BSEP-97-0373, Monthly Operating Repts for Jul 1997 for Brunswick Steam Electric Plant,Units 1 & 2

From kanterella
Jump to navigation Jump to search
Monthly Operating Repts for Jul 1997 for Brunswick Steam Electric Plant,Units 1 & 2
ML20210J694
Person / Time
Site: Brunswick  Duke energy icon.png
Issue date: 07/31/1997
From: Harrison F, Jury K
CAROLINA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
BSEP-97-0373, BSEP-97-373, NUDOCS 9708180266
Download: ML20210J694 (8)


Text

. .

4

  • CP&L Casolina Power & Light Company P.O. Box 1o429 Southport, NC 28401 o429 AUG 131997 SERIAL: BSEP 97 0373 FILE: B0913510C 1

U. S. Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2 DOCKET NOS. 50-325 AND 50-324 LICENSE NOS. DPR 71 AND DPR 62 MONTHLY OPERATING REPORT Gentlemen:

In accordance with Technical Specification (TS) 6.9.1.11 for the Brunswick Steam Electric Plant (BSEP), Unit Nos.1 and 2, Carolina Power & Light Company is submitting the enclosed report of operating statistics and shutdown experience for the month of July 1997. This report is being submitted to the NRC by the 15th day of the month following the calendar month covered by the report as specified in TS 6.9.1.11. No regulatory commitments are contained in '

this letter.

Please refer any questions regarding this submittal to Mr. Warren Dorman, Supervisor -

Licensing, at (910) 457 2068, Sincerely, hw Keith R, Jury Manager- Regulatory Affairs Brunswick Steam Electric Plant WRM/wrm Enclosures

1. BSEP Unit No.1 Monthly Operating Report /[ )
2. BSEP Unit No. 2 Monthly Operating Report

) BOON' %ff 9708190266 970731 M PDR ADOCK-05000324 R PDR ,

4 .

'Docum:nt Control Desk BSEP 97 0373 / Page 2 pc (with enclosures):

U. S. Nuclear Regulatory Commission, Region 11 ATTN.: Mr. Luis A. Reyes, Regional Administrator Atlanta Federal Center i 61 Forsyth Street, SW, Suite 23T85 l Atlanta, GA 30303 l U. S. Nuclear Regulatory Commission ATTN: Mr. C. A. Patterson, NRC Senior Resident inspector 8470 River Road Southport, NC 28461

. =

U. S. Nuclear Regulatory Commission ATTN.: Mr. David C. Trimble, Jr. (Mall Stop OWFN 14H22) i 11555 Rockville Pike- 1 Rockville, MD 20852 2738

- The Honorable J. A. Sanford

- Chairman North Carolina Utilities Commission I P.O. Box 29510  !

Raleigh, NC 27626-0510 1

f'; 2 W'Jiffisi W C

k; l9 l ENCLOSURE 1 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2 DOCKET MOS. 50-325 AND 50-324 LICENSE NOS. OPR 71 AND DPR-62 MONTHLY OPERATING REPORT o

I L BRUNSWICK STEAM ELECTRIC PLANT, UNIT 1 MONTHLY OPERATING REPORT JULY 1997

APPENDlX A l

OPERATING DATA REPORT i

i DOCKET NO. 50-325 UNIT NAME Brunswick Steam Electric Plant, Unit No.1 l

DATE August 4,1997 COMPLETED BY Frances Harrison TELEPHONE (910)457 2756 REPORTING PERIOD July 1.1997 to July 31,1997 (Month / Year)

YEAR TO MONTH DATE CUMULATIVE

1. Design Electrical Rating: 821.0 N/A N/A (MWe Net)
2. Maximum Dependable Capacity: 767.0 N/A N/A (MWe Net).
3. Number of Hours the Reacter Was 744.00 5,087.00 116,086.76 Critical:

744.00 5,087.00 111,929.37

4. Number of Hours the Generator Was On Line:
5. Unit Reserve Shutdown Hours: 0.00 0.00 0.00
6. Nat Electrical Energy (MWH):

600,464.00 4,053,056.00 79,137,926.00

APPENDIX B UNIT SHUTDOWNS DOCKET NO. 50-325 UNIT NAME Brunswick Steam Electnc Plant. Unit No.1 DATE- July 1997 COMPLETED BY Frances Harrison TELEPHONE (910) 457-2756 REPORTING PERIOD July 1.1997 to July 31,1997 '

(MonthlYear)

NO. DATE' . TYPE DURATION REASON (1) METHOD OF CAUSE/ CORRECTIVE ACTIONS F:. FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A 7/97 No unit shutdowns for July 1997.

SUMMARY

(1) Reason (2) Method A - Equement Failure (Explain) 1 - Manual B - Maintenance or Test 2 - ManualTrg/ Scram C - Refue!mg 3- Automate Trescram D - Regulatory Restnction 4-Cwan s .

E - Operator Traorgt.icense Exammaton 5- Other (Explae)

F- Admastratrve G - Operatonal Error (Exp!ain)

H - Other (Expiari) .

ENCLO3URE 2 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS.1 AND 2 DOCKET NOS. 50-325 AND 50 324 LICENSE NOS, DPR-71 AND DPR 62 MONTHLY OPERATING REPORT i l

l BRUNSWICK STEAM ELECTRIC PLANT, UNIT 2 MONTHLY OPERATING REPORT JULY 1997

APPENDIX A OPERATING DATA REPORT DOCKET NO. 50 324 UNIT NAME Brunswick Steam Electric Plant, Unit No. 2 DATE August 4,1997 l

COMPLETED BY Frances Harrison TELEPHONE (910)457 2756 l REPORTING PERIOD July 1,1997 to July 31,1997 ,

l (Month / Year) i j- YEAR  ;

l l

TO MONTH DATE CUMULATIVE

1. Design Electrical Rating: 821.0 N/A N/A (MWe Net)
2. Maximum Dependable Capacity: 754.0 N/A N/A (MWe-Net).
3. Number of Hours the Reactor Was 744.00 5,087.00 125,878.55 Critical:
4. Number of Hours the Generator Was 744.00 5,087.00 120,244.02 On Line:
5. Unit Reserve Shutdown Hours: 0.00 0.00 0.00
6. Net Electrical Energy (MWH): 564,789.00 3,008,987.00 81,146,322.00

APPENDIX B -

UNIT SHUTDOWNS .

DOCKET NO. 50-324 UNIT NAME Brunswick Steam Electnc Plant. Unit No. 2 DATE July 1997 COMPLETED BY Frances Hamson TELEPHONE (910)457-2756 REPORTING PERIOD July 1.1997 to July 31.1997 (MonthIYear)

NO. DATE TYPE DURATION REASON (1) METHOD OF CAUSE/CORRECTre ACTIONS F: FORCED (HOURS) SHUTTING S: SCHEDULED DOWN (2) COMMENTS N/A 7/97 No unit shutdowns for July 1997.

SUMMARY

(1) Reason (2) Method A - Equtoment Failure (Explam) 1 - Manual B - Mantenance or Test 2-ManualTriprScram C - Refuelmg 3 - Automate TnprScram D- Regulatory Restnction 4-Cwe. a n E - Operator Trasung/Lecense Exammation 5- Other (CA)

F- Adr unistrative G-Om.'uw : Error (Explain)

H - Other (Explairi)

._= - __ _ __

.