05000334/LER-1982-038, Forwards LER 82-038/03L-0 & Updated LER 82-036/03X-1

From kanterella
Jump to navigation Jump to search
Forwards LER 82-038/03L-0 & Updated LER 82-036/03X-1
ML20071P309
Person / Time
Site: Beaver Valley
Issue date: 10/21/1982
From: Lacey W
DUQUESNE LIGHT CO.
To: Haynes R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20071P312 List:
References
ND1SS1:643, NUDOCS 8211020472
Download: ML20071P309 (2)


LER-2082-038, Forwards LER 82-038/03L-0 & Updated LER 82-036/03X-1
Event date:
Report date:
3342082038R00 - NRC Website

text

_

.. w N

7A@

Telephone (412) 4564000 Nuclear Division P.O. Box 4 Shippingport, PA 15077 0)04 October 21, 1982 NDISS1:643 Beaver Valley Power Station, Unit No. 1 Docket No. 50-334, License No. DPR-66 LER 82-036/03X-1, 82-038/03L Mr. R. C. Haynes, Regional Administrator United States Nuclear Regulatory Commission Region 1 631 Park Avenue King of Prussia, Pennsylvania 19406

Dear Mr. Haynes:

In accordance with Appendix A Beaver Valley Technical Specifications, the following Licensee Event Report are submitted:

LER 82-038/03L, Technical Specification 3.7.1.2, Auxiliary Feedwater System.

LER 82-036/03X-1, Technical Specification 3.8.1.1, Electrical Power Systems /A.C. Sources. This update is being submitted to correct the Event Date previously reported as 6/19/82. The actual Event Date was 9/19/82.

Ve truly yours,

,. 1 g/! [l[E W. . Lacey Acting Superin dent Attachment 8211020472 821021 DR ADOCK 05000 J

. . .. . . _ - - . ~ . . . . - _ - . . . - -_ .

. 4 e

b Mr. R. C. Haynes October 21, 1982 NDISS1:643

. Page 2 cc: Director Of Management & Program Analysis United States Nuclear Regulatory Commission Washington, D. C. 20555 J. Hultz, Ohio Edison Director, Office of Inspection and Enforcement Headquarters United States Nuclear Regulatory Commission Washington, D. C. 20555 Mr. Peter Tam, BVPS Licensing Project Manager

, United States Nuclear Regulatory Commission Washington, D. C. 20555 W. M. Troskoski, Nuclear Regulatory Commission, BVPS Site Inspector

{ Mr. Alex Timme, CAPCO Nuclear Projects Coordinator, Toledo Edison J

INPO Records Center Suite 1500 1100 Circle 75 Parkway -

< Atlanta, GA 30339 C. E. Muckle, Factory Mutual Engineering, Pittsburgh Arthur Alford, Stone & Webster / Boston i

f n.. a. - , . -

. - ,_, - - . .,-.,-.._,.-,n- - . - -., ----