4.3.3.5.2.Encl 1 Identifies Actions Committed to by Util ML20195B9811999-05-26026 May 1999 Forwards 1998 Annual Repts for Ks Electric Power Cooperative Inc,Ks City Power & Light Co & Western Resources,Inc, Including Wholly Owned Subsidiary Kg&E Co ML20196L3361999-05-18018 May 1999 Forwards Rev 1 to Cycle 11 COLR for WCGS, IAW TS Section 6.9.1.9 05000482/LER-1999-004, Forwards LER 99-004-00 Re Failure to Maintain Containment Closure During Fuel Movement as Required by TS 3.9.4.c. Attachment I to Ltr Identifies Actions Committed to by Plant in Encl LER1999-05-12012 May 1999 Forwards LER 99-004-00 Re Failure to Maintain Containment Closure During Fuel Movement as Required by TS 3.9.4.c. Attachment I to Ltr Identifies Actions Committed to by Plant in Encl LER ML20206Q8141999-05-11011 May 1999 Requests NRC Work with Industry to Resolve Generic Changes to Allow Permanent Change to TSs Prior to June 2000.Encl Provides TS Limited Duration Action Statement Until 990930 05000482/LER-1999-003, Forwards LER 99-003-00,re Failure to Perform TS SR 4.9.2.c Prior to Entering Mode 6.Commitments Made by Util Are Encl1999-05-10010 May 1999 Forwards LER 99-003-00,re Failure to Perform TS SR 4.9.2.c Prior to Entering Mode 6.Commitments Made by Util Are Encl ML20206K5141999-05-0707 May 1999 Provides Info Re Number of Tubes Plugged in Each Sg,As Required by TS 4.4.5.5.ISI of SGs B & C Completed on 990424,resulting in Mechanical Plugging of One Tube in SG B & Five Tubes in SG C ML20206J0711999-05-0505 May 1999 Forwards Guarantees of Payment of Deferred Premiums for Owners of Wolf Creek Generating Station,As Required by 10CFR140.21 ML20206D9551999-04-29029 April 1999 Forwards 1999 Annual Radioactive Effluent Release Rept 22, for Reporting Period Jan-Dec 1998,per Section 6.9.1.7 of WCGS Ts.Attachment to Ltr Identifies Commitments Resulting from Correspondence ML20206C7321999-04-22022 April 1999 Provides Notification of Changes at WCGS Affecting Plant Physical Security Plan,Per 10CFR50.54(p).Changes Identified in Attachment I Will Be Incorporated Into Plan by 990831. Commitments Made by Util Are Included in Attachment II ML20206B2051999-04-20020 April 1999 Forwards Revs to RERP Implementing Procedures,Including Rev 1 to EPP 06-001, CR Operations, Rev 1 to EPP 06-002, TSC Operations, Rev 3 to EPP 06-004, Public Info Organization & Rev 1 to EPP 06-005, Emergency.. ML20205L7431999-04-0606 April 1999 Confirms 990401 Telcon with NRC Re Late Payment Notice That Util Received for Invoice RL0295-99.Licensee Understands Invoice to Be Cancelled ML20205F1601999-03-30030 March 1999 Forwards Rept Re Status of Decommissioning Funding for WCGS, Per 10CFR50.75.Kansas Gas & Electric Co Decommissioning Trust Agreement,Encl ML20205K9481999-03-26026 March 1999 Responds to NRC Ltr Re Violations Noted in Insp Rept 50-482/98-05.Corrective Actions:Training Was Provided to Mrep Members Through Use of Contract Individual Experienced in Maint Rule Programs.Change to Commitment Date,Encl ML20196K7261999-03-26026 March 1999 Forwards Certified Copy of ITS & ITS Bases,As Committed in Licensee to Nrc.Summary of Editorial Corrections, Also Encl ML20205A1961999-03-25025 March 1999 Provides Suppl 2 to 970515 Application for Amend to License NPF-42,providing Changes to TS Based on 990310 & 19 Discussions with NRC Re Conversion to Improved TS 1999-09-03
[Table view] |
Text
_ _ _ _ . - _ _ _ -
1
-e W$LF CREEK NUCLEAR OPERATING CORPORATION Ned S. " Buzz" Carns Chairman, President and enief Executive Offw:er WM 94-0199 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station P1-137 Washington, D.C. 20555 -
Reference 1) NRC Letter dated December 22, 1993, " Request For c Additional Information Regarding Generic Letter 92-08 (TAC No. M85625)"
- 2) Letter WO 94-0013 dated February 9, 1994, from O. L. Maynard, WCNOC, to the Nuclear Regulatory Commission
- 3) Letter CO 94-0013 dated July 15, 1994, from R. N. Johannes, WCNOC, to the Nuclear Regulatory Commission S 51.: 6'.:: Docket No. 50-482: Response to Follow-Up to the Request for Additional Information Regarding Generic Letter 92-08 Gentlemen The NRC issued a letter dated September 23, 1994, " Follow-Up to the Request for Additional Information Regarding Generic Letter 92-08 Issued Pursuant to 10 CFF. 50.54(f) on December 22, 1993," which required a response to be submitted to the NRC within 90 days of receipt of the letter. In that letter, ycu indicated that our response (References 2 and 3) to three sections of the RAI (Reference 1) had been deferred or was incomplete. Specifically, the sections requiring a revised response are: Section II, "Important Barrier Parameters,"Section IV, "Ampacity Derating," and Section V, " Alternatives."
The attachment provides Wolf Creek Nuclear Operating Corporation's (WCNOC) response to the requested information. For completeness, we have duplicated our responses to Sections II, IV, and V from the original submittal, References 2 and 3, and revised them as necessary.
k 0 Y e N ^ on o m 41i / Burnngton. KS 66839 / Phone (316) 364-8831 5 9412290209 941222 ~
PDR ADOCK 05000482 An uuai opportun<ty Empiover u r sc.vtr P PDR t
WM 94-0199 Page 2 of 2 If you have any questions concerning this matter, please contact me at (316) 364-8831, extension 4000, or Mr. Richard D. Flannigan at extension 4500.
Very truly yours, Neil S. Carns NSC/jra Attachment cc: L. J. Callan (NRC), w/a D. D. Chamberlain (NRC), w/a J. F. Ringwald (NPC), w/a J. C. Stone (NRC), w/a
Fettachment to WM 94-0199 Page 1 of 5 RESPONSE TO THERMO-LAG REQUEST FOR ADDITIONAL INFORMATION RAI 3ection II. IMPORTANT BARRIER PARAMETERS NRC Item II.B.1 State whether or not you have obtained and verified each of the aforementioned parameters for each Thermo-Lag barrier installed in the plant. If not, discuss the parameters you have not obtained or verified. Retain detailed information on site for NRC audit where the aforementioned parameters are known.
WCNOC RESPONSE WCNOC has obtained and verified the 24 parameters listed in the RAI for WCGS BTP CMEB 9.5-1 applications. Total enclosed mass (raceway and cabling), panel rib location, protection of intervening and support steel, and wall interfaces have also be:en obtained as part of WCNOC's Application Guide evaluation.
Detailed information is available on-site for NRC audit of the known parameters.
Parameters of importance concerning cable items 1, 2, 3, 4 (cable fill), 5, 6, and 7 have also been obtained. Items 4 (distribution of cables) and 8 have not been obtained. WCNOC's NEI Application Guide evaluations do not warrant cable functionality evaluations. Therefore, WCNOC does not intend to obtain and verify the remaining cable parameters or to perform cable functionality evaluations.
NRC ITEM II.B.2 For any parameter that is not known or has not been verified, describe how you will evaluate the in-plant barrier for acceptability.
WCNOC RESPONSE WCNOC has obtained and verified the parameters of importance at WCGS concerning cables protected by fire barriers used for safe shutdown in the event of a fire. Tf the NEI Thermo-Lag testing application to WCGS installations had demonstrated temperature criteria exceedance, one optional approach to resolution would have been to evaluate cable functionality at the elevated temperature using cable performance test data or information for specific installed cable types. However, the results of NEI testing and i subsequent NEI Application Guide evaluations of WCGS Thermo-Lag installations l indicate that cable functionality evaluations are not warranted. Therefore, WCNOC does not intend to obtain and verify cable parameters items 4 (cable distribution) and 8, or to perform cable functionality evaluations.
a
httachment to WM 94-0199 Page 2 of 5 NRC ITEM II.B.3 To evaluate NUMARC's application guidance, an understanding of the types and extent of the unknown parameters is needed.
Describe the type and extent of the unknown parameters at your plant in this context.
WCNOC RESPONSE All 24 raceway parameters of importance were obtained by WCNOC to perform NEI Application Guide evaluations. NEI Guidelines do not 1.iclude cable functionality. Therefore, no impact is caused by WCNOC plans to not obtain items 4 (cable distribution) or 8 information on parameters of importance concerning cables protected by fire barriers.
{
RAI Section IV. AMPACITY DERATING Your response to Section IV.B may depend on unknown specifics of the NUMARC ampacity derating test program (e.g., the final barrier upgrades) . However, your response should be as complete as possible. In addition, your response should be updated as additional information becomes available on the NUMARC program.
NRC IIEM IV.B.1. For the barriers described under Item I.B.1, describe those that you have determined will fall within the scope of the NUMARC program for ampacity derating, those that will not be bounded by the NUMARC program, and those for which ampacity derating does not apply.
ECHQC_ RESPONSE NEI did not perform ampacity derating testing as part of their testing program. Thus, they did not provide bounding data for application to WCGS installations.
As discussed in the April 16, 1993 WCNOC response to NRC Generic Letter 92-08 (Letter ET 93-0047, F. T. Rhodes, WCNOC, to USNRC), WCGS ampacity derating i
factors for conduit and cable trays covered with Thermo-Lag 330-1 are based on i
vendor supplied heat transfer coefficient values for Thermo-Lag 330-1. During original design, WCNOC performed heat transfer calculations to address the specific applications and provide the basis for ampacity derating. The ampacity derating values are not based on ampacity derating tests.
Conservatism was used in the assumptions made to bound operating parameters.
The generic concern with the acceptability of ampacity derating factors is that long term life of the cable insulation may be degraded due to a potentially higher operating temperature for the cable.
WCNOC has evaluated WCGS Thermo-Lag 330-1 applications of conduits and cable trays for ampacity margin. Ampacity margin is the percentage difference between the actual current of the cable and the acceptable current of the cable not including the thermal insulating effects of Thermo-Lag. It was determined that WCGS has very conservative ampacity margins compared to results of tests performed by other organizations. The ampacity margins will be applied to future upgrades as appropriate. Furthermore, WCGS Class 1E l
Attachment to WM 94-0199 Page 3 of 5 l electrical cables are qualified for a 40 year life and have been in service ,
less than one-quarter of the qualified life. l I
WCNOC currently has no plans to evaluate instrumentation and control cable as I they do not carry a significant current compared to the ampacity of the conductors. Furthermore, the heat generated is not significant compared to that generated by power conductors.
WCNOC also does not intend to evaluate ampacity deratings on fire barrier configurations which enclose a raceway for six (6) inches or less in length.
This is based on the fact that this small an area will not create a significant temperature rise.
NRC ITEM IV.B.2. For the barriers you have determined fall within the scope of the NUMARC program, describe what additional testing or evaluation you will need to perform to derive valid ampacity derating factors.
i HCHOC RESPONSE NEI did not perform ampacity derating testing as part of th2ir testing program. Thus, they did not provide bounding data for application to WCGS installations. The NRC has questioned the generic use of the industry testing procedure for ampacity derating (IEEE P848). Therefore, WCNOC does not plan to perform any ampacity testing.
HRC ITEM IV.B.3. For the barrier configurations that you have datermined will not be bounded by the NUMARC test program, describe your plan for evaluating whether or not the ampacity darating tests relied upon for the ampacity derating factors used for those electrical components protected by Thermo-Lag 330-1 (for protecting the safe-shutdown capability from fire or to achieve physical independence of electrical systems) are correct and applicable to the plant design. Describe all corrective actions needed and submit the schedule for completing such actions.
NCHQC RESPONSE As stated in our response to NRC Item IV.B.1 WCNOC has evaluated WCGS Thermo-Lag 330-1 applications of conduits and cable trays for ampacity margin and determined that WCGS has a very conservative ampacity margin. Considering the margin of safety built into our circuits, WCGS does not intend to perform additional ampacity derating calculations at this time.
I HEC ITEM IV.B.4. In the event that the NUMARC fire barrier tests indicate the need to upgrade existing in-plant barriers or to replace existing Thermo-Lag barriers with another fire barrier 1 system, describe the alternative actions you will take (and l
l l
Attachment to WM 94-0199 Page 4 of 5 the schedule for performing those actions) to confirm that the ampacity derating factors were derived by valid tests and are applicable to the modified plant design.
WCNOC RESPONSE Should WCNOC decide to perform upgrades to existing Thermo-Lag barriers, pertinent ampacity derating test results from other organizations, if applicable, will be considered. However, until the NRC concerns with ampacity derating issues (especially the use of IEEE P840) are resolved, insufficient basis exists for further action by WCNOC at this time.
This response is applicable for both Regulatory Guide 1.75 and BTP CMEB 9.5-1 applications.
RAI Section V. ALTERNATIVES NRC ITEM V.B2 Describe the specific alternatives available to you for achieving compliance with NRC fire protection requirements in plant areas that contain Thermo-Lag fire barriers.
Examples of possible alternatives to Thermo-Lag based upgrades include the following:
- 1. Upgrade existing in-plant barriers using other materials.
- 2. Replace Thermo-Lag barriers with other fire barrier materials or systems.
- 3. Roroute cables or relocate other protected components.
- 4. Qualify 3-hour barriers as 1-hour barriers and install detection and suppression systems to satisfy NRC fire protection requirements.
WCNOC RESPONSE If additional WCNOC evaluations using the NUMARC Application Guide indicate that some upgrades that rely on additional thickness of Thermo-Lag material (or other fire barrier materials) may not be practical due to the effects of ampacity derating or clearance problems, alternative methods exist to restore the fire barriers to operable status. The following is a discussion of some of the alternatives available. However, the following discussion is not meant to limit WCNOC to only those methods described.
- 1. The majority of WCGS applications involve 3-hour rated fire barriers.
Evaluations, based upon calculations, testing, or analysis may be performed to justify the barrier as-installed.
- 2. Reroute of cable, or replacement of specific cables with fire rated cable (i.e., Rockbestos Firezone R)
1
. Attachment to WM 94-0199 i Page 5 of 5
- 3. If evaluation using the NUMARC Application Guide indicates that the specific WCGS applications are not bounded due to differences in baseline Thermo-Lag 330-1 installation details, WCNOC can rework the l WCGS baseline installations to achieve compliance with the as-tested NUMARC configurations.
- 4. In many WCGS applications it would be possible to install fire suppression and fire detection to the area and then qualify the existing 3-hour barriers as 1-hour rated barriers.
- 5. Performing a re-evaluation of engineering analyses used for determination of safe shutdown pathways, equipment, and actions, could provide a basis for reduction in the scope of protected circuits and their associated fire barriers.
- 6. For certain applications, WCNOC could replace the Thermo-Lag fire barrier with rated fire barriers using other qualified materials or systems.
- 7. Upgrades using other fire barrier materials may be developed. However, the final approved test methods and acceptance criteria must be evaluated to determine net effect on the scope and complexity of upgrades to WCGS installed barriers before this option could be chosen.
The WCGS applications of Thermo-Lag 330-1 material installed to meet the requirements of Regulatory Guide 1.75 are not intended to meet 1-hour or 3-hour rated fire barrier configuration requirements. Future ampacity derating evaluations, or combustibility evaluations, for these applications may indicate Thermo-Lag 330-1 material is not suitable for use in specific applications. In this event, the Thermo-Lag 330-1 material will be replaced with an alternate material which is suitable as a radiant energy shield.