ML20147H309

From kanterella
Jump to navigation Jump to search
Safety Insp Repts 50-454/87-27 & 50-455/87-25 on 870707-09 & 0820-21.Violations Noted.Major Areas Inspected:Previous Insp Findings,Observation of Maint Surveillance Activities & Training
ML20147H309
Person / Time
Site: Byron  Constellation icon.png
Issue date: 01/14/1988
From: Falevits Z, Gardner R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20147H179 List:
References
50-454-87-27, 50-455-87-25, NUDOCS 8801220264
Download: ML20147H309 (6)


See also: IR 05000454/1987027

Text

. _ _

o

e

'

mo.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

' Reports No. 50-454/87027(DRS); 50-455/87025(DRS)

Docket Nos. 50-454; 50-455-

Licenses No. NPF-37; NPF-66

Licensee:

Commonwealth Edison Company

Post Office Box 767

Chicago, IL 60690

Facility Name:

Byron Station, Units 1 and 2

Inspection At:

Byron Site, Byron, Illinois and

CECO Corporate Office

Inspection Conducted:

Ju

7-9, and August 20-21, 1987

  • si2 L s_

I[l'l[88

Inspector:

2. Falevits

Date

?-tsk%k-

Approved By:

Ronald N. Gardner, Chief

l!/

88

Plant Systems Section

Dat'e

Inspection Summary

Inspection on July 7-9, and August 20-21, 1987 (Reports do. 50-454/87027(DRS);

No. 50-455/87025(DRS))

Areas Inspected:

Routine, unannounced safety inspection of licensee action on

previous inspection findings; followup review of non-seismically qualified

components in Emergency Diesel Generator (OG) control circuitry; observation of

maintenance surveillance activities, and training (62705, 92702, 92705, 41400).

Results:

Of the four areas inspected, no violations or deviations were

identified in three areas.

One violation was identified in one area (failure

to assure, via the design review process, that seismically qualified

electrical components were used in the DG control circuitry - Paragraph 3).

I

8801220264 880114

'

'

PDR

ADOCK 05000454

0

DCD

_ - -,

_

_

-

-

i

e

s

1

-

.

.

DETAILS

1.

Persons Contacted

C;mmonwealth Edison Company (CECO)

  • R. E. Querio, Station Manager
  • R. C. Ward, Services Superintendent
  • G. K. Schwartz, Assistant Superintendent, Maintenance
  • D. W. Berg, Nuclear Safety Engineer
  • D. K. Johnson, General Foreman, I.M.
  • W. D. Pirnat, Regulatory Assurance Engineer
  • M. F. Blessing, Technical Staff Engineer
  • R. J. Morvec, Assistant Construction Superintendent
  • R. B. Klingler, Senior Quailty Assurance Engineer
  • W. J. Walter, Assistant Technical Staff Supervisor
  • H. Snow, Regulatory Assurance Supervisor
  • E. Zittle, Regulatory Assurance Staff

B. Shelton, Engineering Manager, PWR

+0. Elias, Byron & Braidwood Engineering Superintendent

+W. J. Grosko, Project Engineering, PWR Engineer

K. Ainger, Nuclear Licensing Engineer

R. Gesior, QA Engineer

Sargent & Lundy Engineers (S&L)

+D. P. Galanis, Electrical Project Engineer

R. J. Moery, Component Qualification Engineer

+S. Malak, PMED Engineer

+M. Hassaballa, Component Qualification Supervisor

The inspector also contacted and interviewed other licensee and

contractor personnel during this inspection.

  • Denotes persons attending the July 9, 1987, site exit interview.

+ Denotes persons attending the August 21, 1987, exit interview at the

CECO Corporate office.

2.

Licensee Action on Previous Inspection Items

a.

(Closed) Unresolved Item [454/87002-04(DRP); 455/87002-03(DRP)]

This item concerned an event described in LER 454/86035 in which

the licensee determined on December 17, 1986, that non-seismically

qualified parts were installed in the Emergency Diesel Generators

I

(DG) for Units 1 and 2.

During the review of this item, the

!

inspector determined that the licensee's design control measures

l

failed to assure that only seismically qualified components were

used in the DG control circuitry.

As a result, this item is

I

considered a violation of 10 CFR 50, Appendix B, Criterion III,

l

as discussed in Section 3 of this report.

l

l

i

2

1

.

.

- -

- -

-

-

.

.

-

.

a

b.

(Closed) Unresolved Item [454/87017-04(DRP); 455/87016-04(DRP)]

During a previous inspection, the resident inspector noted that the

time from the start of. decay of the voltage on bus 142 to the

actuation of the bus.undervoltage relay appeared to exceed the limit

of Technical Specification 3.3.2, Table 3.3-4, Functional Unit 8.a

-(2.2 verses 1.8 seconds).

However, bench testing of the undervoltage

relay, both before and after the test, indicated that the relay was

within the TS limit of 1.8 seconds and that its setpoint had not

changed.

The licensee believed that the inductive loading on the

4.16kv bus caused a slower voltage decay which caused the undervoltage

relay to energize at 2.2 seconds.

The licensee also believed that

this was acceptable and that the relays met the TS requirements.

The inspector reviewed this issue and discussed the findings with NRR.

NRR concluded that bench testing was an acceptable method for

calibrating and setting the undervoltage relays to the Technical

Specification requirements.

Based on this position, this item is

considered closed.

3.

Followup Review of Non-Seismically Qualified Components in' Emergency

Diesel Generator Control Circuitry

a.

The inspector conducted a followup review of the event described

in LER 454/86035.

This LER stated that on December 17, 1986,

with Unit 1 in Mode 1 and Unit 2 in Mode 3, the licensee's AE,

Sargent & Lundy (S&L), identified that non-seismically qualified

components were erroneously installed (wired) in the control

circuits of the Units 1 and 2 Emergency Diesel Generators (DGs).

The inspector conducted interviews with licensee and S&L personnel

and examined the applicable design and logic drawings and procedures

to determine the cause of the installation error.

(1) The review indicated that on December 4, 1986, the Byron

Architect Engineer, Sargent & Lundy (S&L), identified

four components (limit switches 12E01 and 12E02 and pressure

switches 33E02 and 33E01) which were not listed as

safety-related on the qualified parts list for the DGs.

These components were erroneously wired into the electrical

overspeed safety related trip circuitry of the DGs.

Failure

of either component in both diesel logic trains would have

caused a de-energization of the emergency master run relays

which would in turn de energize the fuel oil solenoids and

stop the DGs.

It was also determined that during a seismic

event these non qualified devices could actuate, preventing

the DGs from starting or cause them to stop.

The cause of

the design error was determined to be Cooper-Bessemer's (CB)

erroneous placement of non-seismicially qualified components

l

into a safety-related circuit.

The original intent for the

components used in the overspeed circuitry was for alarm

l

purposes only.

The inspector determined that the initial

i

design review conducted by S&L failed to identify the design

'

error.

3

.

..

.

.

.

.

.

.,

-

.

.(2)- During this followup- review, the inspector examined S&L'.s design

review methodology as it pertains to the seismic qualification

and technical adequacy of safety-related components and vendor

supplied design drawings.which had been reproduced onto S&L

. approved design drawings.

Sargent & Lundy Procedure GQ-3.09,

Revision 5, entitled "Foreign-Design Documents," states in

-

Paragraph A.3 that "the Project Leader, Project Supervisor or

Supervising Design Engineer shall assign a qualified individual

to review foreign design drawings."

In addition, Paragraph B.1

states that "the Inter and/or Intra Department Commentators

shall review the design drawings, as. required within their area

of responsibility, for compliance with the requirements of the

procurement specification . . . latest design information

and/or Vendor.'s proposal data . . . ."

S&L Procedure GQ-3.09 further requires that the foreign design

drawings be forwarded to the client (CECO) and other external

interfacing organizations for design reviews and comments; that

the Engineer / Supervisor satisfactorily resolve those comments

within its area of responsibility; that the contractor's

technical data, such as design data, design specifications,

seismic reports, etc., be sent to the responsible engineer.for

review and processing; that the Project Manager establish

a system for monitoring receipt of contractor's technical data

documents to ensure that all required documents.have been

submitted for review; and that the responsible engineer

prepare a letter of reply to the vendor which will include

any comments and the action to be-taken by-the vendor.

The inspector reviewed Sargent & Lundy's Procedure GQ-3.07,

Revision 7, entitled, "Sargent & Lundy Drawings" which described

the quality assurance requirements for the preparation, comment,

~

review, approval and distribution of S&L drawings that pertain

to safety-related structures, systems and components.

Paragraph 3.2.'3.1 of Procedure GQ-3.07, states "Provisions

shall be established for obtaining comments, as necessary, on

the technical adequacy of a drawing from interfacing departments

and divisions, and external sources such as clients".

In

addition, Paragraph 3.2.4 requires that provisions shall be

established to provide for a documented review and review

of the technical adequacy of a drawing.

A design review shall

be performed prior to release of the drawing for fabrication,

installation, construction, or release to another organization

for use in other design activities.

The drawing shall be

reviewed and commented upon, in accordance with a departmental

standard, for technical adequacy for the purpose of release.

When the drawing is technically adequate, the reviewer shall

sign the drawing on the drawing release record as reviewer.

Furthermore, the reviewer's signature on the drawing certifies

that the drawing is technically correct, that interfacing

conditions have been addressed, that all comments have been

4

. .

-_

_--

---

..

.-.

. .

.

.

.-

.

.

.

.-

t

Ex

-

.-

.

resolved and that the review was conducted in accordance'with

the' departmental standard.

The inspector determined that.S&L standard EDSI-73,

Revision 04-29-85, stated that,the vendor'is responsible for

the technical adequacy of the base design provided on the

drawing submitted, that S&L is only responsible for technically

reviewing any interface information added to the vendor produced

drawings.

However, the inspector concluded that this standard

did not apply to the DG drawings that have been reviewed and

issued prior to the issuance date of Standard EDSI-73.

Based on this review, the inspector determined that CECO, C8

and S&L engineers failed to identify the design _ error during the

initial design reviews that should have been conducted prior to

equipment installation.

Consequently, these switches existed

in the Diesel Generato'r circuitry since Byron's receipt of

operating license (October 31, 1984 for Unit 1 and November 6,

1986 for Unit 2), rendering _the Diesel Generators inoperable

and in violation of Technical Specification since the units

started operating.

The inspector informed the licensee that failure to identify design

errors during the design review process is considered a violation

of 10 CFR 50, Appendix B, Criterion III (454/87027-01(ORS);

455/87025-01(DRS)).

b.

The inspector reviewed QA audits which were conducted by CECO at

the Cooper Industries (CI) facilities during the period from 1979

to 1986.

The review indicated that Audit No. G-86-12 conducted in

August, 1986 identified serious problems with CI's QA program.

As a

result of these findings, CECO removed CI industries from the Quality

Approved Bidders List on May 1, 1987.

The inspector expressed the

concern that additional vendor design errors mi0ht exist in the

DG system possibly compromising safety.

The licensee informed the

inspector that during a recent system design description review and

spare parts review which was performed by S&L on Byron Units 1 and 2

all safety-related components were examined.

Several design problems

were identified and corrected in each unit.

No other deficiencies

'

were noted.

Based on this review the licensee believes that all

safety-related components in Byron Units 1 and 2 are qualified.

4.

Observation of Maintenance Surveillance Activities

The inspector witnessed surveillance and calibration activities

conducted on Auxiliary Feed Pump 28 Crank Case Pressure Switch 2PSH-AF154.

The following items were considered during this review:

calibration was

accomplished in accordance with an approved procedure and test report;

appropriate authorization signatures were obtained prior to starting the

calibration; test instrumentation was within its calibration interval;

the task was accomplished by qualified personnel; test results conformed

with acceptance criteria and tolerances.

5

-

---

-.

. .

4

-w

'

.

.

The inspector reviewed the following associated documents:

Calibration of Auxiliary Feed Pump 2B Crank Case' Pressure Switch

(AF) Test Report Package BIP 2400-008, dated July 9,- 1987.

Calibration of Pressure Switch Procedure No. BIP 2400-008,

Revision 2.

Maintenance Alteration Log BAP 400-TS, Revision 8.

No violations or deviations were identified.

5.

Training

The effectiveness of the licensee's training program was' reviewed by'the

. inspector during the witnessing of the licensee's performance.of routine

surveillance and maintenance activities.. Personnel appeared to be

knowledgeable of the task being performed.

No violations or deviations were identified.

6.

Exit-Interview

The Region'III inspector met with licensee representatives (denoted

under Paragraph 1) at the conclusion of the inspection on July 9, and.

on August 21, 1987.

The inspector summarized the purpose and findings

of the inspection.

The licensee acknowledged this information.

The

inspector also discussed the likely informational content of the

inspection report with regard to documents or processes reviewed by the

inspector during the inspection.

The licensee did not identify any such

documents / processes as proprietary.

f

l

6

-

.-

-

-.

-.

-

. .

-

- . -

.

--

.

-