LIC-02-0141, November 2002 Monthly Operating Report for Calhoun Station Unit 1
| ML023540393 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 12/12/2002 |
| From: | Ridenoure R Omaha Public Power District |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LIC-02-0141 | |
| Download: ML023540393 (3) | |
Text
- ,mmmmrwwm*,mimr Omaha Public Power Distnict 444 South 16th Street Mall Omaha NE 68102-2247 December 12, 2002 LIC-02-0141 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Reference:
Docket No. 50-285
SUBJECT:
November 2002 Monthly Operating Report (MOR)
Pursuant to Fort Calhoun Station (FCS) Unit No. 1 Technical Specification 5.9.1.c, Omaha Public Power District (OPPD) submits the attached MOR for November 2002. No commitments are made to the NRC in this letter.
If you hlive any jiihetidns, please contact Mr. Erick Matzke at (402) 533-6855.
Attachments c:
E. W. Merschoff, NRC Regional Administrator, Region IV A. B. Wang, NRC Project Manager J. G. Kramer, NRC Senior Resident Inspector INPO Records Center
'Winston & Sttawn Employment with Equal Opportunity 4171
LIC-02-0141 Page 1 ATTACHMENT 1 OPERATING DATA REPORT DOCKET NO.
50-285 UNIT NAME Fort Calhoun Station DATE December 02, 2002 COMPLETED BY E. P. Matzke TELEPHONE (402) 533-6855 REPORT PERIOD:
November 2002
- 1. Design Electrical Rating
- 2. Maximum Dependable Capacity (MWe-Net):
(MWe-Net):
OPERATING STATUS MONTH
- 3. Number of Hours Reactor was Critical:
- 4. Number of Hours Generator was On-line:
720 720 YEAR TO DATE 7,338 7,317 5.--Unit-Reserve-Shutdown--Hours:-...............
- 6. Net Electrical Energy Generated (MWh):
478 478 CUMULATIVE 207,218 205,184 353,153 3,443,942 88,651,453
1
LIC-02-0141 Page 1 ATTACHMENT 2 UNIT SHUTDOWNS REPORT MONTH November 2002 DOCKET NO. 50-285 UNIT NAME Fort Calhoun Station DATE December 2, 2002 COMPLETED BY E. P. Matzke TELEPHONE (402) 533-6855
,,Type
'Method of Cas orrective Date F, Forced' Duration,,,
Shutting Action to No.
(YY/MMIDD)
S: Scheduled((Hours)n DownReactor" PreventAR-t° Down Ra Recu (1) Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training/License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain)
(2) Method:
I-Manual 2-Manual Trip/Scram 3-Automatic Trip/Scram 4-Continuation 5-Other (Explain)
OPERATIONS
SUMMARY
The Fort Calhoun Station operated at a nominal 100% power for the entire month.
SAFETY VALVE OR PORV CHALLENGES/FAILURES No failures or challenges to safety valves or PORVs occurred during the month.