Public Meeting Between USNRC Oversight Panel and FirstEnergy Nuclear Operating Company April 15, 2003

Davis-Besse Oversight Panel - Public Meeting April 2003 PURPOSES OF THIS MEETING

  • Discuss Licensees Progress on Implementing the Return to Service Plan
  • Inform the Public of the NRCs Oversight Panel Activities 2

Davis-Besse Oversight Panel - Public Meeting April 2003 AGENDA

  • Introduction and Opening Remarks
  • Summary of Mar. 11th Public Meetings
  • Discussion of Significant NRC Activities Since Mar. 11 Public Meeting
  • Licensee Presentation on the Status of Their Return to Service Plan
  • Adjourn NRC meeting with FENOC

<break>

  • Public Comments and Questions of NRC
  • Adjourn Meeting 3

Davis-Besse Oversight Panel - Public Meeting April 2003

SUMMARY

OF MAR. 11, 2003 PUBLIC MEETING

  • Topics Discussed

- Return to service plan progress

- Management and human performance

- Quality oversight

- Return to service building blocks progress

- Integrated schedule progress

  • Transcripts of the Mar. 11, 2003 meetings will be available on our web site. http://www.nrc.gov/

4

Davis-Besse Oversight Panel - Public Meeting April 2003 SIGNIFICANT NRC ACTIVITIES SINCE MAR. 11 PUBLIC MEETING

  • April 4, Held Public Meeting to Discuss Normal Operating Pressure Simulation Results
  • April 7, Initiated Safety Culture/Safety Conscious Work Environment Inspection
  • April 11, Completed Containment Sump Inspection

Davis-Besse Oversight Panel - Public Meeting April 2003 SIGNIFICANT NRC ACTIVITIES SINCE MAR. 11 PUBLIC MEETING

  • Closed Restart Checklist Items 6a-6f - Licensing Issue Resolution 6

Davis-Besse Oversight Panel - Public Meeting April 2003 UPCOMING NRC ACTIVITIES

  • Preparation for Under-Vessel Head Inspection
  • Preparation for Fire Protection Inspection
  • Preparation for Restart Assessment Team Inspection
  • Public Meetings to Discuss Design Issues and Licensee Assessment of Safety Culture 7

Davis-Besse Oversight Panel - Public Meeting April 2003 CONTINUING NRC ACTIVITIES

  • System Health Reviews / Design Issues
  • Safety Significant Program Effectiveness
  • Corrective Action Team Inspection
  • Resident Inspection 8

Davis-Besse Oversight Panel - Public Meeting April 2003 PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION PORT CLINTON, OHIO April 15, 2003, 7:00 pm EDT Purpose of Meeting:

Inform the Public of the NRCs Oversight Panel Activities 9

Davis-Besse Oversight Panel - Public Meeting April 2003 GOALS

  • Brief Public With Results of Afternoon Meeting with FENOC
  • Receive Comments and Questions From Public To ensure we hear all comments, please limit comments or questions to 5 minutes each. We will follow the format from previous meetings where we start with local members of the public.

10