09-18-2017 | On July 17, 2017, at 1606 CDT, Waterford 3 experienced an automatic reactor scram due to a loss of forced circulation, which was the result of a loss of off-site power to the safety and non-safety electrical busses. Prior to the scram, plant operators manually tripped the main turbine and generator due to overheating of the isophase bus duct due to the failure of a shunt assembly connection in the duct to Main Transformer 'B'. The automatic electrical bus transfer did not occur due to relay failures in the fast dead bus transfer system. Both 'A' and 'B' Emergency Diesel Generators started and loaded as designed to re-energize the 'A' and 'B' safety busses. The loss of off-site power caused a loss of both Main Feedwater pumps, resulting in an automatic actuation of the Emergency Feedwater system.
The Root Cause of this event was the design change procedure used for modifications to the fast dead bus transfer circuitry did not include guidance to detect the susceptibility of the relays to DC coil inductive kick. The faulty relays in the fast bus transfer circuit were replaced prior to plant startup.
An Unusual Event was declared at 1617 CDT due to loss of off-site power to safety buses for >15 minutes.
All required safety-related equipment responded as expected during this event. |
---|
LER-2017-002, Automatic Reactor Scram due to the Failure of Fast Bus Transfer Relays to Automatically Transfer Station Loads to Off- Site Power on a Main Generator TripWaterford Steam Electric Station, Unit 3 |
Event date: |
07-17-2017 |
---|
Report date: |
09-18-2017 |
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
10 CFR 50.73(a)(2)(iv)(A), System Actuation
10 CFR 50.73(a)(2)(vii), Common Cause Inoperability
10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor |
---|
Initial Reporting |
---|
ENS 52863 |
10 CFR 50.72(b)(3)(v)(A), Loss of Safety Function - Shutdown the Reactor, 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(a)(1)(i), Emergency Class Declaration, 10 CFR 50.72(b)(3)(iv)(A), System Actuation |
---|
3822017002R00 - NRC Website |
|
|
---|
Category:Letter
MONTHYEARIR 05000382/20244022024-10-10010 October 2024 Security Baseline Inspection Report 05000382/2024402 Public IR 05000382/20244032024-10-0909 October 2024 Security Baseline Inspection Report 05000382/2024403 IR 05000382/20240112024-10-0101 October 2024 State Fire Protection Team Inspection Report 05000382/2024011 IR 05000382/20230042024-09-25025 September 2024 Integrated Inspection Report 05000382/2023004, Disputed Non-Cited Violation Revised ML24268A1132024-09-24024 September 2024 Acknowledgment of Response to NRC Inspection Report 05000382/2024013, and Notice of Violation ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000382/20240052024-08-21021 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Waterford Steam Electric Station, Unit 3 Report 05000382/2024005 ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000382/20240132024-08-20020 August 2024 Notice of Violation; NRC Inspection Report 05000382/2024013 05000382/LER-2024-004, Automatic Reactor Trip Due to Lightning Strike2024-08-15015 August 2024 Automatic Reactor Trip Due to Lightning Strike IR 05000382/20240022024-08-0808 August 2024 Integrated Inspection Report 05000382/2024002 ML24164A2512024-08-0707 August 2024 Issuance of Amendment No. 271 Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program ML24213A1632024-08-0101 August 2024 2024 Waterford Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification 05000382/LER-2024-003, Automatic EFAS Actuation During Surveillance Test2024-07-10010 July 2024 Automatic EFAS Actuation During Surveillance Test ML24150A3852024-06-0404 June 2024 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000382/2024011) and Request for Information ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 ML24141A1012024-05-20020 May 2024 Amended Integrated Inspection Report 05000382/2023004 05000382/LER-2024-002, Automatic Reactor Trip Due to Transformer Failure2024-05-16016 May 2024 Automatic Reactor Trip Due to Transformer Failure 05000382/LER-2024-001, Manual Reactor Trip Due to Engineered Safety Features Actuation System Relay Failure2024-05-15015 May 2024 Manual Reactor Trip Due to Engineered Safety Features Actuation System Relay Failure ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions IR 05000382/20240012024-05-0606 May 2024 Integrated Inspection Report 05000382/2024001 ML24067A1032024-04-25025 April 2024 Closeout of Generic Letter 2004 02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams IR 05000382/20244012024-03-18018 March 2024 Material Control and Accounting Program Inspection Report 05000382/2024401 ML24074A3742024-03-15015 March 2024 Acknowledgement of Response to NRC Inspection Report 05000382/2023004 and Disputed Non-Cited Violation ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24032A0032024-03-0606 March 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0053 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000382/20230062024-02-28028 February 2024 Annual Assessment Letter for Waterford Steam Electric Station, Unit 3 Report 05000382/2023006 05000382/LER-2023-004, Non-Compliance with Technical Specifications Due to Performing Startup Channel 1 Functional Testing During Fuel Movement2024-02-14014 February 2024 Non-Compliance with Technical Specifications Due to Performing Startup Channel 1 Functional Testing During Fuel Movement ML24039A1992024-02-12012 February 2024 – Integrated Inspection Report 05000382/2023004 IR 05000382/20230102024-01-31031 January 2024 Comprehensive Engineering Team Inspection Report 05000382/2023010 ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 – Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and 05000382/LER-2023-003, Steam Generator Tube Degradation Indicated by Failed In-Situ Pressure Testing2023-12-30030 December 2023 Steam Generator Tube Degradation Indicated by Failed In-Situ Pressure Testing ML23340A2292023-12-28028 December 2023 Withdrawal of an Amendment Request to Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability (EPID L-2022-LLA-0169)-LTR ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1442023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000382/20230032023-11-14014 November 2023 Integrated Inspection Report 05000382/2023003 and Notice of Violation ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000382/20234012023-10-0404 October 2023 Cyber Security Inspection Report 05000382/2023401 (Cover Letter Only) IR 05000382/20230052023-08-21021 August 2023 Updated Inspection Plan for Waterford Steam Electric Station, Unit 3 - (Report 05000382/2023005) IR 05000382/20233012023-08-15015 August 2023 NRC Initial Operator Licensing Examination Approval 05000382/2023301 IR 05000382/20230022023-08-0808 August 2023 Integrated Inspection Report 05000382/2023002 2024-09-06
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000382/LER-2024-004, Automatic Reactor Trip Due to Lightning Strike2024-08-15015 August 2024 Automatic Reactor Trip Due to Lightning Strike 05000382/LER-2024-003, Automatic EFAS Actuation During Surveillance Test2024-07-10010 July 2024 Automatic EFAS Actuation During Surveillance Test 05000382/LER-2024-002, Automatic Reactor Trip Due to Transformer Failure2024-05-16016 May 2024 Automatic Reactor Trip Due to Transformer Failure 05000382/LER-2024-001, Manual Reactor Trip Due to Engineered Safety Features Actuation System Relay Failure2024-05-15015 May 2024 Manual Reactor Trip Due to Engineered Safety Features Actuation System Relay Failure 05000382/LER-2023-004, Non-Compliance with Technical Specifications Due to Performing Startup Channel 1 Functional Testing During Fuel Movement2024-02-14014 February 2024 Non-Compliance with Technical Specifications Due to Performing Startup Channel 1 Functional Testing During Fuel Movement 05000382/LER-2023-003, Steam Generator Tube Degradation Indicated by Failed In-Situ Pressure Testing2023-12-30030 December 2023 Steam Generator Tube Degradation Indicated by Failed In-Situ Pressure Testing 05000382/LER-2023-002, Plant Shutdown Required by Technical Specifications for Unidentified Reactor Coolant System Leakage in Containment2023-05-0909 May 2023 Plant Shutdown Required by Technical Specifications for Unidentified Reactor Coolant System Leakage in Containment 05000382/LER-2023-001, Non-Compliance with Technical Specifications Due to pico-ammeter Circuit Board Fluctuations in Containment High Range Radiation Monitor B2023-05-0101 May 2023 Non-Compliance with Technical Specifications Due to pico-ammeter Circuit Board Fluctuations in Containment High Range Radiation Monitor B 05000382/LER-2022-001-02, Non-Compliance with Technical Specifications Due to Incorrect Procedural Guidance for Radiation Monitors2023-02-22022 February 2023 Non-Compliance with Technical Specifications Due to Incorrect Procedural Guidance for Radiation Monitors 05000382/LER-2022-001-01, On Non-Compliance with Technical Specifications Due to Incorrect Procedural Guidance for Radiation Monitors2023-01-0303 January 2023 On Non-Compliance with Technical Specifications Due to Incorrect Procedural Guidance for Radiation Monitors 05000382/LER-2022-006, Non-Compliance with Technical Specifications Due to Incorrect Conversion Factors in Plant Stack and Fuel Handling Building Radiation Monitors2022-11-0707 November 2022 Non-Compliance with Technical Specifications Due to Incorrect Conversion Factors in Plant Stack and Fuel Handling Building Radiation Monitors 05000382/LER-2022-005, Engineered Safety Features Actuation System Relay Failure Results in Reactor Trip and Emergency Feedwater Actuation2022-08-23023 August 2022 Engineered Safety Features Actuation System Relay Failure Results in Reactor Trip and Emergency Feedwater Actuation 05000382/LER-2022-004, Regarding Operation Prohibited by Technical Specifications Due to Inadequate Radiation Monitor Calibration Procedures2022-06-23023 June 2022 Regarding Operation Prohibited by Technical Specifications Due to Inadequate Radiation Monitor Calibration Procedures 05000382/LER-2022-003, Operation Prohibited by Technical Specifications Due to Radiation Monitor Calibration Error2022-06-13013 June 2022 Operation Prohibited by Technical Specifications Due to Radiation Monitor Calibration Error 05000382/LER-2022-002, Operation Prohibited by Technical Specifications Due to Personnel Error2022-05-13013 May 2022 Operation Prohibited by Technical Specifications Due to Personnel Error 05000382/LER-2022-001, Non-Compliance with Technical Specifications Due to Incorrect Conversion Factors in Three Gaseous Radiation Monitors2022-03-18018 March 2022 Non-Compliance with Technical Specifications Due to Incorrect Conversion Factors in Three Gaseous Radiation Monitors 05000382/LER-2021-003, Non-Compliance with Technical Specifications Due to Failed Ambient Pressure Input2021-12-16016 December 2021 Non-Compliance with Technical Specifications Due to Failed Ambient Pressure Input 05000382/LER-2021-002, Loss of Offsite Power Due to Hurricane Ida2021-11-22022 November 2021 Loss of Offsite Power Due to Hurricane Ida 05000382/LER-2021-001, Re Loss of Offsite Power Due to Hurricane Ida2021-10-28028 October 2021 Re Loss of Offsite Power Due to Hurricane Ida 05000382/LER-2017-0022017-09-18018 September 2017 Automatic Reactor Scram due to the Failure of Fast Bus Transfer Relays to Automatically Transfer Station Loads to Off- Site Power on a Main Generator Trip, LER 17-002-00 for Waterford, Unit 3, Regarding Automatic Reactor Scram due to the Failure of Fast Bus Transfer Relays to Automatically Transfer Station Loads to Off-Site Power on a Main Generator Trip 05000382/LER-2017-0012017-05-0404 May 2017 1 of 5, LER 17-001-00 for Waterford, Unit 3 Regarding Both Trains of Emergency Core Cooling System Inoperable due to Inadvertently Performing Maintenance on Train 'B' Resulting in Event or Condition that Could Have Prevented Fulfillment of a Safety Function 05000382/LER-2016-0022016-11-30030 November 2016 Both Trains of Essential Services Chilled Water Inoperable due to Failing to Maintain Exiting Chilled Water Temperature in Specification Resulting in Event or Condition that Could Have Prevented Fulfillment of a Safety Function, LER 16-002-01 for Waterford, Unit 3, Regarding Both Trains of Essential Services Chilled Water Inoperable Due to Failing to Maintain Exiting Chilled Water Temperature in Specification Resulting in Event or Condition That Could Have Prevented... 05000382/LER-2016-0012016-09-0101 September 2016 Incorrect Core Protection Calculator Addressable Constant Entered Because of Inadequate Procedure Resulting in a Condition Prohibited by Technical Specifications, LER 16-001-00 for Waterford, Unit 3, Regarding Incorrect Core Protection Calculator Addressable Constant Entered Because of Inadequate Procedure Resulting in a Condition Prohibited by Technical Specifications W3F1-2013-0007, Special Report SR 13-001-00 Fuel Handling Building Wide Range Gas Radiation Monitor PRMIR3032 Inoperable for Greater than 7 Days2013-01-24024 January 2013 Special Report SR 13-001-00 Fuel Handling Building Wide Range Gas Radiation Monitor PRMIR3032 Inoperable for Greater than 7 Days W3F1-2012-0075, Submittal of Special Report SR-12-001-00, Primary Met. Tower Upper Level Wind Speed Instrument Inoperable for Greater than 7 Days2012-09-17017 September 2012 Submittal of Special Report SR-12-001-00, Primary Met. Tower Upper Level Wind Speed Instrument Inoperable for Greater than 7 Days ML0611801332005-08-27027 August 2005 Event Number 41954 ML0611801321992-08-24024 August 1992 Event Number 24112 2024-08-15
[Table view] |
EVENT DESCRIPTION
A. Plant Status C. Event Causes B. Event Chronology At the time of this event Waterford 3 was operating at 100% reactor power. The site was experiencing a severe thunderstorm. No structures, systems or components were out of service that contributed to this event.
On July 17, 2017, at approximately 1555 CDT, Waterford 3 control room operators received indications of an electrical grid spike. The control room received several control panel alarms related to the Waterford 3 switching station [FK] and operators were dispatched to investigate the electrical components in the transformer yard [EL]. During this investigation field operators reported that the Isophase Bus duct to Main Transformer ‘B' [MT] was glowing orange and arcing and sparks were observed.
At 1606 CDT, control room operators manually tripped the main turbine [TA] to de-energize Main Transformer ‘B'. When the main turbine was tripped the main generator [TB] automatically tripped and Reactor Power Cutback [JD] initiated as designed. The transfer of electrical busses did not occur as expected and the site experienced a loss of off-site power to the safety and non-safety electrical busses [SWGR]. This loss of off-site power resulted in a loss of all four Reactor Coolant Pumps (RCP) [P] which then resulted in an automatic reactor scram [JC] on loss of forced circulation. Both emergency diesel generators (EDG) [DG] started and loaded to provide power to both safety busses. The automatic actuation of the reactor protection system [JC], reactor scram, and the automatic start of both EDG's, are reportable conditions pursuant to 10 CFR 50.73(a)(2)(iv)(A).
At 1617 CDT the Shift Manager declared an Unusual Event for a loss of off-site power for >15 minutes (EN 52863).
Due to the loss of power both Main Feedwater Pumps [SK] tripped resulting in levels in both Steam Generators [SG] lowering to the initiation setpoint of Emergency Feedwater (EFW) [BA] at the time of the automatic scram. At 1630 CDT, when reactor coolant system cold leg temperature lowered to 530 degrees Fahrenheit, plant operators took manual control of EFW to control Steam Generator levels as required in site Emergency Operating procedures. The automatic actuation of the EFW system is a reportable condition pursuant to 10 CFR 50.73(a)(2)(iv)(A).
At 1831 CDT off-site power was restored to the ‘A' train non-safety electrical busses.
At 1844 CDT off-site power was restored the ‘A' train safety electrical bus.
At 1854 CDT EDG ‘A' was secured and returned to standby, operating for two (2) hours and 47 minutes.
At 1944 CDT off-site power was restored to the ‘B' train non-safety electrical busses.
At 2001 CDT off-site power was restored to the ‘B' train safety electrical bus.
At 2015 CDT EDG ‘B' was secured and returned to standby, operating for four (4) hours and eight (8) minutes.
At 2056 CDT the Shift Manager exited the Emergency Plan and secured from the Unusual Event.
At 0116 CDT on July 18, 2017, control room operators started the Auxiliary Feedwater Pump and commenced feeding both SG's from the condensate system.
At 0128 CDT on July 18, 2017, the emergency feedwater actuation signal was reset. EFW pumps ‘A', ‘B', and ‘AB' were secured, operating for nine (9) hours and 21 minutes.
The direct cause of the Isophase Bus Duct overheating is the failure of a shunt assembly connection to the Phase B bus duct.
The most likely apparent causes are: (1) a grid transient recorded on July 17, 2017, produced a dynamic response between the isophase bus and the bus duct that resulted in the separation of the shunt assembly connection, and; (2) Isophase Bus Duct Overheating:
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
The inadequate design of the fast bus transfer relays resulted in a common cause inoperability of both trains of off-site power. This condition is reportable pursuant to 10 CFR 50.73(a)(2)(vii).
CORRECTIVE ACTIONS
A. Isophase Bus Overheating:
B. Failure of Fast Dead Bus Transfer:
The direct cause of the failure of the fast dead bus transfer was the Struthers Dunn (S-D) 237 Series Direct Current (DC) Time Delay on Dropout (TDDO) relays [62] installed in the fast dead bus transfer circuitry instantaneously timed out when they were exposed to DC coil inductive kick, which prevented automatic transfer of the safety and non-safety electrical busses from the Unit Auxiliary Transformers [XFMR] to the Startup Transformers [XFMR].
The Root Cause of this event was design change procedures in effect during the development of the 1997 and 2017 modifications to the fast dead bus transfer circuitry did not include guidance that electronic devices have a greater susceptibility to DC coil inductive kick than electro-mechanical devices and did not require identification of critical characteristics for non-quality related plant changes.
The Contributing Cause of this event was the post-modification testing performed following change of the relays from Allen Bradley to Struthers Dunn did not exercise the fast dead bus transfer timing circuitry. This contributed to this condition by delaying detection of relay failure.
degraded connections between the laminated shunt assemblies and the bus duct resulted in formation of gaps between the contact surfaces. Electrical arcing across these gaps over time eroded the contact surfaces which increased resistance and weakened the connection.
Completed corrective actions include:
a. The Main Transformer ‘B', Phase ‘B' isolated phase bus duct was repaired by cutting out the damaged duct sections and welding in new aluminum material. All laminated shunt assemblies were replaced using new bolting hardware.
b. The Main Transformer ‘B' Phase ‘A' and ‘C' laminated shunt assemblies were removed, cleaned and re-installed with new bolting hardware.
c. Performed a complete inspection and torque check for all laminated shunt assemblies to identify any other degraded bolted connections and adjusted torque as needed.
Corrective actions planned include:
a. Revise preventive maintenance strategy for isophase bus based on EPRI and industry recommendations to include shunt assembly torque checks, regular bus inspections, thermography scans, and corona scans.
b. Revise the site procedure for inspection of the isophase busses and ducting based on engineering input.
Completed corrective actions include:
a. The installation of a suppression diode in parallel with fast bus transfer relay. (Corrective Action to Prevent Recurrence) b. The Struthers-Dunn relays were removed from service and replaced with Allen Bradley relays.
c. Entergy Nuclear Fleet has adopted the Standard Design Process in accordance with IP-ENG-0001, Revision 0, Standard Design Process.
d. Fast Dead Bus Transfer engineering change test procedure was developed during troubleshooting and was performed following re-installation of the Allen Bradley relays and the installation of flyback diodes.
Corrective actions planned include:
a. Verify that all Allen-Bradley 700RTC relays installed in the plant are immune to the effects of inductive kick. If any Failure of Fast Dead Bus Transfer:
used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
SAFETY EVALUATION
The inoperability of both trains of off-site electrical distribution is a reportable condition pursuant to 10 CFR 50.73(a)(2)(v)(A) and (D).
The non-compliance with Technical Specifications is a reportable condition pursuant to 10 CFR 50.73(a)(2)(i)(B).
The safety significance determination of this event is still being determined. The safety significance will be included as a planned update to this LER.
PREVIOUS OCCURRENCES
CR-WF3-2015-3566: Failure of ‘B' Fast Dead Bus Transfer during Plant Scram on June 3, 2015. (Reported under Technical Specification (TS) 3.8.1.1 requires two physically independent circuits between the off-site transmission network and the on-site Class 1E distribution system to be operable. The operability of the electrical distribution systems during operation ensures that sufficient power will be available to supply the safety-related equipment required for (1) the safe shutdown of the facility, and (2) the mitigation and control of accident conditions within the facility. The minimum specified independent and redundant A.C. and D.C. power sources and distribution systems satisfy the requirements of General Design Criterion 17 of Appendix A to10 CFR Part 50. The fast dead bus transfer system is required to be functional per the Waterford 3 FSAR to support the operability of off-site power.
The Struthers-Dunn relays were installed in the fast dead bus transfer circuit in May of 2017, and were required to be functional on June 2, 2017, at 1902, when the main generator was paralleled to the grid and loads were transferred to the Unit Auxiliary Transformers at the conclusion of Refueling Outage 21. Both trains of the offsite transmission network have been inoperable from that time until the time of the generator trip on July 17, 2017. Action ‘e' of TS 3.8.1.1 requires restoration of one of the inoperable offsite A.C. circuits to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Because of this, Waterford 3 was not in compliance of TS 3.8.1.1 for 45 days.
Directly following a manual plant scram on June 3, 2015, due to a secondary system malfunction, a loss of off-site power occurred on the ‘B' Train due to the failure of the fast dead bus transfer relays on the ‘B' train. The Apparent Cause of this event was determined to be Unknown Equipment Cause (FEUU). A contributing cause was that the 1997 Plant Change was due to a Design Change That Was Not Adequate (FE18) because a latent design deficiency did not take into account the observed failure mode where a two coil design allowed one coil to fail preventing the fast dead bus transfer function (timed contacts) without actuating the contacts for the alarm circuit.
The corrective actions from this earlier event did not correct the issue and prevent recurrence because the nature of the relay failure was not determined conclusively. Corrective actions were assigned from the apparent cause without a solid understanding of the causal factors for the respective failure.
Allen-Bradley relays are discovered to not be immune to the effects of Inductive kick, generate additional actions to correct the lack of immunity.
b. Review and verify the existing EMC qualifications of currently installed Allen-Bradley 700RTC relays to ensure that they are appropriate for their operating environment. If any Allen Bradley relays are discovered to not be appropriate for their operating environment, generate additional corrective actions to correct the deficiency.
c. Anchor surge suppression/flyback diodes into design basis drawings and the Fast Dead Bus Transfer circuit Control Wiring Diagrams to ensure they are not removed if the Fast Dead Bus Transfer circuit is modified. (Corrective Action to Prevent Recurrence) From this event, all fast dead bus transfer relays were replaced with new Allen -Bradley relays. Preventative Maintenance strategies were revised to replace the relays on a three (3) year frequency.