IR 05000455/1985033

From kanterella
Jump to navigation Jump to search
Insp Rept 50-455/85-33 on 851028-31,1105 & 07.No Violation or Deviation Noted.Major Areas Inspected:Containment Structural Steel Welding,Preservice Insp Quality Records, Work Activities & Observation of Const
ML20137H621
Person / Time
Site: Byron 
Issue date: 11/25/1985
From: Danielson D, Ward K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20137H587 List:
References
50-455-85-33, NUDOCS 8512020433
Download: ML20137H621 (7)


Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-455/85033(DRS)

-

Docket No. 50-455 License No. CPPR-131 Licensee: Connonwealth Edison Company Post Office Box 767 Chicago, IL 60690 Facility Name: Byron Station, Unit 2 Inspection At: Byron Site, Byron, IL Inspection Conducted: October 28 through 31, November 5 and 7, 1985 K.'S

// 4$~/fr Inspector:

D. Ward

/

W D T

!

Approved By:

D. H. Danielson, Chief Materials and Processes Section Date

.

-

Inspection Summary Inspection on October 28 through 31, November 5 and 7 1985

""""~"-"x~"~

(Report No. 50-455/85033(DYSl f'

Treas Inspected: Unannounced, special safety inspection of containment structural steel welding and preservice inspection quality records and work activities and observation of the independent verification of construction perforred by the NRC nondestructive examination (NDE) van. The inspection involved a total of 48 inspector-hours by one NRC inspector.

Results: No violations or deviations were identified.

8512O20433 851125 DR ADOCK O5000455 i

PDR

-

-

-

-

-

-

-

DETAILS 1.

Persons Contacted Commonwealth Edison Company (Ceco)

.

  • J. Porter, Construction Supervisor R. Tuetken, Start-Up Superintendent E. Martin, QA Superintendent V. Schlosser, Project Manager G. Sorensen, Construction Manager W. Witt, General Supervisor NDE, Chief Level III R. Moravec, Mechanical Supervisor J. Woldridge, QA Supervisor R. Klinger, QC Supervisor M. Dellbetta, QA Supervisor R. Gaitonde, Supervising Staff Engineer J. Mihovilovich, Lead Structural Engineer D. Christiana, Mechanical Engineer E. Briette, QA Engineer W. Wolbor, QA Engineer R. Friedel, Engineer B. Harl, Staff Assistant (QA)

Pittsburgh Testing Laboratory (PTL)

..

.

-

J. Becker, Manager Conam Inspection Incorporated (Conam)

R. Marlow, Supervisor

.

Rockwell International (RI)

R. McCurnin, Supervisor Ebasco Services Incorporated J. Sencenberger, PSI Supervisor Blount Brothers Corporation (BBC)

T. Calsyn, Chief Field Inspector Hunter Corporation (HC)

P. Mall, Foreman Nuclear Regulatory Comission (NRC)

J. Hinds, Jr., Senior Resident Inspector (Region III)

,

P. Brochman, Resident Inspector (Region III)

H. Kercli, Lead Reactor Engineer (Region 1)

-

.

_

.

-

--

.

R. Harris, Engineering Technician, NDE (Region I)

A. Lodewyk, Reactor Inspector (Region I)

'

D. Payne, Level III, Thompson Engineering Testing, Inc. (TETI)

D. Wiggins, Level II, TETI The inspector also contacted and interviewed other licensee and

,

contractor employees.

  • Denotes the individual attending the final exit interview November 7, 1985.

2.

NRC Independent Measurements There was an independent verification inspection performed at the Byron Station, Unit 2, using the NRC NDE van and contractor technicians under NRC direction.

Construction activities and materials were sampled through nondestructive examinations (NDE) as a supplement to the existing inspection efforts.

The onsite inspection began on October 28, 1985, and was completed on November 7, 1985. The NRC (Region I) requested documentation packages for each of the welds selected to be prepared by the licensee.

The NRC

,

reviewed the licensee's documentation packages in Region I prior to site inspection and updated the NRC's procedures to be consistent with the licensee's procedures. The licensee prepared packages containiag the following information for each of the welds selected:

~ ~

Inspection Report

.

Weld History (QC History)

Material Certifications for base materials

Weld Wire Certifications

Piping drawings, Isometric of weld locations

NDE Reports on all NDE performed

.

NDE Procedures for RT, PT, MT, and VT

Weld Procedures

Bolt Torquing Procedures (Structural and Pipe Hangers)

Piping and Installation Procedure (only section that specifies

code and addenda)

The NDE van team performed the following examinations and inspections,

as appropriate:

Radiography - Pipe butt and socket welds, appropriate pressure boundary

components.

Ultrasonics - Flaw detection and material thickness measurements, as

appropriate, piping, welds, structural components, vessels,

heat exchangers, bolting, and other equipment.

Liquid Penetrant - Piping system components and structural elements.

Magnetic Particle - Piping system components and structural elements.

Hardness Testing - All of the previously listed components.

Delta Ferrite Indications (Severn Gage) - Stainless steel welds.

Alloy Analysis - Selected metallic components will have confirmatory

chemical analysis performed.

Visual Examination - Weld quality, cot. figuration verification of piping

and structural systems.

'

Quality Records Review - Welding documentation, materials and personnel

certifications, NDE records to incit.de radiographs.

The results of the above inspections are documented in NRC Inspection

Report No. 50-455/85031.

No violations or deviations were identified by the NRC Region III

inspector.

3.

Preservice Inspection (PSI)

a.

General

Ref.

NRC Inspection Report No. 50-454/84-50; 50-455/84-34

NRC Inspection Report No. 50-455/85015

b.

Procedure Review

The NRC inspector reviewed the foljowing proceduresc *

Conam, Multifrequency Eddy Current, No. 42-EC-122, Revision 0.

Rockwell International (RI), Examination Plan, No. 4451SI000004,

Revision A.

.

RI, Preservice/ Inservice Inspection - Ultrasonic Examination of

Reactor Vessel Circumferential Shell Welds, No. 44515I000005,

Revision A.

RI, Preservice/ Inservice Inspection - Ultrasonic Examination

of Nuclear Reactor Nozzle to Vessel Welds No. 445151000006,

Revision A.

RI, Preservice/ Inservice Inspection - Ultrasonic Examination

of Reactor Nozzle Inside Radius Section, No. 44515I000008,

Revision A.

RI, Preservice/ Inservice Inspection - Ultrasonic Examination

for Near Surface Resolution of Vessel Welds From the Inside

Surface, No. 445I5I000009, Revision A.

EBASCo, Magnetic Particle Examination of Welds and Bolting,

No. ISI-MT-S78-1, Revision 1.

.

- -

-

-

-

-

.

.

-

- -

-

-

.

EBASCo, Ultrasonic Manual Examination of Class 1 and 2 Vessel

Welds Including Reactor Pressure Vessel Welds, No. ISI-UT-S78-2,

Revision 1.

c.

Material and Equipment Certification

The NRC inspector reviewed the certification documents, relative to '

the following items:

Ultrasonic Instruments, Calibration Blocks, Transducers, and

Couplant.

Magnetic Particle Materials and Equipment.

Eddy Current Equipment,

d.

NDE Personnel Certifications, Observations of Work Activities, Data

Reports and Audits

The NRC inspector reviewed selected NDE personnel certifications in

accordance with SNT-TC-1A.

The certifications of Level IIs and IIIs

that were certified by EPRI for IGSCC were also reviewed.

The NRC inspector also observed the work and had discussions

with personnel during review of the following activities.

These

observations included calibrations, performance of t,he, examinations,

and review of selected documentation.

Ultrasonic examination of Weld No. PN-02, pressurizer nozzle,

performed by EBASCO and ultrasonic automatic examination of

Weld No. WR-34, reactor vessel, performed by Rockwell.

Eddy current examinations of steam generator (SG) tubes in

SG No. ZRCOLBA (SG No. 1) and SG No. ZRC01BD (SG No. 4),

performed by Conam.

Magnetic particle examinations of reactor vessel studs,

performed by EBASCO.

Audits of PSI, performed by EBASCO and surveillances, performed

by Ceco.

Data reports.

No violations or deviations were identified.

4.

Containment (Structural Steel Welding) - Work Activities and Review

of Quality Records

The NRC inspector observed the following field welding activities

associated with steel containment structures and steel supports within

containment acd determined that the requirements of applicable

specifications, standards, work performance, and inspection procedures

were me6

,

Beam No. 63301 was being prepared for a side coverplate.

Observed

that the in plate Angle stiffeners were notched to receive a backup

bar for the coverplate.

Beam No. 74118 was being prepared for a side coverplate.

Observed

fit up of a backup bar to the bottom of the top flange.

.

Beams Nos. 15811 and 22201.

Visually examined completed beams in

place including side coverplates.

Supports No. 2SIO4009 and 2RY06012.

Observed welding and visually

examined welding on the supports that were being increased in

structural size.

Support No. 2RC93A012.

Observed fit up and welding on a new

installation.

Support Nos. 2RY0615, 2RY06012, 2RY06103, and 2RYO6104.

Observed

welding and visually examined welding on a new installation.

Component support process sheets, weld records, bill of materials,

drawings, weld material stores requisitions and ECN's were included as

part of this review.

The NRC inspector also toured the welding material issuing room and

observed the storage of materials, identification, segregation and

cleanliness for conformance with the requirements of applicable

specifications and procedures.

A#ditionally, the NRC inspector determined that the records of the

following welds were in conformance with established procedures and

reflected work accomplishment consistent with applicable requirements:

Weld Member I.D. Number

Piece I.D. Number

15504L

BBC1089

15504R

EBC1024

15520R

BBC1164

15520R

BBC1234

23803L

BBC1435

23803L

BBC1903

23503R

BBC1837

33311R

BBC1024

33807R

BBC1304

35833L

BBC933

44204R

BBC1242

44202L

BBC1242

Weld inspection records which included fit ups, visual examinations,

welder qualifications, NDE records, and field changes were included as

part of this review.

The NRC inspector also toured the pre-issue storage

area for the weld rod.

,

._

_

_

.

No violations or deviations were identified.

5.

Exit Interview

The inspector met with site representatives (denoted in Persons Contacted

paragraph) at the conclusion of the inspection. The inspector summarized

the scope and findings of the inspection noted in this report.

The

'

inspector also discussed the likely informational content of the inspection

report with regard to documents or processes reviewed by the inspector

during the inspection.

The licensee did not identify any such documents /

processes as proprietary.

,