ML103130159
Letter Sequence RAI | |
---|---|
TAC:ME4028, Steam Generator Tube Integrity (Approved, Closed) | |
Initiation
Administration Questions
Answers Results Other: ML103620318, ML110270026, ML110280424, ML110970260, ML11280A045, ML11304A002, ML11304A109, ML12009A007, ML12164A756, ML12164A759, ML12214A607, ML12242A198, ML12264A648, ML13261A145, ML15149A280, ML15149A282, ML15183A020, ML15287A017, ML15307A022, ML15310A102, ML15337A047, ML15343A186, ML15349A918, ML19205A362, ML19205A365, ML19205A389, SBK-L-15073, Responses to Applicant/Licensee Action Items for the Inspection and Evaluation Guidelines for Pressurized Water Reactor Vessel Internals (MRP-227-A) | |
MONTHYEARML1036203182010-01-21021 January 2010
[Table View]Attachment 2, Document SEA-FLU-001-R-004, Rev 0, Non-Proprietary Version of Seabrook Station Reactor Pressure Vessel Fluence Evaluation at 55 EFPY Project stage: Other ML1022205712010-08-10010 August 2010 License Renewal Process Overview and Scoping Public Meeting Slides Project stage: Meeting ML1025202222010-09-20020 September 2010 Summary of Public License Renewal Overview and Environmental Scoping Meeting Related to the Review of the Seabrook Station License Renewal Application (TAC No. ME3959 and ME4028) Project stage: Meeting ML11307A1392010-10-28028 October 2010 2010/10/28 Seabrook Lr - FW: Seabrook Station, Unit No. 1 - Fire Protection Request for Additional Information Regarding License Renewal Application Project stage: RAI SBK-L-10192, Supplement 2 to License Renewal Application2010-11-15015 November 2010 Supplement 2 to License Renewal Application Project stage: Supplement ML1030905582010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application - Aging Management Programs Project stage: RAI ML1030903082010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application Project stage: RAI ML1031301592010-11-18018 November 2010 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1032605542010-12-14014 December 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application (TAC No. ME4028) Aging-Management Programs Project stage: RAI ML1034202732010-12-14014 December 2010 Request for Additional Information Related to the Review of the Seabrook Station, License Renewal Application (TAC No. ME4028) - Aging Management Programs Project stage: RAI SBK-L-10204, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs2010-12-17017 December 2010 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs Project stage: Response to RAI SBK-L-10203, Response to Request for Additional Information Set 2 Related to the Review of the License Renewal Application2010-12-22022 December 2010 Response to Request for Additional Information Set 2 Related to the Review of the License Renewal Application Project stage: Response to RAI ML1034205872011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1034205852011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1034205832011-01-0505 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11003, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 52011-01-13013 January 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 5 Project stage: Response to RAI SBK-L-11002, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 42011-01-13013 January 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Aging Management Programs - Set 4 Project stage: Response to RAI ML1100701282011-01-21021 January 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11015, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Sets 6, 7 and 82011-02-0303 February 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Sets 6, 7 and 8 Project stage: Response to RAI ML1102700262011-02-0404 February 2011 Scoping and Screening Audit Summary Regarding the Seabrook Station License Renewal Application (TAC Number ME4028) Project stage: Other SBK-L-11027, Response to Request for Additional Information, License Renewal Application, Request for Additional Information - Set 92011-02-18018 February 2011 Response to Request for Additional Information, License Renewal Application, Request for Additional Information - Set 9 Project stage: Response to RAI ML1102602662011-02-24024 February 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1105509202011-03-0707 March 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1103506302011-03-17017 March 2011 Letter Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI ML1102804242011-03-21021 March 2011 Audit Report Regarding the Seabrook Station License Renewal Application Project stage: Other ML1109702602011-03-28028 March 2011 Nwt 817, Chemistry Control in the Seabrook Thermal Barrier Loop, Final Project stage: Other ML1107000182011-03-30030 March 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11062, Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Request for Additional Information - Set 112011-04-0505 April 2011 Response to Request for Additional Information NextEra Energy Seabrook License Renewal Application Request for Additional Information - Set 11 Project stage: Response to RAI SBK-L-11069, Response to Request for Additional Information - Set 12 and Associated License Renewal Application Changes2011-04-22022 April 2011 Response to Request for Additional Information - Set 12 and Associated License Renewal Application Changes Project stage: Response to RAI ML11132A0072011-05-23023 May 2011 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11123, Response to Request for Additional Information, NextEra Energy Seabrook License Renewal Application, Request for Additional Information - Set 142011-06-0202 June 2011 Response to Request for Additional Information, NextEra Energy Seabrook License Renewal Application, Request for Additional Information - Set 14 Project stage: Response to RAI ML11139A1462011-06-0909 June 2011 Summary of Telephone Conference Call Held Between the NRC and Nextera Energy Seabrook, LLC, to Clarify Responses to RAI and Draft Requests for Additional Information Pertaining to the Seabrook Station LRA Project stage: Draft RAI ML11143A1652011-06-15015 June 2011 5/18/11, Summary of Telephone Conference Call Held Between NRC and Nextera Energy Seabrook, LLC, Concerning the D-RAI Pertaining to the Seabrook Station License Renewal Application Project stage: RAI SBK-L-11133, Response to Request for Additional Information - Set 14 RAI B.1.4-12011-06-24024 June 2011 Response to Request for Additional Information - Set 14 RAI B.1.4-1 Project stage: Response to RAI ML11178A3652011-07-12012 July 2011 Schedule Revision for the Safety Review of the Seabrook Station License Renewal Application Project stage: Approval ML11284A0202011-10-14014 October 2011 Summary of Telephone Conf Call Held on August 4, 2011 Between the USNRC and Nextera Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Response Project stage: RAI ML11280A0452011-10-17017 October 2011 Summary of Telephone Conference Call Held on May 5, 2011, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning Clarification of Information Pertaining to the Seabrook Station LRA Project stage: Other ML11304A0022011-11-0404 November 2011 Summary of Tele Conf Call Held on 3/18/11, Between the USNRC and NextEra Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook Station License Renewal Application Project stage: Other ML11304A1092011-11-0404 November 2011 Summary of Tele Conf Call Held on 5/31/11, Between the USNRC and Nextera Energy Seabrook, Llc., Concerning Clarification of Information Pertaining to the Seabrook LRA Project stage: Other ML11304A1512011-11-0404 November 2011 Summary of Tele Conf Call Held on 4/8/11 Between USNRC and NextEra Energy Seabrook, Llc. Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Responses Project stage: RAI ML11304A1662011-11-0404 November 2011 Summary of Tele Conf Call Held on 3/3/11, Between the USNRC and NextEra Energy Seabrook, Llc. Concerning Clarification of Information Pertaining to the Seabrook Station Request for Additional Information Responses Project stage: RAI ML12009A0072012-01-25025 January 2012 Project Manager Change for the License Renewal of Seabrook Station Project stage: Other ML12054A7662012-03-26026 March 2012 022312, Telecon Summary Between NRC and NextEra Seabrook, Discussing RAIs Response Project stage: RAI ML12160A3742012-06-0808 June 2012 Safety Evaluation Report with Open Items Related to the License Renewal of Seabrook Station Project stage: Approval ML12053A1922012-06-0808 June 2012 Safety Evaluation Report with Open Items Related to the License Renewal of Seabrook Station (TAC No. ME4028). Seabrook SER with Open Items Transmittal Letter Project stage: Approval ML12165A7422012-06-21021 June 2012 Summary of Telephone Conference Call Held on April 10, 2012, Between NRC and Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA Project stage: RAI ML12165A5952012-06-22022 June 2012 Summary of Telephone Conference Call Held on May 16, 2012, Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook, LLC, Concerning the Response to Request for Additional Information Pertaining to the Seabrook Station LRA Project stage: RAI ML12164A9012012-06-22022 June 2012 Summary of Telephone Conference Call Held on 5/24/12, Between the NRC and NextEra Energy Seabrook, LLC Concerning the Drai Pertaining to the Seabrook Station LRA Project stage: RAI ML12164A7562012-06-22022 June 2012 Summary of Telephone Conference Call Between NRC and NextEra Seabrook Project stage: Other ML12164A7592012-07-0303 July 2012 041912, Telecon Summary Between NRC and NextEra Seabrook Project stage: Other 2011-02-04 |
ML103130159 | |
Person / Time | |
---|---|
Site: | Seabrook |
Issue date: | 11/18/2010 |
From: | Plasse R License Renewal Projects Branch 2 |
To: | Freeman P NextEra Energy Seabrook |
Plasse, R, A., NRR/DLR, 415-1427 | |
References | |
TAC ME4028 | |
Download: ML103130159 (4) | |
Similar Documents at Seabrook | |
---|---|
Category:Letter
MONTHYEARIR 05000443/20244022024-10-17017 October 2024
[Table view]Material Control and Accounting Program Inspection Report 05000443/2024402 (Cover Letter Only) L-2024-159, Core Operating Limits Report for Reload Cycle 242024-10-15015 October 2024 Core Operating Limits Report for Reload Cycle 24 ML24254A2552024-09-25025 September 2024 Alternative Request No. 4A-01 for the Fourth 10-Year Inservice Inspection Interval L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24239A5382024-09-20020 September 2024 Issuance of Amendment No. 175 One-Time Allowable Outage Time Extension to the Technical Specification 3.8.1.1, A.C. Sources – Operating, Limiting Condition for Operation L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000443/20240052024-08-29029 August 2024 Updated Inspection Plan for Seabrook Station (Report 05000443/2024005) ML24232A1142024-08-21021 August 2024 Correction to Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves L-2024-141, Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit2024-08-15015 August 2024 Third Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Be L-2024-137, Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent .2024-08-12012 August 2024 Second Supplement to NextEra Energy Seabrook, LLC, Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent . IR 05000443/20240022024-08-0606 August 2024 Integrated Inspection Report 05000443/2024002 and Independent Spent Fuel Storage Installation Inspection Report 07200063/2024001 L-2024-127, Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent2024-08-0505 August 2024 Supplement to Letter L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-108, Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite.2024-07-16016 July 2024 Response to Request for Additional Information (RAI) Regarding One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite. ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-098, Preparation and Scheduling of Operator Licensing Examinations2024-06-12012 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-084, Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-05-30030 May 2024 Relief Request 4A-01, Rev 1 - Revision to Relief Request for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld IR 05000443/20240102024-05-29029 May 2024 Biennial Problem Identification and Resolution Inspection Report 05000443/2024010 IR 05000443/20240112024-05-24024 May 2024 Age-Related Degradation Inspection Report 05000443/2024011 IR 05000443/20240012024-05-13013 May 2024 Integrated Inspection Report 05000443/2024001 L-2024-061, NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distribut2024-05-10010 May 2024 NextEra Energy Seabrook, LLC, License Amendment Request - One Time Extension to Technical Specification 3.8.1.1.a, Allowed Outage Time with One Independent Circuit Between the Offsite Transmission Network and the Onsite Class 1E Distributio ML24046A0512024-05-0707 May 2024 Issuance of Amendment No. 174 to Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (LTOP) Curves ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-078, 2023 Annual Radioactive Effluent Release Report2024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report L-2024-077, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000443/20245012024-04-22022 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000443/2024501 L-2024-058, Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources2024-04-19019 April 2024 Condition Prohibited by Technical Specifications - Transformer Bushing Failure - Offsite AC Sources SBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report L-2024-011, and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications ML24067A2622024-03-0808 March 2024 Issuance of Amendment No. 173 Revise Technical Specification 3/4.8.1 to Allow Replacement of Reserve Auxiliary Transformer (Emergency Circumstances) L-2024-038, to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0808 March 2024 to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-037, to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0606 March 2024 to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source ML24065A2522024-03-0505 March 2024 Notice of Enforcement Discretion for Seabrook Station, Unit No. 1 (EPID: L-2024-033) L-2024-035, Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0505 March 2024 Supplement to Seabrook Emergency License Amendment Request - One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source L-2024-033, Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B2024-03-0404 March 2024 Request for Enforcement Discretion - Technical Specification (TS) 3/4.8.1.1 Ac. Sources Required Action Completion Time to Replace ED-X-3-B L-2024-032, Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source2024-03-0404 March 2024 Emergency License Amendment Request- One Time Extension to Technical Specifications (TS) 3/4.8.1 Action a.3 Allowed Outage Time for an Inoperable Offsite Source IR 05000443/20230062024-02-28028 February 2024 Annual Assessment Letter for Seabrook Station (Report 05000443/2023006) L-2024-019, Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld2024-02-28028 February 2024 Relief Request 4A-01- Request for an Alternative to the Requirements of the ASME Code for Examination of Control Rod Drive Mechanism (Rod) Housing H-4 Canopy Seal Weld L-2024-016, Radiological Emergency Plan (Ssrep), Revision 822024-02-13013 February 2024 Radiological Emergency Plan (Ssrep), Revision 82 IR 05000443/20230042024-02-12012 February 2024 Integrated Inspection Report 05000443/2023004 ML24009A1152024-01-29029 January 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24022A0652024-01-22022 January 2024 Senior Reactor and Reactor Operator Initial License Examinations L-2024-003, NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report2024-01-11011 January 2024 NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report ML23312A1822023-12-22022 December 2023 Issuance of Amendment No. 172 Revision to Cooling Tower Service Water Loop or Cell Requirements L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update 2024-09-25 Category:Request for Additional Information (RAI) MONTHYEARML24193A2432024-07-12012 July 2024
[Table view]– Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23011A3082023-01-11011 January 2023 Request for Additional Information Regarding Relief Request 4RA-22-001 (L-2022-LLR-0074) ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22228A0552022-08-15015 August 2022 Request for Additional Information Steam Generator Tube Inspection Report Review ML22153A4152022-05-31031 May 2022 Request for Additional Information Re 120V Inverter LAR from TS Branch - Final ML22062B6642022-02-0707 February 2022 Request for Additional Information 120V Inverter LAR from the Electrical Branch ML22063A0002022-01-25025 January 2022 Requests for Additional Information from Risk Branch Regarding 120V Inverter LAR ML21245A4382021-10-0505 October 2021 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Revise 120-Volt AC Vital Instrument Panel Technical Specification Requirements ML21097A2512021-04-0707 April 2021 Request for Additional Information Regarding Steam Generator Tube Inspection Report Review for RFO 20 (EPID L-2020-LRO-0066) (Email) ML21054A0482021-02-23023 February 2021 Request for Additional Information Regarding Heat Flux Hot Channel Requirement Amendment Request ML20343A0942020-12-0303 December 2020 Request for Additional Information Regarding Seabrook (COVID-19) Part 73 Force-on-Force Exemption Request (L-2020-LLE-0219) ML20258A1502020-09-14014 September 2020 Request for Additional Information Related to Seabrook License Amendment Request Regarding One-Time Change to the AC Sources Operating TS ML20204A5422020-07-21021 July 2020 Request for Additional Information Related to Seabrook License Amendment Request Regarding Degraded Voltage Time Delay Setpoint ML20167A1842020-06-11011 June 2020 Request for Additional Information Related to Seabrook License Amendment Request Regarding TSTF-411 and TSTF-418 (L-2019-LLA-0237) ML20114E1592020-04-23023 April 2020 Email and Request for Additional Information Related to Seabrook License Amendment Request to Degraded Voltage Time Delay Setpoint (L-2020-LLA-0012) ML19296D9122019-10-23023 October 2019 NRR E-mail Capture - Request for Additional Information Related to Seabrook Inverter Amendment (L-2019-LLA-0216) ML18163A0352018-06-11011 June 2018 Requests for Additional Information for the Review of the Seabrook Station License Renewal Application ML18121A3992018-05-0101 May 2018 NRR E-mail Capture - Request for Additional Information Regarding ASR Amendment Request ML18113A5292018-04-18018 April 2018 NRR E-mail Capture - Draft - Request for Additional Information Regarding ASR Amendment Request ML18058A0522018-02-27027 February 2018 Enclosurequest for Additional Information (Letter: RAI Regarding Florida Power and Light/Nextera Decommissioning Funding Plan Updates for St. Lucie, Units 1 & 2; Seabrook Station; Duane Arnold Energy Center; and Point Beach, Units 1 and 2) ML18026A8792018-01-29029 January 2018 Final Requests for Additional Information for the Safety Review of the Seabrook Station License Renewal Application Docket No. 05-443 ML17332A3412017-11-29029 November 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment to Delete Operator Action and Request for Exemption ML17261B2172017-10-11011 October 2017 Request for Additional Information Regarding License Amendment Request Related to Alkali-Silica Reaction (CAC No. MF8260; EPID L-2016-LLA-0007) ML17276B7572017-10-0202 October 2017 NRR E-mail Capture - Draft - Request for Additional Information Regarding ASR Amendment Request ML17214A0852017-08-0404 August 2017 Request for Additional Information Regarding License Amendment Request Related to Alkali-Silica Reaction ML17201Q1072017-07-18018 July 2017 NRR E-mail Capture - Draft - Request for Additional Information Regarding ASR Amendment Request ML17139B8352017-05-24024 May 2017 Final Request for Additional Information Regarding Seabrook License Renewal Application - Set 26 ML17150A2862017-05-0505 May 2017 NRR E-mail Capture - Draft - Request for Additional Information Regarding ASR Amendment Request ML17088A6142017-03-29029 March 2017 Request for Additional Information for the Review of the Seabrook Station License Renewal Application ML16341B9022017-03-0707 March 2017 03/07/2016 Summary of Telecon Held on Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Request for Additional Information Pertaining to the Seabrook Station License Renewal Application ML16342C4672017-03-0101 March 2017 12/01/2016 Summary of Teleconference Between the U.S. Nuclear Regulatory Commission and NextEra Energy Seabrook Concerning Requests for Additional Information Pertaining to the Seabrook Station License Renewal Application ML16337A0082016-12-0101 December 2016 NRR E-mail Capture - Need for Supplement to ILRT License Amendment Seabrook Station, License Amendment Request 16-01, Request to Extend Containment Leakage Test Frequency ML16326A0372016-11-30030 November 2016 Requests for Additional Information for the Review of the Seabrook Station License Renewal Application ML16326A0092016-11-18018 November 2016 NRR E-mail Capture - Request for Additional Information Re. Nextera/Fpl LAR to Adopt TSTF-545 - CACs MF8203, MF8204, MF8208, and MF8209 ML16301A4282016-11-14014 November 2016 Requests for Additional Information for the Review of the License Renewal Application ML16319A4222016-11-10010 November 2016 NRR E-mail Capture - Need for Supplement to ILRT License Amendment ML16319A4212016-11-10010 November 2016 NRR E-mail Capture - Need for Supplement to EAL License Amendment ML16230A1062016-10-0303 October 2016 Request for Additional Information Request to Extend Containment Leakage Test Frequency ML16230A5332016-09-22022 September 2016 Request for Additional Information Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6 ML16258A0222016-09-19019 September 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action Alkali-Silica Reaction ML16187A2032016-07-0808 July 2016 Requests For Additional Information For The Severe Accident Mitigation Alternatives (SAMA) Review Of The Seabrook Station License Renewal Application (TAC No. Me3959)- Enclosure ML15328A1392015-12-0404 December 2015 November 23, 2015, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Nextera Energy Seabrook, LLC, Concerning Requests for Additional Information Pertaining to the Seabrook Station ML15251A3332015-10-0202 October 2015 Request for Additional Information Related to the Review of the Seabrook Station, Unit 1, License Renewal Application-SET 25 ML15224A5662015-08-28028 August 2015 Request for Additional Information Related to the Review of the Seabrook Station License Renewal Application-Set 24 ML15131A3382015-06-0505 June 2015 Request for Additional Information Regarding License Amendment 14-03, Changes to Technical Specification 3.3.3.1,Radiation Monitoring for Plant Operations ML15043A2212015-02-24024 February 2015 Request for Additional Information for the Spring 2014 Steam Generator Tube Inspections ML14363A3672015-01-0909 January 2015 Request for Additional Information Regarding the License Amendment Request to Revise the Technical Specification Pressure-Temperature Limits and Request for Exemption from 10 CFR Part 50, Appendix G Minimum Tempt Requirements ML14358A0732014-12-24024 December 2014 Request for Additional Information for License Amendment Request 13-05. Fixed Incore Detector System Analysis Methodology 2024-07-12 |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 18, 2010 Mr. Paul Freeman Site Vice President c/o Mr. Michael OKeefe NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4028)
Dear Mr. Freeman:
By letter dated May 25, 2010, NextEra Energy Seabrook, LLC, submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the Operating License NPF-86 for Seabrook Station, Unit 1, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
The request for additional information was discussed with Mr. Rick Cliche, and a mutually agreeable date for the response is within 45 days from the date of this letter. If you have any questions, please contact me at 301-415-1427 or bye-mail at richard.plasse@nrc.gov.
Sincerely, Richard Plas e, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosure:
As stated cc w/encl: Distribution via Listserv
Seabrook Station License Renewal Application Request for Additional Information Set 2 RAI4.2.1-1
Background
The Seabrook Station, Unit 1, license renewal application (LRA) states that fluence values were calculated using the RAMA methodology, which, as noted in the LRA, has not been approved by the U.S. Nuclear Regulatory Commission for generic use at pressurized water reactors. The LRA states, "This prior work has been extended in the Seabrook Station analysis to additional PWR benchmarks and plant-specific dosimetry comparisons, further validating the use of RAMA for aI/light water reactor designs. "
Regulatory Basis RG 1.190, RP 1.3.3: The capsule fluence is extremely sensitive to the geometrical representation of the capsule geometry and internal water region, and the adequacy of the capsule representation must be demonstrated.
RG 1.190, RP 1.4: The calculational methodology must be qualified by both (1) comparisons to measurement and calculational benchmarks and (2) an analytic uncertainty analysis. The methods used to calculate the benchmarks must be consistent (to the extent possible) with the methods used to calculate the vessel fluence. The overall calculational bias and uncertainty must be determined by an appropriate combination of the analytic uncertainty analysis and the uncertainty analysis based on the comparisons to the benchmarks.
Request Please provide documentation of the referenced additional PWR benchmarks and plant-specific dosimetry comparisons to demonstrate adherence to the regulatory positions described above.
ENCLOSURE
'.. ML103130159 *concurrence via e-mail OFFICE LA:DLR PM:RPB2:DLR OGC (NLO) BC:RPB2:DLR PM:RPB2:DLR NAME SFigueroa* RPIasse MSpencer DWrona RPlasse DATE 11/10/10 11/18/10 11/15/10 11/18/10 11/18/10
Letter to P. Freeman from R. Plasse dated November 18, 2010
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE SEABROOK STATION LICENSE RENEWAL APPLICATION (TAC NO. ME4028)
DISTRIBUTION:
HARDCOPY:
DLRRF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource JSusco RPlasse BPham DWrona EMiller ICouret, OPA EDacus,OCA MSpencer, OGC WRaymond, RI DTifft, RI NMcNamara, RI NSheehan, RI DScrenci, RI JJohnson, RI ABurritt, RI ENCLOSURE