MONTHYEARML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML22020A2812022-02-11011 February 2022 Subsequent License Renewal Application Summary of December 2, 2021, Public Meeting on Proposed Aging Management Activities ML22004A0772022-01-0606 January 2022 Summaries of December 8, 2021 Draft Supplemental Environmental Impact Statement for Subsequent License Renewal Application Public Meetings ML21062A0702021-04-21021 April 2021 Memo to File: Final Ea/Fonsi of 2012 and 2015 Decommissioning Funding Plans for Point Beach Units 1 and 2 Independent Spent Fuel Storage Installation (2012 and 2015) ML21075A3422021-03-17017 March 2021 Meeting Summary: Public Scoping Meeting for the Environmental Review of the Subsequent License Renewal Application for Point Beach Nuclear Plant, Unit Nos. 1 and 2 (EPID No.: L-2020-SLE-0002) - Memo ML20233A7902020-08-20020 August 2020 Summary of the July 30, 2020, Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center and the Point Beach Nuclear Plant ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML15302A1702015-11-0202 November 2015 Forthcoming Closed Pre-Application Teleconference with NextEra Energy Point Beach, LLC (Nextera), Regarding Steam Generators H* License Amendment Request ML13154A5112013-06-0404 June 2013 Rai'S Following Ifib Analysis of NextEra Energy'S 2013 Decommissioning Funding Status Reports for Duane Arnold Energy Center and Point Beach Units 1 and 2 ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML12243A5232012-07-19019 July 2012 Letter from FEMA Region 5 to FEMA Hq Regarding Closure of Point Beach Deficiency ML1212805092012-06-18018 June 2012 May 1, 2012 - Summary of Teleconference with Performance Contracting, Inc., Regarding Large Flume Testing for Point Beach Nuclear Plant ML12115A0802012-04-24024 April 2012 Memo 042412 TIA 2012-07 for Point Beach EDG Tornado Missiles ML11228A2572011-08-16016 August 2011 Final - Task Interface Agreement (TIA) - Evaluation of Point Beach Nuclear Plant Torado Missile Protection Licensing Basis (TIA 2011-011) ML1106104272011-03-0707 March 2011 Notice of Forthcoming Pre-Application Meeting with Florida Power & Light Company and NextEra Energy Regarding Turkey Point, Units 3 and 4, St. Lucie, Units 1 and 2, Point Beach, Units 1, and 2, and Duane Arnold ML0921805182009-08-0606 August 2009 Notice of Public Meeting with Florida Power & Light Energy ML0827307072008-09-29029 September 2008 Pre-application Meeting with FPL Energy Point Beach, LLC to Discuss Their Proposed Alternate Source Term Amendment ML0824102292008-08-28028 August 2008 Notice of Forthcoming Meeting with Florida Energy Point Beach LLC, to Discuss Their Proposed Extended Power Uprate ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0712002952007-05-18018 May 2007 Cover Memo to Safety Evaluation by the Office of Nuclear Reactor Regulation - Direct Transfer of License from Nuclear Management Company, LLC & Wisconsin Electric Power Company to FPL Energy Point Beach, LLC (TAC # MD4112 & TAC # MD4113) ML0634003252006-12-0707 December 2006 Notice of Presubmittal Conference for Proposed Emergency Plan Changes ML0621603282006-08-29029 August 2006 Request for Additional Information Related to Evaluation of Event Notification 42129 ML0617805592006-07-10010 July 2006 Revised Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0607503402006-04-20020 April 2006 Trip Report Regarding Staff Observations of Scaled Flume Testing of the Point Beach Nuclear Plant Proposed Replacement Suction Strainer Design ML0603000432006-02-13013 February 2006 Document Reclassified as Non-Proprietary ML0602301932006-02-10010 February 2006 Document Reclassified as Non-Proprietary ML0602400292006-02-0909 February 2006 Document Reclassified as Non-Proprietary ML0602502942006-01-25025 January 2006 Canceled Notice of Meeting with Nuclear Management Company Regarding Fleet Transition to NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants ML0602400772005-12-23023 December 2005 Memo 12/23/05 Point Beach One-Time Deviation from Regulatory Response Column of Reactor Oversight Process Action Matrix ML0529401992005-12-0202 December 2005 Unit 2 - Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors. ML0526203802005-09-30030 September 2005 Fiscal Year 2005 Evaluation of the Operating Reactor Licensing Program ML0523801282005-08-31031 August 2005 Unit 2 - Closeout Letter for Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors ML0626504112005-08-29029 August 2005 Memorandum to Region III Office Allegation Coordinator from P. Louden, Review of Discrimination Complaint Filed with Department of Labor ML0518203592005-07-0808 July 2005 Notice of Meeting with Nuclear Management Company Regarding the Planned Amendment to the Point Beach Nuclear Plant, Unit 1, Updated Safety Analysis Report Relating to Movement of the Reactor Vessel Head ML0626504042005-06-22022 June 2005 Memorandum to P. Louden from P. Pelke, Review of Receipt of Allegation, Allegation No. RIII-05-A-0062 (Point Beach) ML0626802612005-06-21021 June 2005 Memorandum to Allegation File from P. Pelke Receipt of Allegation (Point Beach) IR 05000266/20040032005-05-24024 May 2005 or Inspection Report Input to Point Beach Integrated Report 50-266/04-003 & 50-301-04-003 ML0515202472005-05-24024 May 2005 Previous Revision of Inspection Input to Point Beach Integrated Report 50-266-04-003 & 50-301-04-003 ML0502700462005-01-19019 January 2005 Summary of Telephone Conference Held on January 10, 2005, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear ML0432706522004-11-17017 November 2004 Summary of Telephone Conference Heldon November 17, 2004, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, Llc. Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear Plan, U ML0432705872004-11-16016 November 2004 Summary of Telephone Conference Held on October 26, 2004, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear Plant, ML0420404302004-07-22022 July 2004 Notice of Meeting Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Nuclear Management Company, LLC (NMC) on Recent Decisions Involving Unit 2 Reactor Vessel Pressurized Thermal Shock ML0419604622004-07-0707 July 2004 Wpdes Permit Reissuance ML0421003322004-06-30030 June 2004 Close-out of Tacs Relating to the Review of 35-day Letters Submitted in Response to the April 29, 2003, Orders Revising the Design Basis and Security Guard Force Training Enhancements and Physical Fitness Requirements ML0418803242004-06-29029 June 2004 Audit and Review Plan for Plant Aging Management Reviews and Programs at Point Beach Nuclear Power Plant, Units 1 and 2 ML0417400862004-06-21021 June 2004 All Region III Facility Training Managers Revised NRC Form 398 - Personal Qualification Statement Licensee ML0508304222004-06-0202 June 2004 Memo T.Chan, NRR, to L. Raghavan, NRR, Safety Evaluation for Point Beach Unit 1 First Revised Order 2023-02-15
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24215A2092024-08-0101 August 2024 NRR E-mail Capture - Final RAI - Point Beach 1 & 2 - License Amendment Request to Modify Containment Average Air Temperature Requirements ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24176A2242024-06-24024 June 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24149A1922024-05-28028 May 2024 Notification of NRC Baseline Inspection and Request for Information ML24141A1382024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection.Docx ML24030A0352024-01-30030 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23163A2422023-06-13013 June 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000266/2023004 ML23136A2802023-05-0505 May 2023 SLRA Second Annual Update RAI Set 1 ML23122A0132023-05-0101 May 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding Risk-Informed Approach to Address GSI-191 ML23033A0292023-01-31031 January 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI (Volume 2) - License Amendment Request Regarding TSTS-505 ML23003A8022023-01-0303 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22354A1612022-12-20020 December 2022 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding TSTS-505 ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22266A0872022-09-23023 September 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22172A1192022-06-27027 June 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Adopt TSTF-505 Provide Risk Informed Extended Complete Times - RITSTF Initiative 4B ML22130A5712022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22041B0752022-02-10010 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000266/2022002 ML21362A6812021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final ML21362A6822021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final Email ML21362A6702021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final ML21362A6712021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final Email ML21287A0852021-10-14014 October 2021 SLRA Safety RAI Set 11 Final Email ML21286A6042021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final ML21286A6032021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final Email ML21273A0222021-09-29029 September 2021 SLRA Safety RAI Set 9 Final ML21287A0862021-09-29029 September 2021 SLRA Safety RAI Set 11 Final ML21253A1672021-09-10010 September 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000266/2022010 05000301/2022010 ML21242A2292021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 Email ML21242A2282021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 ML21242A2472021-08-26026 August 2021 SLRA Safety RAIs Set 8 Final ML21242A2222021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 ML21242A2232021-08-23023 August 2021 SLRA Draft Safety RAI Set 8 Email ML21242A2192021-08-20020 August 2021 SLRA Safety RAI Set 7 Final Email ML21242A2202021-08-20020 August 2021 SLRA Safety RAI Set 7 Final ML21242A2142021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft ML21242A2132021-08-13013 August 2021 SLRA Safety RAIs Set 7 Draft Email ML21242A0152021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final ML21242A2392021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final ML21242A2032021-08-12012 August 2021 Srla Safety RAIs Set 5 Final ML21242A2382021-08-12012 August 2021 SLRA Safety RAIs Set 6 Final Email ML21242A2042021-08-12012 August 2021 SLRA Safety RAIs Set 5 Final Email ML21242A0122021-08-0909 August 2021 SLRA Draft Safety RAIs Set 6 ML21285A1212021-08-0505 August 2021 SLRA Public Meeting Discussion Questions August 5 2021 ML21242A2002021-08-0505 August 2021 SLRA Draft Safety RAIs Set 5 Email ML21242A1992021-08-0505 August 2021 Srla Draft Safety RAIs Set 5 ML21238A2322021-08-0404 August 2021 SLRA Safety RAI Set 4 Final Email ML21238A2332021-08-0404 August 2021 SLRA Safety RAI Set 4 Final ML21237A0062021-08-0202 August 2021 SLRA Draft Safety RAIs Set 4 ML21208A1892021-07-27027 July 2021 SLRA Safety RAIs Set 2 Final 2024-08-01
[Table view] |
Text
August 29, 2006 MEMORANDUM TO: File FROM: Carl F. Lyon, Project Manager, Section 1 /RA/
Project Directorate III Division of Operating Reactor Licensing
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO EVALUATION OF EVENT NOTIFICATION 42129 (TAC NOS. MC9035 AND MC9036)
This memorandum documents the telephone conference on March 9, 2006, between J. Lehning and F. Lyon (NRC) and T. Kendall (NMC), to discuss questions from the NRC staffs review of Nuclear Management Company, LLCs (NMC's) letter dated February 16, 2006 regarding Event Notification 42129. The NRC staff requested clarification of the basis for the scaling factor approach used to: (1) reduce the size of the zone of transport (ZOT) around the sump screens, based upon the reduced sump flow rate and assumed increased pool height, and (2) reduce the containment pool flow velocities in the vicinity of the sump screens, based upon the reduced sump flow rate. The scaling calculations were performed in Engineering Evaluation 2005-0024, which was provided in Enclosure 3 to NMCs February 16, 2006, letter.
NMC indicated that the scaling approach for the ZOT was based upon the nodal network calculation used in the current licensing basis for computing containment pool velocities. The NRC staff noted that the scaling approach did not address the geometric convergence of flow near the sump screens or uncertainties associated with the perturbations in nodal channel flow resistance that would result from the perturbation in sump flow rate. NMC responded that no degraded coatings are within 7 feet of the sump screens and further clarified that (1) coating washdown along the liner plate was not predicted to occur and (2) even if coating washdown occurred, these coatings would enter the containment pool over 7 feet away from the sump screens.
The licensee indicated that the scaling approach for the containment pool flow velocity was also based upon the nodal network calculation used in the current licensing basis. The NRC staff noted that this approach did not account for the geometric convergence of the containment pool flow as it approaches the sump screens. The NRC staff also noted that the reduced sump flow rate would induce perturbations in the nodal channel resistance that could reduce the accuracy of NMCs simplified scaling approach. NMC recognized these concerns, but concluded that they would not have a significant effect on the overall debris transport calculation results. NMC stated that its conclusion was based upon engineering judgment.
Docket Nos. 50-266 and 50-301
August 29, 2006 MEMORANDUM TO: File FROM: Carl F. Lyon, Project Manager, Section 1 /RA/
Project Directorate III Division of Operating Reactor Licensing
SUBJECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO EVALUATION OF EVENT NOTIFICATION 42129 (TAC NOS. MC9035 AND MC9036)
This memorandum documents the telephone conference on March 9, 2006, between J. Lehning and F. Lyon (NRC) and T. Kendall (NMC), to discuss questions from the NRC staffs review of Nuclear Management Company, LLCs (NMC's) letter dated February 16, 2006 regarding Event Notification 42129. The NRC staff requested clarification of the basis for the scaling factor approach used to: (1) reduce the size of the zone of transport (ZOT) around the sump screens, based upon the reduced sump flow rate and assumed increased pool height, and (2) reduce the containment pool flow velocities in the vicinity of the sump screens, based upon the reduced sump flow rate. The scaling calculations were performed in Engineering Evaluation 2005-0024, which was provided in Enclosure 3 to NMCs February 16, 2006, letter.
NMC indicated that the scaling approach for the ZOT was based upon the nodal network calculation used in the current licensing basis for computing containment pool velocities. The NRC staff noted that the scaling approach did not address the geometric convergence of flow near the sump screens or uncertainties associated with the perturbations in nodal channel flow resistance that would result from the perturbation in sump flow rate. NMC responded that no degraded coatings are within 7 feet of the sump screens and further clarified that (1) coating washdown along the liner plate was not predicted to occur and (2) even if coating washdown occurred, these coatings would enter the containment pool over 7 feet away from the sump screens.
The licensee indicated that the scaling approach for the containment pool flow velocity was also based upon the nodal network calculation used in the current licensing basis. The NRC staff noted that this approach did not account for the geometric convergence of the containment pool flow as it approaches the sump screens. The NRC staff also noted that the reduced sump flow rate would induce perturbations in the nodal channel resistance that could reduce the accuracy of NMCs simplified scaling approach. NMC recognized these concerns, but concluded that they would not have a significant effect on the overall debris transport calculation results. NMC stated that its conclusion was based upon engineering judgment.
Docket Nos. 50-266 and 50-301 DISTRIBUTION PUBLIC LPL3-1 RF RidsNrrLADClarke RidsNrrPMFLyon JLehning RidsNrrDorlLpl3-1 ADAMS ACCESSION NO. ML062160328 OFFICE LPL3-1/PM LPL3-1/LA LPL3-1/BC(A)
NAME FLyon:ca DClarke MMurphy DATE 8/29/06 8/23/06 8/29/06 OFFICIAL RECORD COPY