IR 05000455/1985004

From kanterella
Jump to navigation Jump to search
Insp Rept 50-455/85-04 on 840727-850618.Violation Noted: Boeing Steam Generator Snubber Life Cycle Test Not Conducted in Accordance W/Approved Procedure
ML20128G976
Person / Time
Site: Byron Constellation icon.png
Issue date: 07/02/1985
From: Danielson D, Yin I
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20128G956 List:
References
50-455-85-04, 50-455-85-4, NUDOCS 8507090374
Download: ML20128G976 (8)


Text

. - - -

.

.

.

.

.

.

, .

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-455/85004(DRS)

Docket No. 50-455 License No. CPPR-131 Licensee: Commonwealth Edison Company Post Office Box 767 Chicago, IL 60690 Facility Name: Byron Station, Unit 2 Inspection At: ITT-Grinnell Corporation, Warren, OH and Providence, RI (ITT-G)

USNRC, Region III, Glen Ellyn, IL (RIII)

Inspection Conducted: July 27, 1984 and February 4, 1985 at ITT-G, Providence, RI September 10-11 and October 24-25, 1984 at ITT-G, Warren, OH October 11 and 23, 1984, and January 16 and June 18, 1985 at RIII hf6(bNevT ~

Inspector- th T. Yin Date

>

Approved By:

D.H[.Danielson,Chiefk7bwhcbw Materials and Processes'Section 7l I

/

Date Inspection Summary Special Inspection on July 27, 1984 through June 18, 1985 (Report No. 50-455/85004(DRS)) '

Areas Inspected: Special, announced inspection to evaluate Boeing steam generator snubber (SGS) requalification tests conducted by ITT-G. The inspection involved a total of 80 inspector-hours at the vendor testing facilities, and at the RIII office by one NRC inspecto Results: Within the areas inspected, one violation was identified (SGS life cycle test was not conducted in accordance with the approved procedure - Paragraph 3).

8507090374 850702 PDR ADOCK 05000455 Q PDR

_ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _

"

,

e f v q t t

'

.

DETAILS

,

/t Persons Contacted ,

Commonwealth Edison Company (CECO).

  1. '

'

  • E. D. Swartz, Project Engineer .
  • P. R. Donavin, Field Engf aeering Coordinator
  • K. Ainger, Nuclear Licensing

> ,

-

Administrator ,1

.

I Sargent and Lundy Engineers (S&L)'

'

S. Putman, Supervising Structura'l Engineering Specialist a *R. A. Salsbury, Mechanical Engireer

  • C. S. Lim, Mechanical Project Ergineer< ,

1 *T. R. Tysen, Structural Engineer Specialist ITT-Grinnell Corporation (ITT-G)~ f

.

R. B. Mulcahey, Vice President and Director of Engineering ,

D. M. Sewell, Vice _Presideat and Director of QA , i 0. , ;

E. R. Eramiam Engineering Manager - Field Service' .

>

t \

A. M. Guglie Mo, Assistant Engineering Manager . Field Seriices R. K. Taylor, Project Manager; , Contract Ads:inistration D.-W. Mills, Senior Project Engineer D. L. Jew, Analysis Section Leader '

a

'

  • Denotes thnse participating in the management exit interview telephorie conference on June 18, 11,8 (

i

' ' Licensee Action on Previously Identified Items t f Q.iestionable qualification

[ .(Closed) Unresolved tests for,the SGSs conducted by Item (455/83-17-07):

Boe'in See Paragraph 3 for detail . Requ'alification Testing of B einq S SGS =

In conhnction with the scubber' replacement efforts reported in Inspection Report'Nos. 50-454/84-51; 50-455/84-35,Section III. the' Byron Unit 2 '

'

'g Boeing SGSs were redesigned and modified by ITT-Giand a series of requal-ification tests were conducte s ,

>

'

, , Review of Procedures

,

-

i

-

, ;

The inspector reviewed the follcwing requalification telt procedures

> contained in the ITT-G test program SPS-8471'-11-0 rnd had no adverse comments s

  • Test No. 1, "End Block /End Block Spring Rate with Block Valve," dated'Hovember 7,198 TestNo.2,"EndBlock/EndBlobkketallicComponentSpring ,

t Rates," dated November 7,198 ,

'

s

'. p

- . _ _ _ _ . . _

. 2

, . _ ._ . _ _ . _ _ . _ _

%

i

-

'

.

,

./

Test No. 3, "End Block /End Block Spring Rates With High Bulk Modules," dated November 7, 198 '

Test No. 4, " Functional and End Block /End Block Spring

. Ji - Rate Testing Standard Boeing Valve with GE SF-1154 Fluid,"

-

,

dated November 7, 198 . Test No.'5, " Life Cycle Test to Evaluate Piston Ring as

.

, Cylinder Bore Wear," dated December 11, 1984

'

~ Test No. 6, " Valve Dynamic Test," dated December 26, 198 Observation of Tests

-

The inspector cbserved the following requalification tests:

Test No. 1: The seal design test was conducted on October 24-25, 4 1984. Fluid leakage was observed at the control valve to cylinder body seal connection. The preliminary test showed that the ITT-G main SGS seal rodification was adequate for the maximum design rated load capacity. Subsequently, the control valve seal leakage problem was correcte (Testing performed on November 15-16, 1984, which was not observed by the inspector verified that the SGS effective spring rate met the S&L design specification requirements).

The valve dynamic test was conducted on February 4,

'

Test No. 6:

1985; The original Boeing control valve perfonned effectively under tie dynamic loading condition '*

,

No;violatiodsordeviationswereidentifie Review of Test Report The inspsetor' reviewed ITT-G Summary Report SPS 8471-13-0,

. i; " Developmental Testing of ITT Grinnell Modified Boeing Steam Generator

/P i Snubbers Byron and Braidwood Station," dated February 21, 1985, and had no ahverse comments concerning Test Nos.1, 2, 3, 4, and 6. The J( O i

procedure for Test No. 5 stated, " Block the valve passage in the direction to be tested and determine the bypass rate while stroking the voubber at 260,000 lbs. through onc inch of stroke centered on the hot. piston setting of the snubber, (3.07 in. from fully retracted),

in both the tension and compression directions. The bypass rate shall te determined by measuring the slope of displacement versus time recorded continuously during the test." Contrary to this provision, the ITT-G, Summary Report SPS 8471-13-0 stated that "The bypass rate was menured ~over one-half inch of stroke centered on the hot piston setting or for 30 minutes whichever occurred first. This was changed due to tae low bypass experienced which required that the load be applied for up to four hours to move one inch."

e

'

,

,

' f

_ _ . _ , _ _ _ . , , _ _ _ _ , , , _ , . . . _ _ _ . . . - . - _ . . , . . , _ - - . _ _ .

_ _ _ _ _ _ _ - _ _ _ _ _ _

.

.

.

Based on a review of test data and discussions with Ceco and S&L technical personnel, the inspector concluded that even though the test as conducted was not as stringent as the specified testing, the test acceptably demonstrated that the snubber internal cylinder wear after repeated cycles would not impair the snubber functionabilit The failure to conduct SGS testing in accordance with an approved procedure is a violation of 10 CFR 50, Appendix B, Criterion V (455/85004-01). Inadequate Ccrrective Action The NRC inspector previously identified that the test procedure was not followed during testing of the Byron Unit 1 Paul-Munroe Hydraulic Company (PMH) SGSs, (Reference Inspection Report Nos. 50-454/84-51; 50-455/84-35,Section III, Paragraph 2) and a citation was issued for that matter. That testing was conducted during the week of September 10, 1984. The testing to satisfy Test No. 5 for the modified

Boeing SGS was conducted on January 23 through February 1,1985, and the NRC in:pector identified that this testing was not conducted in accordance with the test procedur This is a repetitive violation in that effective corrective measures were not taken to prevent recurrence of a previous violation (Reference Inspection Report Nos. 50-454/84-51; 50-455/84-35 Item 3.b).

4. Ineffective Licensee Communication with RIII RIII issued a letter to CECO dated March 7, 1984, requesting an opportunity to review testing procedures for the original Boeing snumbers, and that RIII be provided sufficient notification to allow the NRC an opportunity to observe the test facility and snubber testin Instances of the licensee's failure to report SGS test problems in a timely manner to RIII are documented in Inspection Report Nos. 50-454/84-39; 50-455/84-28, Paragraph 2.c, and Nos. 50-454/84-51; 50-455/84-35, Paragraph 2 (close out of Unresolved Item 454/84-39-01;455/84-38-01).

As a result of the inspector's concern regarding the licensee's failure to assure approved testing procedures are followed and failure to keep RIII informed of snubber testing activities, the licensee's Nuclear Licensing Administrator issued a Memorandum of Understanding (M00) to the responsible SGS technical QA personnel on October 5, 1984. The memorandum states that, "In order to address the Region III concerns as discussed with Mr. Isa T. Yin at the Sargent and Lundy Offices on October 3 and 4,1984, Commonwealth Edison has committed to heighten its coramunications with the Region concerning the Boeing and Paul Monroe Steam Generator Snubber activities including those activities associated with the ultimate Byron Unit 2 and Braidwood Units 1 and 2 resolution. In order to accoinplish this objective as committed, the above listed individuals must keep the Nuclear Licensing Department appraised of all developments concerning the above activity such that effective communications can be naintained between the Region and Commonwealth Edison."

.. . - . _- .

.

.

.

Since the issuance of the MOU, changes were made to facilitate completion of Test No. 5 of the ITT-G SGS requalification test program and these changes were not communicated to RIII. The NRC inspector stated that further improvement in communication regarding SGS testing activities is needed. Pending the licensee's evaluation of this matter and review of the licensee's actions by the inspector, this is considered to be an open item (455/85004-02). Open Items Open items are matters which have been discussed with the licensee, which will be reviewed further by the inspector, and which involve some action on the part of the NRC or licensee or both. An open item disclosed during the inspection is discussed in Paragraph . Exit Interview A telephone exit interview was conducted with licensee representatives on June 18, 1985, to discuss the inspection findings. The inspector discussed the likely informational content of the inspection report with regard to documents reviewed by the inspector during the inspection. The licensee did not identify any such documents proprietary.

!

,

'}

.

. . , . .~.- . , . . _ - - - - - - - - - . .

. - . -