|
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARML20029D0371994-04-26026 April 1994 LER 94-004-00:on 940324,found Five Slow Rods While Scram Time Testing Was Being Performed.Caused by Contamination of Internal Scram Solenoid Pilot Valve Head Assemblies. Corrective Action:Install New Head assemblies.W/940426 Ltr ML20046C3991993-08-0606 August 1993 LER 92-009-01:on 920509,observed That Some of Fuel Rod Compression Springs Compressed More than Expected for Assembly Exposure Achieved.Max Envelope Size of Lower Tie Plate Will Be reduced.W/930806 Ltr ML20045G7911993-07-0808 July 1993 LER 93-005-00:on 930608,indicated That Response Time Test for RCIC Low Steam Pressure Isolation Instrumentation Invalid.Caused by Inappropriate Test Method.Procedures Governing Method of Testing Will Be revised.W/930708 Ltr ML20045E9601993-06-30030 June 1993 LER 92-017-02:on 920804,reactor Scrammed Due to Low Primary Water Tank Level Signal.Implemented Minor Change Package Which Will Install DC to DC Converter Between 24 Volt DC Power Supply & Pw Tank Level transmitters.W/930630 Ltr ML20045C5261993-06-16016 June 1993 LER 93-004-00:on 930517,inboard Containment Isolation Valve Which Supplies Steam to RCIC Sys Automatically Isolated Due to Topaz Inverter Failure.Calibr Instructions & PM Program Will Be reviewed.W/930616 Ltr ML20045A0151993-05-28028 May 1993 LER 92-011-02:on 920608,determined That Design Inadequacies Could Result in Exceeding 10CFR100 Limits.Caused by Failure of Original Design to Specify leak-tight Const for Fan Housing.Shaft Seal Design installed.W/930528 Ltr ML20024G9701991-05-0606 May 1991 LER 91-002-00:on 910406,operating Module Breaker in Automatic Turbine Tester Circuitry Tripped Open,Deenergizing Control Solenoid for change-over Valve.Caused by Use of Undersized Circuit Breaker.Module replaced.W/910506 Ltr ML20029A3331991-02-13013 February 1991 LER 91-001-00:on 910114,Tech Spec Limiting Condition of Operation Action Was Not Satisfied After DG Removed from Standby Svc to Perform Preventive Maint.Caused by Personnel Error.Procedure Changed to Prevent recurrence.W/910213 Ltr ML20044A6881990-06-25025 June 1990 LER 90-009-00:on 900526,nonlicensed Personnel Performed Step Out of Sequence During Breaker rack-out & Caused LPCS Pump Breaker to Close.Operator Involved Counseled on Failure to Adhere to Breaker Operation procedure.W/900625 Ltr ML20043H2951990-06-15015 June 1990 LER 90-007-00:on 900516,discovered That Actions Taken for Inoperable Reactor Water Level Transmitter Not Adequate to Comply W/Requirements for Tech Spec 3.3.2.Caused by Personnel Error.Meetings Held w/personnel.W/900615 Ltr ML20043C6741990-06-0101 June 1990 LER 90-006-00:on 900502,review of Effluent Sample Analysis Revealed That Turbine Bldg Ventilation Exhaust Had Not Been Analyzed Exceeding Time Limit.Caused by Personnel Error. Training & Counseling conducted.W/900601 Ltr ML20042F2251990-05-0404 May 1990 LER 90-005-00:on 900406,discovered That Current Surveillance Practices for Stroke Testing Fresh Air Makeup Intake Valves Could Have Resulted in Unfiltered Pathway.Administrative Controls Placed on valves.W/900504 Ltr ML20012D8071990-03-22022 March 1990 LER 89-018-01:on 891215,determined That Inappropriate Quality Level Designations Applied to Class 1E Circuits, in Violation of Reg Guide 1.75.Caused by Discrepant Instrument Index Controls.Handswitch replaced.W/900228 Ltr ML20012D4801990-03-16016 March 1990 LER 90-003-00:on 900215,identified Potential Single Failure Scenario That Could Result in Unavailability of Both Core Spray Sys for Long Term post-LOCA Core Cooling.Detailed Heatup Evaluation Performed for Power bundle.W/900316 Ltr ML20012A1661990-02-28028 February 1990 LER 90-002-00:on 900124,discovered That Div II Solenoid Associated W/Secondary Containment Isolation Valve Did Not Operate During Quarterly Valve Stroke Time Tests.Caused by Procedure Inadequacy.Procedures changed.W/900227 Ltr ML20006E4521990-02-15015 February 1990 LER 89-015-01:on 891030,no Data or Evidence Found That Stroke Time Test Performed on Bettis Actuator for Isolation Damper Following Maint.Caused by Programmatic Weaknesses.New Computer Field Data Added to Work orders.W/900215 Ltr ML20006E0461990-02-0909 February 1990 LER 90-001-00:on 900112,determined That Tech Spec Reactor Coolant Cooldown Rate Limit of 100 Degrees F Exceeded in Reactor Bottom Head Drain Pipe.Caused by Programmatic Deficiencies.Incident Rept Form improved.W/900209 Ltr ML20006B8731990-01-29029 January 1990 LER 89-019-00:on 891230,total Loss of Plant Svc Water Experienced Due to Loss of Power to Supply Wells.Caused by Malfunction of Microwave Info & Control Sys.Periodic Microwave Operational Checks established.W/900129 Ltr ML20006B2781990-01-16016 January 1990 LER 89-017-00:on 890718,determined That Isolation for Postulated RWCU Blowdown Line Breaks in Piping Cold Rooms Was 80 S,Causing Plant to Operate in Unanalyzed Condition. Tech Spec Change Request Will Be submitted.W/900116 Ltr ML20005G2121990-01-12012 January 1990 LER 89-007-01:on 890508,RWCU Sys Isolated on Leak Detection Differential Flow Signal While Shifting RWCU Operation from pre-pump to post-pump Mode.Probably Caused by Inadequate Reactor Pressure.Procedure revised.W/900112 Ltr ML20005G2071990-01-12012 January 1990 LER 89-018-00:on 891215,design Basis Review of Instrumentation Determined That 71 Devices,Classified as nonsafety-related,contained in Class 1E Circuits.Caused by Level of Control on Instrument index.W/900112 Ltr ML20005D7411989-12-0606 December 1989 LER 89-016-00:on 891107,during Severe Thunderstorm,Lightning Struck Site,Causing Scram & HPCS Low Water Level Channels to Trip.Design Change Package Issued to Install Lightning Dissipation Sys on Vulnerable structures.W/891206 Ltr ML19332F0731989-11-29029 November 1989 LER 89-015-00:on 891030,no Data or Evidence Found for Stroke Time Test Required to Be Performed Following Maint on Bettis Actuator for Isolation Damper QSZ51F001.Caused by Personnel Error.Programmatic Enhancements initiated.W/891129 Ltr ML19325E6971989-10-31031 October 1989 LER 89-008-02:on 890523,two Redundant Secondary Containment Isolation Dampers Failed to Close within 4 Time Limit of Tech Spec 3.6.6.2.Caused by Malfunction of Exhaust Valves. Exhaust Valve replaced.W/891031 Ltr ML19325E6331989-10-27027 October 1989 LER 89-014-00:on 890929,RWCU Sys Isolated on Simulated Steam Line Tunnel High Temp Signal.Caused by Operator Failure to Perform self-verification Prior to Moving Bypass Switch. General Manager Held Briefings w/personnel.W/891027 Ltr ML20024F4561983-08-31031 August 1983 Updated LER 83-001/01X-2:on 830107,electrician Preparing to Route Cable Noticed Two Wall Penetrations Had Been Opened. Because Control Room Not Notified of Work,No Fire Watch in Effect.Caused by Personnel error.W/830831 Ltr ML20024E8741983-08-31031 August 1983 LER 83-108/01T-0:on 830817,radiation Monitor B Trip Setpoint Found High & Grab Samples & Analyses Started Late.Caused by Personnel Error.Personnel counseled.W/830831 Ltr ML20024E9111983-08-30030 August 1983 Updated LER 83-097/03X-1:on 830720,reactor Water Cleanup Auto Isolation Occurred.Caused by Delta Temp Channel B Indicating Temp Above Trip Point Limit.Investigation continuing.W/830830 Ltr ML20024F5091983-08-29029 August 1983 LER 83-112/03L-0:on 830730,while Troubleshooting Initiation Circuitry to Find Reason for Improper Operation of E12F087B & F025B,partial LOCA Signal Occurred.Caused by Error in Work Order.Administrative Fix underway.W/830829 Ltr ML20024F2091983-08-29029 August 1983 LER 83-111/03L-0:on 830730,during Performance of Work Order to Correct Malfunction W/Div I Isolation Reset Status lights,amphenol-type Signal Cable Connector in C/R Panel Disconnected.Caused by Personnel error.W/830829 Ltr ML20024E9311983-08-29029 August 1983 Updated LER 83-002/01X-1:on 830114,personnel Discovered Heat Detectors in Control Room Standby Fresh Air Sys Not Functionally Tested.Caused by Lack of Proper Procedure. Procedure rewritten.W/830829 Ltr ML20024F6131983-08-29029 August 1983 Updated LER 83-010/99X-2:on 830105,fire Protection Deficiencies on Redundant Raceways/Cables Discovered in Auxiliary,Turbine & Control Bldgs.Caused by Incomplete Const.Maint Work Now complete.W/830829 Ltr ML20024F6071983-08-29029 August 1983 Updated LER 82-050/99X-1:on 820806,Fire Detection Zone 2-10 Went Into Alarm Condition & Would Not Clear.Caused by Diesel Exhaust Fumes Drifting Into Corridor.Detectors Cleaned. Design Change submitted.W/830829 Ltr ML20024D8781983-07-29029 July 1983 LER 83-078/03L-0:on 830701,control Room Operators Unable to Maintain Air Receiver Pressure for Diesel Generator 11. Caused by Setpoint Drift on Relief Valves for diesel-driven & Electric motor-driven Air compressors.W/830729 Ltr ML20024D0891983-07-25025 July 1983 LER 83-079/03L-0:on 830625,auxiliary Trip Unit for High Drywell Pressure Indicated Trip Condition Yet No Reactor Protection Sys Trip Occurred.Caused by Defective Rosemount Auxiliary Trip Unit.Trip Unit replaced.W/830725 Ltr ML20024D0761983-07-25025 July 1983 LER 83-080/03L-0:on 830626,control Room Operators Experienced Problems W/Hvac Sys Involving Inadequate Cooling Capacity & Sys Losses.Partially Caused by Malfunctioning Condenser Cooling Water Flow Control valve.W/830725 Ltr ML20024B9941983-06-29029 June 1983 LER 83-072/01T-0:on 830615,operations Shift Supervisor Discovered Some Continuous Fire Watches Not Performed on 830614.Caused by Personnel Error.Personnel Reinstructed Not to Pull Fire Watch W/O approval.W/830629 Ltr ML20024C4031983-06-27027 June 1983 LER 83-071/03L-0:on 830607,RHR Shutdown Cooling Mode Isolated When Valve E12-F009 Closed.Caused by Blown Fuse. Fuse replaced.W/830627 Ltr ML20024B9981983-06-24024 June 1983 LER 83-070/03L-0:on 830525,reactor Water Cleanup Sys Isolated When Standby Liquid Control Pump B Breaker Closed. Caused by Personnel Error.Isolation Signal reset.W/830624 Ltr ML20024C3121983-06-22022 June 1983 LER 83-069/03L-0:on 830523,during Attempt to Reenergize Div II Motor Operated Valves,Shutdown Cooling Mode of RHR Sys & Reactor Water Cleanup Sys Isolated.Caused by Failure to Install Power Fuses.Fuses installed.W/830622 Ltr ML20023E0441983-05-27027 May 1983 Updated LER 83-058/01X-1:on 830311,discovered That Fire Watches Not Conducted in Two Areas of Fire Detection Zone 2-19.Limiting Conditions for Operation Entered on 830227. Caused by Personnel Oversight.Zone restored.W/830527 Ltr ML20023D4331983-05-12012 May 1983 LER 83-046/03L-0:on 830412,monthly Functional Surveillance for Div I Chlorine Detection Sys Not Performed by 830410. Caused by Personnel Error ML20023D4771983-05-11011 May 1983 LER 83-052/03L-0:on 830411,while Reviewing Vessel Head Installation Work Package,Discovered Head Flange/Vessel Flange Thermocouples Not Physically Reinstalled During Insulation Installation.Cause Under Evaluation ML20023C5591983-05-0909 May 1983 Updated LER 83-031/99X-1:on 830113,fire Rated Door OC104 Blocked Open to Route Temporary Discharge Hose from Hot Machine Shop Sump to Turbine Bldg Floor Drain Sys.Caused by Inadequacy of Present Sys.Mod to Be Completed by Sept 1983 ML20023D2511983-05-0909 May 1983 LER 83-049/03L-0:on 830409,during Cold Shutdown,Diesel Generator 12 Auto Start Not Available When Alarm Actuated. Caused by Condensate Drain Valve Downstream of Tank C Not Fully Closed.Compressors Reworked ML20023C5611983-05-0909 May 1983 Updated LER 83-004/01T-1:on 830110,penetration AP-72B Found Open & Had Been Open Since 821213.Caused by Planned Maint Work & Personnel Error.Hourly Fire Watch Established. Penetration to Be Resealed by 830630 ML20023C5511983-05-0909 May 1983 LER 83-048/01T-0:on 830423,suppression Pool Level Instrumentation Discovered Not Functionally Tested Since 830409.Cause Under Investigation.Instrumentation Tested Satisfactorily within 8 H ML20023B5541983-04-28028 April 1983 LER 83-060/03L-0:on 830329,during Cold Shutdown,Load Shedding & Div I LSS Sequencing Panel Failure Alarm Actuated.Caused by Failure of 15-volt Dc Power Supply Used to Power Solid State Electronics for Sys Logic ML20023B6731983-04-27027 April 1983 LER 83-061/03L-0:on 830328,one Solenoid Operated Freon Valve Found W/Blown Gasket.Caused by Defective Alco Controls Solenoid Operated Gasket.Valve Reworked W/Valve Repair Kit & New Gasket Installed ML20028G6031983-02-11011 February 1983 LER 83-019/03L-0:on 830112 & 20,one Smoke Detector in Zone 1-15 & Eight Detectors in Zone 2-18 Covered During Planned Maint Functions to Prevent False Alarms or Damage to Unit. Detectors Uncovered After Maint Completed 1994-04-26
[Table view] Category:RO)
MONTHYEARML20029D0371994-04-26026 April 1994 LER 94-004-00:on 940324,found Five Slow Rods While Scram Time Testing Was Being Performed.Caused by Contamination of Internal Scram Solenoid Pilot Valve Head Assemblies. Corrective Action:Install New Head assemblies.W/940426 Ltr ML20046C3991993-08-0606 August 1993 LER 92-009-01:on 920509,observed That Some of Fuel Rod Compression Springs Compressed More than Expected for Assembly Exposure Achieved.Max Envelope Size of Lower Tie Plate Will Be reduced.W/930806 Ltr ML20045G7911993-07-0808 July 1993 LER 93-005-00:on 930608,indicated That Response Time Test for RCIC Low Steam Pressure Isolation Instrumentation Invalid.Caused by Inappropriate Test Method.Procedures Governing Method of Testing Will Be revised.W/930708 Ltr ML20045E9601993-06-30030 June 1993 LER 92-017-02:on 920804,reactor Scrammed Due to Low Primary Water Tank Level Signal.Implemented Minor Change Package Which Will Install DC to DC Converter Between 24 Volt DC Power Supply & Pw Tank Level transmitters.W/930630 Ltr ML20045C5261993-06-16016 June 1993 LER 93-004-00:on 930517,inboard Containment Isolation Valve Which Supplies Steam to RCIC Sys Automatically Isolated Due to Topaz Inverter Failure.Calibr Instructions & PM Program Will Be reviewed.W/930616 Ltr ML20045A0151993-05-28028 May 1993 LER 92-011-02:on 920608,determined That Design Inadequacies Could Result in Exceeding 10CFR100 Limits.Caused by Failure of Original Design to Specify leak-tight Const for Fan Housing.Shaft Seal Design installed.W/930528 Ltr ML20024G9701991-05-0606 May 1991 LER 91-002-00:on 910406,operating Module Breaker in Automatic Turbine Tester Circuitry Tripped Open,Deenergizing Control Solenoid for change-over Valve.Caused by Use of Undersized Circuit Breaker.Module replaced.W/910506 Ltr ML20029A3331991-02-13013 February 1991 LER 91-001-00:on 910114,Tech Spec Limiting Condition of Operation Action Was Not Satisfied After DG Removed from Standby Svc to Perform Preventive Maint.Caused by Personnel Error.Procedure Changed to Prevent recurrence.W/910213 Ltr ML20044A6881990-06-25025 June 1990 LER 90-009-00:on 900526,nonlicensed Personnel Performed Step Out of Sequence During Breaker rack-out & Caused LPCS Pump Breaker to Close.Operator Involved Counseled on Failure to Adhere to Breaker Operation procedure.W/900625 Ltr ML20043H2951990-06-15015 June 1990 LER 90-007-00:on 900516,discovered That Actions Taken for Inoperable Reactor Water Level Transmitter Not Adequate to Comply W/Requirements for Tech Spec 3.3.2.Caused by Personnel Error.Meetings Held w/personnel.W/900615 Ltr ML20043C6741990-06-0101 June 1990 LER 90-006-00:on 900502,review of Effluent Sample Analysis Revealed That Turbine Bldg Ventilation Exhaust Had Not Been Analyzed Exceeding Time Limit.Caused by Personnel Error. Training & Counseling conducted.W/900601 Ltr ML20042F2251990-05-0404 May 1990 LER 90-005-00:on 900406,discovered That Current Surveillance Practices for Stroke Testing Fresh Air Makeup Intake Valves Could Have Resulted in Unfiltered Pathway.Administrative Controls Placed on valves.W/900504 Ltr ML20012D8071990-03-22022 March 1990 LER 89-018-01:on 891215,determined That Inappropriate Quality Level Designations Applied to Class 1E Circuits, in Violation of Reg Guide 1.75.Caused by Discrepant Instrument Index Controls.Handswitch replaced.W/900228 Ltr ML20012D4801990-03-16016 March 1990 LER 90-003-00:on 900215,identified Potential Single Failure Scenario That Could Result in Unavailability of Both Core Spray Sys for Long Term post-LOCA Core Cooling.Detailed Heatup Evaluation Performed for Power bundle.W/900316 Ltr ML20012A1661990-02-28028 February 1990 LER 90-002-00:on 900124,discovered That Div II Solenoid Associated W/Secondary Containment Isolation Valve Did Not Operate During Quarterly Valve Stroke Time Tests.Caused by Procedure Inadequacy.Procedures changed.W/900227 Ltr ML20006E4521990-02-15015 February 1990 LER 89-015-01:on 891030,no Data or Evidence Found That Stroke Time Test Performed on Bettis Actuator for Isolation Damper Following Maint.Caused by Programmatic Weaknesses.New Computer Field Data Added to Work orders.W/900215 Ltr ML20006E0461990-02-0909 February 1990 LER 90-001-00:on 900112,determined That Tech Spec Reactor Coolant Cooldown Rate Limit of 100 Degrees F Exceeded in Reactor Bottom Head Drain Pipe.Caused by Programmatic Deficiencies.Incident Rept Form improved.W/900209 Ltr ML20006B8731990-01-29029 January 1990 LER 89-019-00:on 891230,total Loss of Plant Svc Water Experienced Due to Loss of Power to Supply Wells.Caused by Malfunction of Microwave Info & Control Sys.Periodic Microwave Operational Checks established.W/900129 Ltr ML20006B2781990-01-16016 January 1990 LER 89-017-00:on 890718,determined That Isolation for Postulated RWCU Blowdown Line Breaks in Piping Cold Rooms Was 80 S,Causing Plant to Operate in Unanalyzed Condition. Tech Spec Change Request Will Be submitted.W/900116 Ltr ML20005G2121990-01-12012 January 1990 LER 89-007-01:on 890508,RWCU Sys Isolated on Leak Detection Differential Flow Signal While Shifting RWCU Operation from pre-pump to post-pump Mode.Probably Caused by Inadequate Reactor Pressure.Procedure revised.W/900112 Ltr ML20005G2071990-01-12012 January 1990 LER 89-018-00:on 891215,design Basis Review of Instrumentation Determined That 71 Devices,Classified as nonsafety-related,contained in Class 1E Circuits.Caused by Level of Control on Instrument index.W/900112 Ltr ML20005D7411989-12-0606 December 1989 LER 89-016-00:on 891107,during Severe Thunderstorm,Lightning Struck Site,Causing Scram & HPCS Low Water Level Channels to Trip.Design Change Package Issued to Install Lightning Dissipation Sys on Vulnerable structures.W/891206 Ltr ML19332F0731989-11-29029 November 1989 LER 89-015-00:on 891030,no Data or Evidence Found for Stroke Time Test Required to Be Performed Following Maint on Bettis Actuator for Isolation Damper QSZ51F001.Caused by Personnel Error.Programmatic Enhancements initiated.W/891129 Ltr ML19325E6971989-10-31031 October 1989 LER 89-008-02:on 890523,two Redundant Secondary Containment Isolation Dampers Failed to Close within 4 Time Limit of Tech Spec 3.6.6.2.Caused by Malfunction of Exhaust Valves. Exhaust Valve replaced.W/891031 Ltr ML19325E6331989-10-27027 October 1989 LER 89-014-00:on 890929,RWCU Sys Isolated on Simulated Steam Line Tunnel High Temp Signal.Caused by Operator Failure to Perform self-verification Prior to Moving Bypass Switch. General Manager Held Briefings w/personnel.W/891027 Ltr ML20024F4561983-08-31031 August 1983 Updated LER 83-001/01X-2:on 830107,electrician Preparing to Route Cable Noticed Two Wall Penetrations Had Been Opened. Because Control Room Not Notified of Work,No Fire Watch in Effect.Caused by Personnel error.W/830831 Ltr ML20024E8741983-08-31031 August 1983 LER 83-108/01T-0:on 830817,radiation Monitor B Trip Setpoint Found High & Grab Samples & Analyses Started Late.Caused by Personnel Error.Personnel counseled.W/830831 Ltr ML20024E9111983-08-30030 August 1983 Updated LER 83-097/03X-1:on 830720,reactor Water Cleanup Auto Isolation Occurred.Caused by Delta Temp Channel B Indicating Temp Above Trip Point Limit.Investigation continuing.W/830830 Ltr ML20024F5091983-08-29029 August 1983 LER 83-112/03L-0:on 830730,while Troubleshooting Initiation Circuitry to Find Reason for Improper Operation of E12F087B & F025B,partial LOCA Signal Occurred.Caused by Error in Work Order.Administrative Fix underway.W/830829 Ltr ML20024F2091983-08-29029 August 1983 LER 83-111/03L-0:on 830730,during Performance of Work Order to Correct Malfunction W/Div I Isolation Reset Status lights,amphenol-type Signal Cable Connector in C/R Panel Disconnected.Caused by Personnel error.W/830829 Ltr ML20024E9311983-08-29029 August 1983 Updated LER 83-002/01X-1:on 830114,personnel Discovered Heat Detectors in Control Room Standby Fresh Air Sys Not Functionally Tested.Caused by Lack of Proper Procedure. Procedure rewritten.W/830829 Ltr ML20024F6131983-08-29029 August 1983 Updated LER 83-010/99X-2:on 830105,fire Protection Deficiencies on Redundant Raceways/Cables Discovered in Auxiliary,Turbine & Control Bldgs.Caused by Incomplete Const.Maint Work Now complete.W/830829 Ltr ML20024F6071983-08-29029 August 1983 Updated LER 82-050/99X-1:on 820806,Fire Detection Zone 2-10 Went Into Alarm Condition & Would Not Clear.Caused by Diesel Exhaust Fumes Drifting Into Corridor.Detectors Cleaned. Design Change submitted.W/830829 Ltr ML20024D8781983-07-29029 July 1983 LER 83-078/03L-0:on 830701,control Room Operators Unable to Maintain Air Receiver Pressure for Diesel Generator 11. Caused by Setpoint Drift on Relief Valves for diesel-driven & Electric motor-driven Air compressors.W/830729 Ltr ML20024D0891983-07-25025 July 1983 LER 83-079/03L-0:on 830625,auxiliary Trip Unit for High Drywell Pressure Indicated Trip Condition Yet No Reactor Protection Sys Trip Occurred.Caused by Defective Rosemount Auxiliary Trip Unit.Trip Unit replaced.W/830725 Ltr ML20024D0761983-07-25025 July 1983 LER 83-080/03L-0:on 830626,control Room Operators Experienced Problems W/Hvac Sys Involving Inadequate Cooling Capacity & Sys Losses.Partially Caused by Malfunctioning Condenser Cooling Water Flow Control valve.W/830725 Ltr ML20024B9941983-06-29029 June 1983 LER 83-072/01T-0:on 830615,operations Shift Supervisor Discovered Some Continuous Fire Watches Not Performed on 830614.Caused by Personnel Error.Personnel Reinstructed Not to Pull Fire Watch W/O approval.W/830629 Ltr ML20024C4031983-06-27027 June 1983 LER 83-071/03L-0:on 830607,RHR Shutdown Cooling Mode Isolated When Valve E12-F009 Closed.Caused by Blown Fuse. Fuse replaced.W/830627 Ltr ML20024B9981983-06-24024 June 1983 LER 83-070/03L-0:on 830525,reactor Water Cleanup Sys Isolated When Standby Liquid Control Pump B Breaker Closed. Caused by Personnel Error.Isolation Signal reset.W/830624 Ltr ML20024C3121983-06-22022 June 1983 LER 83-069/03L-0:on 830523,during Attempt to Reenergize Div II Motor Operated Valves,Shutdown Cooling Mode of RHR Sys & Reactor Water Cleanup Sys Isolated.Caused by Failure to Install Power Fuses.Fuses installed.W/830622 Ltr ML20023E0441983-05-27027 May 1983 Updated LER 83-058/01X-1:on 830311,discovered That Fire Watches Not Conducted in Two Areas of Fire Detection Zone 2-19.Limiting Conditions for Operation Entered on 830227. Caused by Personnel Oversight.Zone restored.W/830527 Ltr ML20023D4331983-05-12012 May 1983 LER 83-046/03L-0:on 830412,monthly Functional Surveillance for Div I Chlorine Detection Sys Not Performed by 830410. Caused by Personnel Error ML20023D4771983-05-11011 May 1983 LER 83-052/03L-0:on 830411,while Reviewing Vessel Head Installation Work Package,Discovered Head Flange/Vessel Flange Thermocouples Not Physically Reinstalled During Insulation Installation.Cause Under Evaluation ML20023C5591983-05-0909 May 1983 Updated LER 83-031/99X-1:on 830113,fire Rated Door OC104 Blocked Open to Route Temporary Discharge Hose from Hot Machine Shop Sump to Turbine Bldg Floor Drain Sys.Caused by Inadequacy of Present Sys.Mod to Be Completed by Sept 1983 ML20023D2511983-05-0909 May 1983 LER 83-049/03L-0:on 830409,during Cold Shutdown,Diesel Generator 12 Auto Start Not Available When Alarm Actuated. Caused by Condensate Drain Valve Downstream of Tank C Not Fully Closed.Compressors Reworked ML20023C5611983-05-0909 May 1983 Updated LER 83-004/01T-1:on 830110,penetration AP-72B Found Open & Had Been Open Since 821213.Caused by Planned Maint Work & Personnel Error.Hourly Fire Watch Established. Penetration to Be Resealed by 830630 ML20023C5511983-05-0909 May 1983 LER 83-048/01T-0:on 830423,suppression Pool Level Instrumentation Discovered Not Functionally Tested Since 830409.Cause Under Investigation.Instrumentation Tested Satisfactorily within 8 H ML20023B5541983-04-28028 April 1983 LER 83-060/03L-0:on 830329,during Cold Shutdown,Load Shedding & Div I LSS Sequencing Panel Failure Alarm Actuated.Caused by Failure of 15-volt Dc Power Supply Used to Power Solid State Electronics for Sys Logic ML20023B6731983-04-27027 April 1983 LER 83-061/03L-0:on 830328,one Solenoid Operated Freon Valve Found W/Blown Gasket.Caused by Defective Alco Controls Solenoid Operated Gasket.Valve Reworked W/Valve Repair Kit & New Gasket Installed ML20028G6031983-02-11011 February 1983 LER 83-019/03L-0:on 830112 & 20,one Smoke Detector in Zone 1-15 & Eight Detectors in Zone 2-18 Covered During Planned Maint Functions to Prevent False Alarms or Damage to Unit. Detectors Uncovered After Maint Completed 1994-04-26
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217F9921999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20212F5641999-09-23023 September 1999 SER Concluding That All of ampacity-related Concerns Have Been Resolved & Licensee Provided Adequate Technical Basis to Assure That All of Thermo-Lag Fire Barrier Encl Cables Operating within Acceptable Ampacity Limits ML20211Q3171999-09-0909 September 1999 Safety Evaluation Accepting BWROG Rept, Prediction of Onset of Fission Gas Release from Fuel in Generic BWR, Dtd July 1996 ML20216E4881999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Grand Gulf Nuclear Station.With ML20211A6921999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20209J1961999-07-12012 July 1999 Special Rept 99-001:on 990528,smoke Detectors Failed to Alarm During Performance of Routine Channel Functional Testing.Applicable TRM Interim Compensatory Measure of Establishing Roving Hourly Fire Patrol Was Implemented ML20196K4981999-07-0101 July 1999 Safety Evaluation Authorizing PRR-E12-01,PRR-E21-01, PRR-P75-01,PRR-P81-01,VRR-B21-01,VRR-B21-02,VRR-E38-01 & VRR-E51-01.Concludes That Alternatives Proposed by EOI Acceptable ML20209G0691999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20196A1161999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Grand Gulf Nuclear Station.With ML20206Q4831999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Grand Gulf Nuclear Station Unit 1.With ML20206J1201999-04-30030 April 1999 Redacted ME-98-001-00, Pressure Locking & Thermal Binding Test Program on Two Gate Valves with Limitorque Actuators ML18016A9011999-04-12012 April 1999 Part 21 Rept Re Defect in Component of DSRV-16-4,Enterprise DG Sys.Caused by Potential Problem with Connecting Rod Assemblies Built Since 1986,that Have Been Converted to Use Prestressed Fasteners.Affected Rods Should Be Inspected ML20205P8771999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20207K5141999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20206T7991999-01-31031 January 1999 Iodine Revolatizitation in Grand Gulf Loca ML20207A8301998-12-31031 December 1998 1998 Annual Operating Rept for Ggns,Unit 1 ML20206R9501998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Grand Gulf Nuclear Station,Unit 1.With ML20206D7721998-12-31031 December 1998 South Mississippi Electric Power Association 1998 Annual Rept ML20198E2481998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Grand Gulf Nuclear Station,Unit 1.With ML20195F4121998-11-13013 November 1998 Rev 16 to GGNS-TOP-1A, Operational QA Manual (Oqam) ML20195C4841998-11-0606 November 1998 SER Accepting QA Program Change to Consolidate Four Existing QA Programs for Arkansas Nuclear One,Grand Gulf Nuclear Station,River Bend Station & Waterford 3 Steam Electric Station Into Single QA Program ML20195C2791998-11-0505 November 1998 BWR Feedwater Nozzle Inservice Insp Summary Rept for GGNS, NUREG-0619-00006 ML20195F4801998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Grand Gulf Nuclear Station,Unit 1.With ML20155C1351998-10-26026 October 1998 Rev B to Entergy QA Program Manual ML20154K2391998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Grand Gulf Nuclear Station Unit 1.With ML20155F1961998-09-0101 September 1998 Engineering Rept for Evaluation of BWR CR Drive Mounting Flange Cap Screw ML20153B2161998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Grand Gulf Nuclear Station,Unit 1.With ML20237B6661998-07-31031 July 1998 Monthly Operating Rept for Jul 1998 for Grand Gulf Nuclear Station,Unit 1 ML20236R0231998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Grand Gulf Nuclear Station,Unit 1 ML20155J0811998-05-31031 May 1998 10CFR50.59 SE for Period Jan 1997 - May 1998 ML20249B1251998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Grand Gulf Nuclear Station,Unit 1 ML20248B6261998-05-11011 May 1998 Rev 6 to Grand Gulf Nuclear Station COLR Safety-Related ML20217Q6701998-05-0606 May 1998 SER Approving Proposed Postponement of Beginning Augmented Exam Requirements of 10CFR50.55a(g)(6)(ii)(A)(2) at Grand Gulf for Circumferential Shell Welds for Two Operating Cycles ML20206J1271998-04-30030 April 1998 Pressure Locking Thrust Evaluation Methodology for Flexible Wedge Gate Valves ML20247F3591998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Grand Gulf Nuclear Plant,Unit 1 ML20217M8951998-04-30030 April 1998 QA Program Manual ML20217P8281998-04-0707 April 1998 Safety Evaluation Accepting Relief Authorization for Alternative to Requirements of ASME Section Xi,Subarticle IWA-5250 Bolting Exam for Plants,Per 10CFR50.55a(a)(3)(i) ML20217P0381998-04-0606 April 1998 Safety Evaluation Supporting Amend 135 to License NPF-29 ML20217A0291998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Grand Gulf Nuclear Sation,Unit 1 ML20216J4211998-03-18018 March 1998 SER Approving Alternative to Insp of Reactor Pressure Vessel Circumferential Welds for Grand Gulf Nuclear Station ML20216J2021998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Grand Gulf Nuclear Station,Unit 1 ML20203A2891998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Grand Gulf Nuclear Station ML20247B4111997-12-31031 December 1997 1997 Annual Financial Rept for South Mississippi Electric Power Association ML20203H9741997-12-31031 December 1997 1997 Annual Operating Rept, for Ggns,Unit 1 ML20198P1121997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Grand Gulf Nuclear Station,Unit 1 ML20203B5581997-12-0404 December 1997 Special Rept 97-003:on 971111,valid Failure of Div 2 EDG Occurred,Due to Jacket Water Leak.Failure Reported,Per Plant Technical Requirements Manual Section 7.7.2.2 ML20203K4031997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Grand Gulf Nuclear Station,Unit 1 ML20199H3711997-11-19019 November 1997 SER Accepting Approving Request Relief from Requirements of Section XI, Rule for Inservice Insp of NPP Components, of ASME for Current or New 10-year Inservice Insp Interval IAW 50.55(a)(3)(i) of 10CFR50 ML20199F3431997-11-18018 November 1997 SER Accepting Rev 15 of Operational Quality Assurance Manual for Grand Gulf Nuclear Station,Unit 1 1999-09-09
[Table view] |
Text
- ,- --
[ .. ~
' , , - -._/
- y.
em- *
- sv.iem eniray :
PO Box 750 t
. ER$7g:
.';g Port G boon, MS 39150 '
' Tel 601437 6470 ,
~
{ J.
s,- John G, Cesare, Jr.
7; cm,c oor .
February 15, 1990- """" '
O.S. Nuclear Regulatory Commission :
Mail Station P1-137
- Washington, D.C. 20555 ;
Attention: Document Control Desk Gentlemen:
SUBJECT:
Grand Gulf Nuclear' Station Unit 1 Docket No. 50-416 License No. NPF-29 Update on Failure to Retest Isolation Dampers Following Maintenance LER 89-015-01 '
AECM-90/0033 Attached is Licensee Event Report (LER) 89-015-01 which is a final report.
Yours truly,
'JGC:cg j Attachment cc: Mr. D. C. Hintz (w/a)
Mr. T. H. Cloninger (w/a)
Mr. R. B. McGehee (w/a)
Mr. N. S. Reynolds (w/a)
Mr. H. L. Thomas (w/o)
Mr. H. O. Christensen (w/a)
Mr. Stewart D. '!bneter (w/a)
Regional Administrator U.S. Nuclear Regulatory Commission Region II 101 Marietta St., N.W., Suite 2900 Atlanta, Georgia 30323 Mr. L. L. Kintner, Project Manager (w/a) p,. Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission f I M' *N Mail Stop 14B20 fi '
t Washington, D.C. 20555
'b 9002230191 900215 ilc PDR ADOCK 05000416 lf d,s S- PDC 6 /
l y
.. ~ .
.e q
=RC P ipe , U# =UCLtu ReoV6ATORT coMMen.o= l APPROVtD Oest 800. 3150104 l
'~ '
UCENSEE EVENT REPORT (LER) l 1
PAciLITY esanat tu DOcettiBeURADtR m raus us Grand Gulf Nuclear Station - Unit 1 0 l 5 l 0 l 0 l 0 l4 l1 16 1lorl0l5 ;
TITLE ida l Update on Failure to Retest Isolation Dampers Following Maintenance !
EVOtrT OATS (Si LER NutSER (4) REPost? DATE m CTHtR F ACf .lTIES IIfv0LVED iti MONTH DAY ytAR YEAR e 88$U , "8/uS MONTH DAY YEAR p acaLitv hawls DOCsLET NUMDERtS)
NA 0l5l0l0l0 1 l l 1 1l0 3l 0 8 9 8l9 0l1l5 0l 1 0 l2 1l5 9 l0 0 isio 1 0 io n i
,,,,,,,,,, THis RaPORT is sueMiTTED PUReuANT TO THE RsOuiReMsNTs Of to CrR I: tenece eae e, mere er rae renocae) (In "oos
- 1 m ani a m .i unieH2Hivi tuini ;
g 00
- m. mieHuus m mieHuoH X
e0 mieHu
.0.mm m senieHnw soni.Hmvin tunsi i n0i 11 i _ _ gutgsg g 4,
, ]
20.40Blelf1 Hill) 90.? SieH2HQ 00,734eH2HviintA) Jf6AA s j;[# . M 405:el(1 Hist 90.734eH2 Hill 90.734eH2HvillH56 s
_ _ ]
s 30.405deH1Hv) 90.734e H2 HilH to.73(eH2Hal l LICEN688 CONT ACT FOR THIS L8R n2)
NAME TELEPMONE NUM95R ARE A CQQg Ronald Byrd / Licensing Engineer 6 10 l1 4l3l7l-121118l2 COMPLETE ONE Leelt FOR E ACM COMPONE8st F AILURE Df 8CRISED IN THIS REPORT H31 ,
CAu$$ $YSTEM COMPO8 5NT
- NNfkO' O PR $ ' CAUSE SYSTEM COMPONENT ""hgkO' TO PR s
l I I I I I I I I I I I I I ' '
s l l l l l l l l 1 I l I l i SUPPLEMGNTAL REPORT EXPECTED 114) MONTH DAY YEAR SUOMi&SiON YES IIf yes, eemplete IXPECTRO SV04915SION QA fth NO l l. l AneTRACT tv,,n a um a.,. a. e -wr r,N.e m.ne rnm > o nel During a special review of stroke time data on October 30, 1989, no data or evidence could be found for a stroke time test that was required to be performed following maintenance on the Bettis actuator for isolation damper QSZ51F001. Further investigation of other Bettis actuator maintenance l revealed six similar cases of missing rotest documentation. It is concluded <
that the retests were not performed prior to returning the isolation dampers to operable status.
The failure to perform the stroke time tests is attributed to personnel error with programmatic deficiencies as contributing factors. Neither maintenance personnel nor licensed operators ensured that the post-maintenance stroke time tests were performed as required by plant procedures. The repetitive task program was not fully effective in that the tasks were not subject to a consistent, documented retest review process. .A new computer data field has been added to the repetitive task work orders to indicate whether or not a retest is required. If a required retest is indicated, then a form will be included in the work package to perform and document the retest. Initially, retests for each task will be determined prior to performance of the task. The retest applicability determination will remaih constant unless a change is approved in accordance with the repetitive task program procedure.
It was subsequently determined that all of the subject isolation dampers had closure times within the maximum limit of 4 seconds. Therefore, there was no reduction of the safety functions provided by the components.
NRC Peres 300 tr831 1
. Y ""
a ownsam neemavear -
- go men awaoveo o= =a vow
- m LDC88$1"!E EVENT REPORT ILERI TEXT CONT 6NUAT90N se mes sin e
,mamm m assas, meses a 6.. m e es a vaan JMD6M h&6 75M Grand Gulf Nuclear Station olsjojelol4l1l6 8l9 0 l 1l5 0 l1 0l2 or 0 l5 6 .
vert e sse ssm e meses im asame ame == mem nn ,
A. Reportable Occurrence During a special review of stroke time data on October 30, 1989, no data or evidence could be found for a stroke time test that was required to be performed following maintenance on the Bettis actuator for isolation damper QSZ51F001. Further investigation,of other Bettis actuator maintenance revealed six similar cases of missing retest docume_nt ation. It is concluded that the retests were not performed prior to returning the isolation dampers to operable status as required by Technical Specifications 4.0.5, 4.6.4.1, 4.6.6.2.a and 4.7.2.d.2.
This situation is reported pursuant to 10CFR50.73(a)(2)(1)(B).
i A.- Initial Conditions The plant was operating at 100 percent power at the time of discovery.
C. Description of Occurrence Safety-related Bettis actuators in service at Grand Gulf Nuclear Station are on a five year rebuild frequency. Periodic maintenance tasks cards are. issued to accomplish these tasks. Since 1984, Bettis actuators on thirty-nine safety-related valves / dampers have been rebuilt,under this program. During a review of stroke time data for damper QSZ51F001, which had been rebuilt during RF03, no data or evidence could be found for a stroke time test that was required to be performed prior to returning it to operable status. However, a stroke time test had since been performed by the quarterly surveillance required by Technical Specification 4.0.5 which demonstrated that the L damper closing time was within the 4 second limit.
An investigation was performed to determine if there were similar
. situations on other components. The investigation revealed that six additional dampers with rebuilt Bettis actuators had not been stroke time tested prior to restoring the dampers to operable status. The subject dampers are as follows:
Date Work Date Dampers Function Completed Tested QSZ51F001 Control Room Fresh Air Isolation 4-11-89 6-3-89
['> QSZ51F002 Control Room Fr th Air Isole'i^n 4-12-89 6-3-89 QSZ51F004 Control Room Fresh Air Isola.icn 4-12-89 6-3-89 QSZ51F011 Control Room Fresh Air Isolation 4-09-89 6-3-89 Q1T41F006 Secondary Containment Isolation 4-22-89 8-18-89 Q1M41F015 Drywell Isolation 4-19-89 10-31-89 Q1M41F016 Drywell Isolation 4-19-89 10-31-89 g'*""s** LER89015/SCMPFLR - 4 Y-2 .
o ,
p s. . uo aw6ean neematon, emanssism l <
UCEf!iSEE EVENT REPORT ILERI TEXT CONTINUATION aaaovse om an **-*
p oness.mo U sesan namnen m w n mamm m , to. .amesa e enes is
- m. .=Fert6 =v.!rr; Grand Gulf y clear Station olsl0l0lel4l1l6 8l 9 -
0 11 l5 --
Oll 0l3 OP O 15 inn n === e amais sammm mme swa manw a .
A review was conducted to ensure that stroke time tests on these i components were current. It was determined on October 31,_1989 that all had.been tested since the actuator rebuild with the exception of two drywell isolation dampers, Q1M41F015 and Q1M41F016. These two dampers were rebuilt during RF03 and are normally tested only during Operational Condition 4, Cold Shutdown. A Limiting Condition for Operation was entered for the two dampers pending a stroke time test.
The test was then performed on October 31, 1989, approximately one hour after discovering that the dampers had not been retested. The test verified that the dampers closed within the 4 second time limit.
The following reviews were conducted to provide assurance that i
safety related components subject to periodic maintenance were currently retested.
o Safety-related maintenance task cards performed within the last 4 months were reviewed against the applicable surveillance completion dates. Tasks performed after the surveillance completion dates were further reviewed to ensure that retest requirements were met.
o Safety-related components subject to surveillance testing only during Operational Condition 4, Cold Shutdown, were investigated to ensure that retest requirements were met following any preventive maintenance that was performed after the surveillance completion date.
o Safety-related maintenance task cards performed during RF03 (approximately.1,000 task cards) were reviewed to ensure that appropriate retests were completed before returning the system or component to operable state.
There were no other safety-related components identified as not being currently retested.
D. Apparent Cause The maintenance instructions for rebuilding Bettis actuators required maintenance personnel to contact the LLRT Coordinator to determine if leak rate testing was required and to contact operations to dotermine if stroke time testing was required. In addition, the procedure instructed maintenance personnel to support the retests to ensure that all required testing was performed.. The investigation determined that all required leak rate tests and most of the stroke time tests were performed following refurbishment of the actuators. However, no evidence could be found documenting that a stroke time test was performed prior to returning the subject 7 dampers to operable status.
1
' g('"" *"' LERB9015/SCMPFLR - 5 i
~
m j p
v' .. l g UCENSEE EVENT REPORT (LERI TEXT CONTINUAT60N
~ .e
.=aoves one no as-oo l'
ow nes;e w s F -m osent mass. m 6e. .umen . . i n.. v m *6 ew=
[
Grand Gulf Nuclear Station 0 ll to lo le l4 11 l6 8l 9 -
0l 1l 5 -
0 l1 0 l4 or 0 l5 !
vare . ..se wamea.-anewim. !
Stroke time tests are normally performed by operators in accordance with and documented by the applicable Operations Section surveillance [
procedures. There are no retest documentation requirements in the !
actuator rebuild procedures or on the tasks cards, which complicates j the search for documentation. Nevertheless, since no retest documents i for.the subject 7 dampers were found, it is concluded that these stroke I time tests wero not performed. ;
The failure to perform the stroke time tests is attributed to personnel i error by maintenance personnel and licensed operators. Maintenance personnel did not. ensure that stroke time tests were performed as i required by the maintenance procedure, and the Operations Shift l Supervisor f ailed to ensure that post-maintenance surveillance testing <
was performed as required by procedure 01-S-06-2, Conduct of -
Operations.
t programmatic weaknesses also contributed to the error. The maintenance :
procedure was not written in accordance with standard practices regarding maintenance / operations interface for performing retects. The i task card packages provided to operations for review, did not address additional retest requirements nor provide for documentation of completed retests. Normally, the type of periodic maintenance 'I performed under task cards (e.g., lubrication, inspection, calibration) do not require additional retests and the task cards are not subject to i the same documented retest review process as Maintenance Work Orders (MW0s). ;
P E. Supplemental Corrective Actions As an immediate action, preventive maintenance (pM) task cards,.
excluding surveillances, were retrieved from the field and retest ,
control forms, similar to those used for Mhos, were added to the task t card packages to require a documented review for retest applicability.
Surveillance tasks were excluded because any required retests for .
surveillance activities are accomplished by specific steps within the i
,. surveillance procedures.
l l
As a long term measure, a new computer data field was added to repetitive task work orders to indicate whether or not a retest is I required. If a required rotest is indicated,-a form will be included ;
{ in the work package for performing and documenting the retest.
Initially, retests for each task will be determined prior to
]
i performance of the task. The retest applicability determination will remain constant unless a change is approved in accordance with the I repetitive task program procedures, j l
g?**" *** LER89015/SCMPFLR - 6 I
., e 4-p am UCENSEE EVENT REPOMT EERI TEXT CONTINUATION v2 mm6aan asemarearenemm e.
.[
i man. .w. i
.-- m .,====== . .a .
6.. !
.... . -sam *6 r mm !
GrandiGulf Nuclear Station 8 la le l 0 l 014 11 16 819 -
Olll 5 -
3 II n I; " n Is a n . .e ,
..tr, I
Maintenance mechanics and supervisors were instructed that when a l procedure step is.not clearly understood or deviates from the normal ,
way of doing business, they are to stop and obtain clarification or a [
procedure change before proceeding. ,
r Operations Shift Supervisors were informed of their responsibility to ensure that when a safety-related system or component is returned to e service following maintenance, required tests are completed before i declaring it operable.
F. Safety Assessment All of the subject isolation dampers had closure time within the '
maximum limit of 4 seconds. Therefore, there was no reduction of the e safety functions provided by the components. '
Although no reduction of a safety function occurred, System Energy '
Resources, Inc. (SERI) realizes the potential significance of failing to perform adequate retests on components or systems following maintenance and has taken comprehensive corrective actions to strengthen programmatic weaknesses.
/
li l
i.
l l
g?oa""** LER89015/SCMPFLR - 7
_ !