ML20028F115
ML20028F115 | |
Person / Time | |
---|---|
Site: | Quad Cities |
Issue date: | 01/20/1983 |
From: | COMMONWEALTH EDISON CO. |
To: | |
Shared Package | |
ML20028F111 | List: |
References | |
NUDOCS 8301310163 | |
Download: ML20028F115 (74) | |
Text
. __. . _. . - . .
1 1 ,
1 i.
i REACTOR CONTAINMENT BUILDING INTEGRATED LEAK RATE TEST i
i 1
l i.
QUAD-CITIES NUCLEAR POWER STATION UNIT ONE DECEMBER 16-17, 1982 i
a
{
e l
1 I B301310163 830120 i PDR ADOCK 05000254 p PDR
TABLE OF CONTENTS, PAGE TABLE AND FIGURES INDEX. . . . . . . . . . . .. .. .. . .. . . .3 INTRODUCTION . . . . . . . . . . . . . . . . .. . .. . . . . . . .4:
A. TEST PREPARATIONS A.1 Type A Test Procedures . . . . . . . . . . ... . . . . . .5 A.2 Type A Test Instrumentation. . . . . . .. . .. . .. .. .5 A.2.a. Temperature . . . .. .. . .. . . .. . .. . . .9 A.2.b. Pressure. . . . . . . . . . .. . . . . . . . . . .9 A.2.c. Vapor Pressure. . . . . . . . . . . .. . . . . . .9 A.2.d. Flow. . . . . . . . . . . . .. . . . . . . .. . .10 A.3 Type A Test Measurements . . . . . . .. . . .. . .. . . 10 A.4 Type A Test Pressurization . . . . . .. . . . . . . . . . .11 B. TEST METHOD B.1 Basic Technique. . . . . . . . . . . . . . . . . . . . . . .13 B.2 Supplemental Verification Test . . . . . . . .. . . . . . .14 B.3 Instrument Error Analysis. . . . . . .. . . . . . . . . . .14 C. SEQUENCE OF EVENTS C.1 Test Preparation Chronology. . . . . . . . . . . . . . . . .16 C.2 Test Preparation and Stabilization Chronology. . . .. . . .16 C.3 Measured Leak Rate Phase Chronology. . . . . .. . . . . . .17 C.4 Induced Leakage Phase Chronology . . . . . . . . . . . . . .18 C.5 Depressurization Phase Chronology. .. . . . .. . . . . . .18 i
D. TYPE A TEST DATA D.1 Measured Leak Rate Phase' Data . . . . . . . .. . . . . . . 19 D.2 Induced Leakage Phase Data. . . . . . . . . . . . . . . . . 19 i
1 L
TABLE OF CONTENTS (CONTINUED)
PAGE-E. TEST CALCULATIONS. . . . . . . . .. . . . . . . . . . . . . . .32 F. TYPE A TEST RESULTS F.1 Measured Leak Rate Test Results. . . . . . . . . . . . . . .33 F.2 Induced Leakage Test Results . . . . . . . . . . . . . . .33 F.3 Leak Rate Compensation for Non-Vented Penetrations . . . . .34 F.4 Pre-Operational Results vs. Test Results . . . . . . . . . .34-APPENDIX A TYPE B AND C TESTS. ... . . . . . . . . . . . . .36 APPENDIX B
SUMMARY
OF AS FOUND LEAK RATES. . . . . . . . . . .46 APPENDIX C COMPUTATIONAL PROCEDURES. . . . . . . . . . . . . .48 APPENDIX D INSTRUMENT ERROR ANALYSIS . . . . . . . . . . . . .57 APPENDIX E BN-TOP-1, REV. 1 ERRATA . . . . . . . . . . . . . .63 i
APPENDIX F TYPE A TEST RESULTS USING MASS-PLOT . . . . . . . .67 METHOD (ANS/ ANSI 56.8)
APPENDIX G BLOCK DIAGRAM OF COMPUTER . . . . . . . . . . . . .70 PROGRAM TO PERFORM CALCULATIONS BASED ON BN-TOP-1, REV. 1 f
1 y w --
TABLES AND FIGURES INDEX PAGE TABLE 1 Instrument Specifications. .. . . . . . . . . . . . .6 TABLE 2 Sensor Physical Locations. . . .. . . . . . . . . . .7 TABLE 3 Measured Leak Rate Phase Test Results. . . . . . . . . .20 TABLE 4 Induced Leakage Phase Test Results . . . . . . . . . . .21 TABLE A-1 Type B and C Test Results. .. . . . . . . . . . . . . .37 FIGURE 1 Idealized View of Drywell and Torus. . . . . . . . . . .8 Used to Calculate Free Air Volumes FIGURE 2 Measurement System Schematic Arrangement . . .. . . . .12 FIGURE 3 Measure Leak Rate Phase - Graph of Calculated. . . . . .22 Leak Rate and Upper Confidence Limit FIGURE 4 Measured Leak Rate Phase - Graph of Total. . . . . . . .23 Time Measured Leak Rate and Regression Line FIGURE 5 Measured Leak Rate Phase - Graph of. . . . . . . . . . .24 Dry Air Pressure FIGURE 6 Measured Leak Rate Phase - Graph of. . . . . . . . . . .25 Volume Weighted Average Containment Vapor Pressure FIGURE 7 Measured Leak Rate Phase - Graph of Volume . . . . . . .26 Weighted Average Containment Temperature FIGURE 8 Induced Leakage Phase - Graph of Calculated. . . . . . .27-Leak Rate and Upper Confidence Limit FIGURE 9 Induced Leakage Phase - Graph of Total Time. . .. . . .28 Measured Leak Rate and Regression Line FIGURE 10 Induced Leakage Phase - Graph of Volume. . . . . . . . .29 Weighted Average Containment Temperature FIGURE 11 Induced Leakage Phase - Graph of Volume. . . . . . . . .30 Weighted Average Containment Vapor Pressure FIGURE 12 Induced Leakage Phase - Graph of . . .. . . . . . . . .31 Dry Air Pressure FIGURE 13 Statistically Averaged Leak Rate and Upper . . . .. . .35 Confidence Limit (ANS/ ANSI 56.8 Method)
INTRODUCTION This report presents the test method and results of the Integrated Primary Containment Leak Rate Test (IPCLRT) successfully performed on December 16-17, 1982 at Quad-Cities Nuclear Power Station, Unit One. The test was performed in accordance with 10 CFR 50, Appendix J, and the Quad-Cities Unit One Technical Specifications.
For the first time at Quad-Cities a short duration test (less than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />) was conducted usin2 the general test method outlined in BN-TOP-1, Revision 1 (Bechtel Corporation Topical Report) dated November 1,1972.
Using the above test method, the total primary containment integrated leak rate, adjusted to include penetrations not tested during the IPCLRT, was calculated to be 0.524 wt %/ day at a test pressure greater than 48 PSIG. The calculated leak rate was within the 0.750 wt %/ day acceptance criteria (75% of L ).
A The associated upper 95% confidence limit was 0.731 wt %/ day.
Excluding non-testable penetrations,.the supplemental induced leakage test result was calculated to be 1.326 wt %/ day. This value should compare with the sum of the measured leak rate phase result (0.453 wt %/ day) and the induced leak of 8 SCFM (0.980 wt %/ day). The calculated leak rate of 1.326 wt %/ day lies within the allowable tolerance band of 1.433 wt %/ day i 0.250 wt %/ day.
i
i SECTION A - TEST PREPARATIONS J A.1 Type A Test Procedure.
The IPCLRT was performed in accordance with Quad-Cities Procedure QTS 150-6, Rev. 1, including checklists QTS ISO-SI through S13 and subsections T2, T3,-
T6, T8, T9, and T10. Approved Temporary Procedure 1748 was written for the proper operation of the. IPCLRT air compressor and the. method for pressurizing .
the containment volume. Temporary ' Procedure 1757 slightly modified the instrument
~
location of four test instruments without changing subvolume locations.
Temporary Procedure 1756 modified the pre-test valve line-up to reflect valves that had been removed (with lines capped) since the last IPCLRT and' valves that were not locked in their position and needed no locks. Temporary Procedure 1758 modified the post test valve line-up to bring it in agreement with the start up preparations for the Unit that were in progress following the IPCLRT.
These procedures were written to comply with 10 CFR 50, Appendix-J, ANS/ ANSI i N45.5-1972, Quad-Cities Unit One Technical Specifications, and to. reflect the l Commission's approval of a short duration test using the BN-TOP-1, Rev. 1 Topical report as a general test method.
A.2 Type A Test Instrumentation Table One shows the specifications for the instrumentation utilized in the IPCLRT. Table Two lists the physical locations of the temperature and humidity sensors within the primary containment. Figure 1 is an idealized view of the drywell and suppression chamber used to calculate the primary containment free air subvolumes. Plant personnel performed all test instrumentation calibrations using NBS traceable standards, i
i I
i l
l
TABLE ONE INSTRUMENT SPECIFICATIONS INSTRUMENT, MANUFACTURER MODEL NO. SERIAL NO. RANGE ACCURACY REPEATABILITY Precision Pressure Gages (2) Voluetrics 846,847 0-100 PSIA i.015 PSI .001 PSI 44209 to Burns 44238 RTD's (30)
Engineering SP1Al-5\-3A inclusive 50-200 F 1.5 F .i.1 F 5835-1, Volumetrics 2,3,6,7, Dewcells (8) (Foxboro) 8,9,10 +140 F 11.0 F .5'F w
Pall Trinity Thermocouple Micro 14-T-2H 0-600 F 12.0 F- ' i.1*F '
Fischer Flowmeter & Porter 83 8209A9118 RIB 0-8.44 scfm I.084 scfm Level Indicator LI 1-263-100A- Yarway SCR/M 967-25377 +60"H O 2
- - _. J
I r
. TABLE TWO SENSOR PHYSICAL LOCATIONS RTD NUMBER SERIAL NUMBER SUBVOLUME ELEVATION AZIMUTH 1 ~44209 1 670'0" 180*
2 44210 1 670'0" 0*
3 44211 2 657'0" 20 4 44212 2 657'0" 200*
4 5 44213 3' 634'0" 70*
6 44214 3 634'0" 265*
7 44215 4(Annular Ring) 643'0" 45
- 8 44216= 4 615'0" 225*' ;
9 44217 5 620'0" 5*
10 -44218 5 620'0" 100 11 44219 5 620'0" 220*
12 44220 6 608'0" 335*
13 44221 6 608'0" 130*
14 44222 6 608'0" 220*
1 15 44223 6 608'0" 310 16 44224 7 598'0" 70*
17 44225 7 598'0" 160*
18 44226 7 598'0" 200*
19 44227 7 598'0" 340*
20 44228 8 587'0" 10*
. 21 44230 8 587'0" - 100
22 44232 8 587'0" 190*
23 44233 8 587'0" 280*-
24 44234 9(CRD Space) -586'0" 0*
25 44235 10(Torus) 578'0" 0*
26 44236 10(Torus) 578'0" 120*
27 44237 10(Torus) -578'0" 60*-
l 28 44238 10(Torus) 578'0" 180*
4 29 44229 10(Torus) 578'0" -240*
30' 44231 10(Torus) 578'0" 300 Thermocouple (inlet to 11(Rx Vessel)-
clean-up HX) i DEWCELL NO. SERIAL NUMBER- SUBVOLUME ELEVATION AZIMUTH 1 5835-3 2 657'0" 160 4 2 5835-1 5 620'0"' 340*
! 3 5835-6 7 598'0" 70*'
4 5835-8 7 598'0" 250 5 5935-10 9 586'0" 0*
6 5835-9 10 578'0" 0*
7 5835-7 10 578'0" 120*
8 5835-2 10 578'0" 240*
i Thermocouple Vessel 11 a
Saturated
~7-
7 i
FIGURE 1 idealized View of Drf.all and Tur us Used to Calculate Free Volunes 37'0" y
, 34'8" d _.681'9"
_ _677'6"
'/ /
_ 666'9" A _ 11 , ,
. .,, 662'0" l/ 42'0" '
_ _ 655'2"
,,,. .l [ [ , / / / U / 652'8"
- I / / (Grating)
((/ /'I0ccupied / / '
f ,f,fj Vol'ume r / / g
' Free 'Uli' l ' "
e v
~
volume / i./ / 635'10" 7" ,
/ 62e'8"
- ; //- v- # ~ >
, [44,.
, h /)' ,
s 'N
/
// /'
/p h- _ 614'6"
- / lf// .
s t
= tcos.e,.?'
y____ pj p.____;l _ Go2'io"
/q , ...._/ , i
/ \/ /
s I/ / ssa'0"
/
m
^
/ . /,'_ _ _f _$'M Y
30'0" W////////7 569'?on Floor)
W'&
'- 54'6" 3 J<
A.2.a. Temperature The location of the 30 platinum RTD's was chosen to avoid conflict with local temperature variations and thermal influeuce from metal structures.
The RTD's were manufactured by Burns Engineering Inc. and are Model
'SP 1Al-5\-3A. Each RTD and its associated bridge network.was calibrated to yield an output of approximately 0-100 mV over a temperature range of 50-150 F.
Each RTD was calibrated by comparing the bridge output-to the true temperature as indicated by the temperature standard. Three temperatures were used for the calibration. Two calibration constants (a slope and intercept of the regression line) were computed for each RTD by performing a least squares fit of the RTD bridge cotput to the' reference standard's indicated true temperature.
The temperature standard used for all calibrations was a Volumetrics RTD Model VMC 701-B used with a Dewcell/RTD Calibrator Model 07731. The standard was calibrated by Volumetrics on November 11, 1982 to standards traceable to-the NBS.
The plant process computer scanned the output of each RTD-bridge network I
and converted the output to engineering units using the calibration constants.
A.2.b. Pressure Two precision quartz bourdon tube, absolute pressure gauges were utilized' to measure total containment pressure. Each gauge had a local digital readout and a Binary Coded Decimal (BCD) output to the process computer. Primary containment pressure was sensed by the pressure gauges in parallel through a 3/8" tygon tube connection to a special one inch pipe penetration to the containment.
Each precision pressure gauge was calibrated from 50-70 PSIA in 5 PSI increments using a third precision pressure gauge (Volumetrics Model 07726) that had been sent to Volumetrics for calibration. The pressure standard was calibrated on October 22, 1982 using NBS traceable reference standards.
The digital readout of the instruments were in " counts" or arbitrary units. Calibration constants (a slope and intercept of a regression line) were entered into the computer program to convert'" counts" ~into true atmospheric pressure as read by the third, reference gauge. No mechanical calibration of the gauges was performed to bring their digital displays into agreement with true pressure.
A.2.c. Vapor Pressure l The eight lithium chloride dewcells were physically situated in the contain-ment based on the results of the last four IPCLRT's performed at Quad-Cities and remained unchanged from the last IPCLRT performed for Unit One in February, 1979. The dewcells used were supplied by Volumetrics and manufactured by Foxboro.
i I
The calibration constants (the slope and intercept of a regression line) for each dewcell were computed relating the 0-150 mV output of the sensor conditioning card to the actual dewpoint indicated by a reference standard.
A three point calibration was performed for each dewcell. The reference standard was a chilled mirror dewcell standard, Volumetrics Model VMC 305, used with the Dewcell/RTD Calibrator Model 07731. The reference standard was calibrated by Volumetrics on October 22, 1982 using NBS traceable standards.
A.2.d. Flow A rotameter flowmeter, Fischer-Porter serial number 8209A9118RIA, was used for the flow measurement during the induced leakage phase.of the IPCLRT. The flowmeter was calibrated on October 20, 1982 by Fischer-Porter to within 11%
of full scale ( 8-8.44 SCFM) using NBS traceable standards.
Plant personnel continuously monitored the flow during the induced leakage phase and corrected any minor deviations from the induced flow rate of 8 SCFM by adjusting a 3/8" needle valve on the. flowmeter inlet.
A.3 Type A Test Measurement The IPCLRT was performed utilizing a direct interface with the station process computer. This system consists of a hard-wired installation of temperature, dewpoint, and pressure inputs for the IPCLRT to the process computer. The interface allows the process computer to scan, calculate, and print results with minimal manual input. The process computer output gave measured and calculated leak rate data using the dry air mass method given in i ANS/ ANSI 56.8-1981. This output was used for comparison purposes only.
Data sets giving instrument outputs were automatically transferred to a Prime 750 computer where the containment data was used to compute the leak rates and confidence limits based on BN-TOP-1, Rev. 1. A Ramtek color terminal was used to aid in monitoring the containment environmental configuration and instrument stability. The BN-TOP-1, Rev. I calculations were also' displayed in summary form showing the results and trends as each additional data. set was received. Key parameters such as containment volume weighted dry air pressure and temperature and calculated leak rates with upper confidence limits were plotted and displayed on the computer terminal.
l During the IPCLRT plant personnel plotted a number of subvolume, containment, and calculated parameters in order to quickly identify any problems that might develop during the test such as a failed sensor or unusual leak rate data that might indicate excessive leakage.
Figure 2 shows a schematic diagram of the IPCLRT data acquisition system.
A.4 Type A Test Pressurization A 3000 SCFM, 600 hp, 4 kV electric oil-free air compressor was used to pressurize the primary containment. An identical compressor was available in standby during the IPCLRT. The compressors were physically located on a single, enclosed truck trailer located outside the Reactor Building. The compressed air was piped using flexible metal hose to the Etactor Building, through an existing four inch fire header penetration, and piped to a temporary spool piece that, when installed, allowed the pressurization of the drywell through the "A" containment spray header. The inboard, containment spray isolation valve, M0-1-1001-26A was open during pressurization. Once the containment was pressurized, the MO 1-1001-26A valve was closed and the spool piece was removed and replaced with a blind flange.
HEAUSREliENT SYSTEli SCHEtiATIC ARRAllGEMENT RTD 3/C LOCAL JUNCTl0:1 (4) B0XES (8)
RTD F9 3/C La (26)
(26)
POWER SUPPLY C0X (1)
DEWCELL 5/C , 3/C (3)
(3)
Q 110V DRYWELL TERillflAL X D0X FLOWitETER
-Q.
, , PRESSURE I I SE!!S lliG "d TUBlilG 40/C ,
40/C I
IPCLRT (3) I (3) l lllSTRUtiENT CONSOLE _
DRYWELL PERS0!1tlEL litTERLOCK BULKilEAD RTD & DEWCELL SIGilAL 40/C (2)
CONDITIONING CARDS PROCESS 32/C (2) C0ftPUTER ltASS PRESSURE GAUGES PLOT f1ETil0D h
Il0V PR1i1E 3:1-TOP-1 C0ftPUTER liETHOD FIGURE 2 SECTION B - TEST METHOD B.1 Basic Technique The absolute method of leak rate determination was used. The absolute method uses the ideal gas laws to calculate the measured leak rate, as defined in ANS/ ANSI N45.4-1972. The inputs to.the measured. leak rate calculation include subvolume weighted containment temperature, subvolume weighted vapor pressure, total air pressure, and a total containment volume correction for reactor water level.
As required by the Commission in order to perform 4 short duration' test (measured leak rate phase of 12-24 hours), the measured lea's rite was-strtisti-cally analyzed using the principles outlined in BN-TOP-1, Rev. 1. A least squares regression line for measured leak rate versus time since the startiof the test is calculated af ter each new data set is scanned. The calculated leak rate at a point in time, t i, is the leak rate on the regression line at the time t g.
The use of a regression line in the BN-TOP-1, Rev. I report is different from the way it is used in the ANS/ ANSI 56.8-1981 standard. The latter standard uses the slope of the regression line for dry air mass as a function of time to derive a statistically averaged leak rate. In contrast, BN-TOP-1, Rev.~1 calculates a regression line for the measured leak late, which is function of the change in dry air mass. For the ANS/ ANSI calculations one would expect to-always see a negative slope for the regression line, because the dry air mass is decreasing over time due to leakage from the containment. _For the regression line computed in the BN-TOP-1, Rev. I method the ideal slope is zero, since you presume that the leakage from the containment is constant over time.
Since it is impossible to instantaneously and perfectly measure the containment leakage, the slope of the regression line will be positive or negative depending on the scatter in the measured leak rate values obtained early in the test.
Since the measured leak rate is a total time calculation, the values computed early in the test will scatter much more than the values computed after a few hours of testing.
The computer printouts titled " Leak Rate Based on Total Time Calculations" attached to the BN-TOP-1, Rev. I topical report are misleading in that the column titled " Calculated Leak Rate" actually has printed out the regression line values (based on all the measured leak rate data computed from the data sets received up until the last time listed on the printout). The calculated leak rate as a function of time (t y ) can only be calculated from data,available up until that point in time, t.. This is significant in that the calculated leak rate may be decreasing over time, despite a substantial positive slope in-the last computed regression line. Extrapolation of the regression line is not required by the BN-TOP-1, Rev. I criteria to terminate a short duration test. What is required is that'the calculated leak rate be decreasing over time or that an increasing calculated leak rate be extrapolated to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
The distinction between the regression line values and the calculated leak rate as a function of- time is made in Section 6.4 of BN-TOP-1, Rev. 1.
Calculated leak rates, as a function of time,' are correctly printed out in the
" Trends Based on Total Time Calculations" computer printouts in Appendix B of BN-TOP-1, Rev. 1.
. - . . .- . . . . - . - . ._-. . ._. ~~_
i
! Associated with each calculated leak rate is a statistically derived upper confidence limit. Just as the calculated leak rate in BN-TOP-1, Rev.-1 and the statistically averaged leak rate in the ANS/ ANSI standard -are not the same (and do not evenl yield nearly equal values), the upper confidence limit calcula-tions are greatly different. In the BN-TOP-1, Rev. I topical report the upper confidence limit is defined as the calculated leak rate plus the product of the two sided 97.5% T-distribution value (as opposed to the one-sided 95%- '
T-distribution used in the ANS/ ANSI standard) and the standard deviation of' the measured leak rate data about the computed regression line (which has no relationship to the value computed in the ANS/ ANSI standard).
There are two important conclusions that can be derived from data analyzed using the BN-TOP-1, Rev. I method: ~1) the upper coafidence limit for the same measured leak rate data can be substantially greater than the value calculated 4 using the ANS/ ANSI method, and 2)the upper confidence limit does not converge to the calculated leak rate nearly as quickly as usually observed in the latter method as the number of data sets becomes large. With this in mind, the upper confidence limit can become the critical parameter for concluding a i short duration test, even when the measured leak rate seems to be well under the maximum allowable leak rate. A graphical comparison of the two methods can be made by referring to Figure 3 for the BN-TOP-1, Rev. 1 calculated leak rate and upper confidence limit and to Figure 13 for the statistically averaged .
leak rate and upper confidence limit based on ANS/ ANSI 56.8-1981.
B.2 Supplemental Verification Test The supplemental verification test superimposes a known-leak of approximately the same magnitude as LA (8.16 SCFM or 1 wt %/ day as defined in the Technical j
Specifications). The degree of detectability of the combined leak rate (contain-ment calculated leak rate plus the superimposed, induced leak rate) provides a basis for resolving any uncertainty associated with the measured leak rate phase of the test. The allowed error band is i 25% of L
- A There are no references to the use of upper confidence limits to evaluate l
, the acceptablility of the induced leakage phase of the IPCLRT in the ANS/ ANSI standards or in BN-TOP-1, Rev. 1.
l L B.3 Instrument Error Analysis l
An instrument error analysis was performed prior to the test in accordance with BN-TOP-1,'Rev. 1 Section 4.5. The instrument system error was calculated in two parts. The first was to determine the system accuracy uncertainty.
The second and more important calculation (since the leak rate is impacted-most by changes in the containment parameters) was performed to determine the j system repeatability uncertainty. The results were 0.0890 wt %/ day and t
0.0175 wt %/ day for a 12-hour test, respectively. -These values are inversely proportional to the test duration.
After pressurizing the containment and at various stages of the test two i
RTD's and one dewcell failed giving unreasonable indications. The two RTD's j were deleted from the subvolume average temperature calculations from the point where they deviated from their past pattern and the values indicated by.
other RTD's in the same subvolume. The deweell, though somewhat erratic in its output, was included in the measured leak rate phase until it failed completely 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> into the test.
Removing the three instruments that failed during the test gives a system accuracy uncertainty of .0911 wt %/ day and a system repeatability uncertainty of .0184 wt %/ day for a 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> test.
The instrumentation uncertainty is used only to illustrate the system's ability to measure the required rarameters to calculate the primary containment leak rate. The mathematical derivation of the above volues can be found in Appendix D. The instrumentation uncertainty is always present in the data and is incorporated in the 95% upper confidence limit.
It is extremely important during a short duration test to quickly identify a failed sensor and in real time back the spurious data out of the calculated '
volume weighted containment temperature and vapor pressure. Failure to do so can cause the upper confidence limit value to place a short duration test in jeopardy.
i l
t t
SECTION C - SEQUENCE OF EVENTS C.1 Test Preparation Chronology The. pretest preparation phase and containment inspection was completed on December 16, 1982 with no apparent structural deterioration being observed.
Major preliminary steps included:
- 1) Completion of all Type B and C tests, component repairs, and retests except for the main steam line drain valve MO 1-220-1. The IPCLRT was conducted, with Commission approval, with this valve closed. The HO 1-220-2 valve, in line with the above valve, minimized leakage-through this flow path during the IPCLRT.
- 2) Blocking open three pairs of drywell to suppression chamber vacuum breakers.
- 3) Installation of all IPCLRT test equipment in the suppression chamber.
- 4) Completion of all <--s4rs and installations in the drywell.
- 5) Venting of the is . vessel to the drywell by opening the manual head vent line t o the drywell equipment drain sump.
- 6) Completion of the.IPCLRT data acquisition system including computer programs , instrument console, locating instruments .:ba the drywell, and associated wiring.
- 7) Re-established water level in the suppression chamber following a seismic piping change to the level instrument sensing lines.
- 8) Completion of the pre-test valve line-up.
C.2 Test Pressurization and Stabilization Chronology DATE TIME EVENT 12-16-82 0315 Began pressurizing containment.
0400 Compressor tripped due to nitrogen leak-on auxiliary
- j. oil pump' emergency air supply.
0430 Compressor back on-line.
0450 Failed RTD 18. Reading 20 F different'than the-
, other three RTD's in the same subvolume. Removed
- it from scan.
0545 Found two leaks on recently installed suppression pool level instrument lines. Flange bolts only finger tight. Each leak estimated at 150 scfh at containment pressure of 40 PSIA. Repairs completed.
l L
\ _ ._-
DATE TIME EVENT 0545 Minor leaks on oxygen analyzer rack isolation valves.
Packing leaks estimated at total of 2 scfh. Tightened pat .ing.
0700 Minor valve packing leak on A0 1-8804 (Drywell Air, Sample Return) estimated at 1.2 scfh. Tightened packing.
0830 Containment is pressurized to 65 PSIA.
0900 Inspected drywell head flange using soap bubble solution. No leaks.
1008 dinor leaks observed in 7IP room. Packing leaks on isolation valves. Total approximate 4 scfh.
Reduced to minute value after tightening packings.
1045 A0 1-8801C had small packing leaks (48 scfh).
Repaired.
1130 Torus water temperature is 58 F. Containment will probably be cooling off during the test due to the above. Containment temperature dropping at 0.33 F/hr.
1330 Containment temperature dropping in the last hour at a rate of 0.55 F/hr.
C.3 Measured Leak Rate Phase Chronology DATE TIME EVENT 12-16-82 1330 Containment temperature stable to misch less than 1*F/hr.
1 1342 Started Measured Leak Rate Phase with RTD 18 removed from the instrument scan.
1805 Observed erratic readings from Dew Cell #1. Dew point temperature changed 22*F in 10 minutes. On the next scan it went back to an intermediate value.
Instrument continued to act erratic, but was not removed from thc scan.
12-17-82 0112 Dew Cell #1 for subvolumes 1 and 2 failed. Computer rejected input automatically for giving an unreason-
! able output. Program assigns partial _ pressure of water vapor from the-nearest.deweell to subvolumes I and 2. Measured leak rate dropped 0.065 wt %/ day.
and stayed steady when Dev Cell #1 was removed from the scan.
i
. .~ . _ _ _
DATE TIME EVENT j 0142 Terminated measured leak rate phase at 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> point. Calculated leak rate was 0.4532 wt %/ day and decreasing over time. The average measured leak rate over the last 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> was 0.3768 wt %/ day.
The upper confidence limit was 0.660 wt %/ day. All other BN-TOP-1, Rev. I criteria for_ terminating the-test cere satisfied.
C.4 Induced Leakage Phase ChronoloaY 12-17-82 0155 Valved in the flowmeter at 8 SCFM (95% scale reading).
Radiation Protection is collecting a sample.
0223 Radiation Protection Department completed sample analysis.
0302 One hour stabilization is complete. Re-initialized program for new base data set.
0325 Failed RTD #23. Changed output by approximately 25*F in one data set. Unreasonable temperature compared to all other temperatures in the drywell.
Three other RTD's in that subvolume. Re-initialized i
base data set with RTD #23 removed from scan.
0332 Scan completed for base data set for the Induced Phase.
0412 Dewcell~#1 reappeared in the scan. Failed Dewcell
- 1 because its sudden reappearance.in the scan shows erratic unreliable output. Will remove the sensor data manually from computer for the three ,
data sets it re-appeared.
0435 Process computer down. No scans.
0515 Computer back up. Beginning scan without Dewcell #1.
0911 Data set lost due to inadvertant manual deletion in program.
0937 Terminated the Induced Phase. Data indicated successful test.
C.5 Depressurization Phase Chronology DATE TIME EVENT 12-17-82 0950 Began containment depressurization as required by procedures for venting through the Reactor Building Ventilation System.
4
DATE TIME EVENT 12-17-82 1800 Containment depressurized.
1830 Technical Staff personnel entered drywell. No apparent structural damage and instruments are still in place.
2030 Made initial entry to r2ppression chamber. No apparent damage and all instruments still in place.
2350 Checked sump levels in Drywell. No change from before the test. Sumps were not pumped during the test.
SECTION D - TYPE A TEST DATA D.1 Measured Leak Rate Phase Data A summary of the computed data using the BN-TOP-1, Rev. I test method for a short duration test can be found in Table 3. Graphic results of the test are found in Figures 3-7. For comparison purposes only, the statistically averaged leak rate and upper confidence limit using the ANS/ ANSI 56.8-1981 standard are graphed in Figure 13. A summary of the computed data using the ANS/ ANSI standard is found in Appendix F.
D.2 Induced Leakage Phase Data A summary of the computed data for the Induced Leakage Phase of the IPCLRT is found in Table 4. The calculated leak rate and upper confidence limit using the BN-TOP-1, Rev. I method are shown in Figure 8. The measured leak rate and last computed regression line are shown in Figure 9. Containment conditions during the Induced Leakage Phase are presented graphically in Figures 10-12.
MEASURED LEAR RATE TEST Rt"SULTS 8 71*C 7C** PPf5SWRC LCAK RA7C CALC LCAM RA7C 951 C04F10C90t 28 13 71 83 88 63 983 0.0000D+00 0.00000+00 0.000D+00 0 0000+00 93 84 63 975 a.65760-01 0 0000D+00 0.0000+00 0.000D+00 29 13 89 0.000D+00 0.000D+00 30 14.05 83 82 63.973 .11760+00 0.00000+00
.e::;^ ;; .;;;;;- . .;7;;::. .;;;;;;; -
^; ; .2i ;; ;;.te; 83.76 63 966 .64340-01 .69270-01 .145D+01 0.131D+01 32 14 38 .120D+01 0.122D+01 33 14.55 83.73 63.959 0.5192D-01 0 575S3-02 7 ;; : '. ; :.;;;;;;;
- .?; ;;.";; ;.";;;;-;; 0.;;;;;-;.
-S+-te.^. 0.7020+00 35 14.PP 93 69 63.950 0 170$D+00 0 13290+00 .4363+00 36 15 05 83.67 63 947 0.15560+00 0 1682D+00 . 2390+00 0.575D+00
- .;" ;;.
- . 0.;;;;;;;; .;;7;;
- :: .00^; :. 0.";;;:;;
-ft-t".e. 0 500D+00 38 15 35 83.61 63.938 0 1661D+00 0 2203D+00 .594D-01 93.59 63 930 0 2563D+00 0.25720+00 0.317D-01 0 4830+00 39 15 55 ^.;- ;^;;; 0.;;;;;:;; ;.;;;;:00 0. ;-: 00
- it.-- ;,. ; ;;. ;-
83 56 0 2924D+00 0.32290+00 0.1SSD+00 0 4863+00 41 15 88 63:922 0.2030+0C 0 4960+00 42 16 05 83.54 63 916 0.3222D+00 0 34960+00 0.;;;;::
-; ;e.;i ; ; .",; el. ;^ ;.;;;;;;;; .00000:00 0.0070:00 83 51 63 905 0 38180+00 0.41280+00 0 293D+00 0.532D+00 44 16 39 0.325D+00 0 550D+00 45 16.SS 83 49 63.900 0 40180+00 0.4374D+00
- . ^^ ; . ;^ ; 7^
- 0 9--0. ,
- ;;;; ;; .0;;0:00 0.^7;;:00
-+t-tt.7; ;;.07
- 7 16 89 83 46 63 898 0.32093+00 0 4463D+00 0.295D+00 0 597D+00 63 897 0.3121D+00 0.44490+00 0 2780+00 0.612D+00 48 17 05 63.4%
^.;;";;-;^ ^ ';;-;; ;.;7^;;;; .;;;;: ;
e; ;7 21 ;;.;- ;;.;;; .--
SO 17 38 83.42 63.890 0.3132D+00 0.4451D+00 0 264D+00 0 6260+00 51 17 55 63.39 63.887 0 29800+00 0.4403D+00 0.2500+00 0 631D+00
- 17. ; ^;.;^ ;.;;; ;.*;;;;;;; .;;;;;-;; :.;;;0:00 0.;;;;: ;
83.37 63 862 0.47280+00 0.4620D+00 0.277D*00 0.6470+00 53 17 88 0 289b.00 0 651D+00 S4 18 05 83.38 63 868 0.4001D*00 0.4700D+00
^;.;7 e^.ee; ^.;;;^;-^^ ;.;7e;; 0^ 0.;;7^ ; ^ 0.;;;;-;;
- - ;o.2.
56 18 38 83.36 63 462 0+4784D+00 0.4835D+00 0 305D+00 0 6623+00 83.34 63.857 0.40963+00 0.48930+00 0.313D+00 0 6660+00 57 18.SS ;.;;;;;;;^ 0.^447;-;; .;;;^:;; .07;; ^;
-SG-iG. i ^;.^e e;.e--
59 18 88 93.32 63.853 0.38780+0C 0.49610+00 0.3193+00 'O.673D+00 to 19 01 93.30 63.849 0.39170+00 0 49760+00 0.3190+00 0 676D+00 o;. ; e .oes ;.4;;;^-^- ^.";;;^ ; ;.;;^;;;^ ;. 770-;"
-ti 17.2i 62 19.38 83.29 63.843 0.3955D+00 0.5012D+00 0.321D+00 0.681D+00 63 19.55 83.27 63.839 0 3972D+00 0.5023D+00 0 321D+00 0 683D+00
- .;;;^;;^; ^.-^;e -^; ;.;;;;-;^ ".e;;; ^;
-St-t'.71 ^;.27 e Ttt-65 19.89 83 24 63.827 0 42590+00 0.50693+00 0 3263+00 0 6883+00 66 20.05 83 24 63.829 0.40390+00 0.50770+00 0 3260+00 0 690D+00
- .o;e ;.4;;e -;- ;. ;;;; ;- ;.;;^; ^; ^ .;;;; ^;
-e7 2^.2i ^ .24 68 20.38 83.22 63.823 0 3986D+00 0.50790+00 0 324D+00 0 692D+00 69 20.55 83 22 63.820 0.40070+00 0.50790+00 0.323D+00 0.6930+00 ssa;i7 .;t-^^ ^; ;.0076^-;; ;.;;;^ ^^ ^. 7 ; ; ; ; t--
M ;trPt---ttuta 71 2*.88 93.18 63.813 0.397?D+00 0.50730+00 0.320D+00 0.694D+00 72 21 05 83 17 63.810 0 39493+00 0.5064D+00 0.3100+00 0 6950 00 .
^.;;ee^:^^ .--,--;; ;.;;7^ ^^ 0.;",";:^;
7; 21 21 ;;.ie e3.^^e 63.804 0.38750+00 0.5044D+00 0.314D+00 0.695D+00 74 21.38 83 14 75 21.55 83.14 63.801 0 38973+00 0.5031D+00 0.312D+00 0.6950+00
.07;;^ ^; ^ .";2^; -- ^.;;;;-;; 0.^7^;;;;
-te-ftr71 ;;.^ ; e;.7^;
77 21.88 83 12 63.796 0 38670+00 0.S0090+00 0 3083+00 0 694D+00
?S 22 05 R3.12 63.792 0 3953D+00 0.5000D+00 0 307D+00 0 693D+00 e;.7e; . ee ; - ^.;^;- ;; ^.;^;^-^; ^ . ;;;; ^
77 22.21 63.ie 80 22.38 83 10 63.786 0 3933D+00 0.4975D+00 0 303D+00 0 692D+00 81 22 25 13 08 63.782 0.39180+00 0.4964D+00 0.301D+00 0.691D+00 ^
-*2 22.71 23.;; e3.7ea ^. ;;;;;^^ ^.e- ;;-; ^. ;;;-;^ 0.e7; 83 22.88 83.06 63.777 0 3900D*00 0.49413+00 0 2990+00 0 690D+00 84 23.05 83 06 63.774 0 3883D+00 0 49280+00 0 2973+00 0 6893+00 ^^
^. ;;;;-;- .e^;;; ;; ;-^ -;^ ^.0^^;
is 23.21 e;.a; a;.77^
93.03 63.770 0 3802D+00 0 4894D+00 0 2920+00 0.6860+00 86 23.3e a7 23.5S 83.04 63.767 0 3871D+00 0.4881D+00 0 291D+00 0 6850*00 43.02 63.765 0.3764D+00 0.4861D+00 0 2890+00 0.684D+00 88 23.71 ll 9 679+64--4,6&&O+44-
--6 4 - 9 3. * *-45 4 7- H,7 69 4,44876+44 0. 0050^88 80 24.0% 83.02 63.760 0.3811D+00 0 48290*00 0+2850+00 0 6R10+00 91 24.21 83.00 63.758 0.3754D+00 0 4811D+00 0.283D*00 0 6790+00 4P 7 + e P A- - 4 3.98--6 5.7 65 --~4.8 7 7 30+8 8 - 4 4 7 940+ 0 8 - --082790+00 2810+0 8 00.6760+00*
6780+88-93 24 55 R2.98 A',751 0.37900+00 0 47790+00 R2.94 ^3.750 0.3754D+00 0.4762D+00 0.278D*00 0 675D+00 94 24.71 0.07;;^00 0.07:0^00
~46-tr.H ~sto: a.'t; O eM4%b+64--0S; 2 0 D 0 0 96 25.05 92.96 63.742 0 37?60+00 0.4 73SD+0 0 0 2750*00 0 672D+00 97 25.21 92 95 6? 760 0.31090+00 6.46830+00 0 2670+00 0 6690+00
-9 9 P S. ? p - - a p r s+ ___5 3. y ge _-_ . - 8. 3 8 6 7 D + 0 8 8 46589+80 0 4689+88 --4 664B+49 - -
99 25.55 42.*3 63.757 0 3051D+00 0 4580D+00 0.2530*00 0.6630+00 100 25.71 82.93 63 755 0.30600+00 0.4532D+00 0 2460+00 0 *6600+00 ME 44-tfe*4 43(-M-keH-44-#e l se 7 9 s 4,56 7 8 &+ 44 TABLE 3 lilDCCED LEAKAGE PilASE TEST RESULTS s TIME TEMP PRESSURE LEAK RATE CALC LEAK RATE 953 CONFIDENCE O 3 55 82.79 63.684 0.00000+00 0.00000+00 0.000D+00 0.0000+00 1 3 71 82 78 63 679 0.7598D+00 0.00000*00 0.0000+00 0.0000+00 2 3.88 82 77 63.671 0.10730+01 0.0000D+00 0.000D+00 0 0003+00 + s e'.r--St e-f f--6Sve0 ", ts;0000;0; Ort 5969++; 0.02 0:00 O rt 699++t-4 4 01 82.75 63.657 0 12010*01 0 1312D+01 0.5770+00 0.2050+01 5 4 38 92.75 63.650 0 12690+01 0.1348D+01 0.8070+00 0 1890+01 M -+s SS--e ttf", 6Ss64; e rt 5 7 te+t t-+ 1+ 1* B+4; 0.00:0:00 O rte +9+41-F 5 33 82.75 63.610 0 14130+01 0.15290+01 0.1010+01 0.205D*01 8 5.50 82 77 63.603 0 1462D+01 0 1523D*01 0 1090+01 0 1950*01 0 SveT G2.7; et:000 0.t2000:0; O rt%; 0 : 0 ; 0.;000:0; 0.;000:01 10 5.83 82 70 63.592 0 12910+01 0 1430D+01 0.101D+01 0 185D+01 11 6 00 82.71 63.584 0 1331D+01 0.14220+01 0.103D+01 0.1820+01
-i t-e s t-7--9e rf 9--*Su tF 0 0 . ; ",169+f t -6 e 4+10 0 : 0 ; 0.1000:01 0.;700:01 13 6.33 82 68 63.571 0 13040+01 0 14050+01 0.1040+01 0 177D+01 14 6 50 82.69 63 564 0 13290+01 0.14030+01 0.1060+01 0 1750+01
-10 6 67 02.00 0 0 . '," O 0,13t+9+4t-411 ",0 00 : 01 0.1070:01 0 ,14 49+4 t -
16 6.83 82.67 63.552 0 1298D+01 0.1392D+01 0 1070+01 0 1720*01 17 7 00 82.67 63.544 0 13300+01 0.1392D+01 0 108D+01 0.1700+01
-te-fa t 7--ets 00 ',0 0*0 0 -5969++t---ee13669; O 1 0 e 1469+41--evM99+41-19 7.33 92.65 63.532 0 12960+01 0.1383D+01 0 1090+01 0.1680+01 20 7 50 82.66 63.525 0 13140+01 0.13810+01 0 1090+01 0 167D+01 P s 6f--et s t ; 00.020 0.12 0 00 ; ; t-43 07 0;;; 0.;000:0; 0.1669+4t-22 7 83 82.63 63.514 0 12780+01 0 13680+01 0 109D+01 0 1650+01 23 8 00 82.63 63 506 0 12920+01 0.1363D+01 0.1090+01 0.164D+01
-t W e t-7--8 e e 6 2 e0.062 0.t e669++t-e n 15569+4; O . ;999+61--91M59+41-25 8 33 82.62 63.495 0 1282D+01 0.13520+01 0.1090+01 0.1620+01 26 8.50 82.62 63.489 0 1281b+01 0.13480+01 0 109D+01 0.1610+01
-t f-Be4 7WP36tWh+e2 0. ; 2 2,00 :ti-6 r ti+00 : 01 0.1000:01 0. ; 00 0 : 0 t-28 8.83 82.60 63.477 0 12700+01 0.13403+01 0 1090+01 0.1590+01 29 9.00 82.60 63 471 0 12650+01 0 13350+01 0 1090*01 0.1580+01
-5 0-* r5 5--et v$9--6-5v4 5 ^ -ertt690+61-o r! 5 5 te+8 ; O rt e99++t-trtS89+61---
31 9 50 82.59 63 453 0.1260D+01 0.13260+01 0 1080+01 0.1570+01 MEAN LEAK RATE OF LAST 20 POINTS:0.1292D+01 TADLE 4 0
0
'2 6
~ '
N 0
0
'l1 O
G A
'l 9
0
'9 D E
E E T C T A N A L E R D 2 UT FI A
K 7 Cl t N
E Lt O L
'b Ai C CL R D E E T
FE P
A 0C P 0 ll U L U 0 l i E C PD
% L '7 A S AI 5 C RF 9 R GN U O O
4 GH
- C _
0 ER
~ - dN SE .
0I ED 0T TN
\ ' , AA
' R .
ER 0 L
_ 0 K .
'4 DA .
EE .
RL l U S
ra A
E 1
O. 1 3
5 k
7, O 9 0
s '2
, 0 0
'6 O
9 0
' O a ' *.v ,g>
5 '< N (> ',
j..4
'. . ~ . ~ :*.e s c. u. ;.
1 1 7 OCWr w
$NNI s,
- h
CONTAINMENi MtALURED l. F Ak RATF O
J
"~ 0.75 sg C.
n h- W O n-O C
-o ,;
to n- r
" e @
a !;
U LJ O l 1*
Or ~~<
H e U . gj -
-i z sn <
~
$h Lt] n
- it 5 u
e L O~ W OF bW
~7 <0
- .' d<
- E 14 W g% <>
O W<
-a H O O OW 2 W >=
MI m
L 30 m-
- j O
<W W3 E
.n
'i!
w
[]
<r- o o
LY '4 LtJ
> o
<C 9 O
4*
09 zf i i s i i i
- :s 00- - 'E t, a ts ar t- : -t- --t9 09 c9 3 s 3 3 ! I 'id O I Y c 3 c! 4 31 FIGURE 7
C ALCUL ATED l.E AK RATE
't INDUCED PHASE a
e i>
i 95 % UPPER
[ CONFIDENCE
?E
?~ i s.ses N co 7
, gCALCULATED LEAK R ATE n
__- 1.183 ,
8 2
k.cc o'. so i.co l '. so i.co i. :o 3'. 0c 3'. o 4'. c c 4'.50
.03 'l so s'. c a TIME IN HOURS lilDUCED LEAKAGE PHASE - GRAPil 0F CALCULATED LEAK RATE AND UPPER C0liFIDEllCE LittlT i l
4l
CONIAlNMENT MEASURED l_ E AK RATE INDUCED PHASE
,.683
- S
> . L'
-* REGRE S Slops LIN E
, h~' MEASURED LEAK RATE}
, E hs
@ 5 m
3", b.v - '
i f .. , , 3 e f~
.r x
yn w --
a i
d-o
?
b.co o'.to l'.00 6'.50 2'.00 2'.50 3'.00 3'.50 4'. cc <.so L'. co '/. so 5.'. 0 0 i l f1E IN HOURS IllDUCED LEAKAGE PHASE - GRAPH OF TOTAL TIME MEASURED LEAK RATE AllD REGRESS 10ll Lli!E
AVERAGE CONTAlNMENT TFMPERATURE
': INDUCED PHASE 19 s N La ;?
$- d
' a h' $ Ei m
ua (L
- O 5?
h.
b't W N X
!'A ' \
'S .,
4.
6 .
.00 0'.50 l'.00 l'.50 I. 0'., I. to 3'.00 3'. *;0 t'. 0 0 4'.50 '[ C0 ,'.,
0 6' 00 T Ifi!: 1N H041RS lilDUCED LEAKAGE PHASE - GRAPil 0F VOLUtiE WElGHTED AVERAGE C0:lTAltlMENT TEtiPERATURE
AVERAGE CONTAINMENT VAPOR PRESSURE
- $ INDUCED PHASE S
'u e~
'o
'A
~ d~
rn
~~~
~h V \ l
= \/ \
us,4 i,;-
'2
,i -
L*
00 0'.50 l'.00 l'.50 2'09 2'.50 3'.00 3'. '20 4 '. 0') 4'.50 '/. 00 '/. LC i.00 '
TIME IN HOURS lilDUCED LEAKAGE PHASE - GRAPH OF VOLUt1E WEIGHTED AVERAGE C0;1TAl'IMEllT VAPOR PRESSURE
AVERAbF i fjN T AI NME N T D h t' AIR PREt,SURE
[ INDUMD Pli AbF 4
4 W
- ', L La..
y ..-
g - G o a
- u. c- u.
3 ;x) v).
m u-
'T _
- as N
M 4
n_
d' 3'. ,o "b.oc c'. to i . c", i.50 f.v, f. t o 5'. c', 4'.00 4'. sc _'. e a . 50 2.ca T I M! IN HOURS INDUCED LEAKAGE Pl!ASE - GRAPH OF DRY AIR PRESSURE
SECTION E - TEST CALCULATIONS Calculaticns for the IPCLRT using the BN-TCP-1, Rev. I test method are found in Quad-Cities procedures QTS 150-T3 and T9. A reproduction of these procedures can be found in Appendix C. In the course of preparing for the IPCLRT a number of errors were identified in the published version of BN-TOP-1, Rev. 1. These errors were editorial in nature and no attempt was made by Station personnel to deviate from the intended procedure outlined in the BN-TOP-1, Rev. I topical report. These errors are identified in Appendix E.
A block diagram of the computer program to perform the calculations based on the BN-TOP-1, Rev. I test method can be found in Appendix G.
4 1
1 4
-32 '
SECTION F - TYPE A TEST RESULTS F.1 Measured Leak Rate Test Results Based upon the data obtained during the short duration test, the following results were determined: (LA = 1.0 wt %/ day)
- 1) Calculated leak rate at 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> equals 0.453 wt %/ day and declining steadily over time (<0.750 wt %/ day).
- 2) Upper confidence limit equals 0.660 wt %/ day and declining
(<0.750 wt %/ day).
- 3) Mean of the measured leak rates for the last 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> (30 data sets) a equals 0.377 wt %/ day (<0.750 wt %/ day).
- 4) Data sets were accumulated st approximately 10 minute time intervals and no intervals exceeded I hour.
- 5) There were 73 data sets accumulated in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
- 6) The minimum test duration of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> was successfully accomplished
(> 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />).
F.2 Induced Leakage Test Results A leak rate of 8.0 scfm (0.980 wt %/ day) was induced on the primary containment for this phase of the test. The leak rates during this phase of the test were ds follows.
Total Time Calculated Leak Rate 0.453 0.453 (Measured Leak Rnte Phase)
Induced Leak (8.0 scfm) 0.980 0.980 Allowed Feror Band + 0.250 -
0.250 1.683 1.183 Total Time Calculated Leak Rate 1.326 wt %/ day (Induced Leak Rate Phase) s
l 4
l F.3 Leak Rate Compenaation For Non-Vented Penetrations The IPCLRT was performed with the following penetrations not drained and a vented as required by 10 CFR 50, Appendix J. The "as left" leak rates for
- each of these penetrations, as determined by Type C testing, is also listed
PENETRATION FUNCTION SCFH VT %/ DAY .
. X-9A "A" Feedwater Line 2.22 0.0045 4
X-9B "B" Feedwater Line 23.9 0.0488 X-12 RHR Supply- 7.79 0.0159 X-14 Rx Water Clean-Up Supply 0.9 0.0018 X-41 Prir.ary System Sample 0.0 0.0
, TOTAL 34.81 0.0711 This yields the following adjusted leak rates:
I Calculated Leak Rate (BN-TOP-1, Rev. 1). .524 wt %/ day Upper Confidence Limit (BN-TOP-1, Rev. 1) .731 wt %/ day i
For the purposes of comparison, using the ANS/ ANSI method the following are the adjusted leak rates:
Statistically Averaged' Leak Rate .376 wt %/ day Upper Confidence Limit (ANS/ ANSI 56.8) .465 wt %/ day _
- It is understood that the leak rates associated with the ANS/ ANSI calculations can only be reported if a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> test is performed.
F.4 Pre-Operational Results vs. Test Results Past IPCLRT reports have compared t e results of those tests with the pre-operational IPCLRT, performed April 20-21, 1971. The last IPCLRT on Unit One conducted February 19-22, 1979 yielded a statistically averaged leak rate (ANS/ ANSI method) of 0.3175 wt %/ day after' correcting for non-tested penetrations.
I The present test, if the same method of data analysis were used, except for the test duration, gave a leak rate of 0.376 wt %/ day. The difference between the results are within each tests uncertainty limits.
The reported leak rate using the BN-TOP-1 Rev. I method of calculating a leak rate for a short duration test will show a significant increase over past
, IPCLRT results. The increase is due almost entirely to the difference in method of computation, rather than an increase in containment leakage.
f i
- . - - - _ _ - ~ _ . _ , , _ _ , . _ ._._, __ .-.
3 4
CALCULATED LEAR RATE (MASS PLOT METHOD)
, .}; '
c ,
1s . ._ __._ _
- /.x
,x4
. . L . .
h
-m i
g gg
( .
g .
.p~/_.-
% y .. .. ._ ..
, pggg. .._..
---~
)-
N
<4
_y.
,---~%
,{;-- M..., ,
s
. ~ ..._ _..
?. _.
f ..
[,N m " i u a d.m. ua m !
i
-- . ~
-+-. ,, N
\_.
U 2
[.
. ... :4 g, . 4 js 4 4 15
, .-._- . . . .5 .- . ._ .. .. .,. ._
r
-. . . , . -. f.w. ..p.c ,. 8 e- k.
- 4 I
-l 6I d Y.
W ,.
.) 6 .., s... . .d-. l .., i...
' .w 4 '. -
. . . 1 a .
'l . u .,
g -{.~ ,,. . .
.i
.}
. . .J. .
....g : . . y , .. -
, / .. / __ ,._ : .. .
3
. . .a y _ ._ ._.
3 L L ' . . - .. .., . .
j
- .. . . . .a . ..a. . _
u ..
r a.s..; . , , ,
t W
._.e.._ _..
j
. - J. .. .
,{ . L h j .. > j , e ' . ..bd
, w .. , I.h ..+. L ., i 3
I. ,.ha4 . , ,
..L i i
. s m .
i..,..
7 l
.. 1... .a 7..
i,
. ,a ..-w... .. ..
s4. . . .
... i. .6 f ..
- y ji .. , 4 4 6 .o .a . . '..
. .'.h. .. .., .4 4 . a I
GP -i $p' +he -. f 6. a
$. $. ki g*- 0+. 1 .. . = =r.- E , 8.. 4- a4 e . $. .=
/ Ir6 .g .p. l.. 6.
- e. 9 .
- p. ... s b. ,a.
p g.,yd.-
9] 44sh.>4 4 gl i.
g 1
}-
- J.
f..
- y. + ,,
p, ., .; 5 .
4 :. l .: ,
,,ig; ... .] >..
.q .. 1 6 P 'd .m. 11.6. g...b 4...jg .$$..d4pm.e e $. $$ =
.. . .. ..- 39 6, b.g sb .se..g. -
4 ie' .
9.e u.. a..1. .'O.j
. . 11., e 4 6 .s 4 !
e i .+ no. p.
f . 2
- q. ._' e, {.p. 6,
.9 9 f.. .
' k- j gi L -
4, e . 1 L,.4 Lap '-
44 4 g.- 4- . .Ie age.p.. 9 q .44 j 6 4 i.d.. E 4 l .
9
..b .
.e 0- 4 4 d.D . .. 6 .p64 4 . 0 .* i p ey g .
r ..g i ,, n$. . .. ..
9i
+ .
1 ,e 9 e. ig- gg .e-p... .ee i. ...e..mghe.. . ;
+
.gi ned .5- ., 4- p). . .
- 1
- 9. . ..+ q. ..
..-, a , .4. _.e ; . ..
- . r. ..' - . p
- 7. , ,
./....: 4 .7 9 [ .ip . :
.w ...> , . . .: - .
- 3. . c q .- . g-Si e a i 4 e a r e o eo o ia Neef IN WOUR$
e FIGURE 13
APPENDIX A TYPE B AND C TESTS Presented herein are the results of local leak rate tests conducted on all penetrations, double-gasketed seals, and isolation valves since the previous IPCLRT in February, 1979. All valves with leakage in excess of the individual valve leakage limit were restored to an acceptable leak tightness prior to the resumption of power operation with the exception of the Main Steam Line Drain Valve, MO 1-220-1. Technical Specification change to T.S. 3.7 A.2.a.2. was approved by the Commission to allow operation withest first repairing this valve. Total leakage for double gasketed seals and total leakage for all other penetrations and isolation valves following repairs satisfied the Technical Specification limits. These results are listed in Table A-1.
1 i
i 1
l i
i e
l i
4 4
TABLE A-1 TYPE B AND C TEST RESULTS VALVE (S) OR MEASURED LEAK RATE (SCFF)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE A0 203-1A Main Steam Line 10.37 09-06-82 10.37 09-06-82 Isolation Valves *** 4.48 09-01-80 4.61 11-05-80 A0 203-2A 10.37 09-06-82 10.37 09-06-82 140.56 09-01-80 4.61 11-05-80 A0 203-1B 19.58 09-06-82 3.46 12-13-82 23.77 09-01-80 5.76 11-20-80 A0 203-2B 19.58 09-06-82 3.46 12-13-82 27.65 09-01-80 5.76 11-20-80 A0 203-1C 43.78 09-06-82 5.76 12-13-82 1.73 09-01-80 1.73 11-26-80 A0 203-2C 43.78 09-06-82 5.76 12-13-82 1.73 09-01-80 1.73 11-26-80 A0 203-1D 8.06 09-06-82 8.06 09-06-82 14.97 09-01-80 0.0 11-26-80 A0 203-2D 8.06 09-06-82 8.06 09-06-82 226.97 09-01-80 0.0 11-26-80 MO 220-1 Main Steam Line Drains UD/5.01 09-06-82 **/5.01 MO 220-2 96.71/5.97 09-01-80 13.05/5.97 11-25-80 A0 220-44 Primary Sample 0.0 09-30-82 0.0 09-30-82 A0 220-45 c.0 :11-24-80 0.0 11-24-80 CV 220-58A Feedwater Inlet UD* 10-08-82 8.06 11-16-82 Loop "A" Inboard. 0.90 09-19-80 0.90 09-19-80 CV 220-62A Feedwater Inlet 194.6 10-08-82 2.22 11-16-82 Loop "A" Outboard UD* 09-19-80 6.66 10-29-80 CV 220-58B Feedvater Inlet UDk 09-08-82 24.64 12-03-82 Loop "B" Inboard 5.39 09-05-80 5.39 09-05-80 CV 220-62B Feedwater Inlet 104.5 09-08-82 23.9 12-08-82 Loop "B" Outboard UD* 09-06-80 17.76 10-14-80
- Unable to determine the leakage due to an inability to pressurize the volume with compressed air.
- Technical Specification change to start-up and run with MO 1-220-1 valve unrepaired.
TABLE A-1 TYPE B AND C TEST RESULTS VALVE (S) OR MEASURED LEAK RATE (SCFH)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE NO 1001-20 RHRS to Radwaste 0.0 12-11-82 0.0 12-11-82 MO 1001-21 '0.0 10-08-80 0.0 10-08-80 MO 1001-23A RHRS Containment Spray - 18.24 10-10-82 18.24 10-10-82 MO 1001-26A System I 4.16 09-30-80 4.16 09-30-80 MO 1001-29A RHRS Return Loop "A" 12.06 10-17-82 12.06 10-17-82 1.51 09-30-80 1.51 09-30-80 NO 1001-34A RHRS Suppres9fon Chamber 60.48 10-24-82 4.54 12-01-82 MO 1001-36A Spray - System I 0.76 09-30-80 0.76 09-30-80 MO 1001-37A MO 1001-23B RHRS Containment Spray - 1.13 10-25-82 1.13 10-25-82 MO 1001-26B System II 0.0 .09-30-80 0.0 09-30-80 MO 1001-29B RHRS Return Loop "8" 0.0- 10-25-82 0.0 10-25-82 6.18 09-30-80 6.18 09-30-80 No 1001-34B RHRS Suppression MO 1001-36B Chamber Spray 4.91 10-24-82 4.91 10-24-82 MO 1001-37B System II 8.42 09-29-80 8.42 09-29-80 MO 1001-47 RHRS Shutdown 15.58 10-04-82 15.58 10-04-82 MO 1001-50 Cooling Suction 0.0 10-01-80 0.0 10-01-80 MO 1001-60 RHRS Head Spray 0.19 10-24-82 0.19 10-24-82 MO 1001-63 0.76 10-01-80 0.76 10-01-80 MO 1201-2 Clean-Up System 14.87 09-30-82 1.80 12-08-82 MO 1201-5 Suction 11.50 10-31-80 11.50 10-31-80 MO 1301-16 RCIC Steam Supply 0.38 09-06-82 0.38 09-06 MO 1301-17 0.48 08-31-80 0.48 08-31-80 l
CV 1301-40 RCIC Condensate Drain 2.50 09-09-82 2.50 09-09-82 1.90 08-31-80 1.90 08-31-80 CV 1301-41 RCIC Turbine Exhaust 1584.0 09-07-82 0.84 12-11-82 1.20 08-31-80 1.20 08-31-80 ,
A0 1601-21 Drywell and Suppression 258.0 09-09-82 0.0 12-04-82 A0 1601-22 Chamber Purge 435.21 09-03-80 2.10 11-18-80 A0 1601-55 A0 1601-56 A0 1601-20A Suppression Chamber 17.58 10-17-82 0.0 10-27-82 CV 1601-31A Vent Lines #1 11.37 09-04-80 11.37. 09-04-80 TABLE A-1 TYPE B AND C TEST RESULTS VALVE (S) OR MEASURED LEAK RATE (SCFH)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE A0 1601-20B Suppression Chamber 0.015 09-09-82 0.015 09-09-82 CV 1601-31B Vent Lines #2 5.02 09-04-80 5.02 09-04-80 A0 1601-57 Drywell and Suppression 1.90 10-20-82 1.90 10-20-82 A0 1601-58 Chamber Supply Air 2.50 09-03-80 2.50 09-03-80 A0 1601-59 Purge A0 1601-23 Drywell and Suppression 9.00 10-17-82 9.00 10-17-82 A0 1601-24 Chamber Exhaust 125.98 09-03-80 18.0 11-02-80 A0 1601-60 A0 1601-61 A0 1603-62 A0 1601 63 A0 2001-3 Drywell Floor Drain 1.10 10-20-82 1.10 10-20-82 A0 2001-4 Sump Discharge 1.30 09-23-80 1.30 09-23-80 A0 2001-15 Drywell Equipment 0.90 10-20-82 0.90 10-20-82 A0 2001-16 Drain Sump Discharge 9.50 09-23-80 9.50 09-23-80 MO 2301-4 HPCI Steam Supply 3.46 09-06-82 3.46 09-06-82 t
M0 2301-5 10.37 08-31-80 10.37 08-31-80 CV 2301-34 HPCI Condensate Drain 0.0 09-09-82 0.0 09-09-82 4.50 08-31-80 4.50 08-31-80 CV 2301-45 HPCI Steam Exhaust UD* 09-07-82 0.80 12-07-82 4.02 08-31-80 4.02 08-31-80 t
A0 4720 Drywell Pneumatic 13.0 09-27-82 13.50 10-22-82 Suction 0.0 09-03-80 0.0 09-03-80 A0 4721 Drywell Pneumatic 14.0 09-27-82 14.0 10-22-82 Suction 0.0 09-03-80 0.0 09-03-80 A0 8801A 0xygen Analyzer Suction 0.0 09-13-82 0.0 09-13-82 1 0.2 09-09-80 0.2 09-09-80 l
A0 8802A 0xygen Analyzer Suction 0.2 09-13-82 0.20 09-13-82 0.6 09-09-80 0.6 09-09-80 A0 8801B 0xygen Analyzer Suction 4.20 09-13-82 4.20 09-13-82 0.2 09-09-80 0.2 09-09-80 (
l A0 8802B 0xygen Analyzer Suction 0.0 09-13-82 0.0 09-13-82 0.3 09-09-80 0.3 09-09-80 TABLE A-1 TYPE B AND C TEST RESULTS ,
VALVE (S) OR MEASURED LEAK RATE (SCFH)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE A0 8801C 0xygen Analyzer Suction 4.20 09-13-82 4.20 09-13-82 0.0 09-09-80 0.0 09-09-80 A0 8802C 0xygen Analyzer Suction 3.90 09-13-82 3.90 09-13-82 0.0 09-09-80 0.0 09-09-80 A0 8801D 0xygen Analyzer Suction 0.20 09-13-82 0.20 09-13-22 0.40 09-09-80 0.40 09-09-80 A0 8802D 0xygen Analyzer Suction 0.20 09-13-82 0.20 09-13-82 1.10 09-09-80 1.10 09-09-80 A0 8803 0xygen Analyzer Return 8.00 09-17-82 8.00 09-17-82 7.50 '09-18-80 7.50 09-18-80 A0 8804 0xygen Analyzer Return 2.70 09-17-82 2.70 09-17-82 1.80 09-18-80 1.80 09-18-80 733-1 Automatic TIP Ball Valve 4.50 09-21-82 0.30 11-23-82 0.0 09-15-80 0.0 09-15-80 733-2 Automatic TIP Ball Valve 0.20 09-21-82 1.70 11-23-82 0.20 09-15-80 0.20 09-15-80 733-3 Automatic TIP Ball Valve 0.0 09-21-82 3.30 11-23-82 0.0 09-15-80 0.0 09-15-80 733-4 Automatic TIP Ball Valve 1.0 09-21-82 7.30 11-23-82 0.0 09-15-80 0.0 09-15-80 733-5 Automatic TIP Ball Valve 0.0 09-21-82 3.10 11-23-82 0.1 09-15-80 0.1 09-15-80 700-743 IJP Purge Check Valve 11.70 09-21-82 5.0 11-23-82 6.0 09-15-80 6.0 09-15-80 SO 2499-1A CAM - Drywell 0.0 09-16-82 0.0 09-16-82 SO 2499-2A 0.0 09-19-80 0.0 09-19-80 SO 2499-3A CAM - Suppression Chamber 0.0 09-16-82 0.0 09-16-82 SO 2499-4A 0.0/2.5 09-19-80 0.0/2.5 09-19-80 SO 2499-1B CAM - Drywell 0.0 09-16-82 0.0 09-16-82 SO 2499-2B 0.6 09-19-80 0.6 09-19-80 SO 2499-3B CAM - Suppression 0.0 09-16-82 0.0 09-16-82 SO 2499-4B Chamber 7.0 09-19-80 7.0 09-19-80 TABLE A-1 TYPE B AND C TEST RESULTS VALVE (S) OR MEASURED LEAK RATE (SCFH)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE FCV 2599-1A ACAD Isolation 2.40 09-15-82 2.40 09-15-82 6.00 09-19-80 6.00 09-19-80 FVC 2499-1B ACAD Isolation 0.0 09-15-82 0.0 09-15-82 6.00 09-19-80 6.00 09-19-80 A0 2599-2A ACAD to Drywell 0.0 09-17-82 0.0 09-17-82 CV 2599-23A 0.0 09-19-80 0.0 09-19-80 A0 2599-3A ACAD to Suppression 0.0 09-16-82 0.0. 09-16-82 CV 2599-24A Chamber 0.0 09-19-80 0.0 09-19-80 A0 2599-2B ACAD to Drywell 0.0/1.2* 09-17-82 0.0/1.2* 09-17-82 CV 2599-23B 0.3 09-19-80 0.3 09-19'80 A0 2599-3B ACAD to Suppression 0.0 09-16-82 0.0 09-16-82 CV 2599-24B Chamber 1.20 09-19-80 1.20 09-19-80 A0 2599-4A ACAD Drywell Bleed to 0.0 09-15-82 0.0 09-15-82 FCV 2599-5A SBGTS 2.5/0.0* 09-19-80 2.5/0.0* 09-19-80 A0 2599-4B ACAD Drywell 2.1/0.0* 09-15-82 2.1/0.0* 09-15-82 FCV 2599-5B Bleed to SBGTS 1.1/1.8* 09-19-80 1.1/1.8* 09-19-80 X-1 Drywell Equipment Hatch 0.0 09-06-82 0.0 12-16-82 0.0 12-17-80 0.0 12-17-80 X-2 Drywell Personnel 0.0 11-26-82 0.0 11-26-82 Airlock 0.0 12-19-80 0.0 12-19-80 X-4 Drywell Head Access 0.0 09-06-82 0.0 09-06-82 Hatch 0.0 09-18-80 0.0 09-18-80 l X-6 CRD Removal Hatch 0.0 09-06-82 0.0 12-16-82 0.0 12-02-80 0.0 12-02-80 X-35A TIP Flux Mon. Flange 0.0 09-20-82 0.0 09-20-82 0.0 09-15-80 0.0 09-15-80 X-35B 0.0 09-20-82 0.0 09-20-82 O.0 09-15-80 0.0 09-15-80
- Valves tested separately. Individual valve leak rates shown.
TABLE A-1 TYPE B AND C TEST RESULTS 2
VALVE (S) OR MEASURED LEAK RATE (SCFH)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE
! X-35C 0.0 09-20-82 0.0 09-20-82 0.0 09-15-80 0.0 09-15-80 X-35D 0.0 09-20-82 0.0 09-20-82 0.0 09-15-80 0.0 15-80 X-35E 0.0 09-20-82 0.0 09-20-82 0.0 09-15-80 0.0 09-15-80 X-35F 0.0 09-20-82 0.0 09-20-82 0.0 09-15-80 0,0 09-15-80 X-35G 0.0 09-20-82 0.0 09-20-82
, 0.0 09-15-80 0.0 09-15-80 X-200A Suppression Chamber 0.0 09-06-82 0.0 12-14-82 Access Hatch 0.0 12-19-80 0.0 12-19-80 1 X-200B 0.0 09-06-82 0.0 12-20-82 O.0 12-19-80 0.0 12-19-80 Drywell Drywell Head UD* 09-06-82 0.0 12-15-82 j Head Flange 0.0 12-17-80 0.0 12-17-80 SL-1 Shear Lug Inspection 0.0 09-21-82 0.0 09-21 Hatches 0.0 09-12-80 0.0 09-12-80 1
SL-2 1.50 09-21-82 1.50 09-21-82 0.0 09-12-80 0.0 09-12-80 SL 0.50 09-21-82 0.50 09-21-82 0.0 09-12-80 0.0 09-12-80 SL-4 0.0 09-21-82 0.0 09-21-82 0.0 09-12-80 0.0 09-12-80 i.
SL-5 0.0 09-21-82 0.0 09-21-82 0.0 09-12-80 0.0 09-12-80 SL-6 0.0 09-21-82 0.0 09-21-82 O.0 09-12-80 0.0 09-12-80 SL-7 0.0 09-21-82 0.0 09-21-82 0.0 09-12-80 0.0 09-12-80
- Unable to determine the leakage, because the flowmeter test rig has a 30 SCFH flow capacity. Leakage exceeded 30 SCFH.
TABLE A-1 TYPE B AND C TEST RESULTS VALVE (S) OR MEASURED LEAK RATE (SCFH)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE SL-8 5.50 09-21-82 5.50 09-21-82 0.0 09-12-80 0.0 09-12-80 X-7A Primary Steam 0.0 09-10-82 0.0 09-10-82 0.0 09-11-80 0.0 09-11-80 X-7B 0.7 09-10-82 0.7 09-10-82 0.9 09-11-80 0.9 09-11-80 X-7C 0.0 09-10-82 0.0 09-10-82 0.0 09-11-80 0.0 09-11-80 X-7D 0.0 09-10-82 0.0 09-10-82 0.0 09-11-80 0.0 09-11-80 X-8 Primary Steam 0.0 09-10-82 0.0 09-10-82 Drain Line 0.0 09-11-80 0.0 09-11-80 X-9A Reactor Feedwater 0.0 09-10-82 0.0 09-10-82 l
0.0 09-11-80 0.0 09-11-80 X-9B 0.0 09-10-82 0.0 09-10-82 0.0 09-11-80 0.0 09-11-80 X-10 Steam to RCIC 0.0. 09-10-82 0.0 09-10-82 0.0- 09-11-80 0.0 09-11-80 X-11 HPCI to Steam Supply 0.0 09-10-82 0.0 09-10-82 0.0 09-11-80 0.0 09-11-80 X-12 RHRS Supply 0.0 09-10-82 0.0 09-10-82 4.3 09-11-80 4.3 09-11-80 X-13A RHRS Reture 0.0 09-10-82 0.0 09-10-82 0.0 09-11-80 0.0 09-11-80 X-13B 0.0 09-10-82 0.0 09-10-82 0.0 09-11-80 0.0 09-11-80 X-14 Cleanup Supply 0.30 09-10-82 0.60 12-10-82 0.0 09-11-80 0.0 09-11-80 X-23 Cooling Water 0.0 09-10-82 0.0 09-10-82 0.5 09-11-80 0.5 09-11-80 X-24 Cooling Water Return 0.0 09-10-82 0.0 09-10-82 0.0 09-11-80 0.0 09-11-80 l
l l
i TABLE A-1 TYPE B AND C TEST RESULTS i VALVEli) OR MEASURED LEAK RATE (SCFH)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE j X-25 Vent From Drywell 0.0 09-10-82 0.0 09-10-82 O.6 09-11-80 0.6 .09-11-80 l
j X-26 Vent to brywell 0.0 09-10-82 0.0 09-10-82 0.3 09-11-80 0.3 09-11-80' i
X-36 CRD Hydraulic- 0.0 09-10-82 0.0 09-10-82 System Return G.05 09-11-80 0.05 09-11-80 j X-47 Standby Liquid 0.0 09-10-82 0.0 09-10-82 Control 0.0 09-11-80 0.0 09-11-80 f X-17 Reactor Vessel 0.0 09-10-82 0.0 09-10-82
& Head Spray 0.0 09-11-80 0.0 09-11-80 l X-16A Core Spray Inlet 0.0 09-10-82 0.0 10-82 j 8.0 09-11-80 8.0 09-11-80 1
l X-16B Core Spray Inlet 5.10 09-10-82 4.7 10-04-82
-0.0. 09-11-80 0.0 09-11-80 ,
X-100A CRD Position 0.0 09-29-82 0.0 09-29-82
- Indication 0.0 09-15-80 0.0 09-15-80 1
X-100B Power ' 0. 0 09-29-82 0.0 09-29-82
- 0.0 09-15-80 0.0 09-15-80 I
X-100C Neutron Monitor 0.0 09-28-82 0.0 09-28-82 0.0 09-11-80 0.0 09-11-80 l X-100D Neutron Monitor 0.0 09-28-82 0.0 09-28-82.
0.0 09-10-80 0.0 09-10-80 X-100E Neutron Monitor 0.0 09-28-82 0.0 09-28-S2 0.0 09-10-80 0.0 G9-10-80' t X-100F CRD Position Indication 0.0 09-29-82 0.0 09-29-82 l 0.0 09-03-80 0.0 09-03-80 i
- X-1000 Power 0.0 09-29-82 0.0 09-29-82 l
t 0.0 09-03-80 0.0 09-03-80 X-101A CRD Position Indication 0.0 09-28-82 0.0 09-28-82
!. 0.0 09-11-80 0.0 11-80 1
!- X-101B CRD Position Indication 0.0 09-28-82 0.0 09-28-82 l 0.0 09-11-80 0.0 09-11-80' I
- - - , , - -,n-. m,--,.---,e---r- 7,n, -,w v--a,,,-.-.- r - . - - - , .,,, , - - . , - - - - - . , , , - -
TABLE A-1 TYPE B AND C TEST RESULTS VALVE (S) OR MEASURED LEAK RATE (SCFH)
PENETRATION TEST VOLUME AS FOUND DATE AS LEFT DATE X-101D Recire Pump Power 0.0 Os-29-82 0.0 09-29-82 0.0 09-03-80 0.0 09-03-80 X-102A Recire Pump Power 0.0- 09-28-82 0.0 09-28-82 0.0 09-11-80 0.0 09-11-80 X-103 Thermocouple 0.0 09-18-82' O.0 09-28-82 0.0 09-11-80 0.0 09-11-80 X-104B CRD Position Indication 0.0 09-29-82 0.0 ~09-29-82 0.0 09-15 0.0 09-15-80 X-104C Recire Pump Power _ '0. 0 09-28-82 0.0 09-28-82 0.0 09-11-80 0.0 09-11-80 X-104F Power 0.0' 09-29-82 0.0 09-29-82 0.0- 09-03-80 0.0 09-03-80.
X-105A Power 0.0 09-29-82 0.0 09-29 0.0 09-15-80 0.0 09-15-80 X-105B Power Drive Modules 0.0 09-28-82 0.0 09-28-82
-0.0 09-10-80 0.0 '09-10-80 X-105C CRD Position Indication 0.0 09-28-82 0.0 09-28 0.0 09-10-80 0.0 09-10-80 X-105D Recire Pump Power 0.0 09-29-82 0. 0_ . 09-29-82 0.0 09-03-80 0.0 09-03-80 X-107A Neutron Monitor 0.0 09-28-82 0.0 09-28-82 1.0 09-10-80 1.0 09-10-80 X-227A ACAD/ CAM 0.0 10-04-82 0.0 10-04-82 0.0 09-18 0.0 09-18-80 X-227B ACAD/ CAM 0.35 10-04-82 0.35 10-04-82 0.0 09-18-80 0.0 09-18-80 APPENDIX B AS FOUND LEAK RATES The as found leak rate for the primary containment isolation valves, excluding the main steam isolation valves and leakages identified during the IPCLRT, was not determined due to excessive leakage in the "A" feedwater line. The total leak rates prior to and after the outage are summarized as follows:
AS FOUND AS LEFT TECHNICAL LEAK RATE LEAK RATE SPECIFICATION ITEM (SCFH) (SCFH) LIMIT (SCFH)
Isolation Valves U.D.* 119.91 293.75 Testable Penetrations 6.45 6.35 Double Gasketed Seals U.D.** 7.50 Main Steam Isolation Valves (tested at 25 psig)
A0 203-1A 10.37 10.37 11.5 A0 203-2A 10.37 10.37 11.5 A0 203-1B 19.58 3.46 11.5 A0 203-2B 19.58 3.46 11.5 A0 203-1C 43.78 5.76 11.5 A0 203-2C 63.78 5.76 11.5 A0 203-1D 8.06 8.06 11.5 A0 203-2D 8.06 8.06 11.5 Total through leakage for MSIV's
@ 25 psig 40.90 13.83 Total adjusted through leakage for MSIV's
@ 48 psig 70.75 23.92 Total through leakage
@ 48 psig U.D. 157.68 Complete-details of these local leak rate test results are contained in LER/RO-82-26/03L.
- The total as found leakage for isolation valves was 2143.76 SCFH plus an unknown value for the "A" feedwater line.
- The total as found leakage for double gasketed seals was 7.5 SCFH plus an unknown value for the drywell head seal.
i Based on the above, the total as found leak rate of the primary containment wan greater than the Technical Specification criteria of I wt%/ day.
If only the leakage' paths tested during the IPCLRT, plus an adjustment for all penetrations not tested during the IPCLRT, are considered, then the containment leak rate is calculated to be 0.524 wt%/ day and falls within the Technical 1 Specification acceptance criteria of 0.750 wt%/ day.
.i l
I I
m APPENDIX C COMPUTATIONAL PROCEDURE
~
QTS 150-T3 Revision 7 CALCULATIONS PERFORMED FOR IPCLRT DATA October 1982 ID/8B Data collected from pressure sensors, dew cells and RTD's located in the containment are processed using the following calculations. If the test is concluded with a test period of < 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, additional calculations given in QTS 150-T9 will be required.
A. Average Subvolume Temperature and Dewpoint.
T I(all RTD's in the jth subvolume) 3= F (1)
Number of RTD's in jth subvolume D.P.d = I(all dew cells in jth subvolume) F (2)
Number of dew cells in j th subvolume where T = average temperature of the j th subvolume D.P.. = average dewpoint of the jth subvolume J
B. Average Primary Containment Temperature and Dewpoint.
T= {0L(VF.)*(T)
J:1 J j F (M D.P. =3:1 {0L(VF)*(D.P..)
j J F (!+ )
where T = average containment temperature iT D.P. = average containment dewpoint VF = volume fraction of the jth subvolume NVOL = number of subvolumes If T) is undefined then T =T pg for 1 1 j $ (NVOL - 2)
T) = Tg for j = NVOL - 1 T) = estimate for j = NVOL % [h[ hfky If D.P.) is undefined D.P.) = D.P.pg for 1 1 j 1 (NVOL - 2)
D.P.) = 0.P.),3 for j = NVOL - 1 D.P.) = estimate for j = NVOL QTS 150-T3 Rsvision 7 C. Calculation of Dry Air Pressure.
D.P.( K) = 273.16 + D.P.( F) - 32 1.8 X = 647.27 - D.P.( K)
EXPON = X (Y + Z
- X + C
- X )
(D.P.("K))*(1 + D
- X) -
P* = (218.167) * (14.696) e(EXPON
- In(10))
P = Z(all absolute pressure gauges) (5)
,p ( , ,)
Number of absolute pressure gauges v where Y = 3.2437814 Z = 5.86826 x'10 -3 C = 1.1702379 x 10 ~0 D = 2.1878462 x 10' Py = volume weighted containment vapor pressure P = containment dry air absolute pressure C, D, X, Y, Z, and EXPON are dewpoint to vapor pressure conversion constants and coefficients. -
D. Containment Dry Air Mass.
W = (28.97) * (144) * (P) * (288737 - 25 * (LEVEL - 35)) (6) 1545.33 * (T + 459.69)
I .
where W = containment dry air mass LEVEL = reactor water level I 289506 = primary containment volume
- l l
l NOTE This volume is the sununation of the subvolumes
- calculated in QTS 150-T2. These subvolumes were calculated using QTS 150-T8. Since the measured leak rate is a difference in air
, masses, this number is just as conservative as using the FSAR number.
y zrmrm w w .
R2 vision 7 E. M2esurod L2nk Rato.
Lm(TOTAL) = (W BASE - W.) 1
- 2400 (7)
%/ DAY i BASE L,(POINT) = (W ,
- W )
- 2400 (
%/ DAY (t -t,)*W g, where W BASE
= c n a naen ry a r mass at t = 0 tg = time from start of test at ith data set t, = time from start of test at (i-1)th data set W = dry air mass at ith data set W ,
= dry air mass at (i-1)th data set L,(TOTAL)= measured leakage from the start of test to ich data set L,(POINT)= measured leakage betwe:n the last two data sets' F. Statistical Leak Rate and Confidence Limit.
LINEAR LEAST SQUARES FITTING THE IPCLRT DATA The method of "Least Squares" is a statistical procedure for finding the best fitting regression line for a set of measured data. The criterion for the best fitting line to a set of data points is that the sum of the squares of the devi&tions of the observed points from the line must be a minimum. When this criterion is met, a unique best fitting line is obtained based on all of the data points in the ILRT. The value af the leak rate based on the regression is called the statistically average leak rate.
Since it is assumed that the leak rate is constant during the testing period, a plot of the measured containment dry air mass versus time would ideally yield a straight line with a negative slope (assuming a non-zero leak rate). Obviously, sampling techniques and test conditions are not perfect and consequently the measured values will deviate from the ideal straight line situation.-
Based on this statistical process, the calculated leak rate is obtained from the equation:
W = At + B where W = contained dry air mass at time t h hk I etna'MID Revisita 7~
B s calculated dry air mass at time t = 0 a = ca'culated leak rate
- 4 est Juration FOR REFERENCE ON.Y 0 y Air rass (lbs) ,,Qo[.
4 I
Test Duration (hrs) ,
The values for the Least Squares fit constants A and B are 3iven by:
A = {N
- 1(tt) * (W g ) - gIt
- IW g } = I(t - t) * (W - 0)
.'N " I(t ) - (It ) } I(tg - t) _ _ . _ .
3 = IW g -A*It g = {I(t t)
- Z(Wg )} - {I(t )g * (W
N N
- Z(t ) - (It g) where E = the average time for all data sets _ _ _ _ _ .
U = the average air mass for all data sets I The second formulas are used in the process computer program to reduce round-off-error. ? l By definition, leakage out of the containment is considered positive leakage; therefore, the statistically average leak rate is given by: d d, = (-A) * (2400) (weight %/ DAY) ( STATISTICAL UNCERTAINTIES In order to calculate the 95% confidence limits of the statistically average leak rate, the standard deviation of the least squares slope and the student's TDistribution function are used as follows. 1 N
- I(Wg ) - (IWg ) 2\
a={ *( (N-2) N
- I(t()2 - (It g )2) - A } .
i When gerforming these calculations on the process computer, I(Wg)2 and (IWg )* become so large that they overflow. To avoid this problem AW. is I substituted for W g. AW g is the difference between Wgand WBASE
- QTS 150-T3 Rsvision 7
- The single sided T-Distribution with 2 degrees of freedom is approximated by the following formula from NBS Handbook 91:
T.E. = 1.646698 + 1.455393 , 1.975971 (N-2) (N-2)' The upper confidence limit (UCL) is given by UCL = sL + c * (TE)
- 2400 (weight *./ DAY) (10)
B-l o e l j FOR REEREiCE DiiLY j i i QTS 150-T9 Revision 1 CALCULATIONS PERFORMED FOR IPCLRT October 1982 ID/80 DATA FOR TEST DURATION LESS THAN 24 HOURS i Data collected from pressure sensors, dew cells, and RTD's located in the containment are processed using the following equations. Some data needs to be analyzed using equations in QTS 150-T3 prior to using these equacions. Those equations are referenced by equation number. The primary reference for these calculations is the Topical Report BN-TOP-1 Revision 1. A. MEASURED LEAK RATE (Total Time) From BN-TOP-1 Rev. 1, Section 4.5 the folic.wtag equation ts given for the measured leak rate using the total time procedure: 3, = 2400 , [l , To Pi \
' tlJ i
( i o where Mg = measured leak rate in weignt '.' per day for the i
- data point assuming rl, R, and V are constant in the Ideal Gas Law equations; ,
h tg = time since the beginning of the test perced to the i data point in hours; . T,, temperature at the Tg =(!beginning mean, volume of theweighted test and containment at the data point i in *R
-(Reference EQ. 3 in QTS 150-T3 and convert to *R
(*F + 459.69 = *R) ). P,, Pg = calculated dry air pressure in PSIA at the bestaning of the test and at the data point i (Referance EQ. 5 in QTS 150-T3). Using the following relationship derived in ANSI N45.4-1972 Appendix B given below: W ~ W TO Pi O i
= 1 (2) o i o where W , , Wg = dry air mass of the containment at the beginning of the test and data point i, respectively.
I FOR 3EFElEEE C
QTS 150-T9 Revision 1 And substituting in the calculation of the contairment dry air mass that corrects for a change in reactor water level given in QTS 150-T3 EQ. 6 gives the following expression for the measured leakage: [ T P. (288737 - 25 (E. - 35))\ o t t M i= t g 0 ,!(I , T P, (288737 - 25 (E , - 35))j} (3) ,
' where E , G = reactor water level in taches (narrow range GEMACS) at the beginning of the test and the data point i, respectively.
B. CALCULATED EAK RATE. The method of Least Squares is a statistical procedure for finding the "best fit" straight line, commonly called the cegression line. for a set of measured data such that the sum of the squares of the deviations of each measured data point from the stratgne line is mtatmtzed. To determine the esiculated leak (L,) rate at time t, , the regresstan line is determined using the measured leak rate data f rom'ene start of the test to time t . The calculated leak rate is tne point on ents une at time t g. L t
=A g +B g t (a) where t = time in hours since the begtaning of the test to tne i data point; a I t. M. - (I t.) (I M.)
B = ' ' '
- i n I (ti)' - (It.)' t
' I' hn .
2 f ' (IM ) (Ict ) - (It ) (It M t t it ) Ai= n I t.' - (Itg)' 1 I= i=1 tY. j
'~~ g'0U,
- 6 l
__4 a = number of data sets to time t. 1 C. CONFIDENCE LIMITS UCLg=Lg + TD
- a (5)
LCLg =Lg + TD
- a (6)
Where, Lg = calculated leak rate for :he i
- data point (Reference EQ. 4);
TD = value of the T - distribution for the 95*. confidence limit and (n -2) degrees of freedom;
.37226 , 2.823 TDi = 1.95996 + (n-Z) (n-2)3 a = number of data points including the i data point; QTS 150-T9 Revision 1 a = standard deviation of the measured leak rate from the regression line calculated using the first a data points; (t - E)2 i
ass *C1+1+[I(e n j z) - 1 (It )2)2 a n I=I J=1 It i=dn j N )2 g i s= (I Ol (n - 2) N.=A.1 + B.
- t J 1 j M 'D j = measured leak rate (total time) at the j data potat.
f. FOR REFERENCE ONI.Y
l l l l APPENDIX D INSTRUMENT ERROR ANALYSIS l 1 i i
QTS 150-T10 Revision 1 IPCLRT SAMPLE ERROR ANALYSIS October 1982 FOR SHORT DURATION TEST ID/8N A. ACCURACY ERh0R ANALYSIS Per Topical Report BN-TOP-1 the measured total time leak rate (M) in weight percent per day is computed using the Absolute Method by the formula: M (% / DAY) =
- 1- _ (1)
N 1 where: P g
= total (volume weighted) contatnment dev n r pressure (PSIA) at the start of the test; P 'y ' = total (volume weighted) containment dry nr pressure :. PSIA; at data point N after the start of the test; H = test duration from the start of the test to data potat N in hours; T = c ntainment volume weighted temperature in *R at the start 1 of the test; T
3
= containment volume weighted temperature in *R at the data point N.
The following assumptions are made: l l _ A A P where P is the average dry air pressure of the containment g =P_3=P (PSIA) during the test; A A T1=T3=T where T is the average volume weighted primary containment air temperature ('R) during the test; Pg =P N where P is the total containment atmospheric pressure (PSIA); Pyg = PVN *** is the partial pressure of water vapor in the primary V containment. j FOR REFERECE 0! t 1 l l
QTS 150-T10 Revision 1 Taking the partial derivative in terms of pressure and temperature of equation (I and substituting in the above assumptions yields the following equation found in Section 4.5 of BN-TOP-1 Rev. 1: e g=1 0*2( )2+2( )2 (2) P T where ep = the error in the total pressure measurement system, e = t ( (*p ) + ( Py)2 } ; p T p = (instrument accuracy error) / J no. of inst. in measuring T total containment pressure; py = (instrument accuracy error) / J no. of inst. in measuring vapor partial pressure; e T = (instrument accuracy error) / / no. of inst. in measuring containment temperature; e 3 = the error in the measured leak rate; 7 H = duration of the test. .
' 0R N'!ERENCE t- ONl.Y y
___ u NOTE t Subvolume #11, the free air space above the water in the reactor vessel, is treated separately from t.ae rest of the containment volume. The reason for the separate treatment is that neither the air temperature or the partial pressure of water vapor is measured directly. The temperature of the air space is assumed to be the temperature of the reactor water, as measured in the shutdown cooling or clean-up desineralizer piping before the heat l exchangers. The partial pressure of water vapor is computed assuming saturation conditions at l the temperature of the water. Volume weighting i the errors for the two volumes (Subvolume #11 and Subvolumes #1-10) is the method used. QTS 150-T10 Revision 1 B. EQUIPErr SPECIFICATIONS FLOWMETER THERM 0COUPI.E INSTRUMENT RTD ('F) PPG (PSIA) DEWCEI.I. (*F) (SCFM) (*F) Range 50-200 0-100 140 0 - 8.44 Accuracy 2.50 2.015 21 :.085 :2.0 Repeat-ability 0.10 0.001 .50 :.02 :.10 C. COMPUTATION OF INSTRtF. Yr ACCURACT UNCERTAINTY
- 1. Computing " e "
t Volume Fraction for Volume 911 = .02276 Volume Fraction for Volumes al-10 = .97721 5
0 e., = : (.9772f. * + .02276 -1) 430 ,l 1 e
T* *I347 R
- 2. Computing " *pT e
P T * = .015 ,---
,, 2 p7 = t .0106 PSIA
- 3. Computing " *py" At a dewpoint of 80'F (assumed), an accuracy of : l'F corresponds to 2 .017 PSIA.
*p7 = 1 (.97724 * ~$ + .02276 * .034) ,
48 41
* ~ '
g = 2 .0066 PSIA j
- 4. Computing " e p "
F0iMEFERENCE E!.y h eP = t [ (.0106)2 + (.0066)2 J e = t .0125 PSIA P
QTS 150-T10 Revision 1
- 5. Computing total instrument accuracy uncertainty " e A" 3
A 'I3'7
,M 2400 H
- 2 * ( 63.0
.0125 )2 + 2 * ( 551.7 )2 h A
assuming P = 63.0 PSIA A T = 551. 7'R Therefore, for a 12 hour test,
^
e 3 =2 .0890% / DAY D. COMPUTATION OF INSTRUME'IT REPEATA.BII.ITY OTCERTAINTY
- 1. Computing " e "
T e.,, a
.10 J37 e
T= .0180'R
- 2. Computing " 'p7 e .001 i P '
T *
- 42 l-d
'pT = 2 .0007 PSIA
- 3. Computing " *py" py = 2 (.97724 * .009 + .02276 * .002 )
4T 4Y py = t .0032 PSIA
- 4. Computing " e "
e s , [ (.0007 2 + (.0032)2 J h p g h hhg h;!tj{,{ e = 2 .0033 PSIA -
--~ I QTS 150-T10 Revision 1
- 5. Computing the total instrument repeatability uncertainty " ".
. R , 2400 , .0180 "M H .0033 63.0 )2 + 2 ( 551.7/ )2T h Therefore, for a 12 hour test, og = 2 .0175.% / DAY E. COMPUTING TOTAL INSTRLHENT UNCERTAINTY e 3 = 2 2 * [ (eh2 , ( )2 J h ~
e h 3 = 2 2 * [ (.0890)2'+ (.0175)2 J e 3 = t .182 weight ". / DAY for a 12 hour test. j fhk f b ' a APPENDIX E BN-TOP-1, REV. 1 ERRATA The Commission has approved short duration testing for'the IPCLRT provided the Station uses the general test method outlined in the BN-TOP-1, Rev. I topical report. The primary difference between that method and the ones previously used is in the statistical analysis of the measured leak rate data. Without making any judgments concerning the validity of this test method, certain errors in the editing of the mathematical expressions were discovered. The intent here is not to change the test method, but rather to clarify the-method in a mathematically precise manner that allows its implementation. The errors are listed below. EQUATION 3A, SECTION 6.2 Reads: Lg=A+Btg o Should Read: L = A. + B. t. i i i i Reason: The calculated leak rate (Lg ) at time t is computed using the regression line constants A ,gBgg (computed using equations 6 and 7). The summation signs in equation 6 are n defined as I = I, where n is the number of data sets up until i=1 time t The regression line constants change each time a newdaba. set is receivsd. The calculated leak rate is not a linear function of time. PARAGRAPH FOLLOWING EQ. 3A, SECTION 6.2 Reads: The deviation of the measured leak rate (M) from the calculated leak rate (L) is shown graphically on Figure A.1 in Appendix 'A and is expressed as: Deviation = M g -L g Shou'd Read: The deviation of the measured leak rate (M g) from the regression line (N )g is shown graphically on Figure A.1 in Appendix A and is expressed as: Deviation = M g -N g where N. 1
= A +B
- t.,
1 P P A,B = Regression line constants computed from all data P P sets available from the start ot the test to the last data set at time t , t g = time from the start of the test to the ith data set.
Reason: The calculated leak rate as a' function of time during the test is based on a regression line. The regression line constaats, Ag and B g, are changing as each additional data set is received. Equation 3A is used later in the test to compute the upper ccafidence limit as a function of time.
-For the yarpose of this calculation, it is the deviation from the last computed regression line at time t that is important.
EQUATION 4, SECTION 6.2 Reads: SSQ = I (M. - L.)2 1 1 Should Read: SSQ = I (M g - Ng )2 Reason: Same As Above EQUATION 5, SECTION 6.2 Reads: SSQ = I [ M g - (A + Btg )]2 Should Read: SSQ = I [ M. 1
- (AP +B P
- t.)]2 1
Reason: Same As Above EQUATION ABOVE EQUATION 6, SECTION 6.2 Reads: B=(i ~ i - 1(tg - t) Should Read: B. = ('i i
~ }
I(t. 1
- t)Z Reason: Regression line constant Bg changes over time (as a function of t ) as each additional data set is received. BSr of "t" left out of denominator.
Summation signs omitted. EQUATION 6, SECTION 6.2 Reads: B=" i "i - ( i ( "i} n It g 2 - (I t g)2 Should Read: B = i "i - ( i) ( i} n It g 2 - (I t )Z Reason: Same As Above EQUATION 7, SECTION 6.2 Reads: A = fi - B t Should Read: Ag =5-B g i Reason: Same As Above EQUATION 10, SECTION 6.2 Reads: A=( i} ( i}~( i} ( i i nit 2g - (I t g)2 Should Ecad: A.* = ( i) ( 'i ( t g ) (I t M) g g nit g2 - (I t )2 f Reason: Same As Above EQUATION 13, SECTION 6.3 Reads: 02=32 [1 +" 1 +p(t -@j (tg - t)2 Should Read: 02=32 [y +" 1 +p(t -@j I (t{ - T)2 where t = time from the start of the test of the last data P set for which the standard deviation of the measured leak rates (M ) from the regression line (N g) is 1 being computed;
- t. = time from the start of the test of the i data set, n = number of data sets to time t ;
n I = I ; and i=1 t = fit g. Reason: Appears to be error in editing of the report. Report does a poor job of defining variables.
EQUATION 14, SECTION 6.3 Reads: a= s[1+ 1+ " ('p~') ] (tg - t)Z
~Should Read: o= s [ 1 + 1" + ('p ~ - ]
I (t g - t)2 Reason: Same As Above EQUATION 15, SECTION 6.3 Reads: Confidence Limit = L i T Should Read: Confidence Limits = L i T x o where L = calculated leak rate at time t p, T= T distributioa value based on n, the number of data sets received up until time t ;- p o= standard deviation of measured leak rate values (Mg ) about the regression line based on data from the start of the test until time t . P Reason: Same As Above EQUATION 16, SECTION 6.3 Reads: UCL = L + T
~
Should Read:' UCL = L + T
- o Reason: Same As Above EQUATION 17, SECTION 6.3 Reads: LCL = L - T Should Read: LCL = L - T
- a Reason: .Same As Above L
APPENDIX F TYPE A TEST RESULTS USING MASS - PLOT METHOD MEASURED LEAK RATE PHASE qitAD ~ CIT!LS UNIT 1 a t 5% 12/1 7/e/
.. .. su m AR Y pr n A T A sE is 1 T+u i s . . ..
11ST CLOCM DA te TE MP MFASURLD C AL C. M ASS I' HT A IR M b A S. ldAK N A IE CA LC . LEAK IP PE R T IME (F ) M AS S is o PH ES S, 2 / DA Y H AT F 95 % C0 tr D8H . HO UR S (PSt At T OT AL P OI NT g/ day Li MI T 0.00 13: 42:44 12/16/87 83.88 0.91566n149c 05 63.964 8 3. 84 0. 9156 64 56 8E 0 5 63 ,9 60 - 0,0695 - 0.06 95 8 0 .1 7 13:52:44 1? /1 6/ 82 63,958 -0,0790 -0.0R85 .-n.079n -0.n524
$7 9.33 14: 2:44 17/16/82 83.B? 0. 9156 7019 6E G 5 0.915659947E US 83,78 0. 9156 69 23 4E 0 5 0.9156611n4E 05 63,952 -0,0476 0.0151 -0.e517 -0.0067 s 0 .S 0 14:12:44 I?/14/82 0. 9156 74 74 5F 05 0.115 661107 f 05 63 ,9 50 - 0.05 54 -0.07HR -0.0517 -0.n 30 7 0.67 1 4:27:44 12/1A/R2 83.76 0, 05 33 0 .1 21 0 8 3, 73 0. 9156 4319 5E 0 5 0.915 66 76 4S E 05 63 .9 44 0. 4883 4. 07 54 0.h 3 14: 32 :4 4 12 /1 A/82 0.2524 n.0773 1.n o 1 4:42 :44 io /1 A/82 8 3. 71 0. 9156 2714 7E 0 5 0.915673144E 09 63,940 0,0d65 0 .1 65 2 0.9 15585854E 05 0 .915 6517 8A E 05 63 ,9 35 0, 16 47 0. 63 37 0,14 53 0 .244 1 1.1 7 1 4: 52 :4 4 i? /1 A/82 8 3.69 1.33 15: 2:44 i?/16)8? 83,67 0. 9155 85 89 9E 0 5 0.9 15689?O6 E 05 63,932 0,14 60 0.0150 g.1683 0.7477 1.50 15: 12 ~4 4 t'?/14)a2 8 3. 65 0.1155 43 87 5E 0 5 0.915 6917 50 E 05 61 ,9 27 0. 20 32 0. 66 09 0. 20 6) 0.7813 1.67 15: ?2 :44 17/16/82 8 3. 61 0.91555507 9E 05 0.9156924 43 E 05 63,923 0.157-0162 6 7 0. 21 ns 0.7706 1.81 1 5: 32 :4 4 12/1 6/82 8 3, 59 0. 9154 75 84 3E 0 5 0.9157013?9E 05 65.9 14 0. 26 35 1. 24 62 0. 25 75 .
0.1185 2.00 15: 42:44 j?/16/82 83,58 0. 9154 2515 4E 05 0.9157114?4E 05 61.910 0,3080 0.7973 n.295d 0.3670 2.1 7 1 5:52:44 12/16/82 83,55 0.91541534 3F 05 0.91571 7317E 05 63,906 0,2961 0.1543 n.3189 0.384n 2.33 tot 2:44 19/1A/B? 83.54 0.915171 891 E 05 0.915723978E 0% 63,901 0.3238 0.6835 n . 3411 0.4043 2.50 16:12:44 i?/16/82 83,52 0.9157R6430E 05- 0.915739328E 05 63,893 0.3918 1.3444 n.3814 0.447? 2.67 16:22:44 12/14/82 83,51 0.915273406E 05 0.915742565E 05 63,890 0.3800 0.2035 n.404: 0.4664 2.33 1 6: 32 84 4 i2 /1 A/82 83.49 0.9 15229241E 05 0.915 74 9718E 05 65.884 0.3986 0.6963 0.42 57 0.4842 5.00 1 6:42:44 13/1 6)82 83,47 0. 9152 7018 9E 0 5 0.915 74 90 75E 05 63,885 0,3407 -0.6443 n.4234 0.4761 3 .1 7 16:52:44 ip /16) B2 8 3, 45 0. 9157 78 96 5E 0 5 0 .915 74 5518 t 05 61,883 0. 31 55 - 0. 13 81- 0, 41 41 0.4622 3.35 17: 2:4 4 i3/16)82 83,45 n. 9152 6193 4E 0 5 0.915 741810 E 05 63,8 81 0,3116 0.2365 n. 40 49 0'4493 3.50 1 7:12:4 4 12 /1 A/ 82 8 3,43 0. 915? 0 7 35 ?E 0 5 0.915 741316E 05 63,8 75 0. 33 91 0.8902 0. 40 17 n,444n 3.67 1 7: 22 :44 12 /1 6/82 8 3.42 0. 915? t F 67 0E 0 5 0.915 73 8183 E n5 63 ,8 75 0. 31 63 - 0. 16 23 0.3 967 0.4340 3.83 1 7: 32 :44 t o /1 A/82 8 3, 39 0. 9152 ?n 98 7E 0 5 0.915 73 35 6? E 05 . 63,8 71 0, 30 03 - 0.05 22 n. 38 69 0.4223 4.n0 17:4?:44 17/16/82 83,40 0.915159444E 05 0.915 732416E 05 63.867 0,3281 0.9683 n.3844 0.4171
- 0. 9149 09 67 6E 0 5 0.915 74 69 54 E 05 63,847 0,4728 3. 94 66 n. 4110 0,4541 4 .1 7 1 7:5?:44 ip /16f8? 8 3.37 4.33 18: ?:44 io /16/ 8? 83.37 0.914999294E 05 0.915751306E 05 61,853 0,4003 -1.4113 n.421? 0.4602 4.5p 1 8:12:44 i ? /16/82 83,37 n.114973 77?E 05 0.915754911E n5 63,851 0.4010 0.4174 n.4277 0.4645 4.67 18: 2? :44 12/16/82 83.36 0.914933970E 05 0.915 75R594 E 05 63,847 0.4079 0.5957 0.4147 0.4689 4.93 1 8: 37 :44 12/16/82 8 3. 34 0. 4149 n F 17 8E 0 5 0.915 7616 46b 05 63,842 0.4063 0.4209 n.4391 n . 4 ,721 s
i
APPEllDIX F (cont'd) _ MEASURED LEAK RATE Pri.^.SE (cont'd) 5.no 18: 42:44 t9/14/82 83.34 0.914970459E 05 0.915764747E 05 63.840 0.4140 0.5779 n . 4414 0.4754 5.11 1 8: 52 :4 4 s p /1 A f87 83.32 n. 9144 96 37 0E 0 5 0.915 76 411/E n5 61, A 3d 0. 3c 75 - 0. 40 78 a.4417 0.4727 5.11 19: ?:44 is/16f87 83,30 0. 914 a i9 69 0E 05 0.915764467E n$ A3.833 0.3939 0.5932 n.44to 0,4717 5 .5 n 19: 1?*44 17 /1 a/82 8 3. 3n 0.914110108E 05 0 .915 76 'w 8s E 05 61.8 30 0.4n51 0. 76 45 9.44 57 n .4 714 5.f 7 19: 22 :4 4 12 /1 Af82 8 3.29 0.934803188F 05 0.'815 76 S6 ?? E 05 63.925 0. 39 64 0. 10 89 q.445s 0.4698 5.R1 19852:44 19/1 4/87 83,27 n. 914 7 74 90 RE n s 0 .015 76 55 69 E n5 63 .9 24 0.397a 0. 44 52 q 44 55 0.4684 6 nn 19:4?:4 4 19 /1 A) 82 8 3.27 0. 9147 43 84 6F 0 5 0 .915 76 56 4 7 E 05 63,820 0. 40 03 0. 43 90 0.4457 0.4672 6,17 1 9* 52 44 17 /1 A/82 83.24 0. 91 16 ^O 24 5E 0 5 0 .915 76 R4 06 k 05 ^3,812 0.4250 1. 31 61 n. 44 91 0.47.10 6.11 2n: 7 44 17/16/8? 83.24 0.91469731nE us n.91%768187E 05 63,813 0.4026 -0.4261 n.4491 0.4686 6.50 70: 1?*44 12/1Af0? 83.24 3.414A61 907F n5 n.915767849h 05 64,811 0.4025 n.3999 a.4496 n,467? 6.67 20!??:44 to/16fBP 83.22 0.9 464416SF 05 0.915 76 70 61 F 05 65,807 0.3994 0.2793 0.4476 0.4654 6.83 70:39 44 12 /15f07 8 3. 22 n. 91 es t 4 As th 0 5 0.015 76 641nE ns 63,805 0.4010 0.4647 q.44A9 0.4639 7.00 2n:42:44 ip/14}82 83.?1 0. 91451117 9F n5 n 91576%A?nE 05 63,801 0.4003 0.3703 4.4451 0.8621 7.17 2 0:52 :44 is/1A/P2 83,18 0. 9145 75 74 6F 06 0.915 76 43 65E 05 63,7 97 0. 3966 n. 24 22 4. 4445 0.4600 kh n.9115%974nF 04 n .915 76?7 E46 n$ 61,794 0.3935 0.2599 n.4494 0.4576 00 1.33 ?l: 2:44 17 /1 %/8? 83.17 0.4561 7.50 21:12:44 n /t sf 82 8 3.16 0. 91451/ 3 7 4F 05 n . # 15 761671E p5 63 .7 91 0. J9 94 0. 65 92 n. 4419 7.67 71 )?:44 ip/16f82 81.14 n.d: 19 94 H8 2F 05 0.015752459E n5 65,789 0.38o1 -0 1179 g. 43 74 0.4533 21: 32 :4 4 ts /1 A/ e? 8 3,14 n.914494926r 0 5 n .915 75 7/ 6/ E n5 63,7 86 0. 39 00 0. 4777- n. 43 7s_ 0:4509 7_.83 9.00 21: 42:44 19/1Af92 83.14 0. 914 4 4416 3F QS 0.915756877E 05 63,782 0.3981 0.7773 n.4357 0.4495 8 3.12 0. 9114 57 n0 7F 0 5 0 .915 75 45 87 E 05 63,7 hD 0. 38 61 - 0. 19 65 n.434t 0 .446 9 6 .1 7 21: 52 :4 4 17/14/ 87 0.8n59 n.4355 n ,4 45 3 9.31 ??? 2:44 i ? /1 A/87 94.12 0. 014A n5 n3 nF 05 n.915751384E 05 63,777 0.3945 22:12:44 17/14f82 8 3. 10 0. 9144 n317 9E n S p .915 7513 89E 05 6t,773 0,3n76 0.0419 n.4314 0.4431 9.50 0.3947 n.7335 n.43nt n.4417 8.A7 72:??!44 12 /14 fn? 83.10 0. 91415659 ?E 05 0.915750259E 05 63.770
? 2: 32 :44 19/1 4/87 8 3, 08 0. 9141391 A1E 05 n .915 74 688 ? E 05 63 ,7 6? 0. 39 2a 0.2745 0. 47 9 0.4401 9.81 0.3917 0.3805 q 4?79 0,4385 9.no 22: 47:44 ja/1Af87 83.08 0.914115n03E 05 0.91574751RE n5 61,765 0.914500 70*E 05 n.915745R35E 05 63.762 0.J887 0.2751 n,4764 0.4368 9.17 22:5?:44 to/1A /7 8 83,06 9.31 ?3: ?44 t ? /14)RP 93.06 0.914793137F 05 D.'15743979E ns 63,759 0.3867 0.2767 n.4?49 0,4349 9.5 n 73: 17:4 4 sp /1 Af 92 8 3. 05 0. 9147 70 59 nE 0 5 0.915 74'18 p3 E 05 63 .7 5S 0.3834 0.1976 n. 42 33 0.4329
- 9. A 7 ?3:22:44 t?/tsf8? 03.03 n. 91475172 nr 0% 0.915739547E n5 63,754 0.3819 0.29 72 0,4711 0.4300 9.81 7 5:37 44 12 /1 A /H2 6 3, 04 0. 914p n2 05 4F 0 5 n .915 73 97 00 6 05 63.751 0.3887 0.78?3 n.4701 n.4795 10.0n 73: 47:44 19/14/0? 93.02 n.9' 4? t9 34 ?F 05 0.9157 5587E 05 63,750- 0.3776 -0.2723 0.41 79 0.4273 10.17 73:57 4 4 t?/t A/82 8 3. 02 0.914181 92 7E 09 0.915 . 3514 F 05 63,747 0.3811 0.5909 n.4163 0.4259 in.3 5 0: 7:44 is /17 /87 83.0? 0.914155897E n5 p.915731584E 05 63,745 0.3815 0.4082 0.414e n.4238 1n .% 9 0:17:44 19/17/87 83.00 0.914tS4874E 05 0.015729n46E 05 63,742 0.3750 0.0161 n , 417 ) 0.4719 83.00 0.914173"4?E n5 0.015726837E 05 63,739 0.3775 0.4888 0.4117 0.420n 10.A7 0 ??:44 12/17iB? 0.4674 0.4185 10.8 1 0:3?!44 is /17/82 82.98 0.914994169F 05 0.915724393E 05 63,735 0.3789 0.4093 11 .9 9 0: 4? ?44 17/1 7/8? B2.98 0. 914n 96 67 4E o s 0.915 722563E 05 ' 63,734 0.3749 0.1188 0.40 81 0.4167 n: 52 :4 4 12/17f82 82.97 n. 9140 44 nR 7E 09 0 .915 72 0 7 53 E 05 63,730 0.3784 n. 60 72 q. 40 68 0.4152 11 .1 7 0.3949 11.33 1: 7:44 15/1 7/87 82.96 0.9140 ?3 n2 3E 0 5 0.0157190'48E 05 63,727 0.3786 9.4056 0 .4 13
- 1:1?:44 12/1 7/82 0.91430095 8E 0 5 0.915 70 915? E 05 63,745 0. 3098 4.3784 0.3989 0.4091 11.50 8 2. 94 q. 39 ?1 11.67 1:22:44 19/17/87 82.94 0. 914? 99 66 3E 0 5 0.915 69 9? 85 E 05 63,744 0.30 56 0.0201
- 0.4040 1: 32 :44 sp/17/ 87 87,93 n; 914p s9 49 9F 05 0.915 68 9719 E c5 63 ,7 41 0. 30 30 0.1758 n. 36 56 0.3989 mat 0.3047 0.3655 0.3937 1?.00 1: 47:44 12/11/82 82.93 n.914765291E n5 n.91568n?5BE n5 63,740 0.3796 1
l L
APPEllDIX F (cont.'d) TYPE A TEST RESULTS USlilG ttASS - PLOT ftETi:0D I!1DUCED LEAK P!:ASE fytAD C i1 lF S HM ~ 1 0926 12/11/H 2
....SuriAHy at NATA SerS 84 IHRu 112 ....
nage *, IMP M F t.9 tHk p C al C'. MASS DHY AIR NtAS, 1 tan WATE Cald, 1X A K :8PPR 1 ['i T CLOCK T IMI JI '1 AS S T*H PRESS, t / OA Y 1 Af f- 95r CO F D HH . (PSI A1 T OI AL P 0l t.T TfDu 11 MI T w H%RS
' O .n 0 3*3?:44 17/17f8? H 2. 79 n. 9135 0614 2E 05 63 .6 68
- n. 4134 53 417E n S 63 ,6 63 0,8113 n. 8 513 0.17 3: 42 :4 4 12 /1 7/82 d 2. 78 1.3401 1.7987 0.'3 3:57:44 19 /17f 82 8 2. 76 n. 9133 68 4n1E ns 0.9135115?SE n5 63,655 1.0856 1.04in q .5 n 4: 2:44 12 /1 7f e? 8 ? 77 n. 9137 61 571E 05 0 .913 52 n188 E n5 63 ,6 47 1,2851 1. 63 43 s . 29 ns 1.a 72 2 8 2, 75 n. 9175 45 38 5F 05 0.913 53 35 05 E 05 63 ,595 1, 41 20 1.4617, 1. 44 1: 1.5322 1.79 5:19*57 19/17f82 1, 47 si 1.5 39 n 1.9 " 5: /9 :S7 1p /3 7/HP 82.76 0.9124?2?i16 05 0 .913 53 66 6 A F 05 63,5 87 1. 45 77 1. 9497 82,71 0. 9174 66 510F 05 0 .913 52 78 27 E 05 65,583 1,7o H3 - 0. 69 80 1.4047 1 .5 13 ?
2.12 5: 39 :57 12 /17f 87
- 0. 91 ?'182 50 6E 0 5 0 .913 52 ?2 56 t: 05 63 ,5 77 1.2909 1. 32 57 1.37nt 1.4687 2.29 5:49*57 12/17f87 8 2. 70 0.91??66177E 06 0.913520545E n$ 63 ,tl69 1,J/78 1.4360 1.3614 1.4427
?.45 5:59:57 19/17/8? 82.71 65,563 1,3104- 1.0553 1.34 74 1.4?o?
2 .6 ' 6: 9:57 t?/17f62 82.70 0.91?1993?dF 05 0 .913 5178 96 F 05 6:19:57 1 6/17 f82 82,6P n.91212?476F n5 0.913515051E 05 65,556 1.3044 1.?131 1.3394 1.4017 2.79 0.912014 97 6E 05 0.91351 4607E 05 63 ,5 48 1.32 65 1. 697/ 1,33 9n 1.397 3 2.95 6: 29 :5 7 12/17/87 82.69 1,3622 82.6h 0. 9119 4? 88 6F 05 0.913 513? 31 E 05 63,5 42 1.3163 t .13 82 i . 33 4n 3.12 6: 39 :5 7 io/17)e2 61,5 36 1.3704 3 .' 9 6: 49:57 12 /17f82 82,67 0.9118h1460E 05 0 .913 51 n? 735 E n5 1.29b7 0. 96 99 1. 32 '1 0.91 17 60 616E e s n .91 3 510 6? E n5 65,5 29 1, 32 79 1. 90 83 1. 37 74 1.3672 3.45 6: 59 :57 19/17/H2 8 2. 67 61,5 23 0.8311 1. 37 76 1.3591 3 .6 ? 7: 9:57 ip /17/87 8 2,66 0. 9117 07 99 4E n $ n.913Sn9616F nS 1. 30 50 82.65 0. 91 16 37 7p ?E 05 0.9 135057 1dE n5 63,517 1.2963 1 110? 1 3166 1.9506 3.79 7: 19:57 19/17/8? 1.6501 1. 31 35 1.3 63 4 3.95 7:29 57 19 /1 7/8p 8 2, 66 0. 9115 33 ?41E 0 5 D .91350 50 n? e: n$ 63 ,5 10 1. 31 11
- 0. 9114 90 714E 05 0.91350109?E n5 63,5n4 1.285? 0.6718 1.304) 1.5379 4.1p 7:39:57 19/17/8? 82.64 1, 28 15 1,1947 1, 3015 1.3 30 0 4.29 7: 49 :5 7 is/17f87 8 2, 63 0. 911415091F 09 0.913 49 7? n9 E c5 63 ,4 98 1.5485 , . ? 9 41 1.324H 4,45 7:$9:57 ,9/17/8? 82,63 0.91131 70RSF 05 0.9 3495thnE ns 63,491- 1.?914 1.41$6
- 0. 9117 7s ?5 6p n5 0.013490nn3h 05 63,486 1,2669 0.61 35 1.79 11 4.62 9: 9:57 1? /17/82 82,62 63,4 79 1.2791 1.6?25 1.2860 1.3113 4,79 8:19:5 7 19/17/8? 8 2, 62 n. 9111 *5 %8 t.F 0 5 n.91348 7??%E n%
61,4 73 1.2h13 1.3182 1. 28 34 1. 3 0$ 5 4.95 8:29:57 19/17/87 82.62 ~ n. 91 1 n 90 77 3F n$ n.91348%137E 05 af,4 67 . 1.3516 1.?8na 1.3029 5 .1 ? 8:39*57 ip/17/82 82,62 0.9tino601?E 05 n.9134835h?E 05 1.2829 8 2, 60 n.910951 50 eE 05 0 .413 48 0/ 4 7 E n5 ti3 ,4 61 1. 20 95 c. R6 03 1.77al 1.9976 5 . 9 R: 49 :57 19/17f82 1.?774 1, M2 h 5.45 H:59:57 17/17/8? 07.60 n. 91 og i4 48 4E c5 r.413471114E,pS t 4,4 56 1.2 hie 1.21Pb
- n. 9107 9 t t h g 05 0 . y 13 4 7 ?5 % I US a t ,4 44 1.2587 - 1. 11 31 1. ?6 70 1,9 66 H 5.74 9:19:57 19/17/8? 8 7, 59
*4 438 1.2616 1. 3654 1.26 l' 1.2B?!
S.95 9: .59 :57 17 /17p 62 82.59 n. 91 n6 4 7 31 4 05 t# .u 13 46 92 36 6 05
APPENDIX G BLOCK DI AGRAli 0F COMPUTER PROGRAM TO PERFORM CALCULATIONS BASED ON BN-TOP-1, REV. 1 i i 1
CPROGRAM BNTOP se SET UP FILES USED BY PROGRAM AND READ IN OLD DATA Y SELECT ONE: M: MANUAL DATA ENTRY A: AUTO DATA ENTRY E: ENTER CALIBRATION CONSTANTS D: DELETE DATA B: CHANGE BASE DATA SET C: CRT DUMP OF OUTPUT L: LINE PRINTER DUMP 0F OUTPUT P: PLOT DATA S: START DATA MOVER H: HALT DATA MOVER Q: QUIT A D h P H M E B @, S @ l 1 l i i
M A ENTER DATA FOR TlHE, RTD READ DATA FOR TIME, RTD, DEWCELL PRESSURE AND DEWCELL, PRESSURE, AND REACT 0F REACT 0k WATER LEVEL WATER LEVEL FROM FILE 1 PERFORM REASONABLE LIMIT VALIDATION I
?'
s-CALCULATE CONTAINMENT AVERAGE TEMPERATURE, VAPOR PRESSURE, AND PRESSURE E PERFORM LEAK RATE AND LEAST SQUARE FIT CALCULATIONS 1 OUTPUT RESULTS OF DATA SET Y D B ENTER START AND FINISH ENTER NEW BASE DATA DATA SET NUMBERS SET NUMBER DELETE DATA SETS AND PACK REMAINING SETS S RECALCULATE LEAK RATE RESULTS FOR ALL DATA SETS Y
E Q
\/ t/
ENTER SLOPE, INTERCEPT, AND CLOSE ALL OPEN FILES CHANNEL NUMBER FOR ALL SENSOF S 1 u EXIT OUTPUT THE CAllBRATION DATA BNTOP 4 ALLOW BAD INPUT TO BE FlXED Y C L v v SELECT ONE: SELECT ONE: B: BNTOP OUTPUT B: BNTOP OUTPUT C: CONTAINMENT CONFIGURATIO!I C: CONTAINMENT CONFIGURATION D: LAST DATA SET D: LAST DATA SET S S GET PROPER OUTPUT FILE GET PROPER OUTPUT FILE h de LIST FILE ON CRT SCREEN SPOOL FILE TO THE LINE PRINTI.R O!;E PAGE AT A TlHE Y Y P PUT GRAPH AXIS ON SCREEP 4r SELECT ONE: T: CONTAINMENT AVERAGE TEMPERATURE P: DRY AIR PRESSURE L: LEAK RATE DATA P
,r SCALE AXIS FOR TEftPER- SCALE AXIS FOR PRESSURE SCALE AXIS FOR MAXI-ATURE MUM VALVE b E 1 PLOT UPPER CONF LIMIT, PLOT TEMPERATURE VS. PLOT PRESSURE VS. TIME LOWER CONF LittlT, TIME MEASURED, & CALCULATED LtMN MMit 4-WAIT FOR WAIT FOR WAIT FOR RETURN RETURN RETURN P P P S H LOG IN PROGRAM TO TRANSFER LOG OUT PROGRAtt TO TRANSFEF DATA FROM PROCESS COMPUTER DATA FROM PROCESS COMPUTER r
Y Y (final) 1
.._._ __. . _ _}}