ML21075A342
Letter Sequence Meeting | |
---|---|
EPID:L-2020-SLE-0002, License Renewal (Approved, Closed) | |
Initiation
| |
MONTHYEARML20329A2482020-11-16016 November 2020
[Table View]Enclosure 3, Attachment 2, Appendix E Applicant'S Environmental Report Subsequent Operating License Renewal Point Beach Nuclear Plant Units 1 and 2 Project stage: Other ML21033A4022021-01-22022 January 2021 NextEra Energy Point Beach - Point Beach Nuclear Plant - Units 1 and 2 Subsequent License Renewal Project stage: Other ML20351A3922021-01-26026 January 2021 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID No. L-2020-SLE-0002) (Docket No. 50 266 and 50-301) - Letter Project stage: Other PMNS20210090, Environmental Scoping Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application2021-02-0303 February 2021 Environmental Scoping Meeting Related to the Point Beach Nuclear Plant, Unit Nos. 1 and 2 (Point Beach), Subsequent License Renewal Application Project stage: Meeting ML21048A0362021-02-0404 February 2021 Comment (1) of Willard Sielaff on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21040A2232021-02-0505 February 2021 Comment (2) of Raymond Hardy on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC, Point Beach, Units 1 and 2 Project stage: Request ML21040A2282021-02-0808 February 2021 Comment (3) from Hannah Mortensen on Behalf of Physicians for Social Responsibility Wisconsin on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Point Beach Nuclear Plant, Units 1 & 2 Project stage: Request ML21050A0822021-02-12012 February 2021 Comment (4) of Geralyn Leannah Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A0862021-02-14014 February 2021 Comment (6) of Theresa Deluca Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A0832021-02-14014 February 2021 Comment (5) of Bruce Krawisz on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A0882021-02-16016 February 2021 Comment (7) of Randy Connour on Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A0892021-02-16016 February 2021 Comment (8) of Eric Newgent on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21056A5612021-02-17017 February 2021 Physicians for Social Responsibility (Psr) Request for Extension of Scoping Comment Period Project stage: Request ML21042B9452021-02-17017 February 2021 Scoping and Process Meeting - February 17, 2021 Project stage: Meeting ML21050A0992021-02-17017 February 2021 Comment (10) of Ann Rogers Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1022021-02-17017 February 2021 Comment (11) of John Duffin Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A1922021-02-17017 February 2021 Transcript from Point Beach Nuclear Plant Subsequent License Renewal Scoping Meeting Project stage: Meeting ML21075A3432021-02-17017 February 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Summary Project stage: Meeting ML21050A0922021-02-17017 February 2021 Comment (9) of Diane Palecek Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1052021-02-17017 February 2021 Comment (12) of Shahla Werner Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1162021-02-18018 February 2021 Comment (14) of Marie Luna on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1252021-02-18018 February 2021 Comment (19) of Ellen Atkison Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1272021-02-18018 February 2021 Comment (20) from Pam Nelson Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1342021-02-18018 February 2021 Comment (26) of Jim Yarbrough Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1092021-02-18018 February 2021 Comment (13) of Pamela Richard Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1172021-02-18018 February 2021 Comment (15) of Joann Nishiura on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Nexteraenergy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1282021-02-18018 February 2021 Comment (21) of Karl Koessel Opposing Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1212021-02-18018 February 2021 Comment (17) from Stephen Roddy Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1292021-02-18018 February 2021 Comment (22) from Dennis Schaef on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1382021-02-18018 February 2021 Comment (27) of Leonard Kellum Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1322021-02-18018 February 2021 Comment (24) of Sandra Couch on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Nexteraenergy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1182021-02-18018 February 2021 Comment (16) from Andrew Benson Supporting Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1332021-02-18018 February 2021 Comment (25) of Mark Giese on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1312021-02-18018 February 2021 Comment (23) from Patrick Bosold Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1222021-02-18018 February 2021 Comment (18) of Kristina Mageau on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Nexteraenergy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21062A0152021-02-19019 February 2021 Comment (30) of Claire Gervais Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0162021-02-19019 February 2021 Comment (31) of Karen Wilson on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21050A1592021-02-19019 February 2021 Comment (29) of Philip Ratcliff on Notice of Lntent to Conduct Scoping Process and Prepare Environmental Impact Statement NextEra Energy Point Beach, LLC; Point Beach Nuclear Plant, Unit Nos. 1 and 2 Project stage: Request ML21050A1392021-02-19019 February 2021 Comment (28) of Croitiene Ganmoryn on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0182021-02-20020 February 2021 Comment (32) of Larry Troshynski on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0272021-02-21021 February 2021 Comment (36) of Ernest Fuller on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0232021-02-21021 February 2021 Comment (33) of Kristin Womack on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0282021-02-21021 February 2021 Comment (37) of Karen Kirschling on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0242021-02-21021 February 2021 Comment (34) of Miriam Kurland Opposing Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0262021-02-21021 February 2021 Comment (35) of Dwight Rousu on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0292021-02-25025 February 2021 Comment (38) of Satya Vayu on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0352021-02-26026 February 2021 Comment (43) of Dawn Wallander on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0412021-02-26026 February 2021 Comment (48) of Thomas Sheley on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0422021-02-26026 February 2021 Comment (49) of Lee Dubois on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request ML21062A0302021-02-26026 February 2021 Comment (39) of Adrianne Greenwood Supporting Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; NextEra Energy Point Beach, LLC, Point Beach Nuclear Plant, Units 1 and 2 Project stage: Request 2021-02-19 |
ML21075A342 | |
Person / Time | |
---|---|
Site: | Point Beach |
Issue date: | 03/17/2021 |
From: | Phyllis Clark NRC/NMSS/DREFS/ELRB |
To: | Robert Elliott NRC/NMSS/DREFS/ELRB |
Clark, P.M, NMSS/REFS/ELRB, 301-415-6447 | |
Shared Package | |
ML21075A333 | List: |
References | |
EPID L-2020-SLE-0002 | |
Download: ML21075A342 (3) | |
Similar Documents at Point Beach | |
---|---|
Category:Meeting Summary
MONTHYEARML24248A0152024-09-0505 September 2024
[Table view]Summary of August 28, 2024, Public Pre-Application Meeting with NextEra Energy Point Beach, LLC Regarding Assessing Seismic Risk ML24227A5082024-08-15015 August 2024 Summary of the July 15, 2024, Public Outreach to Discuss the NRC 2023 End-Of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML23199A0262023-07-18018 July 2023 Summary of Public Outreach to Discuss the NRC 2022 End of Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML23118A1762023-05-0404 May 2023 – Audit Summary for License Amendment Request Regarding Risk-Informed Approach for Closure of Generic Safety Issue 191 ML22144A0022022-09-14014 September 2022 Summary of February 16, and May 18, 2022, Meetings with Nextera Energy/Florida Power & Light Company Regarding Planned Submittal of License Amendment Request for a Common Fleet Emergency Plan ML22181B1182022-06-30030 June 2022 Summary of the June 23, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML22019A2792022-01-20020 January 2022 Summary of Public Webinar with NextEra Energy Point Beach, LLC Regarding Future License Amendment and Exemption Request for Generic Letter 2004-02 Closure for Point Beach Nuclear Plant ML22004A0772022-01-0606 January 2022 Summaries of December 8, 2021 Draft Supplemental Environmental Impact Statement for Subsequent License Renewal Application Public Meetings ML21295A2532021-10-26026 October 2021 Summary of Public Webinar with NextEra Energy Point Beach,Llc Regarding Proposed Future LAR to Adopt TSTF-505, Rev.2, Provide Risk Informed Extended Completion Times-RITSTF Initiative 4B, at Point Beach Plant, Units 1&2 (L-2021-LRM-0086) ML21288A1222021-10-20020 October 2021 SLRA Summary of August 5, 2021, Public Meeting on Proposed Aging Management Activities of Irradiated Concrete and Steel Reactor Vessel Supports ML21214A1512021-08-27027 August 2021 SLRA June 3, 2021, Public Meeting - Proposed Aging Management Activities of Irradiated Concrete and Steel Reactor Vessel Supports ML21214A1652021-08-27027 August 2021 SLRA June 30, 2021, Public Meeting - Proposed Aging Management of Reactor Vessel Internals ML21161A2992021-06-17017 June 2021 Summary of May 18, 2021 Public Webinar with Nextera Energy Point Beach, LLC Regarding Path Forward for Generic Letter 2004-02 Closure ML21166A2192021-06-15015 June 2021 Summary of June 10, 2021, Public Webinar to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of the Point Beach Nuclear Plant ML21148A1162021-06-0101 June 2021 SLRA Public Meeting Discussion Questions 6-3-21 ML21075A3422021-03-17017 March 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Memo ML21075A3432021-02-17017 February 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Summary ML20253A1382020-09-11011 September 2020 8/13/2020 Summary of Public Meeting with NextEra Energy Point Beach, LLC Regarding Proposed License Amendment Request for Point Beach Nuclear Plant, Unit 1, Containment Building Truss License Condition Change Due to COVID-19 ML20233A7902020-08-20020 August 2020 Summary of the July 30, 2020, Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center and the Point Beach Nuclear Plant ML19344A0162019-12-12012 December 2019 Summary of Pre-Application Public Teleconference with Nextera Energy Point Beach, LLC, for Point Beach Nuclear Plant, Units 1 and 2 ML19246A6242019-09-10010 September 2019 Summary of August 14, 2019, Pre-Application Public Teleconference with NextEra Energy Point Beach, LLC, for Point Beach Nuclear Plant, Unit 2 ML19179A0662019-07-17017 July 2019 Summary of Closed Meeting with Nextera Energy, LLC, to Discuss Security-Related Information for Point Beach Nuclear Plant, Unit 1 and 2, and Duane Arnold Energy Center ML19095B7772019-04-0505 April 2019 Summary of Public Outreach/Open House to Discuss the NRC 2018 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML18220B0192018-08-13013 August 2018 7/12/2018 Summary of Meeting with NextEra Energy Point Beach, Llc. to Discuss Supplemental Response to the RAI for Containment Dome Truss License Amendment Request for Point Beach Nuclear Plant, Unit 1 and 2 (CAC Nos. MF9532 & MF9533; ... ML18179A4032018-06-29029 June 2018 Public Meeting Discussion Points ML18136A9052018-05-31031 May 2018 Summary of April 25, 2017, Meeting with Florida Power & Light Company/Nextera Energy Regarding Planned Submittal of Exemption Requests to Support Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML18141A8452018-05-29029 May 2018 Summary of May 1, 2018 Meeting with NextEra Energy Point Beach, LLC, to Discuss License Amendment Request for High Winds Probabilistic Risk Assessment for Point Beach Nuclear Plant, Unit Nos. 1 and 2 ML18121A3142018-05-0101 May 2018 Summary of the April 10, 2018 Public Outreach/Open House for the NRC to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Point Beach Plant, Units 1 and 2 ML17346A9122017-12-22022 December 2017 Summary of November 14, 2017 Public Teleconference with NextEra Energy Point Beach, LLC, to Discuss Containment Dome Truss License Amendment Request for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (CAC Nos. MF9532 and MF9533; EPID L-2017-L ML17310B2062017-11-20020 November 2017 Summary of September 20, 2017, Meeting with Florida Power & Light Company and NextEra Energy Regarding Closure of NRC Generic Safety Issue 191/NRC Generic Letter 2004-02 ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML17202U7272017-07-19019 July 2017 Summary of July 11, 2017, Open House to Discuss the 2016 End-Of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant, Units 1 and 2 ML16305A3882016-11-0808 November 2016 Summary of October 18, 2016 Meeting with Nextera Energy Point Beach, Llc, to Discuss Containment Dome Truss License Amendment Request for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (TAC Nos. MF8403 and MF8404) ML16160A1742016-06-0707 June 2016 Summary of Public Meeting with Nextera Energy Point Beach, LLC to Discuss the 2015 End-of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant Units 1 and 2 ML15341A0182015-12-16016 December 2015 Summary of Closed Pre-Application Teleconference with Nextera Energy Point Beach Regarding Steam Generators H* License Amendment Request ML15217A3312015-08-26026 August 2015 July 28, 2015, Summary of Ublic Meeting with NextEra Energy Point Beach, LLC, to Discuss a Proposed Licensing Basis Change for the Turbine-Driven Auxiliary Feedwater Pumps at the Point Beach Nuclear Plant, Units 1 and 2 ML15215A0502015-08-0505 August 2015 Summary of Public Meeting with NextEra Energy Point Beach, LLC, to Discuss Proposed Changes to Containment Dome Truss Design Bases Code for Point Beach Nuclear Plant, Units 1 and 2 ML15121A0572015-05-15015 May 2015 June 9 - 12, 2014 Summary of Audit at Point Beach Nuclear Plant, Unit Nos. 1 and 2, Associated with License Amendment Request to Transition to National Fire Protection Association Standard 805 ML15113B3862015-04-23023 April 2015 April 20, 2015 Summary of Public Outreach/Open House to Discuss the NRC 2014 End-Of-Cycle Plant Performance Assessment of Point Beach Nuclear Plant ML15106A7122015-04-23023 April 2015 Summary of April 6, 2015, Meeting with NextEra Energy Point Beach, LLC, to Discuss License Amendment Request to Transition to NFPA 805 ML14114A1002014-04-23023 April 2014 Summary of Public Meeting to Discuss 2013 Annual Assessment Results for Point Beach Nuclear Plant ML13192A1432013-07-10010 July 2013 6/26/2013 - Summary of Open House to Discuss the 2012 Point Beach Nuclear Plant End-Of-Cycle Performance Assessment ML1212805092012-06-18018 June 2012 May 1, 2012 - Summary of Teleconference with Performance Contracting, Inc., Regarding Large Flume Testing for Point Beach Nuclear Plant ML11173A2332011-06-22022 June 2011 Summary of Public Meeting with NextEra Energy Point Beach, LLC to Discuss the Point Beach Nuclear Plant End-of-Cycle Performance Assessment for 2010 ML1108208272011-04-21021 April 2011 Summary of Pre-application Meeting with NextEra Energy, Inc., and Florida Power & Light Company, on Turkey Point, Units 3 and 4, St. Lucie, Units 1 & 2, Point Beach, Units 1 & 2, Duane Arnold Transition to NFPA-805 ML1014000432010-05-20020 May 2010 Summary of Public Meeting with FPL Energy Point Beach, LLC to Discuss Progress on the Nuclear Excellence Model and Updates on Operational Excellence, Generation Reliability, and Organizational Effectiveness at Point Beach ML1012502352010-05-0505 May 2010 Summary of the April 22, 2010, Public Meeting to Discuss the 2009 Point Beach End-of-Cycle Performance Assessment ML0924305212009-08-31031 August 2009 July 29, 2009,Summary of Public Meeting to Discuss the Progress on Actions Taken in Response to Substantive Cross Cutting Issues and the Results of an Independent Assessment of Corrective Actions for Recent Nuclear Safety Culture Surveys ML0914001932009-05-20020 May 2009 Summary of Public Meeting to Discuss the Progress on Actions Taken in Response to a Nuclear Safety Culture Survey in 2008 - Point Beach Nuclear Plant ML0832308202008-11-20020 November 2008 Teleconference Summary Regarding the 2008 Steam Generator Tube Inspection Results 2024-09-05 Category:Memoranda MONTHYEARML23044A3662023-02-15015 February 2023
[Table view]Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML22020A2812022-02-11011 February 2022 Subsequent License Renewal Application Summary of December 2, 2021, Public Meeting on Proposed Aging Management Activities ML22004A0772022-01-0606 January 2022 Summaries of December 8, 2021 Draft Supplemental Environmental Impact Statement for Subsequent License Renewal Application Public Meetings ML21062A0702021-04-21021 April 2021 Memo to File: Final Ea/Fonsi of 2012 and 2015 Decommissioning Funding Plans for Point Beach Units 1 and 2 Independent Spent Fuel Storage Installation (2012 and 2015) ML21075A3422021-03-17017 March 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Memo ML20233A7902020-08-20020 August 2020 Summary of the July 30, 2020, Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center and the Point Beach Nuclear Plant ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML15302A1702015-11-0202 November 2015 Forthcoming Closed Pre-Application Teleconference with NextEra Energy Point Beach, LLC (Nextera), Regarding Steam Generators H* License Amendment Request ML13154A5112013-06-0404 June 2013 Rai'S Following Ifib Analysis of NextEra Energy'S 2013 Decommissioning Funding Status Reports for Duane Arnold Energy Center and Point Beach Units 1 and 2 ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML12243A5232012-07-19019 July 2012 Letter from FEMA Region 5 to FEMA Hq Regarding Closure of Point Beach Deficiency ML1212805092012-06-18018 June 2012 May 1, 2012 - Summary of Teleconference with Performance Contracting, Inc., Regarding Large Flume Testing for Point Beach Nuclear Plant ML12115A0802012-04-24024 April 2012 Memo 042412 TIA 2012-07 for Point Beach EDG Tornado Missiles ML11228A2572011-08-16016 August 2011 Final - Task Interface Agreement (TIA) - Evaluation of Point Beach Nuclear Plant Torado Missile Protection Licensing Basis (TIA 2011-011) ML1106104272011-03-0707 March 2011 Notice of Forthcoming Pre-Application Meeting with Florida Power & Light Company and NextEra Energy Regarding Turkey Point, Units 3 and 4, St. Lucie, Units 1 and 2, Point Beach, Units 1, and 2, and Duane Arnold ML0921805182009-08-0606 August 2009 Notice of Public Meeting with Florida Power & Light Energy ML0827307072008-09-29029 September 2008 Pre-application Meeting with FPL Energy Point Beach, LLC to Discuss Their Proposed Alternate Source Term Amendment ML0824102292008-08-28028 August 2008 Notice of Forthcoming Meeting with Florida Energy Point Beach LLC, to Discuss Their Proposed Extended Power Uprate ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0712002952007-05-18018 May 2007 Cover Memo to Safety Evaluation by the Office of Nuclear Reactor Regulation - Direct Transfer of License from Nuclear Management Company, LLC & Wisconsin Electric Power Company to FPL Energy Point Beach, LLC (TAC # MD4112 & TAC # MD4113) ML0634003252006-12-0707 December 2006 Notice of Presubmittal Conference for Proposed Emergency Plan Changes ML0621603282006-08-29029 August 2006 Request for Additional Information Related to Evaluation of Event Notification 42129 ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0607503402006-04-20020 April 2006 Trip Report Regarding Staff Observations of Scaled Flume Testing of the Point Beach Nuclear Plant Proposed Replacement Suction Strainer Design ML0603000432006-02-13013 February 2006 Document Reclassified as Non-Proprietary ML0602301932006-02-10010 February 2006 Document Reclassified as Non-Proprietary ML0602400292006-02-0909 February 2006 Document Reclassified as Non-Proprietary ML0602502942006-01-25025 January 2006 Canceled Notice of Meeting with Nuclear Management Company Regarding Fleet Transition to NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants ML0602400772005-12-23023 December 2005 Memo 12/23/05 Point Beach One-Time Deviation from Regulatory Response Column of Reactor Oversight Process Action Matrix ML0529401992005-12-0202 December 2005 Unit 2 - Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0526203802005-09-30030 September 2005 Fiscal Year 2005 Evaluation of the Operating Reactor Licensing Program ML0523801282005-08-31031 August 2005 Unit 2 - Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors ML0626504112005-08-29029 August 2005 Memorandum to Region III Office Allegation Coordinator from P. Louden, Review of Discrimination Complaint Filed with Department of Labor ML0518203592005-07-0808 July 2005 Notice of Meeting with Nuclear Management Company Regarding the Planned Amendment to the Point Beach Nuclear Plant, Unit 1, Updated Safety Analysis Report Relating to Movement of the Reactor Vessel Head ML0626504042005-06-22022 June 2005 Memorandum to P. Louden from P. Pelke, Review of Receipt of Allegation, Allegation No. RIII-05-A-0062 (Point Beach) ML0626802612005-06-21021 June 2005 Memorandum to Allegation File from P. Pelke Receipt of Allegation (Point Beach) IR 05000266/20040032005-05-24024 May 2005 or Inspection Report Input to Point Beach Integrated Report 50-266/04-003 & 50-301-04-003 ML0515202472005-05-24024 May 2005 Previous Revision of Inspection Input to Point Beach Integrated Report 50-266-04-003 & 50-301-04-003 ML0502700462005-01-19019 January 2005 Summary of Telephone Conference Held on January 10, 2005, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear ML0432706522004-11-17017 November 2004 Summary of Telephone Conference Heldon November 17, 2004, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, Llc. Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear Plan, U ML0432705872004-11-16016 November 2004 Summary of Telephone Conference Held on October 26, 2004, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear Plant, ML0420404302004-07-22022 July 2004 Notice of Meeting Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Nuclear Management Company, LLC (NMC) on Recent Decisions Involving Unit 2 Reactor Vessel Pressurized Thermal Shock ML0419604622004-07-0707 July 2004 Wpdes Permit Reissuance ML0421003322004-06-30030 June 2004 Close-out of Tacs Relating to the Review of 35-day Letters Submitted in Response to the April 29, 2003, Orders Revising the Design Basis and Security Guard Force Training Enhancements and Physical Fitness Requirements ML0418803242004-06-29029 June 2004 Audit and Review Plan for Plant Aging Management Reviews and Programs at Point Beach Nuclear Power Plant, Units 1 and 2 ML0417400862004-06-21021 June 2004 All Region III Facility Training Managers Revised NRC Form 398 - Personal Qualification Statement Licensee ML0508304222004-06-0202 June 2004 Memo T.Chan, NRR, to L. Raghavan, NRR, Safety Evaluation for Point Beach Unit 1 First Revised Order 2023-02-15 |
Text
March 17, 2021 MEMORANDUM TO: Robert B. Elliott, Chief Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguard FROM: Phyllis M. Clark, Project Manager /RA/
Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguard
SUBJECT:
MEETING
SUMMARY
- PUBLIC SCOPING MEETING FOR THE ENVIRONMENTAL REVIEW OF THE SUBSEQUENT LICENSE RENEWAL APPLICATION FOR POINT BEACH NUCLEAR PLANT, UNIT NOS. 1 AND 2 (EPID NO.: L-2020-SLE-0002)
On February 17, 2021, the U.S. Nuclear Regulatory Commission (NRC) staff conduct a scoping process to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the subsequent license renewal of the operating licenses for Point Beach Nuclear Plant, Unit Nos. 1 and 2. Enclosed is the meeting summary.
If you have any questions or comments, please contact me via e-mail at Phyllis.Clark@nrc.gov.
Docket Nos. 50-266 and 50-301
Enclosures:
- 1. Meeting Summary
- 2. List of Attendees
- 3. NRC slide presentation
- 4. Dominion slide presentation
- 5. Meeting transcript cc: w/enclosures:
see next page CONTACT: Phyllis M. Clark, NMSS/REFS 301-415-6447
ML21075A333 (pkg); ML21075A342 (memo); ML21075A343 (summary); attachments listed in summary *via email OFFICE ELRB:REFS LA:REFS/ERMB BC:ELRB:REFS ELRB:REFS NAME PClark* AWalker-Smith* RElliott* PClark*
DATE 03/16/2021 03/17/2021 03/17/2021 03/17/2021 R. Elliott Additional Distribution:
MikeW@badriver-nsn.gov THPO@badriver-nsn.gov rbarrett@potawatomi.org kelli.mosteller@potawatomi.org Ned.DanielsJr@fcpotawatomi-nsn.gov Michael.LaRonge@FCPotawatomi-nsn.gov andy.werk@ftbelknap.org mblackwolf@ftbelknap.org tyderyien@hannahville.org earlmeshigaud@hannahville.org marlon.whiteeagle@ho-chunk.com Bquackenbush@ho-chunk.com louis.taylor@lco-nsn.gov brian.bisonette@lco-nsn.gov jwildcatsr@ldftribe.com ldfthpo@ldftribe.com tribalchair@ltbbodawa-nsn.gov MWiatrolik@LTBBODAWA-NSN.GOV Bob.Peters@glt-nsn.gov mbpi_thpo@glt-nsn.gov.
chairman@mitw.org dgrignon@mitw.org dlankford@miamination.com dhunter@miamination.com jstuck@nhbpi.com Douglas.Taylor@nhbpi.com thill7@oneidanation.org sdanfor3@oneidanation.org cethel.oto@gmail.com rhonda.oto@gmail.com matthew.wesaw@pokagonband-nsn.gov matthew.bussler@pokagonband-nsn.gov cosettewahwassuck@pbpnation.org thomaswabmum@pbpnation.org Richard.Peterson@redcliff-nsn.gov marvin.defoe@redcliff-nsn.gov robert.vanzile@scc-nsn.gov adam.vanzile@scc-nsn.gov susanl@stcroixtribalcenter.com wandam@stcroixojibwe-nsn.gov shannon.holsey@mohican-nsn.gov nathan.allison@mohican-nsn.gov tori.kitcheyan@winnebagotribe.com sunshie.bear@winnebagotribe.com