ML19310A431

From kanterella
Jump to navigation Jump to search
Responds to IE Insp Repts 50-566/80-03 & 50-567/80-03 Re Failure to Establish Adequate Measures to Control Radiography.Radiography of Welds Scheduled for Completion by 800701
ML19310A431
Person / Time
Site: Yellow Creek  Tennessee Valley Authority icon.png
Issue date: 06/10/1980
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8006170540
Download: ML19310A431 (1)


Text

. - - _ _ _ _ _____ _

l TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 374o1 400 Chestnut Street Tower II l June 10, 1980 l

Mr. James P. 'Reilly, Director Office of Insp tion and Enforcement U.S. Nuclear Reg atory Commission Regiva II - Suite 100 101 Marietta Street  !

Atlanta, Georgia 30 3 l

Dear Mr. O'Reilly:

YELLOW CREEK NUCLEAR PLANT UNITS 1 AND 2 - NRC REGION II LETTER RII:WPK 50-566/80.-03 AND 50-567/80 INSPECTION REPORT -

REVISED SCHEDULE FOR COMPLETION OF CORRECTIVE ACTION ON IhTRACTION The subject letter dated February 28, 1980, cited TVA with infraction 50-560/80-03-01 and 50-567/80-03-01, failure to establish adequate measures to control radiography. A response to this infraction was submitted on March 24, 1980, and additional information was submitted ,

on April 28, 1980. I We were unable to complete reradiographing all 12 welds by June 1, 1980, as specified in our April 28, 1980, submittal. The welds are now expected to be reradiographed by July 1, 1980. M. Thomas of your staff was informed of this schedule on June 4, 1980.

If you have any questions concerning this matter, please get in touch with D. L. Lambert at FTS 857-2581, Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Regulation and Safety cc: Mr. Victor Stallo, Jr., Directore/