Monthly Operating Rept for Sept 1996 for Shearon Harris Nuclear Power Plant.W/961014 Ltr
ML18012A400
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 09/30/1996
From: Donahue J, Shannon Rogers
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
HNP-96-170, NUDOCS 9610220353
Download: ML18012A400 (14)


Text

CATEGORY 1 REGULA'l~ Y INFORMATION DISTRIBUTI "YSTEM (RIDS) qp DOCKET FACIL 50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina 05000400 AUTH.NAMQ AUTHOR AFFILIATION ROGER',8. Carolina Power & Light Co.

DONAHUE,J.W. Carolina Power & Light Co.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating rept f t 1996 for Shearon Harris Nuclear Power Plant. 61014 1 r.

DISTRIBUTION CODE: ZE24D COPIES RECEIVED:LTR I ENCL I SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:Application for permit renewal filed. 05000400 F.

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL 0 PD2-1 PD 1 1 LE,N 1 1 R

INTERNAL: ACRS 1 1 AEOD/SPD/RRAB 1 1 LE CEN Ol 1 1 NRR/DRPM/PECB 1 1 0 1 1 RGN2 1 1 EXTERNAL: LITCO BRYCE,J H 1 1 NOAC 1 1 NRC PDR 1 1 D

0 N

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 11 ENCL 11

4 g ~

7 V $

V

'~ 4

, 4

Carolina Power & Light Company Harris Nuclear Plant PO Box 165 New Hill NC 27562 OCT j.4,1996 SERIAL: HNP-96-170 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 SHEARON HARMS NUCLEAR POWER PLANT DOCKET NO. 50-400/LICENSE NO. NPF-63 MONTHLYOPERATING REPORT

Dear Sir or Madam:

In accordance with Technical Specification 6.9.1.5 for the Harris Nuclear Plant, Carolina Power

& Light Company herewith submits the report of operating statistics and shutdown experience for the month of September 1996.

Sincerely, J. W. Donahue Director of Site Operations Harris Plant SGR Enclosure c: Mr. J. B. Brady - NRC Senior Resident Inspector Mr. S. D. Ebneter - NRC Regional Administrator Mr. N. B. Le - NRC Project Manager 9hi0220353 'MO'st30 PDR ADQCK 05000400 R

PDR'tate Road 113k New Hill NC

'nited States Nuclear Regulatory Commission Page 2 bc: Ms. P. Brannan Mr. J. P. Cowan Mr. G. W. Davis Ms. S. F. Flynn Mr. H. W. Habermeyer, Jr.

Mr. G. D. Hicks (BNP)

Mr. M. D. Hill Mr. W. J. Hindman Mr. R. M. Krich (RNP)

Ms. W. C. Langston (PE8cRAS File)

Mr. R. D. Martin Mr. W. S. Orser Mr. W. R. Robinson Mr. G. A. Rolfson Mr. R. S. Stancil Mr. T. D. Walt Mr. W. G. Wendland Nuclear Records File: HI/A-2D

f')P

'L I

I g

't 'I J p II

," I'~f:,'c s> 1i 4 <, I Vl \ ~\I '%" A 4

% ~ 4

Enclosure to Serial HNP-96-170 Sheet 1 of 4 CPRL Co. PLANT PERFORHANCE DATA SYSTEH PAGE 1 RUN DATE '10/08/96 OPERATING DATA REPORT RPD36.000 RUN TIME 12:16:03 'ARRIS UNIT 1 DOCKET NO. 050-400 COMPLETED BY SHEILA ROGERS OPERATING STATUS TELEPHONE (919)362-2573

1. UHIT NAME: HARRIS UNIT 1 ] NOTES
2. REPORTING PERIOD: SEPTEMBER 96 ]
3. L!CEHSED THERMAL POWER (MWT): 2775 ]
4. HAMEPLATE RATIHG (GROSS MWE):, 950.9 ]

5 ~ DESIGN ELECTRICAL RATING (NET MWE): 900.0 ]

6. HAX DEPENDABLE CAPACITY (GROSS MWE): 920.0 ],
7. HAX DEPENDABLE CAPACITY (NET MWE): 860.0-
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED IF ANY (HET MWE):
10. REASONS FOR RESTRICTION IF AHY:

THIS YR TO CUHUL MONTH DATE AT IVE

11. HOURS IN REPORTING PERIOD 720.00 6575.00 82560.00
12. NUHBER OF HOURS REACTOR CRITICAL 577.23 6217.85 69105.11
13. REACTOR RESERVE SHUTDOWN HRS .00 .00 .00
14. HOURS GENERATOR ON LINE 572.00 6158.37 68412.53
15. UNIT RESERVE SHUTDOWN HOURS F 00 .00 F 00
16. GROSS THERMAL ENERGY GEN. (MWH) 1527617.52 16834615. 20 183081295.44
17. GROSS ELEC ~ ENERGY GEN (HWH) 508438.00 5590698.00 60919022 F 00
18. NET ELEC. ENERGY GENERATED (MWH) 472302.00 5238538.00 56795536.00
19. UNIT SERVICE FACTOR 79.44 93.66 82.86
20. UNIT AVAILABILITYFACTOR 79.44 93.66 82.86 21 'NIT CAP ~ FACTOR (USING MDC NET) 76.28 92.64 79.99
22. UNIT CAP. FACTOR (USING DER NET) 72.89 88.53 76.44
23. UNIT FORCED OUTAGE RATE 12.27 5.19 3.34
24. SKU'IDOWHS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):

25 'F SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:

26. UNITS IH TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY INITIAL ELECTRICITY COMHERC IAL OPERATION 1.16 - 9

4 r Ia <

'a I

)

(5 V)'3f

a 1

~ g~

. ~"1 I S

~ ~

pq

~ll p~

~g p" <gi'."

F ~

'g ' " '"$

p lg( f

~ t

~'ff gf C~

Enclosure to Serial HNP-96-170 Sheet 2 of 4 CPEL Co. PLANT PERFORMANCE DATA SYSTEM PAGE 1 RUH DATE 10/08/96 APPENDIX 8 - AVERAGE DAILY POWER LEVEL RPD39.000 RUN TIME 11:04:08 HARRIS UNIT 1 DOCKET NO. 050 400 COHPLETED BY SHEILA ROGERS TELEPHONE (919)362-2573 SEPTEMBER 1996 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET) (MWE-HET) 17 856 861 18 19 870

-30 20

-30 21

-30 22

-33 23

-37 24

-38 25 10 112 26 761 27 861 12 857 28 858 13 29 871 30 871 15 16 1.16 - 8 ~

cl

~ 4s 4't1

~l ~a J.A L

E

<>. I 't li I

t';'

(i::

I]

l C P t

I l

t l

II l~

>4 F

UNIT SHUTDOWNS AND POWER REDUCTION UNITNAME: Harris DATE: 09/30/96 COMPLETED BY: S. G. Rogers TELEPHONE: (919) 362-2573 REPORT MONTH CAUSE AND CORRECTIVE METHOD OF LICENSEE ACTION TO DURATION SHU1TING DOWN EVENT SYSTEM COMPONENT PREVENT RECURRENCE NUMBER DATE TYPE I (HOURS) REASON 2 REACTOR 3 REPORT II CODE 4 CODE 5 96405 960903 80.00 96418 WA PUMPXX Unit was manually tripped 09/03/96 23:42 due to loss of Normal Service Water.

Thc "B" NSW Pump experienced a sheared shafL "A" NStV Pump subsequently tripped.

I 2 3 4 F: Forced Reason: Method: Exhibit G-Instructions S: Scheduled A-Equipment Failure (Explain) I-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee Event C-Refueling 3-Automatic Scram Report (LER) File D-Regulatory Restriction 4~ntinucd (NUREG-0161)

E&perator Training & License Examination 5-Reduced Load F-Administrative 6&ther 5 operational Error (Explain) Exhibit I - Same Source Hither (Explain)

M co CD trt 0 J, g p'RE O

Ch C)

]

UNITSHUTDOWNS AND POWER REDUCTION UNITNAME: Harris DATE: 09/30/96 COMPLETED BY: S. G. Rogers TELEPHONE: (919) 362-2573 REPORT MONfH CAUSE AND CORRECTIVE METHOD OF LICENSEE ACTION TO DURATION SHUTfING DOWN EVENT SYSTEM COMPONENT PREVENT RECURRENCE NUMBER DATE TYPE I (HOURS) REASON 2 REACTOR 3 REPORTS CODE4 CODE 5 96406 960907 68.00 H 96419 Unit remained off-line for an additional 68 hours7.87037e-4 days <br />0.0189 hours <br />1.124339e-4 weeks <br />2.5874e-5 months <br /> awaiting FEMA re-start permission following Hurricane Fran.

Unit was rctumed on-line 09/10/96 03:42. Plant was rctumcd to 100% on 09/l2/96.

I 2 3 4 F: Forced Reason: Method: Exhibit G-Instructions S: Scheduled A-Equipmcnt Failure (Explain) I-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee Event C-Refueling 3-Automatic Scram Report (LER) File D-Regulatory Restriction 4Mntinucd (NUREG4161) operator Training & License Examination 5-Reduced Load F-Administrative 6%ther 5 G&perational Error (Explain) Exhibit I - Same Source Hither (Explain)