Monthly Operating Repts for May 1996 for Brunswick Steam Electric Plant Units 1 & 2
ML20113A625
Person / Time
Site: Brunswick  Duke energy icon.png
Issue date: 05/31/1996
From: Harrison F, Hicks G
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
BSEP-96-0236, BSEP-96-236, NUDOCS 9606250022
Download: ML20113A625 (10)


Text

_ _ _ _ _ _ . _ _ _ _ _ _ _ _ - - _ - _ _ _ _ _ _ _ _ _ _ _ _ .

5 ,

CP&L Carolina Power & Light Company P.O. Box lo429 Southport, NC 28461-o429 JUN 121996 SERIAL: BSEP 96-0236 FILE: B09-13510C U. S. Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62 MONTHLY OPERATING REPORT Gentlemen:

In accordance with Technical Specification 6.9.1.11 for the Brunswick Steam Electric Plant, Units 1 and 2, Carolina Power & Light Company (CP&L) submits the enclosed report of operating statistics and shutdown experience for the month of May 1996. Also in accordance with Technical Specification 6.9.1.11, this report is being submitted to the NRC by the 15th day of the month following the calendar month covered by the report.

Please refer any questions regarding this submittal to Mr. Mark Turkal at (910) 457-3066.

O -

. [

G. D. Hicks Manager- Regulatory Affairs Brunswick Nuclear Plant WRM/wrm Enclosures e4013't 9606250022 960531 PDR ADOCK 05000324 R PDR [hpg 1

\

a Document Control Desk BSEP 96-0236 / Page 2 l  !

cc: U. S. Nuclear Regulatory Commission ATTN.: Mr. Stewart D. Ebneter, Regional Administrator l 101 Marietta Street, N.W., Suite 2000 l Atlanta, GA 30323-0199 l

L i

Mr. C. A. Patterson l NRC Senior Resident inspector - Brunswick Units 1 and 2:

U.S.' Nuclear Regulatory Commission ATTN.: Mr. David C. Trimble, Jr. (Mail Stop OWFN 14H22)

I 11555 Rockville Pike l Rockville, MD 20852-2738 The Honorable H. Wells Chairman - North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510 I l

1 4

l ENCLOSURE 1

BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2
DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62 l MONTHLY OPERATING REPORT
PLANT PERFORMANCE DATA SYSTEM

'! OPERATING DATA REPORT i

k 4

i f

i l

_.=_ _ _ _ _ . _ . . . - . _ . _ . = _ . - - - . . _ _ _ _ _ . _. . - _ _ _ . _ _ . . . . . _ . . . _ _ _ ._. _ . . _

.CP&L'CO . PLAN"I' PERFORMANCE DATA SYSTEM PAGE 1 RUN DATE 06/10/96 APPENDIM B - AVERAGE DAILY POWER LEVEL RPD39-000 RUN' TIME 15:56:48 BRUNSWICK UNIT 1 i

DOCKET NO. 050-0325- .

COMPLETED BY FRANCES HARRISON  !

TELEPHONE (910)457-2756 l l

MAY 1996 l DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET) (MWE-NET) 1 801 17 798  !

l 2 801 18 796 l

l 3 800 19 795 4 798 20 793 5 798 21 793 6 796 22 793 )

l l 7 795 23 792 l' l

l 8 797 24 792 9 796 25 792 l

l 10 795 26 792' i

! 11 592 27 791 l

l 12 723 28 791 13 752 29 789 l 14 799 30 788

! 15 799 31 715 16 799 I i

l l

I 1.16 - 8 d

l I

i .

.CP&L CO. PLANT PERFORMANCE DATA SYSTEM PAGE 1 RUN DATE 06/10/96 OPERATING DATA REPORT RPD36-000 RUN' TIME 15:56:49 BRUNSWICK UNIT 1 DOCKET NO. 050-0325 l COMPLETED BY FRANCES HARRISON i

l OPERATING STATUS TELEPHONE (910)457-2756 t 1. UNIT NAME: BRUNSWICK UNIT 1 NOTES

! 2. REPORTING PERIOD: MAY 96

3. LICENSED THERMAL POWER (MWT) : 2436
4. NAMEPLATE RATING (GROSS MWE) : 867.0
5. DESIGN ELECTRICAL RATING (NET MWE) : 821.0
6. MAX DEPENDABLE CAPACITY (GROSS MWE)
791.0
7. MAX DEPENDABLE CAPACITY (NET MWE) : 767.0 -------------------------------
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:
9. POWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE) :
10. REASONS FOR RESTRICTION IF ANY:

THIS YR TO CUMUL MONTH DATE ATIVE

11. HOURS IN REPORTING PERIOD 744.00 3647.00 168359.00
12. NUMBER OF HOURS REACTOR CRITICAL 744.00 3481.46 106874.20
13. REACTOR RESERVE SHUTDOWN HRS .00 .00 1647.10
14. HOURS GENERATOR ON LINE 744.00 3445.31 102796.48
15. UNIT RESERVE SHUTDOWN HOURS .00 .00 . .00
16. GROSS THERMAL ENERGY GEN. (MWH) 1782549.82 8164164.36 227522735.19
17. GROSS ELEC. ENERGY GEN. (MWH) 597880.00 2735270.00 74842050.00
18. NET ELEC. ENERGY GENERATED (MWH) 581995.00 2664500.00 72041218.00
19. UNIT SERVICE FACTOR 100.00 94.47 61.06
20. UNIT AVAILABILITY FACTOR 100.00 94.47 61.06
21. UNIT CAP. FACTOR (USING MDC NET) 101.99 95.25 54.61
22. UNIT CAP. FACTOR (USING DER NET) 95.28 88.99 52.12
23. UNIT FORCED OUTAGE RATE .00 5.53 13.83
24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH) :

REFUELING, STARTS 10/5/96, 35 DAYS

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION) : FORECAST ACHIEVED INITIAL CRITICALITY -------- -------_

INITIAL ELECTRICITY -------- --------

COMMERCIAL OPERATION -~------ --------

1.16 - 9 l

l

i

. l

.CP&L CO. PLANT PERFORMANCE DATA SYSTEM -

PAGE 2 RUN DATE 06/10/96 APPENDIX B - AVERAGE DAILY POWER LEVEL RPD39-000 RUN' TIME 15:56:48 BRUNSWICK UNIT 2 DOCKET NO. 050-0324 COMPLETED BY FRANCES HARRISON TELEPHONE (910)457-2756 MAY 1996 DAY AVG. DAILY POWER LEVEL DAY AVG. DAILY POWER LEVEL (MWE-NET) (MWE-NET) 1 785 17 785 2' 785 18 784 3 785 19 782 4 785 20 782 5 782 21 -

781

-6 783 22 781 7 784 23 781 8 784 24 780

-9 784 25 779 10 783 26 780 11 782 27 780 j 12 781 28 780 13 785 29 779 14 778 30 781 15 786 31 784 l 16 785 e

1.16 - 8

CP&L'CO. PLANT PERFORMANCE DATA SYSTEM PAGE 2 RUN DATE 06/10/96 OPERATING DATA REPORT RPD36-000 RUN' TIME 15:56:49 BRUNSWICK UNIT 2 DOCKET NO. 050-0324 i COMPLETED BY FRANCES HARRISON I OPERATING STATUS TELEPHONE (910)457-2756

1. UNIT NAME: BRUNSWICK U'.4IT 2 NOTES
2. REPORTING PERIOD: MAY 96

( 3. LICENSED THERMAL POWER (MWT) : 2436 l 4. NAMEPLATE RATING (GROSS MWE) : 867.0

( 5. DESIGN ELECTRICAL RAT"NG (NET MWE) : 821.0

! 6. MAX DEPENDABLE CAPACI1Y (GROSS MWE): 782.0

7. MAX DEPENDABLE CAPACITY (NET MWE) : 754.0 ------------------------------- l
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THRU 7) SINCE LAST REPORT, GIVE REASONS:

l

9. FOWER LEVEL TO WHICH RESTRICTED IF ANY (NET MWE) : .

t

10. REASONS FOR RESTRICTION IF ANY 1

THIS YR TO CUMUL MONTH DATE ATIVE

11. HOURS IN REPORTING PERIOD 744.00 3647.00 180383.00
12. NUMBER OF HOURS REACTOR CRITICAL 744.00 2649.92 115965.62
13. REACTOR RESERVE SHUTDOWN HRS .00 .00 .00

, 14. HOURS GENERATOR ON LINE 744.00 2537.53 110415.24

15. UNIT RESERVE SHUTDOWN HOURS .00 . .00 .00 i
16. GROSS THERMAL ENERGY GEN. (MWH) 1810396.22 5233825.90 237418831.27 l
17. GROSS ELEC. ENERGY GEN. (MWH) 599405.00 1714975.00 76783696.00
18. NET ELEC. ENERGY GENERATED (MWH) 582191.00 1649275.00 73698492.00
19. UNIT SERVICE FACTOR 100.00 69.58 61.21
20. UNIT AVAILABILITY FACTOR 100.00 69.58 61.21
21. UNIT CAP. FACTOR (USING MDC NET) 103.78 59.98 52.35
22. UNIT CAP. FACTOR (USING DER NET) 95.31 55.08 49.76
23. UNIT FORCED OUTAGE RATE .00 6.21 11.10
24. SHUTDOWNS SCHED. OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH) :
25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START UP:
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY -------- --------

INITIAL ELECTRICITY -------- --------

COMMERCIAL OPERATION -------- --------

l 1.16 - 9 l

-a-e 4 4 9

ENCLOSURE 2 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR-71 AND DPR-62 MONTHLY OPERATING REPORT UNIT SHUTDOWN AND POWER REDUCTION REPORT - MAY 1996 l

l l

~

DOCKET NO, 050-0325 UNIT NAME Brunswick I DATE June 1996 COMPLETED BY Frances Harrison TELEPHONE 910-457-2756 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH May 1996 METHOD OF LICENSEE DURATION SHUTTING EVENT SYSTEM ' COMPONENT CAUSE & CORRECTIVE ACTION TO NO. DATE TYPE (1) (HOURS) PIASON (2) DOWN REACTOR REPORT NO. CODE (4) CODE (5) PREVENT RECURRENCE (3)96-015 960511 F .00 A 5 NA HJ VALVEX Downpower for steam leak repair on 140-V18,96-016 960512 5 .00 8 5 NA RC CONROD Rod Inprovement/ Valve i Testing 96-017 960530 F .00 A 5 NA HJ VALVEX Downpower to support steam leak repair of 140-V18.

1: Ing 2: Reason 3: Method 4: System code: 5. Canoonant code F - Forced A- Equipment Failure 1- Manual Instructions for Instructions for 5 - Scheduled (explain) 2- Manual Scram preparation of data entry preparation of data B- Maintenance or test 3- Aut matic scram sheets for Licensee Event entry sheets for LER C- Refueling 4- Continuations Report (LER) file from file frm IEEE D- Regulatory 5- Load reductions IEEE Standard 805-1983. Standard 803A-1983 restriction 6- Other per NUREG-1022, per NUREG-1022.

E- Operator Training & Section VI. Item 13.b Section VI. Item 13.c License Examination F- Adninistrative.

G- Operational error (explain)

H- Other (explain)

l i

ENCLOSURE 3 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2 i

NRC DOCKET NOS. 50-325 AND 50-324 OPERATING LICENSE NOS. DPR-71 AND DPR-62

, MONTHLY OPERATING REPORT 4

s LIST OF REGULATORY COMMITMENTS l The following table identifies those actions committed to by Carolina Power & Light Company in this document. Any other actions discussed in the submittal represent intended or planned i actions by Carolina Power & Light Company. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the Manager-Regulatory Affairs

at the Brunswick Nuclear Plant of any questions regarding this document or any associated regulatory commitments.

i 3 Committed l Commitment date or

,3 outage'

! 1. None 1

i 4

i I

)

i E

i 4

__ ,