|
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARML20029D0371994-04-26026 April 1994 LER 94-004-00:on 940324,found Five Slow Rods While Scram Time Testing Was Being Performed.Caused by Contamination of Internal Scram Solenoid Pilot Valve Head Assemblies. Corrective Action:Install New Head assemblies.W/940426 Ltr ML20046C3991993-08-0606 August 1993 LER 92-009-01:on 920509,observed That Some of Fuel Rod Compression Springs Compressed More than Expected for Assembly Exposure Achieved.Max Envelope Size of Lower Tie Plate Will Be reduced.W/930806 Ltr ML20045G7911993-07-0808 July 1993 LER 93-005-00:on 930608,indicated That Response Time Test for RCIC Low Steam Pressure Isolation Instrumentation Invalid.Caused by Inappropriate Test Method.Procedures Governing Method of Testing Will Be revised.W/930708 Ltr ML20045E9601993-06-30030 June 1993 LER 92-017-02:on 920804,reactor Scrammed Due to Low Primary Water Tank Level Signal.Implemented Minor Change Package Which Will Install DC to DC Converter Between 24 Volt DC Power Supply & Pw Tank Level transmitters.W/930630 Ltr ML20045C5261993-06-16016 June 1993 LER 93-004-00:on 930517,inboard Containment Isolation Valve Which Supplies Steam to RCIC Sys Automatically Isolated Due to Topaz Inverter Failure.Calibr Instructions & PM Program Will Be reviewed.W/930616 Ltr ML20045A0151993-05-28028 May 1993 LER 92-011-02:on 920608,determined That Design Inadequacies Could Result in Exceeding 10CFR100 Limits.Caused by Failure of Original Design to Specify leak-tight Const for Fan Housing.Shaft Seal Design installed.W/930528 Ltr ML20024G9701991-05-0606 May 1991 LER 91-002-00:on 910406,operating Module Breaker in Automatic Turbine Tester Circuitry Tripped Open,Deenergizing Control Solenoid for change-over Valve.Caused by Use of Undersized Circuit Breaker.Module replaced.W/910506 Ltr ML20029A3331991-02-13013 February 1991 LER 91-001-00:on 910114,Tech Spec Limiting Condition of Operation Action Was Not Satisfied After DG Removed from Standby Svc to Perform Preventive Maint.Caused by Personnel Error.Procedure Changed to Prevent recurrence.W/910213 Ltr ML20044A6881990-06-25025 June 1990 LER 90-009-00:on 900526,nonlicensed Personnel Performed Step Out of Sequence During Breaker rack-out & Caused LPCS Pump Breaker to Close.Operator Involved Counseled on Failure to Adhere to Breaker Operation procedure.W/900625 Ltr ML20043H2951990-06-15015 June 1990 LER 90-007-00:on 900516,discovered That Actions Taken for Inoperable Reactor Water Level Transmitter Not Adequate to Comply W/Requirements for Tech Spec 3.3.2.Caused by Personnel Error.Meetings Held w/personnel.W/900615 Ltr ML20043C6741990-06-0101 June 1990 LER 90-006-00:on 900502,review of Effluent Sample Analysis Revealed That Turbine Bldg Ventilation Exhaust Had Not Been Analyzed Exceeding Time Limit.Caused by Personnel Error. Training & Counseling conducted.W/900601 Ltr ML20042F2251990-05-0404 May 1990 LER 90-005-00:on 900406,discovered That Current Surveillance Practices for Stroke Testing Fresh Air Makeup Intake Valves Could Have Resulted in Unfiltered Pathway.Administrative Controls Placed on valves.W/900504 Ltr ML20012D8071990-03-22022 March 1990 LER 89-018-01:on 891215,determined That Inappropriate Quality Level Designations Applied to Class 1E Circuits, in Violation of Reg Guide 1.75.Caused by Discrepant Instrument Index Controls.Handswitch replaced.W/900228 Ltr ML20012D4801990-03-16016 March 1990 LER 90-003-00:on 900215,identified Potential Single Failure Scenario That Could Result in Unavailability of Both Core Spray Sys for Long Term post-LOCA Core Cooling.Detailed Heatup Evaluation Performed for Power bundle.W/900316 Ltr ML20012A1661990-02-28028 February 1990 LER 90-002-00:on 900124,discovered That Div II Solenoid Associated W/Secondary Containment Isolation Valve Did Not Operate During Quarterly Valve Stroke Time Tests.Caused by Procedure Inadequacy.Procedures changed.W/900227 Ltr ML20006E4521990-02-15015 February 1990 LER 89-015-01:on 891030,no Data or Evidence Found That Stroke Time Test Performed on Bettis Actuator for Isolation Damper Following Maint.Caused by Programmatic Weaknesses.New Computer Field Data Added to Work orders.W/900215 Ltr ML20006E0461990-02-0909 February 1990 LER 90-001-00:on 900112,determined That Tech Spec Reactor Coolant Cooldown Rate Limit of 100 Degrees F Exceeded in Reactor Bottom Head Drain Pipe.Caused by Programmatic Deficiencies.Incident Rept Form improved.W/900209 Ltr ML20006B8731990-01-29029 January 1990 LER 89-019-00:on 891230,total Loss of Plant Svc Water Experienced Due to Loss of Power to Supply Wells.Caused by Malfunction of Microwave Info & Control Sys.Periodic Microwave Operational Checks established.W/900129 Ltr ML20006B2781990-01-16016 January 1990 LER 89-017-00:on 890718,determined That Isolation for Postulated RWCU Blowdown Line Breaks in Piping Cold Rooms Was 80 S,Causing Plant to Operate in Unanalyzed Condition. Tech Spec Change Request Will Be submitted.W/900116 Ltr ML20005G2121990-01-12012 January 1990 LER 89-007-01:on 890508,RWCU Sys Isolated on Leak Detection Differential Flow Signal While Shifting RWCU Operation from pre-pump to post-pump Mode.Probably Caused by Inadequate Reactor Pressure.Procedure revised.W/900112 Ltr ML20005G2071990-01-12012 January 1990 LER 89-018-00:on 891215,design Basis Review of Instrumentation Determined That 71 Devices,Classified as nonsafety-related,contained in Class 1E Circuits.Caused by Level of Control on Instrument index.W/900112 Ltr ML20005D7411989-12-0606 December 1989 LER 89-016-00:on 891107,during Severe Thunderstorm,Lightning Struck Site,Causing Scram & HPCS Low Water Level Channels to Trip.Design Change Package Issued to Install Lightning Dissipation Sys on Vulnerable structures.W/891206 Ltr ML19332F0731989-11-29029 November 1989 LER 89-015-00:on 891030,no Data or Evidence Found for Stroke Time Test Required to Be Performed Following Maint on Bettis Actuator for Isolation Damper QSZ51F001.Caused by Personnel Error.Programmatic Enhancements initiated.W/891129 Ltr ML19325E6971989-10-31031 October 1989 LER 89-008-02:on 890523,two Redundant Secondary Containment Isolation Dampers Failed to Close within 4 Time Limit of Tech Spec 3.6.6.2.Caused by Malfunction of Exhaust Valves. Exhaust Valve replaced.W/891031 Ltr ML19325E6331989-10-27027 October 1989 LER 89-014-00:on 890929,RWCU Sys Isolated on Simulated Steam Line Tunnel High Temp Signal.Caused by Operator Failure to Perform self-verification Prior to Moving Bypass Switch. General Manager Held Briefings w/personnel.W/891027 Ltr ML20024F4561983-08-31031 August 1983 Updated LER 83-001/01X-2:on 830107,electrician Preparing to Route Cable Noticed Two Wall Penetrations Had Been Opened. Because Control Room Not Notified of Work,No Fire Watch in Effect.Caused by Personnel error.W/830831 Ltr ML20024E8741983-08-31031 August 1983 LER 83-108/01T-0:on 830817,radiation Monitor B Trip Setpoint Found High & Grab Samples & Analyses Started Late.Caused by Personnel Error.Personnel counseled.W/830831 Ltr ML20024E9111983-08-30030 August 1983 Updated LER 83-097/03X-1:on 830720,reactor Water Cleanup Auto Isolation Occurred.Caused by Delta Temp Channel B Indicating Temp Above Trip Point Limit.Investigation continuing.W/830830 Ltr ML20024F5091983-08-29029 August 1983 LER 83-112/03L-0:on 830730,while Troubleshooting Initiation Circuitry to Find Reason for Improper Operation of E12F087B & F025B,partial LOCA Signal Occurred.Caused by Error in Work Order.Administrative Fix underway.W/830829 Ltr ML20024F2091983-08-29029 August 1983 LER 83-111/03L-0:on 830730,during Performance of Work Order to Correct Malfunction W/Div I Isolation Reset Status lights,amphenol-type Signal Cable Connector in C/R Panel Disconnected.Caused by Personnel error.W/830829 Ltr ML20024E9311983-08-29029 August 1983 Updated LER 83-002/01X-1:on 830114,personnel Discovered Heat Detectors in Control Room Standby Fresh Air Sys Not Functionally Tested.Caused by Lack of Proper Procedure. Procedure rewritten.W/830829 Ltr ML20024F6131983-08-29029 August 1983 Updated LER 83-010/99X-2:on 830105,fire Protection Deficiencies on Redundant Raceways/Cables Discovered in Auxiliary,Turbine & Control Bldgs.Caused by Incomplete Const.Maint Work Now complete.W/830829 Ltr ML20024F6071983-08-29029 August 1983 Updated LER 82-050/99X-1:on 820806,Fire Detection Zone 2-10 Went Into Alarm Condition & Would Not Clear.Caused by Diesel Exhaust Fumes Drifting Into Corridor.Detectors Cleaned. Design Change submitted.W/830829 Ltr ML20024D8781983-07-29029 July 1983 LER 83-078/03L-0:on 830701,control Room Operators Unable to Maintain Air Receiver Pressure for Diesel Generator 11. Caused by Setpoint Drift on Relief Valves for diesel-driven & Electric motor-driven Air compressors.W/830729 Ltr ML20024D0891983-07-25025 July 1983 LER 83-079/03L-0:on 830625,auxiliary Trip Unit for High Drywell Pressure Indicated Trip Condition Yet No Reactor Protection Sys Trip Occurred.Caused by Defective Rosemount Auxiliary Trip Unit.Trip Unit replaced.W/830725 Ltr ML20024D0761983-07-25025 July 1983 LER 83-080/03L-0:on 830626,control Room Operators Experienced Problems W/Hvac Sys Involving Inadequate Cooling Capacity & Sys Losses.Partially Caused by Malfunctioning Condenser Cooling Water Flow Control valve.W/830725 Ltr ML20024B9941983-06-29029 June 1983 LER 83-072/01T-0:on 830615,operations Shift Supervisor Discovered Some Continuous Fire Watches Not Performed on 830614.Caused by Personnel Error.Personnel Reinstructed Not to Pull Fire Watch W/O approval.W/830629 Ltr ML20024C4031983-06-27027 June 1983 LER 83-071/03L-0:on 830607,RHR Shutdown Cooling Mode Isolated When Valve E12-F009 Closed.Caused by Blown Fuse. Fuse replaced.W/830627 Ltr ML20024B9981983-06-24024 June 1983 LER 83-070/03L-0:on 830525,reactor Water Cleanup Sys Isolated When Standby Liquid Control Pump B Breaker Closed. Caused by Personnel Error.Isolation Signal reset.W/830624 Ltr ML20024C3121983-06-22022 June 1983 LER 83-069/03L-0:on 830523,during Attempt to Reenergize Div II Motor Operated Valves,Shutdown Cooling Mode of RHR Sys & Reactor Water Cleanup Sys Isolated.Caused by Failure to Install Power Fuses.Fuses installed.W/830622 Ltr ML20023E0441983-05-27027 May 1983 Updated LER 83-058/01X-1:on 830311,discovered That Fire Watches Not Conducted in Two Areas of Fire Detection Zone 2-19.Limiting Conditions for Operation Entered on 830227. Caused by Personnel Oversight.Zone restored.W/830527 Ltr ML20023D4331983-05-12012 May 1983 LER 83-046/03L-0:on 830412,monthly Functional Surveillance for Div I Chlorine Detection Sys Not Performed by 830410. Caused by Personnel Error ML20023D4771983-05-11011 May 1983 LER 83-052/03L-0:on 830411,while Reviewing Vessel Head Installation Work Package,Discovered Head Flange/Vessel Flange Thermocouples Not Physically Reinstalled During Insulation Installation.Cause Under Evaluation ML20023C5591983-05-0909 May 1983 Updated LER 83-031/99X-1:on 830113,fire Rated Door OC104 Blocked Open to Route Temporary Discharge Hose from Hot Machine Shop Sump to Turbine Bldg Floor Drain Sys.Caused by Inadequacy of Present Sys.Mod to Be Completed by Sept 1983 ML20023D2511983-05-0909 May 1983 LER 83-049/03L-0:on 830409,during Cold Shutdown,Diesel Generator 12 Auto Start Not Available When Alarm Actuated. Caused by Condensate Drain Valve Downstream of Tank C Not Fully Closed.Compressors Reworked ML20023C5611983-05-0909 May 1983 Updated LER 83-004/01T-1:on 830110,penetration AP-72B Found Open & Had Been Open Since 821213.Caused by Planned Maint Work & Personnel Error.Hourly Fire Watch Established. Penetration to Be Resealed by 830630 ML20023C5511983-05-0909 May 1983 LER 83-048/01T-0:on 830423,suppression Pool Level Instrumentation Discovered Not Functionally Tested Since 830409.Cause Under Investigation.Instrumentation Tested Satisfactorily within 8 H ML20023B5541983-04-28028 April 1983 LER 83-060/03L-0:on 830329,during Cold Shutdown,Load Shedding & Div I LSS Sequencing Panel Failure Alarm Actuated.Caused by Failure of 15-volt Dc Power Supply Used to Power Solid State Electronics for Sys Logic ML20023B6731983-04-27027 April 1983 LER 83-061/03L-0:on 830328,one Solenoid Operated Freon Valve Found W/Blown Gasket.Caused by Defective Alco Controls Solenoid Operated Gasket.Valve Reworked W/Valve Repair Kit & New Gasket Installed ML20028G6031983-02-11011 February 1983 LER 83-019/03L-0:on 830112 & 20,one Smoke Detector in Zone 1-15 & Eight Detectors in Zone 2-18 Covered During Planned Maint Functions to Prevent False Alarms or Damage to Unit. Detectors Uncovered After Maint Completed 1994-04-26
[Table view] Category:RO)
MONTHYEARML20029D0371994-04-26026 April 1994 LER 94-004-00:on 940324,found Five Slow Rods While Scram Time Testing Was Being Performed.Caused by Contamination of Internal Scram Solenoid Pilot Valve Head Assemblies. Corrective Action:Install New Head assemblies.W/940426 Ltr ML20046C3991993-08-0606 August 1993 LER 92-009-01:on 920509,observed That Some of Fuel Rod Compression Springs Compressed More than Expected for Assembly Exposure Achieved.Max Envelope Size of Lower Tie Plate Will Be reduced.W/930806 Ltr ML20045G7911993-07-0808 July 1993 LER 93-005-00:on 930608,indicated That Response Time Test for RCIC Low Steam Pressure Isolation Instrumentation Invalid.Caused by Inappropriate Test Method.Procedures Governing Method of Testing Will Be revised.W/930708 Ltr ML20045E9601993-06-30030 June 1993 LER 92-017-02:on 920804,reactor Scrammed Due to Low Primary Water Tank Level Signal.Implemented Minor Change Package Which Will Install DC to DC Converter Between 24 Volt DC Power Supply & Pw Tank Level transmitters.W/930630 Ltr ML20045C5261993-06-16016 June 1993 LER 93-004-00:on 930517,inboard Containment Isolation Valve Which Supplies Steam to RCIC Sys Automatically Isolated Due to Topaz Inverter Failure.Calibr Instructions & PM Program Will Be reviewed.W/930616 Ltr ML20045A0151993-05-28028 May 1993 LER 92-011-02:on 920608,determined That Design Inadequacies Could Result in Exceeding 10CFR100 Limits.Caused by Failure of Original Design to Specify leak-tight Const for Fan Housing.Shaft Seal Design installed.W/930528 Ltr ML20024G9701991-05-0606 May 1991 LER 91-002-00:on 910406,operating Module Breaker in Automatic Turbine Tester Circuitry Tripped Open,Deenergizing Control Solenoid for change-over Valve.Caused by Use of Undersized Circuit Breaker.Module replaced.W/910506 Ltr ML20029A3331991-02-13013 February 1991 LER 91-001-00:on 910114,Tech Spec Limiting Condition of Operation Action Was Not Satisfied After DG Removed from Standby Svc to Perform Preventive Maint.Caused by Personnel Error.Procedure Changed to Prevent recurrence.W/910213 Ltr ML20044A6881990-06-25025 June 1990 LER 90-009-00:on 900526,nonlicensed Personnel Performed Step Out of Sequence During Breaker rack-out & Caused LPCS Pump Breaker to Close.Operator Involved Counseled on Failure to Adhere to Breaker Operation procedure.W/900625 Ltr ML20043H2951990-06-15015 June 1990 LER 90-007-00:on 900516,discovered That Actions Taken for Inoperable Reactor Water Level Transmitter Not Adequate to Comply W/Requirements for Tech Spec 3.3.2.Caused by Personnel Error.Meetings Held w/personnel.W/900615 Ltr ML20043C6741990-06-0101 June 1990 LER 90-006-00:on 900502,review of Effluent Sample Analysis Revealed That Turbine Bldg Ventilation Exhaust Had Not Been Analyzed Exceeding Time Limit.Caused by Personnel Error. Training & Counseling conducted.W/900601 Ltr ML20042F2251990-05-0404 May 1990 LER 90-005-00:on 900406,discovered That Current Surveillance Practices for Stroke Testing Fresh Air Makeup Intake Valves Could Have Resulted in Unfiltered Pathway.Administrative Controls Placed on valves.W/900504 Ltr ML20012D8071990-03-22022 March 1990 LER 89-018-01:on 891215,determined That Inappropriate Quality Level Designations Applied to Class 1E Circuits, in Violation of Reg Guide 1.75.Caused by Discrepant Instrument Index Controls.Handswitch replaced.W/900228 Ltr ML20012D4801990-03-16016 March 1990 LER 90-003-00:on 900215,identified Potential Single Failure Scenario That Could Result in Unavailability of Both Core Spray Sys for Long Term post-LOCA Core Cooling.Detailed Heatup Evaluation Performed for Power bundle.W/900316 Ltr ML20012A1661990-02-28028 February 1990 LER 90-002-00:on 900124,discovered That Div II Solenoid Associated W/Secondary Containment Isolation Valve Did Not Operate During Quarterly Valve Stroke Time Tests.Caused by Procedure Inadequacy.Procedures changed.W/900227 Ltr ML20006E4521990-02-15015 February 1990 LER 89-015-01:on 891030,no Data or Evidence Found That Stroke Time Test Performed on Bettis Actuator for Isolation Damper Following Maint.Caused by Programmatic Weaknesses.New Computer Field Data Added to Work orders.W/900215 Ltr ML20006E0461990-02-0909 February 1990 LER 90-001-00:on 900112,determined That Tech Spec Reactor Coolant Cooldown Rate Limit of 100 Degrees F Exceeded in Reactor Bottom Head Drain Pipe.Caused by Programmatic Deficiencies.Incident Rept Form improved.W/900209 Ltr ML20006B8731990-01-29029 January 1990 LER 89-019-00:on 891230,total Loss of Plant Svc Water Experienced Due to Loss of Power to Supply Wells.Caused by Malfunction of Microwave Info & Control Sys.Periodic Microwave Operational Checks established.W/900129 Ltr ML20006B2781990-01-16016 January 1990 LER 89-017-00:on 890718,determined That Isolation for Postulated RWCU Blowdown Line Breaks in Piping Cold Rooms Was 80 S,Causing Plant to Operate in Unanalyzed Condition. Tech Spec Change Request Will Be submitted.W/900116 Ltr ML20005G2121990-01-12012 January 1990 LER 89-007-01:on 890508,RWCU Sys Isolated on Leak Detection Differential Flow Signal While Shifting RWCU Operation from pre-pump to post-pump Mode.Probably Caused by Inadequate Reactor Pressure.Procedure revised.W/900112 Ltr ML20005G2071990-01-12012 January 1990 LER 89-018-00:on 891215,design Basis Review of Instrumentation Determined That 71 Devices,Classified as nonsafety-related,contained in Class 1E Circuits.Caused by Level of Control on Instrument index.W/900112 Ltr ML20005D7411989-12-0606 December 1989 LER 89-016-00:on 891107,during Severe Thunderstorm,Lightning Struck Site,Causing Scram & HPCS Low Water Level Channels to Trip.Design Change Package Issued to Install Lightning Dissipation Sys on Vulnerable structures.W/891206 Ltr ML19332F0731989-11-29029 November 1989 LER 89-015-00:on 891030,no Data or Evidence Found for Stroke Time Test Required to Be Performed Following Maint on Bettis Actuator for Isolation Damper QSZ51F001.Caused by Personnel Error.Programmatic Enhancements initiated.W/891129 Ltr ML19325E6971989-10-31031 October 1989 LER 89-008-02:on 890523,two Redundant Secondary Containment Isolation Dampers Failed to Close within 4 Time Limit of Tech Spec 3.6.6.2.Caused by Malfunction of Exhaust Valves. Exhaust Valve replaced.W/891031 Ltr ML19325E6331989-10-27027 October 1989 LER 89-014-00:on 890929,RWCU Sys Isolated on Simulated Steam Line Tunnel High Temp Signal.Caused by Operator Failure to Perform self-verification Prior to Moving Bypass Switch. General Manager Held Briefings w/personnel.W/891027 Ltr ML20024F4561983-08-31031 August 1983 Updated LER 83-001/01X-2:on 830107,electrician Preparing to Route Cable Noticed Two Wall Penetrations Had Been Opened. Because Control Room Not Notified of Work,No Fire Watch in Effect.Caused by Personnel error.W/830831 Ltr ML20024E8741983-08-31031 August 1983 LER 83-108/01T-0:on 830817,radiation Monitor B Trip Setpoint Found High & Grab Samples & Analyses Started Late.Caused by Personnel Error.Personnel counseled.W/830831 Ltr ML20024E9111983-08-30030 August 1983 Updated LER 83-097/03X-1:on 830720,reactor Water Cleanup Auto Isolation Occurred.Caused by Delta Temp Channel B Indicating Temp Above Trip Point Limit.Investigation continuing.W/830830 Ltr ML20024F5091983-08-29029 August 1983 LER 83-112/03L-0:on 830730,while Troubleshooting Initiation Circuitry to Find Reason for Improper Operation of E12F087B & F025B,partial LOCA Signal Occurred.Caused by Error in Work Order.Administrative Fix underway.W/830829 Ltr ML20024F2091983-08-29029 August 1983 LER 83-111/03L-0:on 830730,during Performance of Work Order to Correct Malfunction W/Div I Isolation Reset Status lights,amphenol-type Signal Cable Connector in C/R Panel Disconnected.Caused by Personnel error.W/830829 Ltr ML20024E9311983-08-29029 August 1983 Updated LER 83-002/01X-1:on 830114,personnel Discovered Heat Detectors in Control Room Standby Fresh Air Sys Not Functionally Tested.Caused by Lack of Proper Procedure. Procedure rewritten.W/830829 Ltr ML20024F6131983-08-29029 August 1983 Updated LER 83-010/99X-2:on 830105,fire Protection Deficiencies on Redundant Raceways/Cables Discovered in Auxiliary,Turbine & Control Bldgs.Caused by Incomplete Const.Maint Work Now complete.W/830829 Ltr ML20024F6071983-08-29029 August 1983 Updated LER 82-050/99X-1:on 820806,Fire Detection Zone 2-10 Went Into Alarm Condition & Would Not Clear.Caused by Diesel Exhaust Fumes Drifting Into Corridor.Detectors Cleaned. Design Change submitted.W/830829 Ltr ML20024D8781983-07-29029 July 1983 LER 83-078/03L-0:on 830701,control Room Operators Unable to Maintain Air Receiver Pressure for Diesel Generator 11. Caused by Setpoint Drift on Relief Valves for diesel-driven & Electric motor-driven Air compressors.W/830729 Ltr ML20024D0891983-07-25025 July 1983 LER 83-079/03L-0:on 830625,auxiliary Trip Unit for High Drywell Pressure Indicated Trip Condition Yet No Reactor Protection Sys Trip Occurred.Caused by Defective Rosemount Auxiliary Trip Unit.Trip Unit replaced.W/830725 Ltr ML20024D0761983-07-25025 July 1983 LER 83-080/03L-0:on 830626,control Room Operators Experienced Problems W/Hvac Sys Involving Inadequate Cooling Capacity & Sys Losses.Partially Caused by Malfunctioning Condenser Cooling Water Flow Control valve.W/830725 Ltr ML20024B9941983-06-29029 June 1983 LER 83-072/01T-0:on 830615,operations Shift Supervisor Discovered Some Continuous Fire Watches Not Performed on 830614.Caused by Personnel Error.Personnel Reinstructed Not to Pull Fire Watch W/O approval.W/830629 Ltr ML20024C4031983-06-27027 June 1983 LER 83-071/03L-0:on 830607,RHR Shutdown Cooling Mode Isolated When Valve E12-F009 Closed.Caused by Blown Fuse. Fuse replaced.W/830627 Ltr ML20024B9981983-06-24024 June 1983 LER 83-070/03L-0:on 830525,reactor Water Cleanup Sys Isolated When Standby Liquid Control Pump B Breaker Closed. Caused by Personnel Error.Isolation Signal reset.W/830624 Ltr ML20024C3121983-06-22022 June 1983 LER 83-069/03L-0:on 830523,during Attempt to Reenergize Div II Motor Operated Valves,Shutdown Cooling Mode of RHR Sys & Reactor Water Cleanup Sys Isolated.Caused by Failure to Install Power Fuses.Fuses installed.W/830622 Ltr ML20023E0441983-05-27027 May 1983 Updated LER 83-058/01X-1:on 830311,discovered That Fire Watches Not Conducted in Two Areas of Fire Detection Zone 2-19.Limiting Conditions for Operation Entered on 830227. Caused by Personnel Oversight.Zone restored.W/830527 Ltr ML20023D4331983-05-12012 May 1983 LER 83-046/03L-0:on 830412,monthly Functional Surveillance for Div I Chlorine Detection Sys Not Performed by 830410. Caused by Personnel Error ML20023D4771983-05-11011 May 1983 LER 83-052/03L-0:on 830411,while Reviewing Vessel Head Installation Work Package,Discovered Head Flange/Vessel Flange Thermocouples Not Physically Reinstalled During Insulation Installation.Cause Under Evaluation ML20023C5591983-05-0909 May 1983 Updated LER 83-031/99X-1:on 830113,fire Rated Door OC104 Blocked Open to Route Temporary Discharge Hose from Hot Machine Shop Sump to Turbine Bldg Floor Drain Sys.Caused by Inadequacy of Present Sys.Mod to Be Completed by Sept 1983 ML20023D2511983-05-0909 May 1983 LER 83-049/03L-0:on 830409,during Cold Shutdown,Diesel Generator 12 Auto Start Not Available When Alarm Actuated. Caused by Condensate Drain Valve Downstream of Tank C Not Fully Closed.Compressors Reworked ML20023C5611983-05-0909 May 1983 Updated LER 83-004/01T-1:on 830110,penetration AP-72B Found Open & Had Been Open Since 821213.Caused by Planned Maint Work & Personnel Error.Hourly Fire Watch Established. Penetration to Be Resealed by 830630 ML20023C5511983-05-0909 May 1983 LER 83-048/01T-0:on 830423,suppression Pool Level Instrumentation Discovered Not Functionally Tested Since 830409.Cause Under Investigation.Instrumentation Tested Satisfactorily within 8 H ML20023B5541983-04-28028 April 1983 LER 83-060/03L-0:on 830329,during Cold Shutdown,Load Shedding & Div I LSS Sequencing Panel Failure Alarm Actuated.Caused by Failure of 15-volt Dc Power Supply Used to Power Solid State Electronics for Sys Logic ML20023B6731983-04-27027 April 1983 LER 83-061/03L-0:on 830328,one Solenoid Operated Freon Valve Found W/Blown Gasket.Caused by Defective Alco Controls Solenoid Operated Gasket.Valve Reworked W/Valve Repair Kit & New Gasket Installed ML20028G6031983-02-11011 February 1983 LER 83-019/03L-0:on 830112 & 20,one Smoke Detector in Zone 1-15 & Eight Detectors in Zone 2-18 Covered During Planned Maint Functions to Prevent False Alarms or Damage to Unit. Detectors Uncovered After Maint Completed 1994-04-26
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217F9921999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20212F5641999-09-23023 September 1999 SER Concluding That All of ampacity-related Concerns Have Been Resolved & Licensee Provided Adequate Technical Basis to Assure That All of Thermo-Lag Fire Barrier Encl Cables Operating within Acceptable Ampacity Limits ML20211Q3171999-09-0909 September 1999 Safety Evaluation Accepting BWROG Rept, Prediction of Onset of Fission Gas Release from Fuel in Generic BWR, Dtd July 1996 ML20216E4881999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Grand Gulf Nuclear Station.With ML20211A6921999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20209J1961999-07-12012 July 1999 Special Rept 99-001:on 990528,smoke Detectors Failed to Alarm During Performance of Routine Channel Functional Testing.Applicable TRM Interim Compensatory Measure of Establishing Roving Hourly Fire Patrol Was Implemented ML20196K4981999-07-0101 July 1999 Safety Evaluation Authorizing PRR-E12-01,PRR-E21-01, PRR-P75-01,PRR-P81-01,VRR-B21-01,VRR-B21-02,VRR-E38-01 & VRR-E51-01.Concludes That Alternatives Proposed by EOI Acceptable ML20209G0691999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20196A1161999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Grand Gulf Nuclear Station.With ML20206Q4831999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Grand Gulf Nuclear Station Unit 1.With ML20206J1201999-04-30030 April 1999 Redacted ME-98-001-00, Pressure Locking & Thermal Binding Test Program on Two Gate Valves with Limitorque Actuators ML18016A9011999-04-12012 April 1999 Part 21 Rept Re Defect in Component of DSRV-16-4,Enterprise DG Sys.Caused by Potential Problem with Connecting Rod Assemblies Built Since 1986,that Have Been Converted to Use Prestressed Fasteners.Affected Rods Should Be Inspected ML20205P8771999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20207K5141999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Grand Gulf Nuclear Station,Unit 1.With ML20206T7991999-01-31031 January 1999 Iodine Revolatizitation in Grand Gulf Loca ML20207A8301998-12-31031 December 1998 1998 Annual Operating Rept for Ggns,Unit 1 ML20206R9501998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Grand Gulf Nuclear Station,Unit 1.With ML20206D7721998-12-31031 December 1998 South Mississippi Electric Power Association 1998 Annual Rept ML20198E2481998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Grand Gulf Nuclear Station,Unit 1.With ML20195F4121998-11-13013 November 1998 Rev 16 to GGNS-TOP-1A, Operational QA Manual (Oqam) ML20195C4841998-11-0606 November 1998 SER Accepting QA Program Change to Consolidate Four Existing QA Programs for Arkansas Nuclear One,Grand Gulf Nuclear Station,River Bend Station & Waterford 3 Steam Electric Station Into Single QA Program ML20195C2791998-11-0505 November 1998 BWR Feedwater Nozzle Inservice Insp Summary Rept for GGNS, NUREG-0619-00006 ML20195F4801998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Grand Gulf Nuclear Station,Unit 1.With ML20155C1351998-10-26026 October 1998 Rev B to Entergy QA Program Manual ML20154K2391998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Grand Gulf Nuclear Station Unit 1.With ML20155F1961998-09-0101 September 1998 Engineering Rept for Evaluation of BWR CR Drive Mounting Flange Cap Screw ML20153B2161998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Grand Gulf Nuclear Station,Unit 1.With ML20237B6661998-07-31031 July 1998 Monthly Operating Rept for Jul 1998 for Grand Gulf Nuclear Station,Unit 1 ML20236R0231998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Grand Gulf Nuclear Station,Unit 1 ML20155J0811998-05-31031 May 1998 10CFR50.59 SE for Period Jan 1997 - May 1998 ML20249B1251998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Grand Gulf Nuclear Station,Unit 1 ML20248B6261998-05-11011 May 1998 Rev 6 to Grand Gulf Nuclear Station COLR Safety-Related ML20217Q6701998-05-0606 May 1998 SER Approving Proposed Postponement of Beginning Augmented Exam Requirements of 10CFR50.55a(g)(6)(ii)(A)(2) at Grand Gulf for Circumferential Shell Welds for Two Operating Cycles ML20206J1271998-04-30030 April 1998 Pressure Locking Thrust Evaluation Methodology for Flexible Wedge Gate Valves ML20247F3591998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Grand Gulf Nuclear Plant,Unit 1 ML20217M8951998-04-30030 April 1998 QA Program Manual ML20217P8281998-04-0707 April 1998 Safety Evaluation Accepting Relief Authorization for Alternative to Requirements of ASME Section Xi,Subarticle IWA-5250 Bolting Exam for Plants,Per 10CFR50.55a(a)(3)(i) ML20217P0381998-04-0606 April 1998 Safety Evaluation Supporting Amend 135 to License NPF-29 ML20217A0291998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Grand Gulf Nuclear Sation,Unit 1 ML20216J4211998-03-18018 March 1998 SER Approving Alternative to Insp of Reactor Pressure Vessel Circumferential Welds for Grand Gulf Nuclear Station ML20216J2021998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Grand Gulf Nuclear Station,Unit 1 ML20203A2891998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Grand Gulf Nuclear Station ML20247B4111997-12-31031 December 1997 1997 Annual Financial Rept for South Mississippi Electric Power Association ML20203H9741997-12-31031 December 1997 1997 Annual Operating Rept, for Ggns,Unit 1 ML20198P1121997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Grand Gulf Nuclear Station,Unit 1 ML20203B5581997-12-0404 December 1997 Special Rept 97-003:on 971111,valid Failure of Div 2 EDG Occurred,Due to Jacket Water Leak.Failure Reported,Per Plant Technical Requirements Manual Section 7.7.2.2 ML20203K4031997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Grand Gulf Nuclear Station,Unit 1 ML20199H3711997-11-19019 November 1997 SER Accepting Approving Request Relief from Requirements of Section XI, Rule for Inservice Insp of NPP Components, of ASME for Current or New 10-year Inservice Insp Interval IAW 50.55(a)(3)(i) of 10CFR50 ML20199F3431997-11-18018 November 1997 SER Accepting Rev 15 of Operational Quality Assurance Manual for Grand Gulf Nuclear Station,Unit 1 1999-09-09
[Table view] |
Text
. . .
~
_j{ ~ ~ l e \..
-) i 4
m b! System g;3ra" Enerov-
"U#'
Port c>oson us 39'so -
Tel 601437 6809.
' William T. Cottle Vce President
- Nuclear operahons .
January 29,.1990 U.S. Nuclear. Regulatory Commission Mail Station P1-137-Washington, D.C. -20555-Attention: Document Cont..ol Desk Gentlemen:
SUBJECT:
Grand Gulf Nuclear Station Unit Docket No.!50-416 License No. NPF-29 Malfunctioning' Telemetry Causes Loss of Plant Service Water and Manual Reactor Scram ;
LER-90/019-00 l AECM-90/0026 Attached is Licensee Event Report (LER) _ 89-019-00 which is a final' ]
report. '
i-
.I Yours truly, i
W V W-i
! WTC:cg l-l Attachment 1 cc: Mr. D. C. Hintz (w/a)- !
Mr. T. H. Cloninger (w/a)'_ j Mr. R. B. McGehee (w/a) {
Mr. N. S. Reynolds (w/a)
Mr. H. L. Thomas (w/o)
Mr. H. O. Christensen (w/a)
Mr. Stewart D. Ebneter (w/a)
Regional Administrator U.S. Nuclear Regulatory Commission T Region II 101 Marietta St., N.W., Suite 2900 _
j Atlanta, Georgia 30323
)/_
Mr. L. L. Kintner, Project Manager (w/a)
Office of Nuclear Reactor Regulation l U.S. Nuclear Regulatory Commission !
Mail Stop 14B20 Washington, D.C. '20555 -l LER89019/SCMPFLR - 1 90020600191900129 PDR ADOCK 05000416- n:
"- h(
S PDC X
4 Attachment to AECM-90/0026 MRC Form aos U.S. NUCLEA2 5.EOULATORY CommelmeOes M, . APPROVE) Otes NO.3106 4104
LICENSEE EVENT REPORT (LER) i DOCKET NURABER (2) PAGE (31 FACILITY Naast (1)
Grand Culf Nuclear Station - Unit 1 015l0l0l0l4l1 l6 1lOFl016 TITLE 99 Malfunctioning Telemetry Causes Loss of Plant Service Water and Manual Reactor Scram EVGNT DATE (S) LER NUGABER (4) REPORT DATE (7) OTHER F ACILITIES INVOLVED ISI MONTH DAY YEAR YEAR -
n' ' "'/[$ MONTH DAY YEAR F AcittTv hAMEs DOCKET NUMBE9(S)
NA 0 is to l0 l 0 1 l l . .I l
1l 2 3lC 8 9 8l9 0 l1l9 0l0 0l 1 2l9 9l 0 0l5toloioi l l' l THis REPORT 18 SugestTTED PURSUANT TO THE REQUIREMENTS OF 10 CPR $: (Check one or more et ene fenomg) 111)
OPf R ATING
'* 20 402th) 20 406(el X $0.73teH2Hrrt 73.71(b)
R 20.40SleH1Hil 60.35(eH1) 30.73teH2Hv) 73J11el l HO) 01 813 80 405 eH1HiH 50.aste)(2) so.73 eH2Hvii)
_ gHER , y g a,A,epc4 j 20.408(sHIHei) 60.731e H2HI) to.73(eH2HvulHA) J66A.8
_ _ _ l l 20.405teH1Hivl 60.73(el(2Hia) 00.73teH2HvillHM 20.400teHIHet 80.73ie H2HiiH 00.73(eH2 Hat LICENSEE CONTACT FOR THl$ LER (121 NAME TELEPHONE NUMBER ARE A COCE Rilev Ruffin / Licensine Specialist 61011 41317 l -1211 6 17 COMPLETE ONE LINE FOR EACH COMPO*!ENT P AILURE DESCR10ED IN THIS REPORT 113)
CAUSE SYSTEM COMPONENT
, "C' A fo0 ",TAgt n CAUSE SYSTEM COMPONENT "Mf RfD PR l I I i l i l I i I i l i I l l l l l 1 l l l l l l'l l SUPPLEMENTAL REPORT EXPECTED (14) MONTH DAY YEAR SUGMi$$10N DATE ns)
YE$ lif yes, conwere GXPECTED SuestisSION OATEI NO A88TR ACT ILimit to NOC sovaes. (e., enerommatory ritroen EMie-soece troewntren knent Ut>
On December 30, 1989, a total loss of plant Service Water (PSW) was i experienced due to a loss of power to the supply wells. Reactor power
! was reduced by decreasing recirculation flow through the reactor core
- and a reactor shutdown sequence was commenced.
l l
While reducing reactor power, the operators determined that PSW would not be readily restored and the reactor was manually scrammed.
The Reactor Core Isolation Cooling (RCIC) System was initiated for
- reactor vessel level control. The main steam line isolation valves were '
closed in accordance with procedures. This action caused a high l
pressure scram signal and an ATWS/ARI RPT actuation. Standby Service l Water (SSW) was initiated and provided cooling for the component cooling water heat exchangers and the drywell chillers. The SSW basin level dropped below the Tech. Spec. limit due to leakage of SSW into PSW.
Eventually, PSW was restored and SSW basin inventory was recovered. The l power loss to the supply wells was due to a malfunction of the microwave l Information and control systems. Periodic microwave operational checks are being established.
]
l l
l LER89019/SCMPFLR - 3 N/ C Perm att (9 SJ)
.w
~
- Attachment to AECM-90/0026-GIAC tsom M . UJ sIUCLEA1 F500LATORY C0humm60N UCENSEE EVENT REPORT (LER) TEXT CONTINUATION A*'aovao ome ao mo*
sxmn e:wn '
- AlitLifV IIAAAR (14 DOCKET NudSSR G) ggg pegggga (g3 pagg ge v..a 4 sq = p n c,:'= ,
Grand Gulf' Nuclear Station - Unit 1 01s l 0 l o l o l 4 l1 l6 8l 9 -
011l9 -
010 0l2 0F 016 Tur n === anse n aam summin anc s== ma w nn _
.A. Reportable Occurrence ;
On December 30, 1989,,the reactor was manually scrammed following a loss of the Plant Service Water (PSW) System (EIIS. code: KI)... The-immediate operator actions subsequently caused a scram signa 11due ;
to high reactor pressure. The Reactor Protection System (RPS) i actuations are reported pursuant to'10CFR50.73(a)(2)(iv).
B. Initial Conditions The plant was operating at approximately 82.8 percent power, operators had just completed a control rod sequence exchange and were in the process of performing a fuel preconditioning pctmr ramp. -i C. Description of Occurrence ,
On December 30, 1989 at 1747, a complete loss of PSW was experienced. A. malfunction of the telemetric control and information systems (EIIS code:JG) for the radial wells caused pumps to cycle off and on without operator action. . Erroneous i signals were transmitted to the incoming feeder breaker'for Bus 18AG which provided power to radial wells.1-and 3. -The incoming feeder breaker tripped open which deenergized Bus 18AG and caused-an under voltage lockout of the associated wells. An= operator was dispatched to restore power to the bus and reset'the lockout. .The feeder breaker could not be manually closed so the' cross-tie breaker between 18AG and 28AG was closed reenergizing.18AG.
Subsequently, the incoming feeder' breaker for 28AG' tripped open deenergizing the bus and-all radial well pumps.
l In order to redIce the heat load on generator auxiliaries, reactor power was reduced by reducing the recirculation flow through the core. Reactor Recirculation Flow Control Valves (FCVs) were closed to their minimum position, and a reactor shutdown sequence was commenced at 1754.
The operators determined that PSW would not be readily restored and the Shift Superintendent ordered a manual scram of the reactor.
At approximately the same time, the Shift Technical Advisor (STA),
monitoring the power reduction, observed the reactor operating l slightly in the scram region of Technical Specification Figure 3.4.4.1-1 and confirmed that a manual scram was initiated.
neefonu ssa. LERU9019/SCMPFLR - 4 wast
Attachment to AECM-90/0026' IIRC Penn W UA feUCLEA3 5 81UL1 TORY CORERHEBION LICENSEE EVENT REPORT (LER) TEXT CONTINUATION A**aovao one No. mo-o*
EXPIRES: 4/3_1/W PACouTY esamet m DOCKET NUAABER W PAGE (3)
LER 80UhABGR ($1 vtam >
8'M@,^6 : DNu*mN Grand Gulf' Nuclear Station - Unit 1 o l5 l0 lo lo % [ l6 $9 --
O l1 l 9 --
Ol0 013 0F 0 16 .I var a . ns mm w N= e muw nn , r The reactor mode switch was taken to Shutdown and all-rods were verified full-in. The Reactor Core Isolation Cooling (RCIC) System was manually initiated for level control. The Main Steam Line Isolation Valves (MSIVs) were closed in accordance with the Loss of Plant Service Water Off-Normal-Event Procedure (ONEP).
l Prior to establishing reactor pressure control via the Safety Relief Valve (SRVs),-an automatic scram signal was received on high.
reactor pressure and the ATWS/ARI RPT actuated. SRVs were manually opened one at a time to control reactor vessel pressure.
Suppression pool cooling was placed in service to maintain suppression pool. temperature below the Tech. Spec. limit.
The Division II Standby Service Water (SSW) System (EIIS code: BI) was initiated and aligned. to provide cooling water for the -
Component Cooling Water Heat Exchangers and the Drywell Chillers.
The SSW basin level decreased below the Tech. Spec. limit due to leakage into the PSW s.ystem through SSW/PSW cross-tie valves.
Auxiliary Building PSW isolation valves were' closed-to-secure the leak. Relays were pulled in buses-18AG and 28AG breaker control cabinets to allow breaker closure. The buses were reenergized and PSW was restored at 1850. This allowed SSW basin inventory to be increased to the required level and the associated limiting condition for operation was cleared at-1300 hours.
D. Apparent Cause o Loss of Plant Service Water:
' An investigation revealed the following concerning the malfunction of the radial well pump control system (Bristol-Babcock telemetry) and the radial well switchgear control system (Computrol Multiplexor). Condensation from the ceiling of the Auxiliary Building room dripped onto a power supply for the microwave system. The power, supply provided power to the 'A' channel microwave transmitter and receiver and to the pilot signal oscillator for both the 'A' and 'B' '
microwave channels. When the power supply failed, all Control Room control and valid information concerning the radial wells were lost.
Ioss of the pilot signal caused the Microwave System to automatically switch the operating channel from 'B' to 'A'.
The squelch adjustment, on 'A' channel receiver at the switchgear house, was out of tolerance. This allowed the 'A' receiver to amplify any noise it sensed and pass it to the Radial Well Pump Control System and.The Radial Well Switchgear Control System.
ggonwawa LERU9019/SCMPFLR - 5
w 1 Attachment to AECMJ90/0026 IIRC W MSA U.S. NUCLEA) RESULATORY ConsmeB40N LICENSEE EVENT REPORT (LER) TEXT CONTINUATION Anenovgo ome no. sino-oio.
txPints; 8/31/s '
FAceLITY esAsse (1) coCutY souneen ta8 PAte (#
Lam Nummen to: .
Vlam :-
88$$[, :( :;$ $ n" Grand Gulf Nuclear Station - Unit 1 , y,9, g, g,; 41 f 8, 9 0;1;9 00 0p- op 9
0 l6 verr ==. . w.c .ame=,anc e anamm .
The Pump Control System (telemetry) interpreted-the amplified noise as valid control signals and caused pumps to cycle on j and off.
l l The Switchgear Control System (multiplexor) also interpreted the amplified noise as valid control signals and caused a ,
continuous trip signal to Feeder Breaker 18AG. The breaker could not be closed due to the continuous trip signal.
l o High pressure scram and ATWS/ARI initiation: l Closure of the MSIVs, as instructed by the Loss of PSW ONEP, caused reactor pressure to increase causing'a scram signal on high' pressure followed by an ATWS/ARI initiation. Initiation l l
of the ATWS/ARI caused a reactor recirculation pump trip.
This contributed to the Tech. Spec. cooldown limit of 100' )
degrees F. per hour being exceeded at the bottom head drain.
The incident concerning the cooldown rate will be discussed in a separate Licensee Event Report (LER 90-001).
o Reduction of SSW inventory:
The decrease in SSW inventory level was due to leakage into the PSW system through the balance'of plant:PSW/SSW cross-tie check valves. The check valves will-be scheduled for inspection and rework during the next available PSW system outage of sufficient duration.
o Entry into the scram required region of.the Power / Flow Map:
In performing the rapid power reduction, the Licensed Reactor Operator closed the FCVs to their minimum (0 percent) position using the fast' detent on the controllers. The Integrated' operating Instruction (IOI) for Power Operations specifies i that for a rapid power reduction, FCVs be closed to 10 - 15% ,
valve position. This valve position would have prevented '
entry into the scram required region.
E. Supplemental Corrective Actions l
l o Loss of Plant Service Water:
Operator rounds'have been changed to check the microwave panels inside the Auxiliary Building and at the Radial Well Switchgear House.
nac sonu ase. LERd9019/SGMWLR - 6 maa ,
a Y -
Attachment to AECM-90/0026 [
NAC fann MAA UA NUCLEldt G SOULATORY COMMIWlON LICENSEE EVENT REPORT (LER) TEXT CONTINUATION Aa*Rovio oM no mom EXPIRES: 4/31/5 9ACILITY hadst (H DOC 8LET NUndsen (23 LSR NUMptn ig) PAGE (2 vtaa ': saggpa " : :' NNa**
Grand Gulf' Nuclear Station - Unit 1 o l5 l0 l o l 0 ] 4 l116 8l9 -
0l1]9 -
0l0 0 15 0F 0 16 f
! Terr n ==. === = w == .an==v anc i p w tm _
A preventative maintenance task is being developed to '
! periodically check operation-of the microwave system to ensure proper equipment operation. The preventative maintenance task
( is expected to be issued by 04/01/90.
In addition, Engineering Evaluation Requests have'been written j to initiate evaluations for system enhancements such as a backup power supply for the pilot signal oscillator and a-
' drip shield to protect the microwave power supply, o High pressure scram and ATWS/ARI initiation:
k The Loss of PSW ONEP will be evaluated and changed to maintain-the MSIVs open as long as possible to allow use of the main condenser as a heat sink and minimize the use of SRVs to control reactor vessel pressure. This action will be completed by 03/01/90.
1 An Engineering Evaluation Requests has been written.to initiate an evaluation for increasing the setpoint on the ATWS/ARI RPT high pressure signal to a pressure above the lowest relief valve setpoint. This would minimize severe cooldown transients in the reactor bottom head by allowing the reactor recirculation pumps to remain in service, mixing the cooler water in the bottom head region.
o Reduction of SSW inventory:
i A standing order was issued to require operators to close PSW Auxiliary Building Isolation Valves'during a total loss of PSW; thus preventing any loss of SSE inventory should the cross-tie valves leak. The-PSW ONEP will be changed by.
03/01/90 to incorporate the actions of the standing order.
The P44F012 and P44F041, which are check valves in the PSW system, will be scheduled for inspection and rework during the next PSW system outage of sufficient duration.
o Entry into the scram required region of the power flow map:
A memorandum was issued to all Shift Superintendents reiterating the 101. requirements to stop control valve motion I at 10 to 15 percent during a rapid power reduction to prevent l
entry into the scram-required region of the power flow-map. '
refonu ssa. LF.RB9019/SCMPFLR - 7 emas
C.' Attachment to AECM-90/0026 ;
-~
IIIIC Perun MSA UA. seUCLS14 C SOULATORY -
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION waovio ome no. aiso-oio4 )
EXPIRES: t/31/# -l PacetaTY IIAME m 00CetET esumesR 128 Lam nubest ($1 PAGE W vaan j. sagey,a6 ; y g,y,*
Grand Gulf Nuclear Station - Unit 1 0 l5 l0 l0 lc lg l, k glq -
nl1 l0 -
n In ol6 OF n !A tett ar aime a w .asm.wmic r= manwim _
An evaluation is being performed by each Shift Superintendent to !
determine the adequacy of operator training in this area. If deficiencies are found, Training will be notified.concerning the inadequacies.
F. Safety Assessment The Post Trip Analysis confirmed that the safety systems functioned !
properly. RPS response times were satisfactory when compared.to required times. The reactor water level remained at least 159 inches above the top of active fuel during the event.
An evaluation of the bottom head region of the reactor vessel, the-drain piping, and critical penetrations concluded that the impact of the heatup and cooldown rates were insignificant when compared ;
to the design usage factor and that there were no structural integrity concerns associated with continued operations. However, this evaluation was not performed until January 15, 1990. Reactor restart had commenced on December 31, 1989. The delay in recognizing the excessive cooldown rate at the bottom head drains will be discussed-in LER 90-001. ,
The minimum required SSW basin level per Technical Specification 3.7.1.3 is at or above 130' 3" Mean Sea' Level, equivalent to an indicated level of > or = 87 inches. The SSW.'B' basin level decreased to an indicated minimum of approximately 68 inches before isolating the PSW system. The basin was out of Technical Specification limits for 4.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> until level was restored with makeup from PSW. The SSW 'A' basin remained operable at a level above the Technical Specification limits.
During a postulated LOCA, the portion of the PSW system through which SSW inventory was lost is automatjcally isolated.
Consequently, during an accident, there would be no concern of a loss of SSW inventory to the PSW System.
V 1
gonu as
_ . - . . . -