IR 05000482/2024006
| ML25062A177 | |
| Person / Time | |
|---|---|
| Site: | Wolf Creek |
| Issue date: | 03/11/2025 |
| From: | Ami Agrawal NRC/RGN-IV/DORS/PBB |
| To: | Reasoner C Wolf Creek |
| Bloodgood M | |
| References | |
| IR 2024006 | |
| Download: ML25062A177 (1) | |
Text
March 11, 2025
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2024006)
Dear Cleve Reasoner:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Wolf Creek Generating Station, reviewing performance indicators (PIs),
inspection results, and enforcement actions from January 1, 2024, through December 31, 2024.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
The NRC determined the performance at Wolf Creek Generating Station during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).
Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2026.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding. Please contact me at 817-200-1411 with any questions you have regarding this letter.
Sincerely, Ami N. Agrawal, Branch Chief Reactor Projects Branch B Division of Operating Reactor Safety Docket No. 50-482 License No. NPF-42 Enclosure:
Inspection Plan cc w/ encl: Distribution via LISTSERV Signed by Agrawal, Ami on 03/11/25 ANNUAL ASSESSMENT LETTER FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2024006) - DATED MARCH 11, 2025 Distribution:
JMonninger, ORA JLara, ORA GMiller, DORS NTaylor, DORS DCylkowski, RC AAlen-Arias, RIV/OEDO VDricks, ORA TSmith, ORA LWilkins, OCA SLee, NRR AMoreno, RIV/OCA RAlexander, RSLO AAgrawal, DORS MBloodgood, DORS PNwafor, DORS VRand, DORS CHenderson, DORS CSigel, DORS SGalemore, DORS R4-DORS-IPAT R4Enforcement RFelts, DRO, NRR PMcKenna, DRO, NRR JPelton, DORL, NRR ARivera-Varona, DORL, NRR MWaters, DPR, NSIR TInverso, DSO, NSIR TNakanishi, DORL, NRR DORS Branch Chiefs DRSS Branch Chiefs DORS Directors DRSS Directors Senior Allegations Coordinator ROP Assessment DOCUMENT NAME: ANNUAL ASSESSMENT LETTER FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2024006)
ADAMS ACCESSION NUMBER: ML25062A177 X
Non-Sensitive
Sensitive X
Publicly Available
Non-Publicly Available OFFICE SPE:DORS:PBB BC:DORS:PBB NAME MBloodgood AAgrawal SIGNATURE
/RA/
/RA/
DATE 03/06/25 03/11/25 OFFICAL RECORD COPY
Site Inspection Activity Plan Wolf Creek 01/01/2025 - 12/31/2026 Unit Start End Activity CAC Title Staff Count License Renewal 71003 - WC (Phase 2)
1 1/20/2025 1/24/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal
2/3/2025 2/7/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal MC&A - WC
1 2/24/2025 2/28/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)
Security Protective Strategy (71130.05) and Target Sets (71130.14)
1 3/17/2025 3/21/2025 IP 71130.05 000737 Protective Strategy Evaluation
3/17/2025 3/21/2025 IP 71130.09 001656 Security Plan Changes
3/17/2025 3/21/2025 IP 71130.14 000743 Review of Power Reactor Target Sets Commercial Grade Dedication Inspection - Wolf Creek
1 3/24/2025 3/28/2025 IP 71111.21N.03 001808 Commercial Grade Dedication
4/7/2025 4/11/2025 IP 71111.21N.03 001808 Commercial Grade Dedication Security Access Control (71130.02), Security PIV (71151)
1 3/31/2025 4/4/2025 IP 71130.02 000734 Access Control
3/31/2025 4/4/2025 IP 71151 001338 Performance Indicator Verification Cybersecurity-WC
1 5/11/2025 5/17/2025 IP 71130.10 000741 Cybersecurity EP 2025 Biennial Exercise & PI Inspection - WC
1 6/2/2025 6/6/2025 IP 71114.01 000716 Exercise Evaluation
6/2/2025 6/6/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
6/2/2025 6/6/2025 IP 71151 001397 Performance Indicator Verification WC 2025 INITIAL EXAM
1 7/6/2025 7/12/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
8/17/2025 8/23/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
Inservice Inspection-WC
1 10/6/2025 10/17/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
1 10/13/2025 10/17/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
10/13/2025 10/17/2025 IP 71124.04 000728 Occupational Dose Assessment
10/13/2025 10/17/2025 IP 71151 000746 Performance Indicator Verification Security FFD
1 3/23/2026 3/27/2026 IP 71130.08 000740 Fitness-For-Duty Program Age-Related Degradation Inspection - Wolf Creek
Prepared on 2/26/2025 10:54:46 AM 1 of 2
Site Inspection Activity Plan
3/30/2026 4/3/2026 IP 71111.21N.04 001832 Age-Related Degradation
4/13/2026 4/17/2026 IP 71111.21N.04 001832 Age-Related Degradation RP 1,4,PI - WC
1 4/13/2026 4/17/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls
4/13/2026 4/17/2026 IP 71124.04 000728 Occupational Dose Assessment
4/13/2026 4/17/2026 IP 71151 000746 Performance Indicator Verification RP 5,6,7,8 - WC
1 6/8/2026 6/12/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation
6/8/2026 6/12/2026 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment
6/8/2026 6/12/2026 IP 71124.07 000731 Radiological Environmental Monitoring Program
6/8/2026 6/12/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation WC 2026 BRQ
1 6/21/2026 6/27/2026 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance EP Program & PI Inspection (2026) - WC
1 8/17/2026 8/21/2026 IP 71114.02 000717 Alert and Notification System Testing
8/17/2026 8/21/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System
8/17/2026 8/21/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes
8/17/2026 8/21/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness
8/17/2026 8/21/2026 IP 71151 001397 Performance Indicator Verification Wolf Creek 2026 PI&R
1 10/5/2026 10/23/2026 IP 71152B 000747 Problem Identification and Resolution Security AA-AC-Plan Change-PIV
1 11/2/2026 11/6/2026 IP 71130.01 000733 Access Authorization
11/2/2026 11/6/2026 IP 71130.02 000734 Access Control
11/2/2026 11/6/2026 IP 71130.09 001656 Security Plan Changes
11/2/2026 11/6/2026 IP 71151 001338 Performance Indicator Verification Prepared on 2/26/2025 10:54:46 AM 2 of 2