Monthly Operating Rept for Sept 1993 for Harris Nuclear Plant Unit 1.W/931015 Ltr
ML18011A214
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 09/30/1993
From: Crenshaw A, Robinson W
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9310210073
Download: ML18011A214 (12)


Text

ACCEI ERAT%9 DOCUMENT DIST UTION SYSTEM REGULAT~ INFORMATION DISTRIBUTIO SYSTEM (RIDS)

!I DOCKET N FACIL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina 05000400 AUTH. NAME AUTHOR AFFILIATION CRENSHAW,A. Carolina Power &'ight Co.

ROBINSON,W.R. Carolina Power & Light Co.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly opera for Sept 1993 for Harris Nuclear Plant Unit 1 /931015 1 r. D DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs NOTES:Application for permit renewal filed. 05000400 /

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-1 IA 3 3 PD2-1 PD 1 1 D LE,N 1 1 D

INTERNAL: ACRS 10 10 AEOD/DOA 1 1 AEOD/DSP/TPAB 1 1 NRR/DORS OEAB 1 1 NRR/DRIL/RPEB RGN2 1

1 1

1

~ ~LE Ol 1 1 EXTERNAL: EG&G BRYCE,J.H 1 1 NRC PDR 1 1 NSIC 1 1 R i I

D i

/ i A

D D

NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTEI CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 504-2065) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24

~ j Carolina Power & Light Company P.O. Box 165 New Hill, NC 27562 OCT 1 5 1995 File Number: SHF/10-15505 Letter Number: H0931039 Document Control Desk United States Nuclear Regulatory Commission Washington, DC 20555 HARRIS NUCLEAR PLANT DEPARTMENT UNIT NO. 1 DOCKET NO. 50-400 LICENSE NO. NPF-63 MONTHLY OPERATIONS REPORT

Dear Sirs:

In accordance with Technical Specification 6.9.1.5 for the Harris Nuclear Power Plant, Unit No. 1; Carolina Power 6 Light Company herewith submits the report of operation statistics and shutdown experience for the month of September 1993.

Yours vc"y truly, W. R. Robinson General Manager Harris Nuclear Plant APC:bdd Enclosure I

c: Mr. S. D. Ebneter (NRC-RII)

. Mr. J. E. Tedrow (NRC-SHNPP)

MIS/MTH-OPR.RPT/1/OS4 V3i0210073 .930930 PDR ADOCNP,05000400

'"'.~'

8 '

"PDR'

~ ~

~ '

DOCKET NO.: 050-400 UNIT: Harris Unit 1 DATE: September 1993 COMPLETED BY: Amanda Crenshaw OPERATIONS

SUMMARY

Harris Unit 1 operated at 100 percent Availability Factor for the referenced month and a 98.16 percent Capacity Factor. There were two significant power reductions.

There are 157 fuel assemblies in the reactor vessel and 1031 spent fuel assemblies stored in the spent fuel pools. 583 of the spent fuel assemblies are BWR, which were shipped to Harris from CP&L's Brunswick Plant. 224 of the spent fuel assemblies are from CP&L's Robinson Plant.

MISNMTH-OPR.RPTN2%0S4

CPKLCO ,NT PERFORMANCE DATA SYSTEM PAGE RUN DATE (9/66/93 OPERATING DATA REPORT RPD36-000 RUN TIME f 3:87'16 HARR1S UNIT 3 DOCKET NO. 050-400 COMPLETED BY AMANDA CRENBHAW OPERATING STATUS TELEPHONE (919)362-2868 UNIT NAME: HARRIS UNIT t NOTES 2~ REPORTIHG PERIOD: SEPTEMBER 93 I 3J LICENSED THERMAL POWER (MWT): 2775 See Operations Summary.

4, HAMEPLATE RATING (GROSS MWE): 950.9 I 54 DESIGN ELECTRICAL RATING <NET MWE): 909.0

6. MAX DEPENDABLE CAPACITY (GROSS MWE): 920.0 (

71 MAX DEPENDABLE CAPACITY (NET MWE): 860.0

8. IF CHAHGES OCCUR IH CAPACITY RATIHGS ( ITEMS 3 THRU 7) SIHCE LAST REPORT i GIVE REASONS: None.
9. POWER LEVEL TO WHICH RESTRICTED IF AHY (NET MWE): None.
19. REASONS FQR RESTRICTION IF ANY: N/A THIS YR TO CUMUL MONTH DATE ATIVE HOURS IH REPORTIHG PERIOD 720.00 6551.60 56256.00
12. NUMBER OF HOURS REACTOR CRITICAL 728.00 6524.41 46693.33 f3. REACTOR RESERVE SHUTDOWN HRB .98 .00 .60
14. HOURS GENERATOR OH LIHE 720.00 6512.45 45568.63
15. UNIT RESERVE SHUTDOWN HOURS .00 .60 .00
16. GROSS THERMAL ENERGY GEH. (MWH) $ 969357.88 17859694.86 12329)730.30

$ 7. GROSS ELEC. ENERGY GEH. (MWH) 647691.98 5980693.00 40395534.00

18. HET ELEC. ENERGY GENERATED (MWH) 607827.00 5612887.99 37618563.98 UNIT SERVICE FACTOR 399.68 99.41 8$ .60
20. UNIT AVAILABILITYFACTOR 166.96 5'9. 41 81.09 UNIT CAP. FACTOR <UBIHG MDC NET) 98.16 99.63 77.76 22 UNIT CAP. FACTOR (USING DER HET) 93.80 95.20 74.30
23. UNIT FORCED OUTAGE RATE .00 .08 3.49
24. SHUTDOWNS SCHED. OVER NEXT 6 MOHTHS (TYPE, DATE, AND DURATION OF EACH):

Unit scheduled for shutdown on March 5, 1994 for Refueling Outage Number 5.

25. IF SHUTDOWN AT EHD QF REPORT PERIOD, ESTIMATED DATE OF START UP:
26. UNITS IH TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATIOH f.f6 " 9 MIS/MTH-OPR. RPT/3/OS4

~ ~

~

CPKLCO NT PERFORMANCE DATA SYSTEM PAGE RUH -DATE 10/06/93 APPENDIX B AVERAGE DAILY POWER LEVEL RPD39-000 RUN TIME 11:07: 36 HARRIS UNIT 1 DOCKET NO. 050-400 COMPLETED BY AMAHDA CRENSHAW TELEPHOHE (919)362-2808 SEPTEMBER 3993 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWFR LEVEL (MWE-NET) (MWE-HET) 860 860 865 856 2()

86) 862 860 864 859 864 859 24 748 857 25 472 10 820 873 27 858 873 877 29 878 859 30 880 858 859 1.$ 6 8 MIS/MTH-OPR.RPT/4/OS4

~ ~

t "i

~

UNIT SHUTDOWNS AND POWER REDUCTION UNIT NAME: Harris DATE: September 1993 I

Q COMPLEIED BY: A. P. Crenshaw 7 TELEPHONE: (919) 362-2808 REPORT MONTH: September 1993 O

R~

e T a y s Method of P Duration 0 Reactor'icensee Shutting Down Event System Component Cause and Corrective Action Date e (Hours) n Report ¹ Code 4 Code 5 to Prevent Recurrence 93-005 930924 0.0 N/A HH Pump Unit power reduced to 85% to repair leak on the "B" Heater Drain Pump. A turbine valve test was also performed while at 85% power. During this event, power was further reduced to 50% for a period of time for repairs to the "B" Main Feed Pump (see event ¹93-006). Unit was returned to 100% on September 26, 1993.

1 2 3 4 F: Forced Reason: Method: Exhibit G-Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-Continued (NUREG-01 61)

E-Operator Training 5. License Examination 5-Reduced Load F-Administrative 6-Other 5 G-Operational Error (Explain) Exhibit 1 -Same Source H-Other (Explain)

tg v

UNIT SHUTDOWNS AND POWER REDUCTION UNIT NAME: Harris DATE: September 1993 I

O COMPLETED BY: A. P. Crenshaw TELEPHONE: (919) 362-2808 REPORT MONTH: September 1993 O

R~

e T a y s Method of P Duration 0 Reactor'icensee Shutting Down Event System Component Cause and Corrective Action No. Date e (Hours) Report ¹ Code 4 Code 5 to Prevent Recurrence 93406 930924 0.0 A N/A CH Pump Unit power reduced to 50% for repairs of a seal pipiri'g leak on the "B" Main Feed Pump. This power reduction occurred while the plant was at 85%

(see event ¹93%05).

Unit power returned to 85% on September 25, 1993 then to 100% on September 26, 1993.

1 2 3 4 F: Forced Reason: Method: Exhibit G-Instructions S: Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data 8-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-Continued (NUREG-01 61)

E-Operator Training & License Examination 5-Reduced Load F-Administrative 6-Other 5 G-Operational Error (Explain) Exhibit 1 -Same Source H-Other (Explain)

A A

4