ML051520247

From kanterella
Jump to navigation Jump to search
Previous Revision of Inspection Input to Point Beach Integrated Report 50-266-04-003 & 50-301-04-003
ML051520247
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/24/2005
From: Kenneth Riemer
Division of Reactor Safety III
To: Louden P
NRC/RGN-III/DRP/RPB7
References
FOIA/PA-2004-0282 IR-04-003
Download: ML051520247 (8)


See also: IR 05000266/2004003

Text

A UNITED STATES

9 C0

NUCLEAR REGULATORY COMMISSION

-.

Region III

LISLE, ILLINOIS 60532

MEMORANDUM TO: Patrick Louden, Chief (U /C

Projects Branch 7

Division of Reactor Projects

FROM: Kenneth Riemer, Chief

Plant Support Branch i

Division of Reactor Safety

SUBJECT: POINT BEACH NUCLEAR PLANT, UNITS 1 & 2

DRS INPUT TO INTEGRATED REPORT 50-266/04-03;

50-301/04-03

Attached is the report input for Point Beach Nuclear Plant, Units 1 and 2, Inspection

Report 50-266/04-03; 50-301/04-03. Specifically, this report focused on occupational radiation

safety during the recent U1R28 refueling outage as related to the licensee's radiological access

control and ALARA programs. I have reviewed this input and have determined it is ready for

distribution to the licensee and dissemination to the public.

Attachment: Input to Inspection Report 50-266/04-03;

50-301/04-03

CONTACT: Ryan D. Alexander, DRS

(630) 829-9853

DOCUMENT NAME: G:DRS\Point Beach Input to Report 04-03 RDA.wpd

To receive a copy of this document, Indicate in the box: C * Copy without attachmentlenclosure E = Copy with attachment/enclosure N * No copy

lOFFICE lR111 W] R~ll L

I8}i

NAME RAlexander:sd ?gn KRiemer 1,4

DATE 05/1S104 05P /04

OFFICIAL RECORD COPY

0-9

Cover Letter

/ No input, no significant findings.

Input below, no color or green findings were identified.

Title Page

Inspector: R. D. Alexander, Radiation Specialist

SUMMARY OF FINDINGS

ADAMS boilerplate - Inspectable area: Radiation Protection

Modify second paragraph as follows:

The baseline inspection was conducted by a regional radiation specialist inspector.

A. Insnector-ldentified and Self-Revealed Findings

Cornerstones: Occupational and Public Radiation Safety (OS)

None

B. Licensee-Identified Violations

None

REPORT DETAILS

2. RADIATION SAFETY

Cornerstone: Occupational Radiation Safety (OS)

20S1 Access Control to Radiologically Significant Areas (71121.01)

.1 Plant Walkdowns and Radiation Work Permit Reviews

a. Inspection Scone

The inspectors reviewed licensee controls and surveys for selected radiation areas, high

radiation areas and airborne radioactivity areas, as available, in the following

radiologically significant work areas within the plant and reviewed work packages which

included associated licensee controls and surveys for these areas to determine if

radiological controls (including postings and barricades) were acceptable:

  • Primary Auxiliary Building; and
  • Unit 1 Containment (all levels).

The inspectors reviewed the radiation work permits (RWP) and work packages used to

control work in these areas and other high radiation work areas to identify the work

control instructions and control barriers that had been specified. Electronic dosimeter

alarm set points for both integrated dose and dose rate were evaluated for conformity

with survey indications and plant policy. Workers were interviewed to assess their

knowledge of the actions required when their electronic dosimeters noticeably

malfunctioned or alarmed.

The inspectors walked down these areas to verify that the prescribed RWPs,

procedures, and engineering controls were in place, that licensee surveys and postings

were complete and accurate, and that air samplers (if necessary) were properly located.

The inspectors reviewed the RWPs and surveys for the steam generator nozzle dam

installation and eddy current testing activities which had the potential for creating an

airborne radioactivity area. The inspectors reviewed the RWPs to verify barrier integrity

and engineering control contingency plans were in place and to determine if there was a

potential for individual worker internal exposures of greater than 50 millirem committed

effective dose equivalent. This and other work activities/areas having a history of, or the

potential for, airborne transuranic isotopes were evaluated to verify that the licensee had

considered the potential for transuranic isotopes and provided appropriate worker

protection.

The inspectors assessed the adequacy of the licensee's internal dose assessment

process by reviewing personnel contamination event logs (and associated dose

assessments) for the refueling outage. As of April 21, 2004, no personnel

contamination events had resulted in dose assignments of greater than 10 millirem

committed effective dose equivalent.

These reviews represented four inspection samples.

b. Findings

No findings of significance were identified.

.2 Job-In-Progress Reviews

a. Inspection Scope

The inspectors observed the following four activities that were being performed in

radiation areas, airborne radioactivity areas, or high radiation areas for observation of

work activities that presented the greatest radiological risk to workers:

  • Reactor Vessel Head Lift; and
  • Cono-Seal Bullet Replacement.

The inspectors reviewed radiological job requirements for these four activities, including

RWP and work procedure requirements, and attended ALARA pre-job briefings.

Job performance was observed with respect to these requirements to verify that

radiological conditions in the work areas were adequately communicated to workers

through pre-job briefings and postings. The inspectors also verified the adequacy of

radiological controls (including required radiation, contamination, and airborne surveys);

radiation protection job coverage (including audio/visual surveillance for remote job

coverage); and contamination controls.

Radiological work in high radiation work areas having significant dose rate gradients

was reviewed to evaluate the application of dosimetry to effectively monitor exposure to

personnel and to verify that licensee controls were adequate. In particular, the steam

generator eddy current activities and cono-seal bullet replacement involved evolutions

where the dose rate gradients were severe which increased the necessity of providing

multiple or repositioned dosimetry and/or enhanced job controls.

These reviews represented three inspection samples.

b. Findings

No findings of significance were identified.

.4 Radiation Worker Performance

a. Inspection Scope

During job performance observations, the inspectors evaluated radiation worker

performance with respect to stated radiation protection work requirements and

evaluated whether workers were aware of the significant radiological conditions in their

workplace, the RWP controls and limits in place, and that their performance accounted

for the level of radiological hazards present.

These reviews represented one inspection sample.

b. Findings

No findings of significance were identified.

.5 Radiation Protection Technician Proficiency

a. Inspection Scope

During job performance observations, the inspectors evaluated radiation protection (RP)

technician performance with respect to radiation protection work requirements and

evaluated whether they were aware of the radiological conditions in their workplace, the

RWP controls and limits in place, and if their oversight of radiological activities was

consistent with their training and qualifications with respect to the radiological hazards

and work activities.

These reviews represented one inspection sample.

b. Findings

No findings of significance were identified.

20S2 As Low As Is Reasonably Achievable Planning And Controls (ALARA) (71121.02)

.1 Inspection Planning

a. Inspection Scone

The inspectors reviewed the U1 R28 refueling outage work scheduled during the

inspection period and associated work activity exposure estimates for the following four

work activities which were likely to result in the highest personnel collective exposures:

  • U1R28 RP Coverage [RWP No. 04-104];
  • Bottom Mounted Instrumentation Inspection [RWP No. 04-133];
  • Nozzle Dam Installation/Removal [RWP No. 04-141]; and

These reviews represented one inspection sample.

b. Findings

No findings of significance were identified.

.2 Radiological Work Planning

a. Inspection Scope

For those activities identified in Section 20S2.1, the inspectors reviewed the ALARA

evaluations, exposure estimates, and exposure mitigation requirements in order to verify

that the licensee had established procedures, and engineering and work controls that

were based on sound radiation protection principles in order to achieve occupational

exposures that were ALARA.

The interfaces between radiation protection, operations, maintenance, planning,

scheduling, and engineering groups were evaluated by the inspectors to identify

interface problems or missing program elements. The inspectors evaluated if work

activity planning included consideration of the benefits of dose rate reduction activities

such as shielding provided by water filled components/piping, job scheduling, and

shielding and scaffolding installation/removal activities. Finally, the inspectors evaluated

the integration of radiological job planning activities (pre-job ALARA reviews) into work

procedure and RWP documents.

These reviews represented three inspection samples.

b. Findings

No findings of significance were identified.

.3 Verification of Dose Estimates and Exposure Tracking Systems

a. Inspection Scope

The inspectors reviewed the licensee's process for adjusting exposure estimates or

re-planning work, when unexpected changes in scope, emergent work or higher than

anticipated radiation levels were encountered. This review included a determination if

adjustments to estimated exposures (intended dose) were based on sound radiation

protection and ALARA principles, rather than adjustments to account for failures to

adequately control the work. The frequency of these adjustments was reviewed to

evaluate the adequacy of the original ALARA planning process. In particular, the

inspectors reviewed and discussed with the RP staff the In-Progress ALARA reviews

conducted for the bottom mounted instrumentation inspection and steam generator

nozzle dam installation/removal RWPs.

These reviews represented one inspection sample.

b. Findings

No findings of significance were identified.

.4 Job Site Inspections and ALARA Control

a. Inspection Scope

The inspectors observed the four activities identified in Section 20S1.2 that were being

performed in radiation areas, airborne radioactivity areas, or high radiation areas for

observation of work activities that presented the greatest radiological risk to workers.

The licensee's use of engineering controls to achieve dose reductions was evaluated to

verify that procedures and controls were consistent with the licensee's ALARA reviews,

that sufficient shielding of radiation sources was provided for and that the dose

expended to install/remove the shielding did not exceed the dose reduction benefits

afforded by the shielding.

These reviews represented one inspection sample.

b. Findings

No findings of significance were identified.

.5 Radiation Worker Performance

a. Inspection Scope

Radiation worker and RP technician performance was observed during work activities

performed in radiological areas that presented the greatest radiological risk to workers.

The inspectors evaluated whether workers demonstrated the ALARA philosophy in

practice by being familiar with the work activity scope and tools to be used, by utilizing

ALARA low dose waiting areas, and that work activity controls were being complied with.

Also, radiation worker performance was observed to determine whether individual

training/skill level was sufficient with respect to the radiological hazards and the work

involved.

These reviews represented one inspection sample.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES (OA)

40A6 Meetings

.2 Interim Exit Meetings

Interim exit meeting was conducted for:

with Mr. G. VanMiddlesworth on April 23, 2004.

KEY POINTS OF CONTACT

Licensee

G. VanMiddlesworth, Site Vice President

S. Thomas, Radiation Protection Manager

B. Carberry, Radiation Protection - ALARA

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened. Closed, and Discussed

None

LIST OF DOCUMENTS REVIEWED

20S1 Access Control to Radiologically Significant Areas

CAP 055366; Worker Received Electronic Dosimeter Dose Alarm; dated April 5, 2004

CAP 055587; SIG Nozzle Dam Installation Dose Exceeded Estimate; dated April 11,

2004

CAP 055951; Incore Thermocouple Guide ("Bullet Nose") Inadvertently Lifted with

Reactor Head; dated April 22, 2004

CAP 055986; Evaluate Use of RP Greeter at Containment Hatches During Outage

Periods; dated April 23, 2004 [NRC-Identified Issue]

HP 3.2; Radiological Labeling, Posting, and Barricading Requirements; Revision 39

(January 23, 2004)

HPIP 3.52; Airborne Radioactivity Surveys; Revision 30 (June 20, 2003)

PCE No. 04-02-018; Personnel Contamination Event (PCE) Report; dated April 8, 2004

PCE No. 04-02-019; Personnel Contamination Event (PCE) Report; dated April 9, 2004

PCE No. 04-02-020; Personnel Contamination Event (PCE) Report; dated April 8, 2004

RWP No.04-104; RP Coverage; Revision 0

RWP No.04-113; Reactor Head Lift; Revision 0

RWP No.04-122; Reactor Coolant Pump Maintenance; Revision 0

RWP No.04-133; BMI Inspection; Revision 0

RWP No.04-141; Nozzle Dam Install/Remove; Revision 0

RWP No.04-142; Steam Generator Eddy Current Testing; Revision 1

vX - *

RWP No.04-171; NRC Walkdowns for U1R28; Revision 0

RWP No.04-182; Replace Cono-Seal Bullet; Revision 0

20S2 As Low As Is Reasonably Achievable Planninq And Controls (ALARA)

ALARA Review No. 2004-0012; Level 3 Pre-Job ALARA Review for BMI Inspection

(RWP No.04-133); dated April 6, 2004

ALARA Review No. 2004-0017; Level 3 Pre-Job and In-Progress ALARA Reviews for

Nozzle Dam Install/Remove (RWP No.04-141); dated April 2 and 11, 2004

ALARA Review No. 2004-0018; Level 3 Pre-Job ALARA Reviews (Revisions 0 and 1)

for Steam Generator Eddy Current Testing (RWP No.04-142); dated March 16 and

April 12, 2004

ALARA Review No. 2004-0027; Level 3 Pre-Job ALARA Review for Replace Cono-Seal

Bullet (RWP No.04-182); dated April 22, 2004

JIT Briefing Activity MM-8480D3; Just In Time Briefing for Reactor Vessel Head Lift;

dated April 21, 2004

HPIP 4.40; TEDE ALARA Evaluation; Revision 0 (February 6, 2002)

NP 4.2.1; ALARA Program; Revision 11 (November 19, 2003)

Point Beach Nuclear Plant U1R28 Estimated RWP Dose Spreadsheet; dated April 6,

2004

TEDE ALARA Evaluation for RWP 04-141; dated April 3, 2004

TEDE ALARA Evaluation for RWP 04-182; dated April 22, 2004

LIST OF ACRONYMS USED

ALARA As Low As Is Reasonably Achievable

U1R28 Point Beach Unit 1's 28th Refueling Outage

RP Radiation Protection

RWP Radiation Work Permit