ML043140405

From kanterella
Jump to navigation Jump to search
IR 05000361-04-004, IR 05000362-04-004, on 06/27/2004 - 09/26/2004, San Onofre Nuclear Generating Station, Units 2 & 3; Integrated Resident and Regional Report; Operability Evaluation
ML043140405
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 11/09/2004
From: Kennedy K
NRC/RGN-IV/DRP/RPB-C
To: Ray H
Southern California Edison Co
References
IR-04-004
Download: ML043140405 (29)


See also: IR 05000361/2004004

Text

November 9, 2004

Harold B. Ray, Executive Vice President

San Onofre, Units 2 and 3

Southern California Edison Co.

P.O. Box 128, Mail Stop D-3-F

San Clemente, CA 92674-0128

SUBJECT: SAN ONOFRE NUCLEAR GENERATING STATION - NRC INTEGRATED

INSPECTION REPORT 05000361/2004004; 050000362/2004004

Dear Mr. Ray:

On September 26, 2004, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your San Onofre Nuclear Generating Station, Units 2 and 3, facility. The enclosed

integrated report documents the inspection findings, which were discussed on July 1, July 30,

August 5, and September 24, 2004, with Mr. J. Wambold and other members of your staff.

The inspection examined activities conducted under your licenses as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions of your

licenses. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel.

Based on the results of this inspection, the NRC has identified one issue that was evaluated

under the risk significance determination process as having very low safety significance

(Green). The NRC has also determined that a violation was associated with this issue. The

violation is being treated as a noncited violation (NCV), consistent with Section VI.A of the

Enforcement Policy. The NCV is described in the subject inspection report. Additionally, two

licensee-identified violations, which were determined to be of very low safety significance, are

listed in Section 4OA7 of this report. If you contest the violation or significance of the NCV, you

should provide a response within 30 days of the date of this inspection report, with the basis for

your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001, with copies to the Regional Administrator, U.S. Nuclear

Regulatory Commission, Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington, Texas 76011;

the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC

20555-0001; and the NRC Resident Inspector at the San Onofre Nuclear Generating Station,

Units 2 and 3, facility.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be made available electronically for public inspection

in the NRC Public Document Room or from the Publicly Available Records (PARS) component

Southern California Edison Company -2-

of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

K. M. Kennedy, Chief

Project Branch C

Division of Reactor Projects

Dockets: 50-361

50-362

Licenses: NPF-10

NPF-15

Enclosure:

NRC Inspection Report 05000361/2004004; 05000362/2004004

w/Attachment: Supplemental Information

cc w/enclosure:

Chairman, Board of Supervisors

County of San Diego

1600 Pacific Highway, Room 335

San Diego, CA 92101

Gary L. Nolff

Power Projects/Contracts Manager

Riverside Public Utilities

2911 Adams Street

Riverside, CA 92504

Eileen M. Teichert, Esq.

Supervising Deputy City Attorney

City of Riverside

3900 Main Street

Riverside, CA 92522

Joseph J. Wambold, Vice President

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

Southern California Edison Company -3-

David Spath, Chief

Division of Drinking Water and

Environmental Management

California Department of Health Services

P.O. Box 942732

Sacramento, CA 94234-7320

Michael R. Olson

San Onofre Liaison

San Diego Gas & Electric Company

P.O. Box 1831

San Diego, CA 92112-4150

Ed Bailey, Chief

Radiologic Health Branch

State Department of Health Services

P.O. Box 997414 (MS 7610)

Sacramento, CA 95899-7414

Mayor

City of San Clemente

100 Avenida Presidio

San Clemente, CA 92672

James D. Boyd, Commissioner

California Energy Commission

1516 Ninth Street (MS 34)

Sacramento, CA 95814

Douglas K. Porter, Esq.

Southern California Edison Company

2244 Walnut Grove Avenue

Rosemead, CA 91770

Dwight E. Nunn, Vice President

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

Dr. Raymond Waldo

Southern California Edison Company

San Onofre Nuclear Generating Station

P. O. Box 128

San Clemente, CA 92674-0128

Southern California Edison Company -4-

A. Edward Scherer

Southern California Edison

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

Chief, Technological Services Branch

FEMA Region IX

1111 Broadway, Suite 1200

Oakland, CA 94607-4052

Southern California Edison Company -5-

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (GLS)

Senior Resident Inspector (CCO1)

Branch Chief, DRP/C (KMK)

Senior Project Engineer, DRP/C (WCW)

Team Leader, DRP/TSS (RVA)

RITS Coordinator (KEG)

DRS STA (DAP)

Matt Mitchell, OEDO RIV Coordinator (MAM4)

SONGS Site Secretary (SFN1)

Acting Site Secretary (VLH)

Dale Thatcher (DFT)

W. A. Maier, RSLO (WAM)

ADAMS: /Yes G No Initials: __wcw____

/ Publicly Available G Non-Publicly Available G Sensitive / Non-Sensitive

R:\_SO23\2004\SO2004-04R-CCO.wpd

RIV:RI:DRP/C SRI:DRP/C C:DRS/PSB C:DRS/OB

MASitek CCOsterholtz MPShannon ATGody

E - WCWalker E - WCWalker LRicketson for /RA/

11/3/04 11/3/04 11/4/04 11/3/04

C:DRS/EB C:DRS/PEB C:DRP/C

JAClark LJSmith KMKennedy

LEEllershaw for /RA/ /RA/

11/3/04 11/3/04 11/9/04

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Dockets: 50-361, 50-362

Licenses: NPF-10, NPF-15

Report: 05000361/2004004 and 5000362/2004004

Licensee: Southern California Edison Co. (SCE)

Facility: San Onofre Nuclear Generating Station, Units 2 and 3

Location: 5000 S. Pacific Coast Hwy.

San Clemente, California

Dates: June 27 through September 26, 2004

Inspectors: C. C. Osterholtz, Senior Resident Inspector, Project Branch C, DRP

M. A. Sitek, Resident Inspector, Project Branch C, DRP

D. R. Carter, Health Physicist, Plant Support Branch, DRS

P. J. Elkmann, Emergency Preparedness Inspector, Operations Br., DRS

R. P. Mullikin, Senior Reactor Inspector, Plant Engineering Branch, DRS

N. L. Salgado, Senior Resident Inspector, Project Branch D, DRP

Approved By: Kriss M. Kennedy, Chief

Project Branch C

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

IR 05000361/2004004, 05000362/2004004; 06/27 - 09/26/04; San Onofre Nuclear Generating

Station, Units 2 & 3; Integrated Resident and Regional Report; Operability Evaluation.

This report covered a 3-month period of inspection by Resident and Regional office inspectors.

One Green noncited violation was identified. The significance of most findings is indicated by

their color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, "Significance

Determination Process." Findings for which the significance determination process does not

apply may be Green or be assigned a severity level after NRC management's review. The

NRCs program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, "Reactor Oversight Process," Revision 3, dated July 2000.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

  • Green. The inspectors identified a noncited violation of Technical

Specification 5.5.1.1 from a self-revealing finding because the licensee failed to

provide adequate instructions in a maintenance order for the replacement of a

power indicating lamp in a power supply associated with the Unit 2 Train A

emergency diesel generator. The implementation of the inadequate

maintenance order resulted in the unplanned inoperability of the Unit 2 Train A

emergency diesel generator for approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

The finding was determined to be more than minor because it affected the

procedure quality attribute of the mitigating systems cornerstone. The finding

was determined to have very low safety significance (Green) because the

inadequate maintenance order instructions did not result in an actual loss of

safety function. In addition, the fuel transfer pumps were still capable of being

started locally through manual operator action (Section 1R15).

B. Licensee-Identified Violations

Violations of very low safety significance which were identified by the licensee have

been reviewed by the inspectors. Corrective actions taken or planned by the licensee

have been entered into the licensee's corrective action program. These violations and

the associated corrective actions are listed in Section 4OA7 of this report.

Enclosure

REPORT DETAILS

Summary of Plant Status

Unit 2 began the inspection period at approximately 100 percent reactor power and remained at

that power level throughout the inspection period.

Unit 3 began the inspection period at approximately 100 percent reactor power. On

September 10, 2004, Unit 3 was reduced to approximately 85 percent reactor power in order to

address minor intermittent saltwater inleakage into the feedwater system from the condenser.

The circulating water pump associated with the northwest condenser hotwell was taken out of

service and four condenser tubes were plugged. The inleakage stopped and Unit 3 was

returned to approximately 100 percent reactor power on September 12, 2004, where it

remained through the end of the inspection period.

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity

1R01 Adverse Weather Protection (71111.01)

a. Inspection Scope

The inspectors reviewed the design features and procedures for protecting Units 2

and 3 mitigating systems from the adverse effects of high winds and temperatures

(three inspection samples).

The inspectors reviewed Procedure S023-13-8, Severe Weather, Revision 3,

interviewed licensee personnel, and directly observed systems and plant conditions.

The inspectors reviewed licensee actions to minimize the occurrence and impact of

brush fires that are likely to occur during high temperatures and/or high winds. The

inspectors examined: (1) brush growth and clearance, (2) fire department equipment

and training, (3) fire department coordination with offsite firefighting organizations, and

(4) past history of brush fire impact on the facility. The inspectors also reviewed

Procedure S0123-XIII-4.10.7, Fire Department Offsite Response Procedure, Revision

3. In addition, the inspectors walked down areas around Units 2 and 3 to determine the

potential hazard associated with wind-generated missiles.

The inspectors also reviewed the following three systems to ensure that their safety

functions were adequately protected against high temperatures:

  • Safety Injection System

Enclosure

-2-

b. Findings

No findings of significance were identified.

1R04 Equipment Alignment

a. Inspection Scope

1. Partial System Walkdowns. The inspectors performed three partial walkdowns during

this inspection period (three inspection samples). To evaluate the operability of the

selected train or system when the redundant train or system was inoperable or out of

service, the inspectors verified correct valve and power alignments by comparing

positions of valves, switches, and electrical power breakers to the procedures listed

below as well as applicable chapters of the Updated Final Safety Analysis Report:

  • On July 6, the inspectors walked down the Unit 2 Train B EDG while the Train A

EDG was out of service for planned maintenance.

  • On August 20, the inspectors walked down the Unit 2 Train A EDG while the

Train B EDG was out of service for planned maintenance.

  • On September 1, the inspectors walked down the Unit 3 Train A component

cooling water system while the Train B component cooling water system was out

of service for planned maintenance.

b. Findings

No findings of significance were identified

1R05 Fire Protection (71111.05)

a. Inspection Scope

The inspectors performed routine fire inspection tours and reviewed relevant records for

the following six plant areas important to reactor safety (six inspection samples):

  • Unit 3 Train A EDG
  • Unit 3 Train B EDG
  • Unit 2 B009 battery room
  • Unit 2 B010 battery room
  • Unit 2 saltwater cooling pump room
  • Unit 3 Saltwater cooling pump room

Enclosure

-3-

The inspectors observed the material condition of plant fire protection equipment, the

control of transient combustibles, and the operational status of barriers. The inspectors

compared in-plant observations with the commitments in portions of the Updated Fire

Hazards Analysis Report.

b. Findings

No findings of significance were identified.

1R06 Flood Protection Measures (71111.06)

a. Inspection Scope

The inspectors performed an annual visual inspection of the plant intake structure

(Units 2 and 3) to determine the operational status of seals, barriers, sumps, drains, and

alarms to identify the existence of any unanalyzed flooding hazards (one inspection

sample). The inspectors also reviewed Updated Safety Analysis Report Chapter 3.4,

Water Level (Flood) Design, Revision 13.

b. Findings

No findings of significance were identified.

1R11 Licensed Operator Requalification (71111.11Q)

a. Inspection Scope

The inspectors reviewed licensed operator requalification training activities (one

inspection sample), including the licensed operators performance and the evaluators

critique. The inspectors compared performance in the simulator on August 26, 2004,

with performance observed in the control room during this inspection period.

The inspectors observed high-risk operator actions, operator activities associated with

the emergency plan, and reviewed previous lessons-learned items. These items were

evaluated to ensure that operator performance was consistent with protection of the

reactor core during postulated accidents.

b. Findings

No findings of significance were identified.

Enclosure

-4-

1R12 Maintenance Effectiveness (71111.12)

1. Routine Maintenance Effectiveness

a. Inspection Scope

The inspectors independently verified that the licensee appropriately handled safety

significant component performance associated with saltwater cooling check valves (one

inspection sample). The inspectors reviewed AR 040500132 and discussed the plan for

modifying the check valves with engineering and maintenance personnel.

b. Findings

No findings of significance were identified.

2. Periodic Evaluation Reviews

a. Inspection Scope

The inspectors reviewed the San Onofre Nuclear Generating Station report

documenting the performance of the last maintenance rule periodic effectiveness

evaluation to confirm that it was performed in accordance with 10 CFR 50.65(a)(3) (one

inspection sample). The licensees periodic evaluation covered the period from July 1,

2001, through June 30, 2003.

The inspectors reviewed the handling of risk significant structures, systems, and

components with degraded performance or degraded condition to assess the

effectiveness of the licensees evaluation and the resulting corrective actions.

Inspection Procedure 71111.12, Maintenance Effectiveness, requires 3-5 risk

significant examples. The inspectors reviewed five examples: 4 kv system, dc system,

component cooling water system, containment isolation system, and radiation

monitoring system. Additionally, the performance of nonrisk-significant functions were

monitored using plant level criteria.

The inspectors evaluated the use of performance history and industry experience to

adjust the preventive maintenance requirements to adjust (a)(1) goals and to adjust the

(a)(2) performance criteria. The inspectors assessed the licensees adjustment of the

scope of the maintenance rule, the licensees adjustment of the definition of

maintenance rule functional failures, the licensees adjustment of definitions of

available/unavailable hours and required hours, and the licensees review and

adjustment of condition-monitoring parameters and action levels.

The inspectors also reviewed the conclusions reached by licensee personnel with regard

to the balance of reliability and unavailability for specific maintenance rule functions.

This review was conducted by examining the licensees evaluation of all risk significant

functions that had exceeded performance criteria during the evaluation period.

Enclosure

-5-

b. Findings

No findings of significance were identified.

1R13 Maintenance Risk Assessments and Emergent Work Evaluation (71111.13)

a. Inspection Scope

The inspectors verified the accuracy and completeness of risk assessment documents

and that the licensees maintenance risk assessment program was being appropriately

implemented. The inspectors also ensured that plant personnel were aware of the

appropriate licensee established risk categories for maintenance activities, according to

the risk assessment results and licensee program procedures.

The inspectors also reviewed selected emergent work items to ensure that overall plant

risk was being properly managed and that appropriate corrective actions were being

properly implemented.

The inspectors reviewed the effectiveness of risk assessment and risk management for

the following four activities (four inspection samples):

  • Unit 3 Train A EDG 3G002 automatic voltage regulator series boost capacitor

failure (AR 040700701)

  • Unit 3 Train B EDG 3G003 radiator fan thermal overload trip (AR 040701362)
  • Unit 3 Train B Component Cooling Water Heat Exchanger 3E002 tube leak

(AR 040900059)

  • Unit 2 Train B Charging Pump 2P192 water in crankcase oil (AR 040900660)

b. Findings

No findings of significance were identified.

1R15 Operability Evaluations (71111.15)

1. Unit 2 Train A EDG 2G002 Loss of Fuel Oil Storage Tank Level Indication

a. Inspection Scope

The inspectors reviewed Unit 2 EDG 2G002 operability following the loss of the

automatic functions of the fuel oil transfer system during a maintenance activity (one

inspection sample).

Enclosure

-6-

b. Findings

Introduction. A Green, self-revealing, noncited violation of Technical Specification (TS)

5.5.1.1, was identified for the implementation of an inadequate maintenance order which

rendered EDG 2G002 inoperable for approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

Description. On August 3, 2004, a technician performed maintenance on the Train A

EDG 2G002 fuel storage tank level instrument power supply under maintenance

order (MO) 03081421000. The scope of the work in the MO required the technician to

replace the power supply power indicating lamp with a WAMCO B2A-R lamp. The

technician used a WAMCO B2A lamp instead, which did not include a dropping resistor

in the base of the lamp. As a result, a fuse in the fuel storage tank level instrument

power supply blew, causing the low-low level cutout for the fuel transfer pumps to

deenergize. The inability of the fuel transfer pumps to automatically start led operations

personnel to declare EDG 2G002 inoperable and to enter the action statements for

TS 3.8.1, AC Sources - Operating, in accordance with the applicable annunciator

response procedure. Maintenance personnel subsequently recognized that the

incorrect lamp was installed and returned the power supply to its original configuration,

which allowed operators to exit the TS action statements after approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.

The licensee determined that the technician was confused by the instructions in the MO

and that the instructions in the MO were contradictory and inaccurate. Specifically, the

MO problem statement implies that the WAMCO B2A lamp is the correct part, while at

the same time instructing the technician to use a WAMCO B2A-R lamp. Furthermore, in

the planning phase of the MO, the licensee did not recognize the impact that the lamp

replacement activity could have on EDG operability.

Analysis. The failure of the licensee to provide clear instructions in the MO was

considered to be a performance deficiency. The finding was determined to be more

than minor because it affected the procedure quality attribute of the mitigating systems

cornerstone. Based on the results of the significance determination process (Phase 1

evaluation), the finding was determined to have very low safety significance (Green)

because the inadequate MO instructions did not result in an actual loss of safety

function. In addition, the fuel transfer pumps were still capable of being started locally

through manual operator action.

Enforcement. TS 5.5.1.1 states, in part, that written procedures shall be established,

implemented, and maintained covering the applicable procedures recommended in

Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33,

Section 9, Procedures for Performing Maintenance, specifies that maintenance that

can affect the performance of safety-related equipment should be properly preplanned

and performed in accordance with documented instructions appropriate to the

circumstances. Contrary to this criterion, on August 3, 2004, the licensee failed to

provide adequate instructions in an MO for the replacement of a power indicating lamp

in a power supply associated with the Unit 2 Train A EDG. This violation of the TSs is

being treated as a noncited violation (NCV 05000361/2004004-01, failure to provide

Enclosure

-7-

adequate instructions for EDG maintenance) consistent with Section VI.A of the

Enforcement Policy. This violation is in the licensees corrective action program as

AR 040800105.

2. Routine Operability Evaluation Reviews

a. Inspection Scope

The inspectors reviewed selected operability evaluations to evaluate technical adequacy

and to verify that operability was justified. The inspectors considered the impact on

compensatory measures for each condition being evaluated, and referenced the

Updated Final Safety Analysis Report and TSs. The inspectors also discussed the

evaluations with cognizant licensee personnel.

The inspectors reviewed four operability evaluations (four inspection samples) and

cause assessments documented in the following ARs to ensure the operability was

properly justified:

  • AR 040801442, Unit 3 Component Cooling Water cross-train leakage
  • AR 040501377, Control Room Tracer Gas Testing (Units 2 and 3)
  • AR 040500047, Unit 2 High Pressure Safety Injection Valve HV-9332 degraded

position indication

dump valve solenoids

b. Findings

No findings of significance were identified.

1R16 Operator Workarounds (71111.16)

a. Inspection Scope

The inspectors reviewed the following two operator workarounds (two inspection

samples) to determine if the functional capability of the system or human reliability in

responding to an initiating event was affected by the workaround. The inspectors

evaluated the effect that the operator workaround had on the operator's ability to

implement abnormal or emergency operating procedures.

  • Verification of increase in amperage of Unit 3 electrical Bus 3B04 with

postaccident cleanup Unit 3ME370 in service with a degraded air flow chart

recorder

Enclosure

-8-

following a main transformer fault without the use of the automatic trip function of

Relay 49X-1

b. Findings

No findings of significance were identified.

1R19 Postmaintenance Testing (71111.19)

a. Inspection Scope

The inspectors observed and/or reviewed postmaintenance testing for the following

seven activities (seven inspection samples) to verify that the test procedures and

activities adequately demonstrated system operability:

  • Unit 3 containment emergency suction line fill verification per Procedure SO23-5-

1.3, Plant Startup from Cold Shutdown to Hot Standby, Revision 25, performed

on February 9, 2003

  • Unit 2 containment emergency suction line fill verification per Procedure SO23-3-

2.7.2, Filling the Containment Emergency Sump Suction Lines, Revision 11,

performed on March 2, 2004

  • Unit 2 Inverter Power Supply Bus 2Y02 postmaintenance test per

Procedure SO23-6-17, Swapping Kirk Keyed Alternate Power Supply Breakers

When Both Vital Buses are Energized from the Inverters, Revision 10,

performed on July 21, 2004

  • Unit 3 Inverter Power Supply Bus 3Y04 postmaintenance test per

Procedure SO23-6-17, Swapping Kirk Keyed Alternate Power Supply Breakers

When Both Vital Buses are Energized from the Inverters, Revision 10,

performed on July 21, 2004

  • Unit 3 Pressurizer Surge Line Isolation Valve 3HV0513 postmaintenance test per

MO 04030211000, performed on August 4, 2004

  • Unit 3 Train A Component Cooling Water Heat Exchanger 3E001

postmaintenance test per Procedure SO23-2-8.1, Draining and Returning to

Service CCW HX E001 Saltwater Side and SWC System Piping, Revision 2,

performed on August 12, 2004

  • Unit 2 EDG 2G002 postmaintenance test per Procedure SO23-3-3.23, Diesel

Generator G003 Semi-annual Surveillance, Revision 23, performed on

August 20, 2004

Enclosure

-9-

b. Findings

No findings of significance were identified.

1R22 Surveillance Testing (71111.22)

a. Inspection Scope

The inspectors observed and/or reviewed performance and documentation for the

following four surveillance tests (four inspection samples) to verify that the structures,

systems, and components were capable of performing their intended safety functions

and to assess their operational readiness:

  • Unit 3 Train A EDG 3G002 24-month surveillance per Procedure SO23-3-3.23.1,

Diesel Generator Refueling Interval Tests, Revision 20, performed July 14,

2004

Procedure SO23-3-3.60.6, Auxiliary Feedwater Pump and Valve Testing,

Revision 10, performed on July 21, 2004

  • Unit 2 Battery B010 12-month surveillance per Procedure SO123-I-2.6, Battery

Performance Test and Rapid Recharge, Revision 7, performed on September 6,

2004

  • Unit 2 Battery B009 12-month surveillance per Procedure SO123-I-2.6, Battery

Performance Test and Rapid Recharge, Revision 7, performed on

September 20, 2004

b. Findings

No findings of significance were identified.

1R23 Temporary Plant Modifications (71111.23)

a. Inspection Scope

The inspectors reviewed the following three temporary plant modifications (three

inspection samples) to verify that the safety functions of safety systems were not

affected:

  • Temporary Engineering Change Package 030301058-7, Change Input to

3PV0100B Positioner (Unit 3)

  • Temporary Engineering Change Package 040701007-1, Conduct Performance

Test on Battery 2B009 By Utilizing Battery B00X (Unit 2)

Enclosure

-10-

  • Temporary Engineering Change Package 040701007-2, Conduct Performance

Test on Battery 2B010 By Utilizing Battery B00X (Unit 2)

b. Findings

No findings of significance were identified.

Cornerstone: Emergency Preparedness

1EP2 Alert Notification System Testing (71114.02)

a. Inspection Scope

The inspector discussed with licensee staff the status of offsite siren systems to

determine the adequacy of the licensees methods for testing the alert and notification

system in accordance with 10 CFR Part 50, Appendix E. The licensees alert and

notification system testing program was compared with criteria in NUREG-0654,

Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and

Preparedness in Support of Nuclear Power Plants, Revision 1, with Federal Emergency

Management Agency Report REP-10, Guide for the Evaluation of Alert and Notification

Systems for Nuclear Power Plants, and the licensees current Federal Emergency

Management Agency approved alert and notification system design report. The

inspector also reviewed Procedures SO123-VIII-0.301, Emergency

Telecommunications Testing, Revision 10, and SO123-VIII-0.302, Onsite Emergency

Siren System Test, Revision 3.

b. Findings

No findings of significance were identified.

1EP3 Emergency Response Organization Augmentation Testing (71114.03)

a. Inspection Scope

The inspector discussed with licensee staff the status and configuration of primary and

backup systems for staffing licensee emergency response facilities in accordance with

the licensee emergency plan and the requirements of 10 CFR Part 50 Appendix E. The

licensees emergency recall system was compared with criteria in NUREG-0654,

Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and

Preparedness in Support of Nuclear Power Plants, Revision 1. The inspector also

compared the recall system to the requirements of Procedures SO123-VIII-30.7,

Emergency Notifications, Revision 4, and SO123-VIII-0.201, Emergency Plan

Equipment Surveillance Program, Revision 13. The inspector also reviewed the results

of 19 emergency response organization pager and recall tests conducted February 2003

through March 2004.

Enclosure

-11-

b. Findings

No findings of significance were identified.

1EP5 Correction of Emergency Preparedness Weaknesses and Deficiencies (71114.05)

a. Inspection Scope

The inspector reviewed documents related to the licensees corrective action program,

as described in the attachment, to determine the licensees ability to identify and correct

problems in accordance with 10 CFR 50.47(b)(14) and 10 CFR Part 50, Appendix E.

b. Findings

No findings of significance were identified.

1EP6 Drill Evaluation (71114.06)

a. Inspection Scope

The inspectors observed one (one inspection sample) emergency preparedness drill to

evaluate the drill conduct and the adequacy of the licensees performance critique. The

inspectors observed one site-wide drill from the simulator, Technical Support Center,

and Emergency Operating Facility on June 30, 2004.

b. Findings

No findings of significance were identified.

2. RADIATION SAFETY

Cornerstone: Occupational Radiation Safety

2OS2 ALARA (as Low as is Reasonably Achievable) Planning and Controls (71121.02)

a. Inspection Scope

The inspector assessed licensee performance with respect to maintaining individual and

collective radiation exposures ALARA. The inspector used the requirements in 10 CFR

Part 20 and the licensees procedures required by TSs as criteria for determining

compliance. The inspector interviewed licensee personnel and reviewed:

  • Current 3-year rolling average collective exposure

Enclosure

-12-

  • Five outage maintenance work activities scheduled during the inspection period

and associated work activity exposure estimates which were likely to result in the

highest personnel collective exposures

  • Site-specific trends in collective exposures, plant historical data, and source-term

measurements

  • Site-specific ALARA procedures
  • ALARA work activity evaluations, exposure estimates, and exposure mitigation

requirements

  • Interfaces between operations, radiation protection, and maintenance planning
  • Integration of ALARA requirements into work procedure and radiation exposure

permit documents

  • Shielding requests and dose/benefit analyses
  • Postjob (work activity) reviews
  • Method for adjusting exposure estimates, or replanning work, when unexpected

changes in scope or emergent work were encountered

  • Exposures of individuals from selected work groups
  • Radiation worker and radiation protection technician performance during work

activities in radiation areas or high radiation areas

  • Declared pregnant workers during the current assessment period, monitoring

controls, and the exposure results

  • Corrective action documents related to the ALARA program and followup

activities, such as initial problem identification, characterization, tracking, and

resolution

The inspector completed 8 of the required 15 samples and 6 of the optional samples.

b. Findings

No findings of significance were identified.

Enclosure

-13-

4. OTHER ACTIVITIES

4OA1 Performance Indicator Verification (71151)

a. Inspection Scope

The inspectors sampled licensee submittals for the five performance indicators listed

below for the period October 1, 2003, through June 30, 2004, for Units 2 and 3. The

definitions and guidance of Nuclear Energy Institute 99-02, Regulatory Assessment

Indicator Guideline, Revision 2, were used to verify the licensees basis for reporting

each data element in order to verify the accuracy of performance indicator data reported

during the assessment period. Licensee performance indicator data were also reviewed

against the requirements of Procedures SO23-NI-1, NRC Performance Indicator

Program, Revision 3, and SO23-XV-24, Quarterly NRC Performance Indicator

Process, Revision 2.

Reactor Safety Cornerstone

  • Drill and Exercise Performance
  • Emergency Response Organization Participation
  • Alert and Notification System Reliability

The inspectors reviewed 100 percent of drill and exercise scenarios and licensed

operator simulator training sessions, notification forms, and attendance and critique

records associated with training sessions, drills, and exercises conducted during the

verification period. The inspectors reviewed emergency responder drill participation

records and rosters. The inspectors reviewed alert and notification system testing

procedures, maintenance records, and a 100 percent sample of siren test records. The

inspector also interviewed licensee personnel responsible for collecting and evaluating

performance indicator data.

b. Findings

No findings of significance were identified.

4OA2 Identification and Resolution of Problems (71152)

1. Maintenance Rule Review

a. Inspection Scope

The inspectors evaluated the use of the corrective action system within the

maintenance rule program for issues associated with risk significant systems. The

review was accomplished by the examination of a sample of corrective action

Enclosure

-14-

documents, maintenance work items, and other documents listed in the attachment.

The purpose of the review was to establish that the corrective action program was

entered at the appropriate threshold for the purpose of:

  • Implementation of the corrective action process when a performance criterion

was exceeded

  • Correction of performance-related issues or conditions identified during the

periodic evaluation

  • Correction of generic issues or conditions identified during programmatic

assessments, audits, or surveillances.

The purpose of the review was to determine that the identification of problems and

implementation of corrective actions were acceptable.

b. Findings

No findings of significance were identified.

2. ALARA Review

a. Inspection Scope

Section 2OS2 evaluated the effectiveness of the licensee's problem identification and

resolution processes regarding exposure tracking, higher than planned exposure levels,

and radiation worker practices. The inspectors reviewed the corrective action documents

listed in the attachment against the licensees problem identification and resolution

program requirements.

b. Findings

No findings of significance were identified.

3. Emergency Planning Review

a. Inspection Scope

The inspector selected 24 ARs (corrective action program inputs) for detailed review

based on their linkage with event classification, notification of offsite authorities, and

processes for providing protective action recommendations. The reports were reviewed

to ensure that the full extent of the issues were identified, an appropriate evaluation was

performed, and appropriate corrective actions were specified and prioritized. The

inspector evaluated the ARs against the requirements of Procedures SO123-XV-50,

Enclosure

-15-

Corrective Action Process, Revision 4, SO123-XX-1, Action Request/Maintenance

Order Initiation Process, Revision 15-2, and SO123-XV-50.39, Cause Evaluation

Standards, Methods, and Instructions, Revision 4-1.

b. Findings

No findings of significance were identified.

4. Annual Sample Review

a. Inspection Scope

The inspectors selected AR 040900011 for a detailed review. This AR was written in

response to a Unit 3 Loop 1 reactor coolant hot leg instrument failing to stay in

calibration.

b. Findings and Observations

No findings of significance were identified. However, the inspectors noted that

AR 040900011 had been closed without any corrective actions identified or documented.

AR 040900011 indicated that the Unit 3 loop one reactor coolant hot leg instrument failed

to stay in calibration after two attempts. The AR had been closed with only the words

This was determined to be a non problem. After interviewing several licensee

personnel, the inspectors discovered that the reason the hot leg instrument was not

staying in calibration was because a test technician incorrectly attached a test decade

box to the instrument during calibration. The licensee discovered and corrected the

problem, but did not consider any corrective actions to prevent recurrence. Licensee

management indicated that this did not meet expectations and indicated that the AR

would be reopened to reference the MO that described the problem and that Lessons

Learned training would be provided to the maintenance staff on the issue to help prevent

recurrence. The inspectors considered the licensees followup actions appropriate.

5. Quarterly Review of Corrective Action Documents

a. Inspection Scope

The inspectors reviewed a selection of ARs written during this period to determine if: the

licensee was entering conditions adverse to quality into the corrective action program at

an appropriate threshold; the ARs were appropriately categorized and dispositioned in

accordance with the licensee's procedures; and, in the case of significant conditions

adverse to quality, the licensee's root cause determination and extent of condition

evaluation were accurate and of sufficient depth to prevent recurrence of the condition.

b. Findings

No findings of significance were identified.

Enclosure

-16-

4OA3 Event Followup (71153)

1. (Closed) Licensee Event Report (LER) 05000361/2004-001-00: Personnel Error Results

in TS Violation During Movement of Irradiated Fuel

On March 7, 2004, the licensee identified that TS 3.7.14, Fuel Handling Building Post-

Accident Cleanup Filter System [PACU], was violated during the movement of irradiated

fuel. The Train B PACU was inoperable at the time of the fuel movement and the Train A

PACU was operating in the parallel mode as opposed to the isolate mode that was

required by TS 3.7.14. Fuel movement occurred for approximately 19 hours2.199074e-4 days <br />0.00528 hours <br />3.141534e-5 weeks <br />7.2295e-6 months <br /> before the

condition was recognized. Fuel movement was immediately suspended and the Train A

PACU was placed in the isolate mode. The cause of the event was attributed to

operations personnel failing to review the procedure that established the requirements for

the movement of irradiated fuel. The procedure contained steps that would have directed

the operators to place the Train A PACU in the isolate mode of operation. The

inspectors reviewed the LER and no new findings were identified. The inspectors

considered this issue to be minor because:

  • The fuel handling accident analysis does not credit the PACU operation for dose

mitigation.

  • One train of PACU was operating to mitigate a fuel handling accident.
  • One FHIS channel was operable and able to isolate the FHB if a fuel handling

accident occurred.

  • This event was not caused by nor did it result in a safety system functional

failure (SSFF). This event did not impact the ability to shut down the unit or mitigate

the consequences of an accident.

This finding constitutes a violation of minor significance that is not subject to enforcement

action in accordance with Section IV of the NRCs Enforcement Policy. The licensee also

documented the issue in AR 040300624.

2. (Closed) LER 05000361;362/2004-003-00: Momentary Loss of Operability of the Offsite

Power Grid due to 230 kV Transmission Line Fault in Arizona

On June 14, 2004, offsite power frequency dropped below the TS minimum of 59.7 Hz

for approximately 2 minutes due to a grid disturbance that occurred in Arizona. The

lowest frequency recorded during the dip in frequency was 59.5 Hz. The inspectors

considered operator response to the event appropriate, and the momentary dip in

frequency did not disturb plant operation. This LER is closed.

Enclosure

-17-

4OA5 Other

1. Temporary Instruction (TI) 2515/154, Spent Fuel Material Control and Accounting at

Nuclear Power Plants

a. Inspection Scope

The inspectors completed TI 2515/154, Spent Fuel Material Control and Accounting at

Nuclear Power Plants.

b. Findings

No findings of significance were identified.

2. Third-Party Reviews

The inspectors reviewed a third-party assessment dated July 15, 2004. The biennial

assessment was performed from June 7-18, 2004. The inspectors noted that the

assessment was consistent with performance observed by the NRC staff.

4OA6 Meetings, Including Exit

On July 1, July 30, August 5, and September 24, 2004, the Resident and Regional office

inspectors presented the inspection results to Mr. J. Wambold, Mr. D. Nunn, and others

who acknowledged the findings. The inspectors subsequently asked the licensee

whether any materials examined during the inspection should be considered proprietary.

No proprietary information was identified.

4OA7 Licensee-Identified Violations

The following violations of very low significance (Green) were identified by the licensee

and are violations of NRC requirements which meet the criteria of Section VI of the

NRC Enforcement Policy, NUREG-1600, for being dispositioned as noncited

violations (NCV).

  • 10 CFR 50.54(q) requires, in part, that a licensee follow and maintain in effect

emergency plans which meet the standards in §50.47(b) and the requirements in

Appendix E. 10 CFR Part 50, Appendix E, IV.A.2(b), requires that the licensees

emergency plan provide a detailed discussion of plant staff emergency assignments

and the duties of individuals assigned to the licensee's emergency organization.

Contrary to this, the licensees emergency plan did not describe the duties and

responsibilities of some emergency response organization positions. Specifically, the

duties and responsibilities of 5 minimum staff positions and 51 additional responders

were not described in the licensees emergency plan. This was identified in the

Enclosure

-18-

licensees corrective action program in ARs 031200669-18 and 031200669-19. This

finding is of very low safety significance because it did not represent functional

failures of planning standards 10 CFR 50.47(b)(1) or 50.47(b)(2).

drills are corrected. 10 CFR 50.54(q) requires, in part, that the licensee follow and

maintain in effect emergency plans which meet the standards in §50.47(b) and the

requirements in Appendix E. 10 CFR Part 50, Appendix E, IV.F.2(g), requires that all

exercises and drills provide for formal critiques and that any identified weaknesses or

deficiencies be corrected. Contrary to this, the licensee did not enter all identified

weaknesses and deficiencies into its corrective action program. This was identified in

the licensees corrective action program as Apparent Cause Evaluation 040600717.

This finding is of very low safety significance because it did not represent a functional

failure of planning standard 10 CFR 50.47(b)(14).

ATTACHMENT: SUPPLEMENTAL INFORMATION

Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

R. Allen, Supervisor, Reliability Engineering

C. Anderson, Manager, Site Emergency Preparedness

D. Axline, Licensing Engineer, Nuclear Regulatory Affairs

D. Brieg, Manager, Maintenance Engineering

G. Cook, Supervisor, Compliance

M. Cooper, Manager, Plant Operations

B. Culverhouse, Supervisor, Offsite Emergency Planning

M. Goettel, Manager, Business Planning and Financial Services

M. Love, Manager, Maintenance

J. Madigan, Manager, Health Physics

C. McAndrews, Manager, Nuclear Oversight and Assessment

M. McBrearty, Engineer, Nuclear Regulatory Assurance

D. Nunn, Vice President, Engineering and Technical Services

N. Quigley, Manager, Mechanical/Nuclear Maintenance Engineering

J. Ramsdell, Maintenance Rule Coordinator

D. Richards, Supervisor, Onsite Emergency Planning

A. Scherer, Manager, Nuclear Regulatory Affairs

M. Short, Manager, Systems Engineering

T. Vogt, Manager, Operations

R. Waldo, Station Manager

J. Wambold, Vice President, Nuclear Generation

C. Williams, Supervisor, Compliance

T. Yackle, Manager, Design Engineering

NRC Personnel

Christian Araguas, Nuclear Safety Professional Development Program Participant

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000361/2004004-01 NCV Failure to provide adequate instructions for EDG

maintenance (Section 1R15)

Closed

05000361/2004-001-00 LER Personnel Error Results in Technical Specification

Violation During Movement of Irradiated Fuel

A-1 Enclosure

05000361;362/2004-003-00 LER Momentary Loss of Operability of the Offsite Power

Grid due to 230 kV Transmission Line Fault in

Arizona

Discussed

None

LIST OF DOCUMENTS REVIEWED

In addition to the documents listed in the inspection report, the following documents were

selected and reviewed by the inspectors to accomplish the objectives and scope of the

inspection and to support any findings:

Section 1R04: Equipment Alignments

Procedure SO23-2-12.1, Component Cooling Water System Alignments, Revision 6

Procedure SO23-2-17, Component Cooling Water System Operation, Revision 18

Operations Division Manual 5, Operator Rounds, Revision 0

Procedure SO23-3-3.23, Diesel Generator Monthly and Semi-annual Testing, Revision 23

Piping and Instrumentation Diagram 40127ASO3, Component Cooling Water System No.

1203, Revision 27

Section 1R12: Maintenance Implementation

Action Requests

010301123, 020101538, 020800755, 021100192, 021201039, 030202033, 030401327,

030801357, 031101252, 031101253, and 040101394

Maintenance Rule Function Reports

125/250V DC

4160V AC Power

Component Cooling Water

Containment Isolation

Radiation Monitoring - Area, Process, and Effluent

Procedures

SO123-CA-1, Corrective Action Program, Revision 3

SO123-XV-5.3, Maintenance Rule Program, Revision 6

SO123-XV-50, Corrective Action Process, Revision 4

A-2 Enclosure

Miscellaneous Documents

Independent Assessment of Maintenance Rule Implementation, performed April 19-30, 2004

Maintenance Rule Evaluation (MRE) Guideline, Revision 5

Maintenance Rule Expert Panel Meeting Minutes from March 21, 2002, through May 20, 2004

SONGS Maintenance Rule Program (a)(3) Periodic Assessment (3rd Quarter 2001 through 2nd

Quarter 2003), dated October 31, 2003

SONGS System Health Reports (Quarter 2004-1) for DC Power Systems, 4 KV System,

Containment Leak Rate Testing Program, and Component Cooling System

Section 2OS2: ALARA Planning and Controls (71121.02)

Corrective Action Documents and Requests

030201607, 031001084, 030901392, 040100520, 04011521, 040101248, 040101448,

040101751, 040201832, 040500617, 040300392, 040300629, 04021480, 040300629,

040401695, 040401811, 040500671, and 040501354

Audits and Surveillances

Division Self-Assessment Report for the Fourth Quarter 2003

Unit 2 Cycle 13 ALARA In-Progress Reviews

1EP2 Alert Notification System Testing

Procedures:

SO123-XVIII-10, Siren - Community Alert Siren System - System Description and Operational

Guide, Revision 5

SO123-XVIII-10.1, Siren - Community Alert Siren System - Biweekly Silent Test, Revision 4-2

SO123-XVIII-10.3, Siren - Community Alert Siren System - Quarterly Growl Test, Revision 5-3

SO123-XVIII-10.4, Siren - Community Alert Siren System Response to a Report of an

Inadvertent Siren Activation, Revision 3

SO123-XVIII-10.5, Siren - Community Alert Siren System Annual Activation Test Procedures,

Revision 4-1

Section 1EP5: Correction of Emergency Preparedness Weaknesses and Deficiencies

Audit SCES-013-03, Emergency Preparedness, November 27, 2001, through November 26,

2003

Surveillance SOS-064-02, ERO Assignments, October 8, 2002

Surveillance SOS-073-02, Emergency Planning Drills, September 25, 2002

Surveillance SOS-074-62, EOF Emergency Facility Systems, November 29, 2002

Surveillance SOS-077-01, Emergency Plan and ODCM Controls, July 24, 2001

SEP Division Quarterly Self Assessments (8) for the period Second Quarter 2002 through First

Quarter 2004

EP NRC Readiness Review, AR 040600717-10

EP Directed Self Assessment, December 2003 through February 2004

Corrective Action Reports:

021000183 030102372 030700521 030900659 031001265

021000230 030400904 030800139 030901063 040400027

021100577 030501440 030801075 030901063 040400160

021200220 030600920 030900463 031001051 040500381

030100232

Drill Reports:

2003 Environmental Monitoring Drill Critique Report

Critique Report 0203-0205

Critique Report 0206

Critique Report 0302-0305, Revision 1

Critique Report 0306

Critique Report 0307

Critique Report 0312

Procedures:

SO123-CA-1, Corrective Action Program, Revision 3-1

SO123-NP-1, Offsite Emergency Planning Responsibilities and Offsite Interfaces,

Revision 5-3

SO123-XII-18.1, Audit Program, Revisions 8 and 8-2

SO123-SA-1, Self Assessment Program, Revision 2

SO123-VIII-1, Recognition and Classification of Emergencies, Revision 21

SO123-VIII-10.3, Protective Action Recommendations, Revision 8

SO123-VIII-30.7, Emergency Notifications, Revision 4

A-4 Enclosure

SO123-VIII-0.100, Maintenance and Control of Emergency Planning Documents, Revision 7

SO123-VIII-0.200, Emergency Plan Drills and Exercises, Revision 8

LIST OF ACRONYMS

ALARA as low as is reasonably achievable

AR Action Request

CFR Code of Federal Regulations

EDG emergency diesel generator

FEMA Federal Emergency Management Agency

LER licensee event report

MO maintenance order

NCV noncited violation

PACU postaccident cleanup filter system

TI temporary instruction

TS Technical Specification

A-5 Enclosure