LER 89-015-01:on 891030,no Data or Evidence Found That Stroke Time Test Performed on Bettis Actuator for Isolation Damper Following Maint.Caused by Programmatic Weaknesses.New Computer Field Data Added to Work orders.W/900215 Ltr
ML20006E452
Person / Time
Site: Grand Gulf Entergy icon.png
Issue date: 02/15/1990
From: Byrd R, Cesare J
SYSTEM ENERGY RESOURCES, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
AECM-90-0033, AECM-90-33, LER-89-015, LER-89-15, NUDOCS 9002230191
Download: ML20006E452 (6)


Text

- ,- --

[ .. ~

' , , - -._/

- y.

em- *

- sv.iem eniray :

PO Box 750 t

. ER$7g:

.';g Port G boon, MS 39150 '

' Tel 601437 6470 ,

~

{ J.

s,- John G, Cesare, Jr.

7; cm,c oor .

February 15, 1990- """" '

O.S. Nuclear Regulatory Commission  :

Mail Station P1-137

Washington, D.C. 20555  ;

Attention: Document Control Desk Gentlemen:

SUBJECT:

Grand Gulf Nuclear' Station Unit 1 Docket No. 50-416 License No. NPF-29 Update on Failure to Retest Isolation Dampers Following Maintenance LER 89-015-01 '

AECM-90/0033 Attached is Licensee Event Report (LER) 89-015-01 which is a final report.

Yours truly,

'JGC:cg j Attachment cc: Mr. D. C. Hintz (w/a)

Mr. T. H. Cloninger (w/a)

Mr. R. B. McGehee (w/a)

Mr. N. S. Reynolds (w/a)

Mr. H. L. Thomas (w/o)

Mr. H. O. Christensen (w/a)

Mr. Stewart D. '!bneter (w/a)

Regional Administrator U.S. Nuclear Regulatory Commission Region II 101 Marietta St., N.W., Suite 2900 Atlanta, Georgia 30323 Mr. L. L. Kintner, Project Manager (w/a) p,. Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission f I M' *N Mail Stop 14B20 fi '

t Washington, D.C. 20555

'b 9002230191 900215 ilc PDR ADOCK 05000416 lf d,s S- PDC 6 /

l y

.. ~ .

.e q

=RC P ipe , U# =UCLtu ReoV6ATORT coMMen.o= l APPROVtD Oest 800. 3150104 l

'~ '

    • "'**5"

UCENSEE EVENT REPORT (LER) l 1

PAciLITY esanat tu DOcettiBeURADtR m raus us Grand Gulf Nuclear Station - Unit 1 0 l 5 l 0 l 0 l 0 l4 l1 16 1lorl0l5  ;

TITLE ida l Update on Failure to Retest Isolation Dampers Following Maintenance  !

EVOtrT OATS (Si LER NutSER (4) REPost? DATE m CTHtR F ACf .lTIES IIfv0LVED iti MONTH DAY ytAR YEAR e 88$U , "8/uS MONTH DAY YEAR p acaLitv hawls DOCsLET NUMDERtS)

NA 0l5l0l0l0 1 l l 1 1l0 3l 0 8 9 8l9 0l1l5 0l 1 0 l2 1l5 9 l0 0 isio 1 0 io n i

,,,,,,,,,, THis RaPORT is sueMiTTED PUReuANT TO THE RsOuiReMsNTs Of to CrR I: tenece eae e, mere er rae renocae) (In "oos

  • 1 m ani a m .i unieH2Hivi tuini  ;

g 00

m. mieHuus m mieHuoH X

e0 mieHu

.0.mm m senieHnw soni.Hmvin tunsi i n0i 11 i _ _ gutgsg g 4,

, ]

20.40Blelf1 Hill) 90.? SieH2HQ 00,734eH2HviintA) Jf6AA s j;[# . M 405:el(1 Hist 90.734eH2 Hill 90.734eH2HvillH56 s

_ _ ]

s 30.405deH1Hv) 90.734e H2 HilH to.73(eH2Hal l LICEN688 CONT ACT FOR THIS L8R n2)

NAME TELEPMONE NUM95R ARE A CQQg Ronald Byrd / Licensing Engineer 6 10 l1 4l3l7l-121118l2 COMPLETE ONE Leelt FOR E ACM COMPONE8st F AILURE Df 8CRISED IN THIS REPORT H31 ,

CAu$$ $YSTEM COMPO8 5NT

    1. NNfkO' O PR $ ' CAUSE SYSTEM COMPONENT ""hgkO' TO PR s
  • s y s s <

l I I I I I I I I I I I I I ' '

s l l l l l l l l 1 I l I l i SUPPLEMGNTAL REPORT EXPECTED 114) MONTH DAY YEAR SUOMi&SiON YES IIf yes, eemplete IXPECTRO SV04915SION QA fth NO l l. l AneTRACT tv,,n a um a.,. a. e -wr r,N.e m.ne rnm > o nel During a special review of stroke time data on October 30, 1989, no data or evidence could be found for a stroke time test that was required to be performed following maintenance on the Bettis actuator for isolation damper QSZ51F001. Further investigation of other Bettis actuator maintenance l revealed six similar cases of missing rotest documentation. It is concluded <

that the retests were not performed prior to returning the isolation dampers to operable status.

The failure to perform the stroke time tests is attributed to personnel error with programmatic deficiencies as contributing factors. Neither maintenance personnel nor licensed operators ensured that the post-maintenance stroke time tests were performed as required by plant procedures. The repetitive task program was not fully effective in that the tasks were not subject to a consistent, documented retest review process. .A new computer data field has been added to the repetitive task work orders to indicate whether or not a retest is required. If a required retest is indicated, then a form will be included in the work package to perform and document the retest. Initially, retests for each task will be determined prior to performance of the task. The retest applicability determination will remaih constant unless a change is approved in accordance with the repetitive task program procedure.

It was subsequently determined that all of the subject isolation dampers had closure times within the maximum limit of 4 seconds. Therefore, there was no reduction of the safety functions provided by the components.

NRC Peres 300 tr831 1

. Y ""

a ownsam neemavear -

- go men awaoveo o= =a vow

  • m LDC88$1"!E EVENT REPORT ILERI TEXT CONT 6NUAT90N se mes sin e

,mamm m assas, meses a 6.. m e es a vaan JMD6M h&6 75M Grand Gulf Nuclear Station olsjojelol4l1l6 8l9 0 l 1l5 0 l1 0l2 or 0 l5 6 .

vert e sse ssm e meses im asame ame == mem nn ,

A. Reportable Occurrence During a special review of stroke time data on October 30, 1989, no data or evidence could be found for a stroke time test that was required to be performed following maintenance on the Bettis actuator for isolation damper QSZ51F001. Further investigation,of other Bettis actuator maintenance revealed six similar cases of missing retest docume_nt ation. It is concluded that the retests were not performed prior to returning the isolation dampers to operable status as required by Technical Specifications 4.0.5, 4.6.4.1, 4.6.6.2.a and 4.7.2.d.2.

This situation is reported pursuant to 10CFR50.73(a)(2)(1)(B).

i A.- Initial Conditions The plant was operating at 100 percent power at the time of discovery.

C. Description of Occurrence Safety-related Bettis actuators in service at Grand Gulf Nuclear Station are on a five year rebuild frequency. Periodic maintenance tasks cards are. issued to accomplish these tasks. Since 1984, Bettis actuators on thirty-nine safety-related valves / dampers have been rebuilt,under this program. During a review of stroke time data for damper QSZ51F001, which had been rebuilt during RF03, no data or evidence could be found for a stroke time test that was required to be performed prior to returning it to operable status. However, a stroke time test had since been performed by the quarterly surveillance required by Technical Specification 4.0.5 which demonstrated that the L damper closing time was within the 4 second limit.

An investigation was performed to determine if there were similar

. situations on other components. The investigation revealed that six additional dampers with rebuilt Bettis actuators had not been stroke time tested prior to restoring the dampers to operable status. The subject dampers are as follows:

Date Work Date Dampers Function Completed Tested QSZ51F001 Control Room Fresh Air Isolation 4-11-89 6-3-89

['> QSZ51F002 Control Room Fr th Air Isole'i^n 4-12-89 6-3-89 QSZ51F004 Control Room Fresh Air Isola.icn 4-12-89 6-3-89 QSZ51F011 Control Room Fresh Air Isolation 4-09-89 6-3-89 Q1T41F006 Secondary Containment Isolation 4-22-89 8-18-89 Q1M41F015 Drywell Isolation 4-19-89 10-31-89 Q1M41F016 Drywell Isolation 4-19-89 10-31-89 g'*""s** LER89015/SCMPFLR - 4 Y-2 .

o ,

p s. . uo aw6ean neematon, emanssism l <

UCEf!iSEE EVENT REPORT ILERI TEXT CONTINUATION aaaovse om an **-*

p oness.mo U sesan namnen m w n mamm m , to. .amesa e enes is

m. .=Fert6 =v.!rr; Grand Gulf y clear Station olsl0l0lel4l1l6 8l 9 -

0 11 l5 --

Oll 0l3 OP O 15 inn n === e amais sammm mme swa manw a .

A review was conducted to ensure that stroke time tests on these i components were current. It was determined on October 31,_1989 that all had.been tested since the actuator rebuild with the exception of two drywell isolation dampers, Q1M41F015 and Q1M41F016. These two dampers were rebuilt during RF03 and are normally tested only during Operational Condition 4, Cold Shutdown. A Limiting Condition for Operation was entered for the two dampers pending a stroke time test.

The test was then performed on October 31, 1989, approximately one hour after discovering that the dampers had not been retested. The test verified that the dampers closed within the 4 second time limit.

The following reviews were conducted to provide assurance that i

safety related components subject to periodic maintenance were currently retested.

o Safety-related maintenance task cards performed within the last 4 months were reviewed against the applicable surveillance completion dates. Tasks performed after the surveillance completion dates were further reviewed to ensure that retest requirements were met.

o Safety-related components subject to surveillance testing only during Operational Condition 4, Cold Shutdown, were investigated to ensure that retest requirements were met following any preventive maintenance that was performed after the surveillance completion date.

o Safety-related maintenance task cards performed during RF03 (approximately.1,000 task cards) were reviewed to ensure that appropriate retests were completed before returning the system or component to operable state.

There were no other safety-related components identified as not being currently retested.

D. Apparent Cause The maintenance instructions for rebuilding Bettis actuators required maintenance personnel to contact the LLRT Coordinator to determine if leak rate testing was required and to contact operations to dotermine if stroke time testing was required. In addition, the procedure instructed maintenance personnel to support the retests to ensure that all required testing was performed.. The investigation determined that all required leak rate tests and most of the stroke time tests were performed following refurbishment of the actuators. However, no evidence could be found documenting that a stroke time test was performed prior to returning the subject 7 dampers to operable status.

1

' g('"" *"' LERB9015/SCMPFLR - 5 i

~

m j p

v' .. l g UCENSEE EVENT REPORT (LERI TEXT CONTINUAT60N

~ .e

.=aoves one no as-oo l'

ow nes;e w s F -m osent mass. m 6e. .umen . . i n.. v m *6 ew=

[

Grand Gulf Nuclear Station 0 ll to lo le l4 11 l6 8l 9 -

0l 1l 5 -

0 l1 0 l4 or 0 l5  !

vare . ..se wamea.-anewim.  !

Stroke time tests are normally performed by operators in accordance with and documented by the applicable Operations Section surveillance [

procedures. There are no retest documentation requirements in the  !

actuator rebuild procedures or on the tasks cards, which complicates j the search for documentation. Nevertheless, since no retest documents i for.the subject 7 dampers were found, it is concluded that these stroke I time tests wero not performed.  ;

The failure to perform the stroke time tests is attributed to personnel i error by maintenance personnel and licensed operators. Maintenance personnel did not. ensure that stroke time tests were performed as i required by the maintenance procedure, and the Operations Shift l Supervisor f ailed to ensure that post-maintenance surveillance testing <

was performed as required by procedure 01-S-06-2, Conduct of -

Operations.

t programmatic weaknesses also contributed to the error. The maintenance  :

procedure was not written in accordance with standard practices regarding maintenance / operations interface for performing retects. The i task card packages provided to operations for review, did not address additional retest requirements nor provide for documentation of completed retests. Normally, the type of periodic maintenance 'I performed under task cards (e.g., lubrication, inspection, calibration) do not require additional retests and the task cards are not subject to i the same documented retest review process as Maintenance Work Orders (MW0s).  ;

P E. Supplemental Corrective Actions As an immediate action, preventive maintenance (pM) task cards,.

excluding surveillances, were retrieved from the field and retest ,

control forms, similar to those used for Mhos, were added to the task t card packages to require a documented review for retest applicability.

Surveillance tasks were excluded because any required retests for .

surveillance activities are accomplished by specific steps within the i

,. surveillance procedures.

l l

As a long term measure, a new computer data field was added to repetitive task work orders to indicate whether or not a retest is I required. If a required rotest is indicated,-a form will be included  ;

{ in the work package for performing and documenting the retest.

Initially, retests for each task will be determined prior to

]

i performance of the task. The retest applicability determination will remain constant unless a change is approved in accordance with the I repetitive task program procedures, j l

g?**" *** LER89015/SCMPFLR - 6 I

., e 4-p am UCENSEE EVENT REPOMT EERI TEXT CONTINUATION v2 mm6aan asemarearenemm e.

    • aove me no v .e

.[

i man. .w. i

.-- m .,====== . .a .

6..  !

.... . -sam *6 r mm  !

GrandiGulf Nuclear Station 8 la le l 0 l 014 11 16 819 -

Olll 5 -

3 II n I; " n Is a n . .e ,

..tr, I

Maintenance mechanics and supervisors were instructed that when a l procedure step is.not clearly understood or deviates from the normal ,

way of doing business, they are to stop and obtain clarification or a [

procedure change before proceeding. ,

r Operations Shift Supervisors were informed of their responsibility to ensure that when a safety-related system or component is returned to e service following maintenance, required tests are completed before i declaring it operable.

F. Safety Assessment All of the subject isolation dampers had closure time within the '

maximum limit of 4 seconds. Therefore, there was no reduction of the e safety functions provided by the components. '

Although no reduction of a safety function occurred, System Energy '

Resources, Inc. (SERI) realizes the potential significance of failing to perform adequate retests on components or systems following maintenance and has taken comprehensive corrective actions to strengthen programmatic weaknesses.

/

li l

i.

l l

g?oa""** LER89015/SCMPFLR - 7

_  !