Letter Sequence Other |
---|
TAC:ME4028, Steam Generator Tube Integrity (Approved, Closed) |
Results
Other: ML103620318, ML110270026, ML110280424, ML110970260, ML11280A045, ML11304A002, ML11304A109, ML12009A007, ML12164A756, ML12164A759, ML12214A607, ML12242A198, ML12264A648, ML13261A145, ML15149A280, ML15149A282, ML15183A020, ML15287A017, ML15307A022, ML15310A102, ML15337A047, ML15343A186, ML15349A918, ML19205A362, ML19205A365, ML19205A389, SBK-L-15073, Responses to Applicant/Licensee Action Items for the Inspection and Evaluation Guidelines for Pressurized Water Reactor Vessel Internals (MRP-227-A)
|
MONTHYEARML1036203182010-01-21021 January 2010 Attachment 2, Document SEA-FLU-001-R-004, Rev 0, Non-Proprietary Version of Seabrook Station Reactor Pressure Vessel Fluence Evaluation at 55 EFPY Project stage: Other ML1022205712010-08-10010 August 2010 License Renewal Process Overview and Scoping Public Meeting Slides Project stage: Meeting ML1025202222010-09-20020 September 2010 Summary of Public License Renewal Overview and Environmental Scoping Meeting Related to the Review of the Seabrook Station License Renewal Application (TAC No. ME3959 and ME4028) Project stage: Meeting ML11307A1392010-10-28028 October 2010 2010/10/28 Seabrook Lr - FW: Seabrook Station, Unit No. 1 - Fire Protection Request for Additional Information Regarding License Renewal Application Project stage: RAI SBK-L-10192, Supplement 2 to License Renewal Application2010-11-15015 November 2010 Supplement 2 to License Renewal Application Project stage: Supplement ML1030905582010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application - Aging Management Programs Project stage: RAI ML1030903082010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application Project stage: RAI ML1031301592010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1032605542010-12-14014 December 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application (TAC No. ME4028) Aging-Management Programs Project stage: RAI ML1034202732010-12-14014 December 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application (TAC No. ME4028) - Aging Management Programs Project stage: RAI SBK-L-10204, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs2010-12-17017 December 2010 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs Project stage: Response to RAI SBK-L-10203, Response to Request for Additional Information Set 2 Related to the Review of the License Renewal Application2010-12-22022 December 2010 Response to Request for Additional Information Set 2 Related to the Review of the License Renewal Application Project stage: Response to RAI ML1034205872011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1034205852011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1034205832011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11003, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 52011-01-13013 January 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 5 Project stage: Response to RAI SBK-L-11002, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 42011-01-13013 January 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 4 Project stage: Response to RAI ML1100701282011-01-21021 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11015, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Sets 6, 7 and 82011-02-0303 February 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Sets 6, 7 and 8 Project stage: Response to RAI ML1102700262011-02-0404 February 2011 Scoping and Screening Audit Summary Regarding the Seabrook Station License Renewal Application (TAC Number ME4028) Project stage: Other SBK-L-11027, Response to Request for Additional Information, License Renewal Application, Request for Additional Information - Set 92011-02-18018 February 2011 Response to Request for Additional Information, License Renewal Application, Request for Additional Information - Set 9 Project stage: Response to RAI ML1102602662011-02-24024 February 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1105509202011-03-0707 March 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1103506302011-03-17017 March 2011 Letter Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1102804242011-03-21021 March 2011 Audit Report Regarding the Seabrook Station License Renewal Application Project stage: Other ML1109702602011-03-28028 March 2011 Nwt 817, Chemistry Control in the Seabrook Thermal Barrier Loop, Final Project stage: Other ML1107000182011-03-30030 March 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11062, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Request for Additional Information - Set 112011-04-0505 April 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Request for Additional Information - Set 11 Project stage: Response to RAI SBK-L-11069, Response to Request for Additional Information - Set 12 and Associated License Renewal Application Changes2011-04-22022 April 2011 Response to Request for Additional Information - Set 12 and Associated License Renewal Application Changes Project stage: Response to RAI ML11132A0072011-05-23023 May 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11123, Response to Request for Additional Information, NextEra Energy Seabrook License Renewal Application, Request for Additional Information - Set 142011-06-0202 June 2011 Response to Request for Additional Information, NextEra Energy Seabrook License Renewal Application, Request for Additional Information - Set 14 Project stage: Response to RAI ML11139A1462011-06-0909 June 2011 Summary of Telephone Conference Call Held Between the NRC and Nextera Energy Seabrook, LLC, to Clarify Responses to RAI and Draft Requests for Additional Information Pertaining to the Seabrook Station LRA Project stage: Draft RAI ML11143A1652011-06-15015 June 2011 5/18/11, Summary of Telephone Conference Call Held Between NRC and Nextera Energy Seabrook, LLC, Concerning the D-RAI Pertaining to the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11133, Response to Request for Additional Information - Set 14 RAI B.1.4-12011-06-24024 June 2011 Response to Request for Additional Information - Set 14 RAI B.1.4-1 Project stage: Response to RAI ML11178A3652011-07-12012 July 2011 Schedule Revision for the Safety Review of the Seabrook Station License Renewal Application Project stage: Approval ML11284A0202011-10-14014 October 2011 Summary of Telephone Conf Call Held on August 4, 2011 Between the USNRC and Nextera Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Response Project stage: RAI ML11280A0452011-10-17017 October 2011 Summary of Telephone Conference Call Held on May 5, 2011, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning Clarification of Information Pertaining to the Seabrook Station LRA Project stage: Other ML11304A0022011-11-0404 November 2011 Summary of Tele Conf Call Held on 3/18/11, Between the USNRC and NextEra Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook Station License Renewal Application Project stage: Other ML11304A1092011-11-0404 November 2011 Summary of Tele Conf Call Held on 5/31/11, Between the USNRC and Nextera Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook LRA Project stage: Other ML11304A1512011-11-0404 November 2011 Summary of Tele Conf Call Held on 4/8/11 Between USNRC and NextEra Energy Seabrook, Llc. Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Responses Project stage: RAI ML11304A1662011-11-0404 November 2011 Summary of Tele Conf Call Held on 3/3/11, Between the USNRC and NextEra Energy Seabrook, Llc. Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Responses Project stage: RAI ML12009A0072012-01-25025 January 2012 Project Manager Change for the License Renewal of Seabrook Station Project stage: Other ML12054A7662012-03-26026 March 2012 022312, Telecon Summary Between NRC and NextEra Seabrook, Discussing RAIs Response Project stage: RAI ML12160A3742012-06-0808 June 2012 Safety Evaluation Report with Open Items Related to the License Renewal of Seabrook Station Project stage: Approval ML12053A1922012-06-0808 June 2012 Safety Evaluation Report with Open Items Related to the License Renewal of Seabrook Station (TAC No. ME4028). Seabrook SER with Open Items Transmittal Letter Project stage: Approval ML12165A7422012-06-21021 June 2012 Summary of Telephone Conference Call Held on April 10, 2012, Between NRC and Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA Project stage: RAI ML12165A5952012-06-22022 June 2012 Summary of Telephone Conference Call Held on May 16, 2012, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA Project stage: RAI ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA Project stage: RAI ML12164A7562012-06-22022 June 2012 Summary of Telephone Conference Call Between NRC and NextEra Seabrook Project stage: Other ML12164A7592012-07-0303 July 2012 041912, Telecon Summary Between NRC and NextEra Seabrook Project stage: Other 2011-02-04
[Table View] |
|
---|
Category:Note to File incl Telcon Record
MONTHYEARML17278A1662017-10-0505 October 2017 Teleconference Meeting Summary Dated August 28, 2017 with Massachusetts Attorney General'S Office and Massachusetts Emergency Management Agency ML12164A7592012-07-0303 July 2012 041912, Telecon Summary Between NRC and NextEra Seabrook ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA ML12059A0742012-02-28028 February 2012 Comment of Donald Tilbury on NRC-2010-0206-0013, NextEra Energy Seabrook, LLC; Notice of Availability of Draft Supplement 46 to GEIS ML12059A0732012-02-28028 February 2012 Comment of M. Broderick on NRC-2010-0206-0013, NextEra Energy Seabrook, LLC; Notice of Availability of Draft Supplement 46 to GEIS 2017-10-05
[Table view] Category:Verbal Comm
MONTHYEARML17278A1662017-10-0505 October 2017 Teleconference Meeting Summary Dated August 28, 2017 with Massachusetts Attorney General'S Office and Massachusetts Emergency Management Agency ML12164A7592012-07-0303 July 2012 041912, Telecon Summary Between NRC and NextEra Seabrook ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA ML12059A0742012-02-28028 February 2012 Comment of Donald Tilbury on NRC-2010-0206-0013, NextEra Energy Seabrook, LLC; Notice of Availability of Draft Supplement 46 to GEIS ML12059A0732012-02-28028 February 2012 Comment of M. Broderick on NRC-2010-0206-0013, NextEra Energy Seabrook, LLC; Notice of Availability of Draft Supplement 46 to GEIS 2017-10-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 03, 2012 APPLICANT: NextEra Energy Seabrook, LLC FACILITY: Seabrook Station SUBJECT.
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON APRIL 19, 2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING THE RESPONSE TO REQUEST FOR ADDITIONAL iNFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4028)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of NextEra Energy Seabrook, LLC (NextEra or the applicant), held a telephone conference call on April 19, 2012, to discuss the response to a request for additional information (RAJ) concerning the Seabrook Station license renewai application (LRA). provides a listing of the participants and Enclosure 2 contains a listing of the RAls that were discussed with the applicant, including a bnef description on the status of the item.
The applicant had an opportunity to comment on this summary.
Arthur Cunanan, Project Manager Projects Branch 1 Division of License Renewal Office of Nuc!ear Reactor Regulation Docket No. 50-443
Enclosures:
As stated cc w/encls: Distribution via Listserv
TELEPHONE CONFERENCE CALL SEABROOK STATION LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS April 19, 2012 PARTICIPANTS AFFILIATIONS Arthur Cunanan U.S. Nuclear Regulatory Commission (NRC)
Michael Marshall NRC Abdul Sheikh NRC Alice Erickson NRC Richard Cliche NextEra Energy Seabrook, LLC (NextEra)
Paul Willoughby NextEra Ken Chew NextEra Ed Carley NextEra ENCLOSURE 1
TELEPHONE CONFERENCE CALL SEABROOK STATION LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of NextEra Energy Seabrook, LLC (the applicant), held a telephone conference call on April 19, 2012, to discuss the response to the request for additional information (RAls) concerning the Seabrook Station license renewal application (LRA).
RAI B.2.1.28-3 and RAI B.2.1.31-1: Related to the ASME Section XI. Subsection IWL and Structures Monitoring Programs The staff discussed its concerns with the ASME Section XI, Subsection IWL and Structures Monitoring Programs.
The applicant understands the staff's concern and discussed submitting a plant-specific aging management program related to alkali-silica reaction (ASR) as well as submitting the engineering evaluation on the docket.
The staff will review the applicant's submittal. The staff will not send an RAI. This item is tracked as Open Item 01 3.0.3.2.18-1 in the safety evaluation report with open items.
ENCLOSURE 2
Memorandum to NextEra Energy Seabrook, LLC from A. Cunanan dated July 03,2012
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON APRIL 19, 2012, BE1WEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING THE RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4028)
DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource MWentzel ACunanan DMorey JLamb DMclntyre, OPA EDacus,OCA MSpencer, OGC WRaymond, RI DTifft, RI NMcNamara, RI NSheehan, RI DScrenci, RI JJohnson, RI ABurritt, RI
APPLICANT: NextEra Energy Seabrook, LLC FACILITY: Seabrook Station
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON APRIL 19, 2012, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NEXTERA ENERGY SEABROOK, LLC, CONCERNING THE RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4028)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of NextEra Energy Seabrook, LLC (NextEra or the applicant), held a telephone conference call on April 19, 2012, to discuss the response to a request for additional information (RAI) concerning the Seabrook Station license renewal application (LRA). provides a listing of the participants and Enclosure 2 contains a listing of the RAls that were discussed with the applicant, including a brief description on the status of the item.
The applicant had an opportunity to comment on this summary.
IRAJ Arthur Cunanan, Project Manager PrOjects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
As stated cc w/encls: Distribution via Listserv DISTRIBUTION:
See next page ADAMS Accession No. ML12164A759 OFFICE LADLR PM:RPB1 :DLR BC:RPB1 :DLR PM:RPB1 :DLR NAM~E~__~Y~E~d~m~o~n~d~s____~A_C_u_n_an_a_n____-+_D_M_o_re~y______-rA_C_u_n_a_n_an_ ___~
06/25/12 06/25/12 07102/12 071 03/12 OFFICIAL RECORD COpy