Category:Inspection Plan
MONTHYEARML24036A2652024-02-0505 February 2024 Notice of Inspection and Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000266/2024010 and 05000301/2024010 ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection IR 05000266/20230052023-08-24024 August 2023 Updated Inspection Plan for Point Beach Nuclear Plant (Report 05000266/2023005 and 05000301/2023005) ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 IR 05000266/20220062023-03-0101 March 2023 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022006 and 05000301/2022006) ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22256A3182022-09-13013 September 2022 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection Report 05000266/2023010 05000301/2023010 IR 05000266/20220052022-08-26026 August 2022 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2022005 and 05000301/2022005) ML22175A2002022-06-27027 June 2022 Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information: Inspection Report 05000266/2022004: 05000301/2022004 ML22172A2132022-06-22022 June 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML22173A0172022-06-22022 June 2022 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Point Beach Nuclear Plant IR 05000266/20210062022-03-0202 March 2022 Annual Assessment Letter for Point Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021006 and 05000301/2021006) ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 IR 05000266/20210052021-09-0101 September 2021 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2021005 and 05000301/2021005) ML21214A2812021-08-0202 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21180A2302021-06-29029 June 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2021004 and 05000301/2021004 ML21074A3962021-03-15015 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000266/2021010; 05000301/2021010 IR 05000266/20200062021-03-0404 March 2021 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020006 and 05000301/2020006) IR 05000266/20200052020-09-0101 September 2020 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2020005 and 05000301/2020005) ML20218A4322020-08-0505 August 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2020004 ML20168A8912020-06-15015 June 2020 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20190062020-03-0303 March 2020 Annual Assessment Letter for Point Beach Nuclear Plants, Units 1 and 2 (Report 05000266/2019006 and 05000301/2019006) IR 05000266/20190052019-08-28028 August 2019 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2019005 and 05000301/2019005) ML19190A1532019-07-0909 July 2019 Ltr. 07/09/19 Point Beach Nuclear Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000266/2019012; 05000301/2019012 (DRS-G.Hausman) ML19136A1402019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19094B1182019-04-0404 April 2019 Ltr. 04/04/19 Point Beach Nuclear Plant, Units 1 and 2 - Request for Information for an NRC Design Bases Assurance Inspection (Program): Implementation of the EQ Program; Inspection Report 05000266/2019013 and 05000301/2019013 (DRS-B.Jose) IR 05000266/20180062019-03-0404 March 2019 Annual Assessment Letter for Point Beach Nuclear Plant (Report 05000266/2018006 and 05000301/2018006) ML19037A3102019-02-0505 February 2019 Ltr. 02/05/19 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection; Inspection Report 05000266/2019412; 05000301/2019412 (DRS-G.Hausman) ML19024A2772019-01-24024 January 2019 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2019001 (DRS-M.Domke) IR 05000266/20180052018-08-28028 August 2018 Updated Inspection Plan for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2018005 and 05000301/2018005) IR 05000266/20170062018-03-0202 March 2018 Annual Assessment Letter for Point Beach Plant, Units 1 and 2 (Report 05000266/2017006 and 05000301/2017006) IR 05000266/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000266/2017005 and 05000301/2017005) ML17088A7242017-03-29029 March 2017 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000266/2017007; 05000301/2017007 IR 05000266/20160062017-03-0101 March 2017 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2016006 and 05000301/2016006) ML17039B0182017-02-0808 February 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Point Beach Nuclear Plant, Units 1 and 2 - Inspection Report 05000266/2017008; 05000301/2017008 IR 05000266/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant Units 1 and 2 (Report 05000266/2016005; 05000301/2016005) IR 05000266/20150062016-03-0202 March 2016 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Inspection Report 05000266/2015006 and 05000301/2015006) IR 05000266/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2015005; 05000301/2015005) ML15131A3132015-05-0808 May 2015 Ltr. 05/08/15 Point Beach Nuclear Plant, Units 1 and 2 - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (Mod/50.59) Baseline Inspection 05000266/2015010; 05000301/2015010 (Jjc) ML15124A9012015-05-0101 May 2015 Ltr. 05/01/15 Point Beach Nuclear Plant, Unit 2 - Notification of NRC Inspection and Request for Information (Msh) IR 05000266/20140012015-03-0404 March 2015 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2014001; 05000301/2014001) ML15050A2702015-02-19019 February 2015 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Point Beach Nuclear Plant, Units 1 and 2 ML14245A1662014-09-0202 September 2014 Mid-Cycle Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 IR 05000266/20130012014-03-0404 March 2014 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (Report 05000266/2013001; 05000301/2013001) ML14038A3472014-02-0606 February 2014 ISI Request for Information ML13246A2212013-09-0303 September 2013 2013 Point Beach MOC Letter Combined ML13172A4072013-06-20020 June 2013 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000266-13-010; 05000301-13-010 ML13129A1952013-05-0909 May 2013 Ltr 5/9/13 Point Beach Ti 2515-182 Phase 2 Request for Information IR 05000266/20120012013-03-0404 March 2013 Annual Assessment Letter for Point Beach Nuclear Plant, Units 1 and 2 (05000266/2012001; 05000301/2012001) 2024-02-05
[Table view] Category:Memoranda
MONTHYEARML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML22020A2812022-02-11011 February 2022 Subsequent License Renewal Application Summary of December 2, 2021, Public Meeting on Proposed Aging Management Activities ML22004A0772022-01-0606 January 2022 Summaries of December 8, 2021 Draft Supplemental Environmental Impact Statement for Subsequent License Renewal Application Public Meetings ML21062A0702021-04-21021 April 2021 Memo to File: Final Ea/Fonsi of 2012 and 2015 Decommissioning Funding Plans for Point Beach Units 1 and 2 Independent Spent Fuel Storage Installation (2012 and 2015) ML21075A3422021-03-17017 March 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Memo ML20233A7902020-08-20020 August 2020 Summary of the July 30, 2020, Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center and the Point Beach Nuclear Plant ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML15302A1702015-11-0202 November 2015 Forthcoming Closed Pre-Application Teleconference with NextEra Energy Point Beach, LLC (Nextera), Regarding Steam Generators H* License Amendment Request ML13154A5112013-06-0404 June 2013 Rai'S Following Ifib Analysis of NextEra Energy'S 2013 Decommissioning Funding Status Reports for Duane Arnold Energy Center and Point Beach Units 1 and 2 ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML12243A5232012-07-19019 July 2012 Letter from FEMA Region 5 to FEMA Hq Regarding Closure of Point Beach Deficiency ML1212805092012-06-18018 June 2012 May 1, 2012 - Summary of Teleconference with Performance Contracting, Inc., Regarding Large Flume Testing for Point Beach Nuclear Plant ML12115A0802012-04-24024 April 2012 Memo 042412 TIA 2012-07 for Point Beach EDG Tornado Missiles ML11228A2572011-08-16016 August 2011 Final - Task Interface Agreement (TIA) - Evaluation of Point Beach Nuclear Plant Torado Missile Protection Licensing Basis (TIA 2011-011) ML1106104272011-03-0707 March 2011 Notice of Forthcoming Pre-Application Meeting with Florida Power & Light Company and NextEra Energy Regarding Turkey Point, Units 3 and 4, St. Lucie, Units 1 and 2, Point Beach, Units 1, and 2, and Duane Arnold ML0921805182009-08-0606 August 2009 Notice of Public Meeting with Florida Power & Light Energy ML0827307072008-09-29029 September 2008 Pre-application Meeting with FPL Energy Point Beach, LLC to Discuss Their Proposed Alternate Source Term Amendment ML0824102292008-08-28028 August 2008 Notice of Forthcoming Meeting with Florida Energy Point Beach LLC, to Discuss Their Proposed Extended Power Uprate ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0712002952007-05-18018 May 2007 Cover Memo to Safety Evaluation by the Office of Nuclear Reactor Regulation - Direct Transfer of License from Nuclear Management Company, LLC & Wisconsin Electric Power Company to FPL Energy Point Beach, LLC (TAC # MD4112 & TAC # MD4113) ML0634003252006-12-0707 December 2006 Notice of Presubmittal Conference for Proposed Emergency Plan Changes ML0621603282006-08-29029 August 2006 Request for Additional Information Related to Evaluation of Event Notification 42129 ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0607503402006-04-20020 April 2006 Trip Report Regarding Staff Observations of Scaled Flume Testing of the Point Beach Nuclear Plant Proposed Replacement Suction Strainer Design ML0603000432006-02-13013 February 2006 Document Reclassified as Non-Proprietary ML0602301932006-02-10010 February 2006 Document Reclassified as Non-Proprietary ML0602400292006-02-0909 February 2006 Document Reclassified as Non-Proprietary ML0602502942006-01-25025 January 2006 Canceled Notice of Meeting with Nuclear Management Company Regarding Fleet Transition to NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants ML0602400772005-12-23023 December 2005 Memo 12/23/05 Point Beach One-Time Deviation from Regulatory Response Column of Reactor Oversight Process Action Matrix ML0529401992005-12-0202 December 2005 Unit 2 - Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0526203802005-09-30030 September 2005 Fiscal Year 2005 Evaluation of the Operating Reactor Licensing Program ML0523801282005-08-31031 August 2005 Unit 2 - Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors ML0626504112005-08-29029 August 2005 Memorandum to Region III Office Allegation Coordinator from P. Louden, Review of Discrimination Complaint Filed with Department of Labor ML0518203592005-07-0808 July 2005 Notice of Meeting with Nuclear Management Company Regarding the Planned Amendment to the Point Beach Nuclear Plant, Unit 1, Updated Safety Analysis Report Relating to Movement of the Reactor Vessel Head ML0626504042005-06-22022 June 2005 Memorandum to P. Louden from P. Pelke, Review of Receipt of Allegation, Allegation No. RIII-05-A-0062 (Point Beach) ML0626802612005-06-21021 June 2005 Memorandum to Allegation File from P. Pelke Receipt of Allegation (Point Beach) IR 05000266/20040032005-05-24024 May 2005 or Inspection Report Input to Point Beach Integrated Report 50-266/04-003 & 50-301-04-003 ML0515202472005-05-24024 May 2005 Previous Revision of Inspection Input to Point Beach Integrated Report 50-266-04-003 & 50-301-04-003 ML0502700462005-01-19019 January 2005 Summary of Telephone Conference Held on January 10, 2005, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear ML0432706522004-11-17017 November 2004 Summary of Telephone Conference Heldon November 17, 2004, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, Llc. Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear Plan, U ML0432705872004-11-16016 November 2004 Summary of Telephone Conference Held on October 26, 2004, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear Plant, ML0420404302004-07-22022 July 2004 Notice of Meeting Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Nuclear Management Company, LLC (NMC) on Recent Decisions Involving Unit 2 Reactor Vessel Pressurized Thermal Shock ML0419604622004-07-0707 July 2004 Wpdes Permit Reissuance ML0421003322004-06-30030 June 2004 Close-out of Tacs Relating to the Review of 35-day Letters Submitted in Response to the April 29, 2003, Orders Revising the Design Basis and Security Guard Force Training Enhancements and Physical Fitness Requirements ML0418803242004-06-29029 June 2004 Audit and Review Plan for Plant Aging Management Reviews and Programs at Point Beach Nuclear Power Plant, Units 1 and 2 ML0417400862004-06-21021 June 2004 All Region III Facility Training Managers Revised NRC Form 398 - Personal Qualification Statement Licensee ML0508304222004-06-0202 June 2004 Memo T.Chan, NRR, to L. Raghavan, NRR, Safety Evaluation for Point Beach Unit 1 First Revised Order 2023-02-15
[Table view] Category:Project Plans and Schedules
[Table view] |
Text
July 21, 2003 MEMORANDUM TO: J. E. Dyer, Regional Administrator FROM: Geoffrey E. Grant, Director, Division of Reactor Projects /RA/
SUBJECT:
SCHEDULE AND INSPECTION PLAN FOR THE 95003 SUPPLEMENTAL INSPECTION AT POINT BEACH For your approval, attached is the inspection plan and schedule for the Point Beach 95003 Supplemental Inspection.
Background
On April 2, 2003, the NRC determined that a finding associated with the potential common mode failure of the auxiliary feedwater (AFW) system due to a loss of instrument air was not an Old Design Issue. This determination indicated that plant performance at Point Beach Nuclear Plant was within the Multiple/Repetitive Degraded Cornerstone Column of the Action Matrix based on a Red finding in the mitigating systems cornerstone. In accordance with Manual Chapter 0305, Operating Reactor Assessment Program, Inspection Procedure 95003, Inspection for Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs, or One Red Input, will be performed to determine the breadth and depth of the performance deficiencies. Additionally, the April 2, 2003, letter documented a preliminary Red finding associated with the potential common mode failure of the four AFW pumps due to plugging of the recirculation line pressure reducing orifices. During the Regulatory Conference to discuss this issue on June 6, the licensee concurred with the characterization of the apparent violation of 10 CFR 50, Appendix B, Criterion III, Design Control; however, the licensees significance determination of this issue was still in progress. Pending NRC staff review of the licensees significance determination evaluation, this issue remains a preliminary Red issue.
Also, as documented in the March 4, 2003, Annual Assessment Letter - Point Beach Nuclear Plant, the NRC also identified a substantive cross-cutting issue in the area of Problem Identification and Resolution. This was based on the White Findings involving a safety injection pump failure and emergency preparedness program issues and four Green findings. The four Green findings involved the flooding of manholes containing plant equipment, repeat problems with cold weather preparations, delayed maintenance rule action for the G05 gas turbine, and an inadequate extent of condition review when addressing a steam generator narrow range level detector problem.
DOCUMENT NAME: G:\ML032090063.wpd To receive a copy of this document, indicate in the box:"C" = Copy without enclosure "E"= Copy with enclosure"N"= No copy OFFICE RIII RIII IIPB RIII RIII NAME MKunowski/trn AVegel SRichards* GGrant DATE 07/11/03 07/11/03 07/16/03 07/21/03 OFFICIAL RECORD COPY
- Received concurrence via email from J. Jacobson.
J. Dyer As a result of the final Red finding and the discussion at the Agency Action Review Meeting, actions were initiated to accomplish Inspection Procedure (IP) 95003, Supplemental Inspection for Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs, or One Red Input, at Point Beach. The IP 95003 inspection will be conducted in addition to the baseline inspections currently scheduled. However, for those baseline inspections scheduled for after completion of the 95003 team inspections, consideration will be given to taking baseline credit for areas reviewed during the 95003.
Inspection Scope and Schedule The intent of IP 95003 is to allow the NRC to obtain a comprehensive understanding of the depth and breadth of safety, organizational, and performance issues at facilities where data indicates the potential for serious performance degradation. The objectives of the IP 95003 inspection are to: (1) provide additional information to be used in deciding whether the continued operation of the facility is acceptable and whether additional regulatory actions are necessary to arrest declining performance; (2) provide an independent assessment of the extent of risk significant issues to aid in the determination of whether an acceptable margin of safety exists; (3) independently evaluate the adequacy of facility programs and processes used to identify, evaluate, and correct performance issues; (4) independently evaluate the adequacy of programs and processes in the affected strategic performance areas; and (5) provide insight into the overall root and contributing causes of identified performance deficiencies.
As prescribed by IP 95003, the scope of inspection activities at Point Beach will include the assessment of performance in the Reactor Safety Strategic Performance Area, including the inspection of key attributes such as design, human performance, procedure quality, configuration control, and emergency response organization readiness. Also, the 95003 inspection will review the control systems for identifying, assessing, and correcting performance deficiencies to evaluate whether programs are sufficient to prevent further declines in safety that could result in unsafe operation. In developing the scope of this inspection, the NRC considered the results of the licensees ongoing self-assessment, the disposition of the preliminary Red finding and an Unresolved Item from the emergency preparedness drill of August 2002, and the evaluation of the licensees progress in addressing the substantive cross-cutting issue in the area of problem identification and resolution.
The IP 95003 at Point Beach will be conducted in phases to accommodate NRC resource constraints, the licensees fall refueling outage, and the timely completion of this extensive inspection. During the first phase, the Corrective Actions Team (CAT) will review licensee discovery efforts and the quality of the corrective action program. In the second phase, the Emergency Preparedness Team (EPT) will review the emergency preparedness program.
During the third and final phase, the Engineering, Operations, and Maintenance Team (EOMT) will assess implementation of corrective actions and review the design engineering function.
Two systems have been chosen for a detailed review: component cooling water system and 125-volt direct current electrical system. The auxiliary feedwater system will also be reviewed, but that review will be limited to corrective actions taken in 2003. The design of the auxiliary feedwater system was previously reviewed during the recent special inspection in which Old Design Issue credit was disallowed (Inspection Report 50-266/02-15; 50-301/02-15).
J. Dyer In consideration of this, we have developed the attached schedule for the three teams and the inspection plan for the overall inspection effort. In addition, we have worked with NRR inspection program (IIPB) staff in developing the plan and have received concurrence from the IIPB Branch Chief. Tony Vegel has been designated the Team Leader for the Point Beach 95003 efforts and will implement the plan in accordance with the schedule. The results of the three teams will be documented in three separate inspection reports. We will keep you informed of any major changes to the schedule and inspection plan. In addition, we will develop a communication plan to inform other internal stakeholders of major 95003 activities and develop detailed inspection plans for each of the three teams.
Approval: /RA/
J. E. Dyer, Regional Administrator Attachments: As stated
Schedule for the Point Beach 95003 Supplemental Inspection Corrective Action Team (CAT)
July 21-25, 2003 Inspection preparation week July 28-August 8 Onsite inspection weeks August 11-15 Documentation week August 27 Exit meeting Emergency Preparedness Team (EPT)
July 7-11, 2003 Inspection preparation week August 4-15 Onsite inspection weeks August 18-22 Documentation week August 27 Exit meeting Engineering, Operations, and Maintenance Team (EOMT)
September 2-5 Inspection preparation week September 8-12 1st onsite inspection week September 15-19 In-office inspection week September 22-26 2nd onsite inspection week September 29-October 3 Documentation week October 15 Exit meeting 1
Inspection Plan for the Point Beach 95003 Supplemental Inspection The inspection plan consists of two parts: 1) Sections 02.01, 02.02, and 02.03 of the Inspection Requirements will be followed by the CAT and EOMT. 2) Attachment 95003.01, Emergency Preparedness, will be followed by the EPT.
Sections 02.07 and 02.08 of the Inspection Requirements will be implemented in both parts of the plan.
95003-02 Inspection Requirements 02.01.a. Identify the strategic performance area(s) for which performance has significantly declined. Completed. Reactor Safety Strategic Performance Area, Mitigating Systems and Emergency Preparedness cornerstones.
Section 02.03 will be completed for the Mitigating Systems cornerstone by the CAT and EOMT.
02.01.b. Complete Inspection Requirements 02.02, 02.03, 02.07. and 02.08. CAT and EOMT.
02.02.a. Determine whether licensee evaluations of, and corrective actions to, significant performance deficiencies identified in the engineering and corrective action program areas as a result of the Red inspection finding have been sufficient to correct the deficiencies and prevent recurrence.
CAT and EOMT.
02.02.b. Evaluate effectiveness of audits and assessments in arresting declining performance. CAT and EOMT.
02.02.c. Review the process for allocating resources to manage backlogs in the corrective action program and engineering products, such as design mods, work package reviews, test evaluations, temp mod and work around reductions, procedure reviews, and drawing changes. CAT.
02.02.d. Review corporate, site, and organizational strategic plans to determine if corrective action program and engineering program goals are in conflict with actions needed to correct performance issues. CAT.
02.02.e. Review the employee concerns program, using Inspection Procedure 40001, to evaluate the safety consciousness of the work environment.
CAT.
02.02.f. Evaluate the operating experience program regarding corrective action program and engineering program deficiencies. CAT.
02.03.a.1. Review corrective action program documents, audits of the corrective action program and engineering program, LERs, and inspection reports since January 1, 2002. CAT.
1
02.03.a.2. Select system(s) for focus. Completed. Full review of component cooling water system (CCW) and 125-volt DC system. Partial review of auxiliary feedwater system (AFW)-review assessments and corrective actions since January 1, 2003. CAT for AFW and EOMT for CCW and 125-volt DC.
02.03.b. Review the design basis, as-built design features, and several recent modifications of the CCW and 125-volt DC systems to verify the capability of the systems to perform the intended safety functions with a sufficient margin. EOMT.
02.03.c. Evaluate the role of human performance attributes, such as group organization, training and qualifications, communications, control of overtime and fatigue, and human-system interfaces, in the deficiencies in the corrective action and engineering programs. CAT and EOMT.
02.03.d. Evaluate the role of inadequate procedures in the performance deficiencies in corrective actions and engineering. CAT. For CCW and 125-volt DC, evaluate operating, maintenance, and testing procedures to ensure incorporation of appropriate design basis information. EOMT.
02.03.e. Determine if the licensee is adequately maintaining, operating, and testing the CCW and 125-volt DC systems. EOMT.
02.03.f. Conduct detailed walkdowns of the CCW and 125-DC systems to verify that the systems are in configurations which support their safety functions. EOMT.
02.07 Group the safety performance deficiencies identified during the team inspections. CAT, EPT, and EOMT. The technical assistant team leader for each team will perform this. The 95003 team leader will compile the groupings from each team.
02.08 Compare the teams findings with previous NRC inspection and assessment information to determine whether sufficient warning was provided to identify a significant reduction in safety. The results of this comparison will not be contained in the 95003 inspection reports, but should be documented in a separate document to the Region III Regional Administrator and the Director of NRR. The 95003 team leader will perform this comparison, with assistance as needed by the assistant team leaders.
2 5003.01-EPT 02.01 Review the recent inspection record and the E-plan as part of the preparation of this inspection. Consider selecting an RSPS (risk significant planning standard) for in-depth review.
02.02 Review various assessments, drill and exercise critiques, and corrective action program documents to determine the adequacy of problem identification, evaluation, and correction. Implement Inspection Procedure 7114.05, Correction of Emergency Preparedness Weaknesses and Deficiencies.
02.03 Determine if the ERO augmentation system design is adequate, implementing Inspection Procedure 71114.03, Emergency Response Organization Augmentation Testing.
02.04 Determine the adequacy of emergency response facilities and equipment, implementing Inspection Procedure 82001.04, Facilities and Equipment.
02.05 Evaluate the adequacy of changes to EPIPs through the corrective action process, implementing Inspection Procedure 82001.05, Procedure Quality.
02.06 Review various aspects of EP training, including ERO performance drills.
02.07 Conduct an in-depth review of a risk significant planning standard if the failure to comply a planning standard contributed to the current performance decline.
02.08 Group the safety performance deficiencies identified during the inspection. The technical assistant team leader will perform this. The 95003 team leader will compile the groupings from the EPT and the CAT and EOMT.
02.09 Compare the findings with previous NRC inspection and assessment information to determine whether sufficient warning was provided to identify a significant reduction in safety. The results of this comparison will not be contained in the 95003 inspection reports, but should be documented in a separate document to the Region III Regional Administrator and the Director of NRR. The 95003 team leader will perform this comparison, with assistance as needed from the assistant team leaders.
3