MONTHYEARBSEP-99-0168, Monthly Operating Repts for Sept 1999 for Bsep,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Bsep,Units 1 & 2. with ML20212D0431999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Brunswick Steam Electric Plant,Units 1 & 2 ML20210R1191999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Bsep,Units 1 & 2 BSEP-99-0118, Monthly Operating Repts for June 1999 for Bsep,Units 1 & 2. with1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Bsep,Units 1 & 2. with ML20210R1311999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Bsep,Unit 2 BSEP-99-0095, Monthly Operating Repts for May 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-99-0075, Monthly Operating Repts for Apr 1999 for Brunswick Steam Electric Plant,Unit 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Brunswick Steam Electric Plant,Unit 1 & 2.With BSEP-99-0059, Monthly Operating Repts for Mar 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-99-0043, Monthly Operating Repts for Feb 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-99-0005, Monthly Operating Repts for Dec 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-98-0231, Monthly Operating Repts for Nov 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-98-0218, Monthly Operating Repts for Oct 1998 for Bsep,Units 1 & 2. with1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Bsep,Units 1 & 2. with BSEP-98-0202, Monthly Operating Repts for Sept 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-98-0185, Monthly Operating Repts for Aug 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-98-0164, Monthly Operating Repts for July 1998 for BSEP Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for BSEP Units 1 & 2 BSEP-98-0142, Monthly Operating Repts for June 1998 for BSEP Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for BSEP Units 1 & 2 ML20151S9041998-05-31031 May 1998 Revised Pages to Monthly Operating Rept for May 1998 for Brunswick Steam Electric Plant,Unit 1 BSEP-98-0129, Monthly Operating Repts for May 1998 for Bsep,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Bsep,Units 1 & 2 ML20151S8991998-04-30030 April 1998 Revised Pages to Monthly Operating Rept for Apr 1998 for Brunswick Steam Electric Plant,Unit 1 BSEP-98-0104, Monthly Operating Repts for Apr 1998 for Brunswick Steam Electric Plant,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-98-0080, Monthly Operating Repts for Mar 1998 for Bsep,Units 1 & 21998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Bsep,Units 1 & 2 BSEP-98-0055, Monthly Operating Repts for Feb 1998 for Brunswick Steam Electric Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-98-0038, Monthly Operating Repts for Jan 1998 for Brunswick Steam Electric Plant,Units 1 & 21998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-98-0007, Monthly Operating Repts for Dec 1997 for Brunswick Steam Electric Plant,Unit 1 & 21997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Brunswick Steam Electric Plant,Unit 1 & 2 BSEP-97-0528, Monthly Operating Repts for Nov 1997 for Brunswick Steam Electric Plant,Units 1 & 21997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-97-0500, Monthly Operating Repts for Oct 1997 for Brunswick Steam Electric Plant,Units 1 & 21997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-97-0456, Monthly Operating Repts for Sept 1997 for Brunswick Steam Electric Plant1997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Brunswick Steam Electric Plant BSEP-97-0410, Monthly Operating Repts for Aug 1997 for Bsep,Units 1 & 21997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Bsep,Units 1 & 2 BSEP-97-0373, Monthly Operating Repts for Jul 1997 for Brunswick Steam Electric Plant,Units 1 & 21997-07-31031 July 1997 Monthly Operating Repts for Jul 1997 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-97-0323, Monthly Operating Repts for June 1997 for Brunswick Steam Electric Plant,Units 1 & 21997-06-30030 June 1997 Monthly Operating Repts for June 1997 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-97-0266, Monthly Operating Repts for May 1997 for Brunswick Steam Electric Plant Units 1 & 21997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Brunswick Steam Electric Plant Units 1 & 2 BSEP-97-0219, Monthly Operating Repts for Apr 1997 for Brunswick Steam Electric Plant,Units 1 & 21997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-97-0142, Monthly Operating Repts for March 1997 for Bsep,Units 1 & 21997-03-31031 March 1997 Monthly Operating Repts for March 1997 for Bsep,Units 1 & 2 BSEP-97-0105, Monthly Operating Repts for Feb 1997 for Bsep,Units 1 & 21997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Bsep,Units 1 & 2 BSEP-97-0055, Monthly Operating Repts for Jan 1997 for Brunswick Steam Electric Plant Units 1 & 21997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Brunswick Steam Electric Plant Units 1 & 2 ML20138H7881996-12-31031 December 1996 Corrected Monthly Operating Rept for Dec 1996 for Brunswick Unit 1 BSEP-97-0015, Monthly Operating Repts for Dec 1996 for Brunswick Steam Electric Plant Units 1 & 21996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Brunswick Steam Electric Plant Units 1 & 2 BSEP-96-0451, Monthly Operating Repts for Nov 1996 for Brunswick Steam Electric Plant,Units 1 & 21996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Brunswick Steam Electric Plant,Units 1 & 2 ML20138H7821996-11-30030 November 1996 Corrected Monthly Operating Rept for Nov 1996 for Brunswick Unit 1 BSEP-96-0422, Monthly Operating Repts for Oct 1996 for Brunswick Steam Electric Plant,Units 1 & 21996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-96-0375, Monthly Operating Repts for Sept 1996 for Brunswick Steam Electric Plant Unit 1 & 21996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Brunswick Steam Electric Plant Unit 1 & 2 BSEP-96-0330, Monthly Operating Repts for Aug 1996 for Brunswick Steam Electric Plant,Units 1 & 21996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-96-0295, Monthly Operating Repts for July 1996 for Brunswick Steam Electric Plant,Units 1 & 21996-07-31031 July 1996 Monthly Operating Repts for July 1996 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-96-0253, Monthly Operating Repts for June 1996 for Brunswick Steam Electric Plant Units 1 & 21996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Brunswick Steam Electric Plant Units 1 & 2 BSEP-96-0236, Monthly Operating Repts for May 1996 for Brunswick Steam Electric Plant Units 1 & 21996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Brunswick Steam Electric Plant Units 1 & 2 BSEP-96-0204, Monthly Operating Repts for April 1996 for BSEP1996-04-30030 April 1996 Monthly Operating Repts for April 1996 for BSEP BSEP-96-0146, Monthly Operating Repts for Mar 1996 for Brunswick Steam Electric Plant,Units 1 & 21996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Brunswick Steam Electric Plant,Units 1 & 2 BSEP-96-0097, Monthly Operating Repts for Feb 1996 for BSEP1996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for BSEP BSEP-96-0053, Monthly Operating Repts for Jan 1996 for BSEP Units 1 & 21996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for BSEP Units 1 & 2 BSEP-96-0008, Monthly Operating Repts for Dec 1995 for Brunswick Steam Electric Plant1995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Brunswick Steam Electric Plant 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217N3271999-10-21021 October 1999 Part 21 Rept Re non-linear Oxygen Readings with Two (2) Model 225 CMA-X Containment Monitoring Sys at Bsep.Caused by High Gain Produced by 10K Resistor Across Second Stage Amplifier.Engineering Drawings Will Be Revised BSEP-99-0168, Monthly Operating Repts for Sept 1999 for Bsep,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Bsep,Units 1 & 2. with ML20212D0431999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Brunswick Steam Electric Plant,Units 1 & 2 ML20210P9441999-08-10010 August 1999 Safety Evaluation Accepting Licensee Assessment of Impact on Operation of Plant,Unit 1,with Crack Indications of 2.11, 6.36 & 1.74 Inches in Three Separate Jet Pump Risers ML20210P9181999-08-10010 August 1999 Safety Evaluation Authorizing Request for Reliefs CIP-01,02, 06,07,08,09,10 & 11 (with Certain Exceptions) & 12-18,for Second 10-year ISI Interval.Request CIP-04 & 05 Would Result in hardship,CIP-03 Not Required & CIP-11 Denied in Part ML20210N2341999-08-0505 August 1999 SER Accepting Response to NRC GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Unresolved Safety Issues (USI) A-46 ML20210R1191999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Bsep,Units 1 & 2 ML20210R1311999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Bsep,Unit 2 BSEP-99-0118, Monthly Operating Repts for June 1999 for Bsep,Units 1 & 2. with1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Bsep,Units 1 & 2. with BSEP-99-0095, Monthly Operating Repts for May 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20210M8581999-05-14014 May 1999 B214R1 RPV Hydrotest Bolted Connection Corrective Action Evaluation, Rev 0 ML20211L3711999-05-10010 May 1999 Rev 0 to ESR 98-00333, Unit 2 Invessel Feedwater Sparger Evaluation ML20206G1871999-05-0404 May 1999 Safety Evaluation Approving Third 10-year ISI Program Requests for Relief (RR) RR-08,RR-15 & RR-17 BSEP-99-0075, Monthly Operating Repts for Apr 1999 for Brunswick Steam Electric Plant,Unit 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Brunswick Steam Electric Plant,Unit 1 & 2.With ML20206N1791999-04-23023 April 1999 Rev 0 to 2B21-0554, Brunswick Unit 2,Cycle 14 Colr BSEP-99-0059, Monthly Operating Repts for Mar 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20205F9031999-03-30030 March 1999 Safety Evaluation Supporting Proposed Rev to BSEP RERP to Licenses DPR-62 & DPR-71,respectively ML20206N1831999-02-28028 February 1999 Rev 0 to Suppl Reload Licensing Rept for Bsep,Unit 2 Reload 13 Cycle 14 BSEP-99-0043, Monthly Operating Repts for Feb 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20203D7061999-02-0909 February 1999 SER Accepting Proposed Alternatives Contained in Relief Requests PRR-04,VRR-04,VRR-13,PRR-01,PRR-03,VRR-01.VRR-07, VRR-08 & VRR-09 Denied BSEP-99-0005, Monthly Operating Repts for Dec 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-98-0231, Monthly Operating Repts for Nov 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-98-0218, Monthly Operating Repts for Oct 1998 for Bsep,Units 1 & 2. with1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Bsep,Units 1 & 2. with BSEP-98-0210, Special Rept:On 980824,temp Element 2-CAC-TE-1258-22 Failed. Cause of Failed Temp Element Cannot Be Conclusively Determined.Temp Element Will Be Replaced & Cable Connections Repaired1998-10-30030 October 1998 Special Rept:On 980824,temp Element 2-CAC-TE-1258-22 Failed. Cause of Failed Temp Element Cannot Be Conclusively Determined.Temp Element Will Be Replaced & Cable Connections Repaired ML20154P8151998-10-16016 October 1998 SER Accepting Revised Safety Analysis of Operational Transient of 920117,for Plant,Unit 1 ML20154P8591998-10-16016 October 1998 SER Accepting Equivalent Margins Analysis for N-16A/B Instrument Nozzles for Plant,Units 1 & 2 BSEP-98-0202, Monthly Operating Repts for Sept 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20151Y6211998-09-14014 September 1998 BSEP Rept Describing Changes,Tests & Experiments, for Bsep,Units 1 & 2 ML20151Y6371998-09-14014 September 1998 Changes to QA Program, for Bsep,Units 1 & 2 BSEP-98-0185, Monthly Operating Repts for Aug 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20151T5021998-08-0505 August 1998 Project Implementation Plan, Ngg Yr 2000 Readiness Program, Rev 2 BSEP-98-0164, Monthly Operating Repts for July 1998 for BSEP Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for BSEP Units 1 & 2 ML20236T1961998-07-0101 July 1998 Rev 1 to 2B21-0088, Brunswick Unit 2,Cycle 13 Colr ML20236T1921998-07-0101 July 1998 Rev 1 to 1B21-0537, Brunswick Unit 1,Cycle 12 Colr BSEP-98-0142, Monthly Operating Repts for June 1998 for BSEP Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for BSEP Units 1 & 2 ML20236T1971998-06-30030 June 1998 Rev 2 to 24A5412, Supplemental Reload Licensing Rept for Brunswick Steam Electric Plant Unit 2 Reload 12 Cycle 13 ML20249B9691998-06-11011 June 1998 Rev 1 to VC44.F02, Brunswick Steam Electric Plant,Units 1 & 2,ECCS Suction Strainers Replacement Project,Nrc Bulletin 96-003 Final Rept BSEP-98-0129, Monthly Operating Repts for May 1998 for Bsep,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Bsep,Units 1 & 2 ML20151S9041998-05-31031 May 1998 Revised Pages to Monthly Operating Rept for May 1998 for Brunswick Steam Electric Plant,Unit 1 BSEP-98-0104, Monthly Operating Repts for Apr 1998 for Brunswick Steam Electric Plant,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Brunswick Steam Electric Plant,Units 1 & 2 ML20151S8991998-04-30030 April 1998 Revised Pages to Monthly Operating Rept for Apr 1998 for Brunswick Steam Electric Plant,Unit 1 ML20247N7501998-04-30030 April 1998 Rev 0 to BSEP Unit 1,Cycle 12 Colr ML20247N7721998-04-30030 April 1998 Rev 0 to J1103244SRLR, Supplemental Reload Licensing Rept for BSEP Unit 1,Reload 11,Cycle 12 ML20217K8461998-04-24024 April 1998 Safety Evaluation Approving Proposed Use of Code Case N-535 at Brunswick Unit 1 During Second 10-yr Interval,Pursuant to 10CFR50.55a(a)(3)(i).Authorizes Use of Code Case N-535 Until Code Case Included in Future Rev of RG 1.147 ML20217K3941998-04-24024 April 1998 SER Approving Relief Request for Pump Vibration Monitoring, Brunswick Steam Electric Plant,Units 1 & 2 ML20217E6841998-04-23023 April 1998 Safety Evaluation Accepting Code Case N-547, Alternative Exam Requirements for Pressure Retaining Bolting of CRD Housings ML20217E7471998-04-21021 April 1998 Safety Evaluation Accepting Alternative to Insp of Reactor Pressure Vessel Circumferential Welds ML20217B5241998-04-20020 April 1998 SE Accepting Licensee Request for Approval to Use Alternative Exam Requirement for Brunswick,Unit 1,reactor Vessel Stud & Bushing During Second 10-yr ISI Interval Per 10CFR50.55a(a)(3)(ii) BSEP-98-0080, Monthly Operating Repts for Mar 1998 for Bsep,Units 1 & 21998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Bsep,Units 1 & 2 ML20216B1041998-03-0404 March 1998 SER Approving Alternative to Insp of Reactor Pressure Vessel Circumferential Welds for Brunswick Steam Electric Plant, Unit 1 1999-09-30
[Table view] |
Text
. . - _ . . . . - - . . . _ - _ - . - - - - .- - - - . . . - - . . . - - - . . - - . -
CP&L summmmmmmmma Carolina Power & Light Company P. O. Box 10429 Southport, NC- 28401-0429 DEC 151995 FILE: B09-13510C SERIAL: BSEP/95-0634 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
, BRUNSWICK STEAM ELECTRIC PLANT UNITS 1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62
, MONTHLY OPERATING REPORT Gentlemen:
In accordance with Technical Specification 6.9.1.11 for the Brunswick Nuclear Plant, Units 1 and 2, Carolina Power & Light Company herewith submits the report of operating statistics i and shutdown experience for the month of November 1995.
If you have any questions regarding this report, please contact Ms. Frances Harrison at (910) 457-2756.
Very truly yours, R. LoprioFe[ ~
Plant Manager Brunswick Nuclear Plant FH/mcg MSC/93-8524 1
Enclosures cc: Mr. S. D. Ebneter, Regional Administrator, Region 11 Mr. C, A. Patterson, NRC Senior Resident Inspector - Brunswick Mr. D. C. Trimble, NRR Project Manager - Brunswick The Honorable H. Wells, Chairman - North Carolina Utilities Commission 1C0001 9512190008 951130 a PDR R
ADOCK 05000324 PDR
/v 3 g
ENCLOSURE 1 BRUNSWICK STEAM ELECTRIC PLANT, UNITS NOS.1 AND 2 DOCKET NOS. 50-325 & 50 324 LICENSE NOS. DPR-71 & DPR 62 PLANT PERFORMANCE DATA SYSTEM l OPERATING DATA REPORT 1
i i
l i
)
l I
E1-2 I
CP&L Cb PLANT PERFORMANCE DATA SYSTEM PAGE 1 RUN DATE 12/07/95 APPENDIX B - AVERAGE DAILY POWER LEVEL RPD39-000 RUN TIME, 13:23:23 BRUNSWICK UNIT 1 DOCKET NO. 050-0325 I COMPLETED BY FRANCES HARRISON l TELEPHONE (910)457-2756 NOVEMBER 1995 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET) (MWE-NET) l 1 802 17 804 3 801 18 804 i I
3 800 19 803 4 801 20 803 5 803 21 761 6 804 22 804 7 803 23 804 8 802 24 804 9 803 25 803 10 709 26 805 11 737 27 805 12 803 28 804 13 804 29 804 14 804 30 804 15 805 16 803 1.16 - 8 l
l r
l-i CP&L CO PLANT PERFORMANCE DATA SYSTEM PAGE 1 RUN DATE 12/07/95 OPERATING DATA REPORT RPD36-000 RUN TIME, 13:23:24 BRUNSWICK UNIT 1 DOCKET NO. 050-0325 a
COMPLETED BY FRANCES HARRISON OPERATING STATUS TELEPHONE (910)457-2756
- 1. UNIT NAME: BRUNSWICK UNIT 1 NOTES a
- 2. REPORTING PERIOD: NOVEMBER 95
- 3. LICENSED THERMAL POWER (MWT): 2436-
- 4. NAMEPLATE RATING (GROSS MWE): 867.0
- 5. DESIGN ELECTRICAL RATING (NET MWE) : 821.0
- 6. MAX DEPENDABLE CAPACITY (GROSS MWE): 791.0 7 MAX DEPENDABLE CAPACITY (NET MWE): 767.0 -------------------------------
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:
1
- 9. POWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE) :
- 10. REASONS FOR RESTRICTION IF ANY:
THIS YR TO CUMUL MONTH DATE ATIVE I
- 11. HOURS IN REPORTING PERIOD 720 00 8016.00 .163968.00
- 12. NUMBER OF HOURS REACTOR CRITICAL 720.00 6777.42 102648.74
- 13. REACTOR RESERVE SHUTDOWN HRS .00 .00 1647.10 l
- 14. HOURS GENERATOR ON LINE 720.00 6650.18 98607.17
- 15. UNIT RESERVE SHUTDOWN HOURS .00 .00 .00
- 16. GROSS THERMAL ENERGY GEN. (MWH) 1739023.37 16011161.51 217546888.40
- 17. GROSS ELEC. ENERGY GEN. (MWH) 588655.00 5333735.00 71493460.00
- 18. NET ELEC. ENERGY GENERATED (MWH) 573425.00 5179316.00 68778355.00 l
- 19. UNIT SERVICE FACTOR 100.00 82.96 60.14 .)
- 20. UNIT AVAILABILITY FACTOR 100.00 82.96 60,14 l
. 21. UNIT CAP. FACTOR (USING MDC NET) 103.84 84.24 53.51 i
- 22. UNIT CAP. FACTOR (USING DER NET) 97.01 78.70 51.09 l
- 23. UNIT FORCED OUTAGE RATE .00 2.27 14.19 ,
i 24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH) :
l i
i l
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP: i 1
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION) : FORECAST ACHIEVED INITIAL CRITICALITY i INITIAL ELECTRICITY -------- --------
COMMERCIAL OPERATION -------- --------
1.16 -
9
CP&L Cb PLANT PERFORMANCE DATA SYSTEM PAGE 2 RUN DATE 12/07/95 APPENDIX B -
AVERAGE DAILY POWER LEVEL RPD39-000 RU;4 TIME,13:23:23 BRUNSWICK UNIT 2 DOCKET NO. 050-0324 COMPLETED BY FRANCES HARRISON TELEPHONE (910)457-2756 NOVSMBER 1995 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET) (MWE-NET) 1 668 17 656 2 666 18 652 3 663 19 652 4 596 20 648 5 686 21 643 6 e~9 22 641 7 677 23 639 8 674 24 636 9 671 25 629 10 677 26 627 11 672 27 626 12 668 28 623 13 667 29 621 14 664 30 619 15 662 1
16 659 !
1.16 - 8 I 1
l l
- - , . . ~ . . ~ . . - _ _ . . - . - _ . . - - . . . . - . - . . . . - - - _ . . . - . - - - . ~ . . . . . . . - -
i .
1 CP&L CO . PLANT PERFORMANCE DATA SYSTEM PAGE 2 RUN DATE. 12/07/95 OPERATING DATA REPORT RPD36-000 RUN TIME, 13:23:24 BRUNSWICK UNIT 2 DOCKET NO. 050-0324 -
COMPLETED BY FRANCES HARRISON
. OPERATING STATUS TELEPHONE (910)457-2756
- 1. UNIT NAME: BRUNSWICK UNIT 2 NOTES
- 2. REPORTING PERIOD: NOVEMBER 95
'3. LICENSED. THERMAL POWER (MWT) : 2436
- 4. NAMEPLATE-RATING (GROSS .MWE) : 867.0
- 5. DESIGN ELECTRICAL RATING (NET MWE) : 821.0 l 6. MAX DEPENDABLE CAPACITY (GROSS MWE) : 782.0
- 7. MAX DEPENDABLE CAPACITY (NET MWE) : 754.0 -------------------------------
, 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, j GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE) :
- 10. REASONS FOR RESTRICTION IF ANY: l 1
THIS YR TO CUMUL MONTH DATE ATIVE
- 11. HOURS IN REPORTING PERIOD 720.00 8016.00 175992.00 12.' NUMBER OF HOURS REACTOR CRITICAL
~
720.00 8016.00 112571.70
- 13. REACTOR RESERVE SHUTDOWN HRS .00 .00 .00
- 14. HOURS GENERATOR ON LINE 720.00 8016.00 107133.71
- 15. UNIT RESERVE SHUTDOWN HOURS .00 .00 .00
- 16. GROSS THERMAL ENERGY GEN. (MWH) 1501115.82 18628840.35 230879176.85
- 17. GROSS ELEC. ENERGY GEN. (MWH) 487175.00 5996160.00 74645781.00 4
- 18. NET ELEC. ENERGY GENERATED (MWH) 469465.00 5809152.00 71642411.00-
- 19. UNIT SERVICE FACTOR 100.00 100.00 60.87 2 20. UNIT AVAILABILITY FACTOR 100.00 100.00 60.87 ,
- 21. UNIT CAP. FACTOR (USING MDC NET) 86.48 96,11 52.11 l
- 22. UNIT CAP. FACTOR (USING DER NET) 79.42 88.27 49.58 I
- 33. UNIT FORCED OUTAGE RATE .00 .00 11.27
- 34. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
i i
- 35. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
'26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY -------- -------- j INITIAL ELECTRICITY -------- --------
COMMERCIAL OPERATION -------- --------
t 1.16 - 9
. . . - - -- - .., . --- - ,_, .- . . . . . ~ _ . . - , - . - -
l
! ENCLOSURE 2 I BRUNSWICK STEAM ELECTRIC PLANT, UNITS NOS.1 AND 2 l DOCKET NOS. 50-325 & 50-324 l LICENSE NOS. DPR-71 & DPR 62 UNIT SHUTDOWN AND POWER REDUCTION REPORT - NOVEMBER 1995 t
l l
l 1
l l
El-3
l ?
L l' -
l l' .
DOCKET NO. 050-0325 '
i UNIT NAME Brunswick I DATE December 1995
,' COMPLETED BY Frances Harrison [
i TELEPHONE 910-457-2766 t UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH November 1995 l 't r
METHOD OF LICENSEE [
DURATION SHUTTING DOWN EVENT SYSTEM CODE COMPONENT CAUSE & CORRECTIVE ACTION TO i j NO. DATE TYPE (1) (HOURS) REASON (2) -REACTOR (3) REPORT NO. (4) CODE (5) PREVENT RECURRENCE j 1 i
!95-048 951110 S 00 B 5 NA RB CONROD Downpower to 60% for red l 1 improvement ard deep shallcw j rod exchance. [
95-049 951121 F 00 A 5 NA H8 VALVEXX Dowrpower to 60% for steam leak repair of .
i 1-MD-LV-2SRDCV-C-1 i 1: Type 2: Reason 3: Method 4: System Coder 5. Comoonent Code !
F - Forced A- Equipment Failure 1- Manual Instructions for Instructions for ,
S - Scheduled (explain) 2- Manual Scram preparation of data entry preparation of data '
j B- Maintenance or test 3- Automatic scram sheets for Licensee Event entry sheets for LER l C- Refueling 4- Continuations Report (LER) file from file from IEEE D- Regulatory 5- Load reductions IEEE Standard 805-1983. Standard 803A-1983. ,
- restriction 6- Other per NUREG-1022. per NUREG-1022. '
j E- Operator Training & Section VI. Item 13.b Section VI. Item 13.c
, License Examination F- Administrative G- Operational error :
(explain) ,
H- Other (explain) i t
1 i
t i
i i
l r
-._ . _ _ -_ m _ _ _ .. - ..-. _ . _ . _ . -... - . _ . _ - - _ -- _ - _ .~ _. . -- - - _ _.-m _ m _ _ ._.._...m.---m.. . .
)
. L t
1 DOCKET NO. 050 03?4 '
UNIT NAME Brunswick Il DATE December 1995 COMPLETED BY frances Harrison TELEPHONE 910-457-27 %
i UNIT SHUTDOWNS AND POWER REDUCTIONS ;
REPORT MONTH November 1995 METHOD OF' LICENSEE DURATION SHUTTING DOWN EVENT SYSTEM CODE COMPONENT CAUSE & CORRECTIVE ACTION TO l
NO. DATE TYPE (1) (HOURS) REASON (2) REACTOR (3) REPORT NO. (4) CODE (5) PREVENT RECURRENCE t
% -052 950827 S In H 5 N/A RC ZZ Core Coastdown. i j
progress ;
t I
1: Tvoe 2: Reason 3: Method 4: System Code: 5. Component Code
- F - Forced A- Equipment Failure 1- Manual Instructions for Instructions for i S - Scheduled (explain) 2- Manual Scram preparation of data entry preparation of data i B- Maintenance or test 3- Automatic scram sheets for Licensee Event entry sheets for LER !
I C- Refueling 4- Continuations Report (LER) file from file from IEEE D- Regulatory 5- Load reductions IEEE Standard 805-1983. Standard 803A-1933. ;
restriction 6- Other per NUREG-1022. per NUPIG-1022.
! E- Operator Training & Section VI. Item 13.b 5xtion VI. Item 13.c :
License Examination j F- Administrative 1 G- Operational error s (explain) [
i H- Other (explain) j 1
I
. i i !
i
- i. t
, I i
j I i I
i i
I
- i I
?
5 I
ENCLOSURE 3 BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 NRC DOCKET NOS. 50-325 & 50-324 OPERATING LICENSE NOS. DPR-71 & DPR-62 LIST OF REGULATORY COMMITMENTS The following table identifies those actions committed to by Carolina Power &
Light Company in this document. Any other actions discussed in the submittal represent intended or planned actions by Carolina Power & Light Company. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the Manager - Regulatory Affairs at the Brunswick Nuclear Plant of any questions regarding this document or any associated regulatory commitments.
Commitment Committed i date or I outage l
- 1. None l
E 2-1