ML12187A454

From kanterella
Jump to navigation Jump to search
E-mail Form Timothy Riley on Davis Besse Alert Declared and Exited
ML12187A454
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 11/16/2011
From: Riley T
Office of Congressional Affairs
To: Babcock D, Steyer R
US SEN (Senate), US HR (House of Representatives)
References
FOIA/PA-2012-0217
Download: ML12187A454 (4)


Text

Riley (OCA), Timothy From: Riley (OCA), Timothy Sent: Wednesday, November 16, 2011 7:33 AM To: 'DougBabcock@brown.senate.gov'; 'Ryan.Steyer@mail. house.gov';

'nickbutterfield@portman.senate.gov' Cc: 'Howard.Schulman@mail.house.gov'

Subject:

Davis-Besse alert declared and exited Good morning, At 0222 EST on November 16, 2011, an ALERT was declared at Davis-Besse due to an electrical fire in the Auxiliary building which houses safety-related equipment. The apparent cause of the fire was due to an unknown source of water leaking on a breaker; an electrical arc then started a fire. The electrical fire is out.

The plant was at 0% power at the time of the fire; there were no radilogical releases nor reports of injuries. The fire was extinguished and the alert was later exited at 0443.

I will provide further details as they become available.

Sent from an NRC Blackberry.

l(b) 6) Riley Tim I

-4 '.

.. "' UNITED STATES

" .*dNUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 At***,

lc LISLE, IL60532-4352 December 2, 2011 CAL No. 3-11-001 Mr. Barry Allen Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2, Mail Stop A-DB-3080 Oak Harbor, OH 43449-9760

SUBJECT:

CONFIRMATORY ACTION LETTER - DAVIS-BESSE NUCLEAR POWER STATION

Dear Mr. Allen:

This letter confirms commitments by FirstEnergy Nuclear Operating Company (FENOC) regarding the identification of cracks in the reinforced concrete shield building at the Davis-Besse Nuclear Power Station. During the recent mid-cycle outage to replace the reactor vessel closure head, which began on October 1, 2011, FENOC discovered laminar cracking in the safety-related shield building of the containment system while performing hydrodemolition operations. Based on an evaluation of FENOC's extent of condition and technical analysis of the Davis-Besse shield building laminar cracking, the NRC staff concluded that FENOC provided reasonable assurance that the shield building is capable of performing its safety functions. In order to provide continued long-term confidence, FENOC has agreed in telephone conversations between you, Steven West, and Steven Reynolds, on November 21, 2011; a followup telephone conversation between you and Jamnes Cameron on November 22, 2011; in a FENOC commitment letter dated November 23, 2011 (ML 1329A033); and a telephone conversation between you and Steven Reynolds on December 2, 2011, to the following actions (both completed and planned):

1. FENOC will provide the results of the root cause evaluation and corrective actions to the NRC, including any long-term monitoring requirements, by February 28, 2012.
2. FENOC will identify four shield building locations, which were core bored during this evaluation, for examination. These uncracked locations will be directly adjacent to locations that have been confirmed to be cracked. The four uncracked locations, as designated on FENOC drawing C-1 11A, are:
a. adjacent to a flute shoulder [S9-666.0-12];
b. in a flute area [F4-1-666.0-3];
c. adjacent to Main Steam Line penetration 39 [S7-652.0-6.5]; and
d. adjacent to Main Steam Line penetration 40 [S9-650.0-9].

B. Allen 3. FENOC will examine the four core bore locations from Commitment 2 above with a borescope to verify cracking has not migrated to these core bores located in solid (i.e., uncracked) concrete, within 90 days following plant restart (Mode 2) from the 2011 mid-cycle outage.

4. FENOC will examine the crack interface to identify any changes by performing a core bore in a known crack area within the Main Steam Line Room, within 90 days following plant restart (Mode 2) from the October 2011 mid-cycle outage.
5. FENOC will identify two additional shield building locations, which were core bored during this evaluation, for examination. These uncracked locations will be directly adjacent to locations that have been confirmed to be cracked. The two uncracked locations, as designated on FENOC drawing C-1 11A, are:
a. in a flute area [F5-777.0-4]; and
b. adjacent to a flute shoulder [S2-783.5-4.0].
6. FENOC will examine the four core bore locations from Commitment 2 along with the two core bore locations from Commitment 5 with a borescope to verify cracking has not migrated to these core bores located in solid (i.e., uncracked) concrete, during the seventeenth refueling outage currently scheduled to commence in 2012.
7. FENOC will examine the crack interface to identify any changes by examining either existing core bore locations with known cracks, or by performing a core bore in a similar area:
a. adjacent to a flute shoulder [S9-666.0-11];
b. near the top of the shield building [S9-785-22.5]; and
c. adjacent to Main Steam Line penetration [core bore from Commitment 4].

during the seventeenth refueling outage currently scheduled to commence in 2012.

Pursuant to Section 182 of the Atomic Energy Act, 42 U.S.C. 2232, you are required to:

1) Notify me immediately if your understanding differs from that set forth above;
2) Notify me if for any reason you cannot complete the actions and commitments within the specified schedule and advise me in writing of your modified schedule in advance of the change; and
3) Notify me in writing when you have completed the actions and commitments addressed in this Confirmatory Action Letter.

Issuance of this Confirmatory Action Letter does not preclude issuance of an Order formalizing the above commitments or requiring other actions on the part of FENOC, nor does it

B. Allen preclude the NRC from taking enforcement action for violations of NRC requirements that may have prompted the issuance of this letter. Failure to meet the commitments in this Confirmatory Action Letter may result in an Order if FENOC's performance, as demonstrated by the failure to meet any Confirmatory Action Letter commitments, does not provide reasonable assurance that the NRC can rely on FENOC to meet the NRC's requirements and protect public health and safety or the common defense and security.

You should also be aware that while the NRC staff concluded that FENOC provided reasonable assurance that the shield building remains capable of performing its safety functions, NRC staff continues to evaluate whether the shield building (in its current condition) conforms to the design code requirements identified in the plant's licensing basis.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (ifany), will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS),

accessible from the NRC Web site at http://www.nrc.,ov/readinq-rm/adams.html (the Public Electronic Reading Room).

To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the public without redaction. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a redacted copy of your response that deletes such information. Ifyou request withholding of such material, you must specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g.,

explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request for withholding confidential commercial or financial information). Ifsafeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.

Sincerely, (nthia D.Pederson (A tg Regional Administrator Jracting Docket No. 50-346 License No. NPF-3 cc: Distribution via ListServ Tm