Public Meeting Notice for Annual Assessment Meeting with Entergy, Indian Point Station, and NRC to Discuss CY2008 Performance
ML091120310
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 04/21/2009
From: Mel Gray
Reactor Projects Branch 2
To:
Gray M, RI/DRP/BR2/610-337-5209
Shared Package
ML090620501 List:
References
MN 09-019
Download: ML091120310 (6)


Text

U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING April 21, 2009 MN No.09-019 Licensee: Entergy Nuclear Operations, Inc.

Facility: Indian Point Nuclear Generating Unit 2 and Unit 3 Docket No. 50-247 and 50-286 Date and Time: May 21, 2009 5:30p.m. to 6:30 p.m. - Information Session 6:30 p.m. to 9:30 p.m. - Annual Assessment Meeting Location: Doubletree Hotel 455 South Broadway Tarrytown, NY

Purpose:

The NRC requested an Annual Assessment Meeting with Entergy to discuss the NRCs assessment of the safety performance of Indian Point Nuclear Generating Units 2 and 3 for calendar year 2008. The NRCs assessment is documented in a letter dated March 4, 2009.

Attendees*:

NRC: S. Collins, Regional Administrator, Region I M. Gray, Chief, Projects Branch 2, Region I P. Cataldo, Senior Resident Inspector, Indian Point 3 C. Hott, Resident Inspector, Indian Point 2 Entergy: J. Pollock, Site Vice President A. Vitale, General Manager Plant Operations P. Conroy, Director of Nuclear Safety Assurance T. Orlando, Director of Engineering Public Participation: The Indian Point Annual Assessment Meeting is a Category 1 Meeting. The public is invited to observe this meeting and will have opportunities to communicate with the NRC staff following the business portion, before the meeting is adjourned. Several NRC representatives will also be available for an extended information session both prior to and during the Annual Assessment Meeting with Entergy. The information session is being provided to maximize discussion with the public to ensure their issues and concerns may be presented, understood, and considered by the NRC.

2 The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Website, www.nrc.gov, and contains information regarding visitors and security.

The NRCs Annual Assessment Letter - Indian Point Nuclear Generating Units 2 and 3, can be located in ADAMS (Accession Number ML090620503). ADAMS is accessible from the NRC Web Site at: http://www.nrc.gov/reading-rm/adams.html.

Additional information relative to the NRC's Annual Assessment Process and the safety performance of Indian Point Nuclear Generating Units 2 and 3 can be found on the NRC's web site at: www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Meeting

Contact:

Mel Gray, Chief, Projects Branch 2 610-337-5029 E-mail: mel.gray@nrc.gov

  • Handicapped persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by May 7, 2009, via telephone to the NRC meeting contact.

Approved by: _/RA/______________

Mel Gray, Chief Projects Branch 2 Division of Reactor Projects cc w/encl:

Senior Vice President, Entergy Nuclear Operations Vice President, Operations, Entergy Nuclear Operations Vice President, Oversight, Entergy Nuclear Operations Senior Manager, Nuclear Safety and Licensing, Entergy Nuclear Operations Senior Vice President and COO, Entergy Nuclear Operations Assistant General Counsel, Entergy Nuclear Operations Manager, Licensing, Entergy Nuclear Operations C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law A. Donahue, Mayor, Village of Buchanan J. G. Testa, Mayor, City of Peekskill R. Albanese, Four County Coordinator S. Lousteau, Treasury Department, Entergy Services, Inc.

Chairman, Standing Committee on Energy, NYS Assembly Chairman, Standing Committee on Environmental Conservation, NYS Assembly Chairman, Committee on Corporations, Authorities, and Commissions M. Slobodien, Director, Emergency Planning P. Eddy, NYS Department of Public Service Assemblywoman Sandra Galef, NYS Assembly T. Seckerson, County Clerk, Westchester County Board of Legislators A. Spano, Westchester County Executive R. Bondi, Putnam County Executive

3 C. Vanderhoef, Rockland County Executive E. A. Diana, Orange County Executive T. Judson, Central NY Citizens Awareness Network M. Elie, Citizens Awareness Network D. Lochbaum, Director, Nuclear Safety Project, Union of Concerned Scientists Public Citizen's Critical Mass Energy Project M. Mariotte, Nuclear Information & Resources Service F. Zalcman, Pace Law School, Energy Project L. Puglisi, Supervisor, Town of Cortlandt Congressman John Hall Congresswoman Nita Lowey Senator Kirsten E. Gillibrand Senator Charles Schumer G. Shapiro, Senator Gillibrand's Staff J. Riccio, Greenpeace P. Musegaas, Riverkeeper, Inc.

M. Kaplowitz, Chairman of County Environment & Health Committee A. Reynolds, Environmental Advocates D. Katz, Executive Director, Citizens Awareness Network K. Coplan, Pace Environmental Litigation Clinic M. Jacobs, IPSEC W. Little, Associate Attorney, NYSDEC M. J. Greene, Clearwater, Inc.

R. Christman, Manager Training and Development J. Spath, New York State Energy Research, SLO Designee F. Murray, President & CEO, New York State Energy Research A. J. Kremer, New York Affordable Reliable Electricity Alliance (NY AREA)

4 Agenda NRCs Annual Assessment Meeting Information Session Indian Point Nuclear Generating Unit 2 and Unit 3 5:30 p.m. - 9:30 p.m.

May 21, 2009 Information Session .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (5:30 p.m. - 6:30 p.m.)

Annual Assessment Meeting . . . . . . . .. . . . . . . . . . . . . . . . . . . . (6:30 p.m. - 9:30 p.m.)

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (5 minutes)

Review of Reactor Oversight Process . . . . . . . . . . . . . . . . . . . NRC (5 minutes)

Discussion of Indian Point Unit 2 and Unit 3 Performance . . . NRC (15 minutes)

Entergys Response and Remarks . . . . . . . . . . . . . . . . . . . Entergy (15 minutes)

Closing Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . NRC (5 minutes)

Short Break . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (5 minutes)

NRC to address public questions . . . . .NRC/Members of the Public (as needed)

2 The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC Website, www.nrc.gov, and contains information regarding visitors and security.

The NRCs Annual Assessment Letter - Indian Point Nuclear Generating Units 2 and 3, can be located in ADAMS (Accession Number ML090620503). ADAMS is accessible from the NRC Web Site at: http://www.nrc.gov/reading-rm/adams.html.

Additional information relative to the NRC's Annual Assessment Process and the safety performance of Indian Point Nuclear Generating Units 2 and 3 can be found on the NRC's web site at: www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Meeting

Contact:

Mel Gray, Chief, Projects Branch 2 610-337-5029 E-mail: mel.gray@nrc.gov

  • Handicapped persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meeting. Attendance by NRC personnel at this meeting should be made known by May 7, 2009, via telephone to the NRC meeting contact.

Approved by: _/RA/______________

Mel Gray, Chief Projects Branch 2 Division of Reactor Projects Distribution w/encl: (VIA E-MAIL)

Executive Director for Operations, OEDO (RIDSEDOMAILCENTER RESOURCES)

Deputy Executive Director for Reactor Programs, OEDO (RIDSEDOMAILCENTER RESOURCES)

Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD)

Deputy Director, Office of Nuclear Reactor Regulation, NRR/ADPR (RIDSNRROD)

RIDSNRRADRO RIDSNRRDIRSLPAB RIDSNRRDORlLpl1-1 RIDSNRRDIRS RIDSNRRDORL RIDSNRRDORlLpl1-2 Asst. General Counsel Materials Litigation and Enforcement, OGC (RIDSOGCMAILCENTER)

S. Collins, RA G. Malone, DRP D. Tifft, SLO M. Dapas, DRA P. Cataldo, DRP Region I Docket Room D. Lew, DRP C. Hott, DRP (w/concurrences)

J. Clifford, DRP T. Koonce, DRP G. Matakas, ORA S. Campbell, RI OEDO J. Boska, PM NRR C. ODaniell, ORA A. Stuyvenberg, PM J. Hughey, NRR DRP Division Secretary, RI S. Lopas, PM D. Roberts, DRS DRS Division Secretary, RI J. Boska, PM P. Wilson, DRS DNMS Division Secretary, RI J. Hughey, PM D. Screnci, PAO DRM Division Secretary, RI M. Gray, DRP N. Sheehan, PAO Region I Receptionist B. Bickett, DRP N. McNamara, SLO SUNSI Review Complete: SCM (Reviewer=s Initials) Non-Public Designation Category: MD 3.4 Non-Public (A.3 - A.7 or B.1)

DOCUMENT NAME: G:\DRP\BRANCH2\Meetings\2009 Annual Assessment Meetings\IP\Indian Point Meeting Notice.doc After declaring this document AAn Official Agency Record@ it will/will not be released to the Public.