LIC-04-0027, September 2004 Monthly Operating Report for Fort Calhoun Station Unit 1

From kanterella
Jump to navigation Jump to search
September 2004 Monthly Operating Report for Fort Calhoun Station Unit 1
ML042810090
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 10/06/2004
From: Bannister D
Omaha Public Power District
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LIC-04-0027
Download: ML042810090 (2)


Text

444 South 16th Street Mall Omaha NE 68102-2247 October 6, 2004 LIC- 04-002 7 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Reference:

Docket No. 50-285

SUBJECT:

September 2004 Monthly Operating Report (MOR)

Pursuant to Fort Calhoun Station (FCS) Unit No. 1 Technical Specification 5.9.1 .c, Omaha Public Power District (OPPD) submits the attached MOR for September 2004. No commitments are made to the NRC in this letter.

If you have any questions, please contact Mr. Erick Matzke at (402) 533-6855.

Sincerely, D. J. Bannister Manager - Fort Calhoun Station DJB/EPM/epm Attachment Employment with Equal Opportunity

LIC-04-0027 Attachment OPERATING DATA REPORT DOCKET NO. 50-285 UNIT NAME Fort Calhoun Station DATE October 2, 2004 COMPLETED BY E. P. Matzke TELEPHONE (402) 533-6855 REPORT PERIOD: September 2004 Design Electrical Rating (MWe-Net): 478 Maximum Dependable Capacity (MWe-Net): 478 MONTH YR-To- CUMULATIVE DATE Number of Hours Reactor was Critical: 720 6,3 11 221,179 Number of Hours Generator was On-line: 720 6,294 219,819 Unit Reserve Shutdown Hours: 0 Net Electrical Energy Generated (MWh): 342.043 2.997.995 95.524.098 1

r I 1 I Method of Date Type Duration Shutting Cause & Corrective No. F: Forced Reason' (yy/mnddd) S: Scheduled (Hours) Down Action Comments Reactor2 (1) Reason: (2) Method:

A-Equipment Failure (Explain) l-Manual B-Maintenance or Test 2-Manual Trip/Scram C-Refueling 3-Automatic Trip/Scram D-Regulatory Restriction 4-Continuation E-Operator Training/License Examination 5-Other (Explain)

F-Administrative G-Operational Error (Explain)

H-Other (Explain)

OPERATIONS

SUMMARY

Fort Calhoun Station operated at a nominal 100 percent power for the month of September 2004.