G20070202/LTR-07-0203 - Rep. Dennis Kucinich Ltr FENOC Request to Be Relieved from Independent Oversight at the Davis-Besse Nuclear Facility
ML071020513
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/18/2007
From: Reyes L
NRC/EDO
To: Kucinich D
US HR, Comm on Oversight and Government Reform, US HR, Subcomm on Domestic Policy
References
G20070202, LTR-07-0203
Download: ML071020513 (2)


Text

April 18, 2007 The Honorable Dennis J. Kucinich Chairman, Subcommittee on Domestic Policy Committee on Oversight and Government Reform United States House of Representatives Washington, DC 20515

Dear Mr. Chairman:

I am responding to your March 9, 2007, letter in which you requested that the U.S. Nuclear Regulatory Commission (NRC) brief the subcommittee on a request from FirstEnergy Nuclear Operating Company (FENOC). This FENOC request sought relaxation from the remaining two years of annual independent assessments of Operations performance at the Davis-Besse Nuclear Power Plant that were required by an NRC Order.

Subsequently, FENOC withdrew this request. In its letter of withdrawal, FENOC indicated that they see value in the continuance of the independent assessments as the assessments provide external perspectives that will further assist Davis-Besse in achieving top industry performance.

A copy of FENOCs withdrawal letter was forwarded by the NRCs Office of Congressional Affairs (OCA) to your office.

As you requested in your letter, the OCA staff contacted the subcommittees staff director, Mr. Jaron Bourke. OCA looks forward to working with him to schedule a briefing on NRCs current work if that would be helpful to you and your colleagues.

Sincerely,

/RA/

Luis A. Reyes Executive Director for Operations

April 18, 2007 The Honorable Dennis J. Kucinich Chairman, Subcommittee on Domestic Policy Committee on Oversight and Government Reform United States House of Representatives Washington, DC 20515

Dear Mr. Chairman:

I am responding to your March 9, 2007, letter in which you requested that the U.S. Nuclear Regulatory Commission (NRC) brief the subcommittee on a request from FirstEnergy Nuclear Operating Company (FENOC). This FENOC request sought relaxation from the remaining two years of annual independent assessments of Operations performance at the Davis-Besse Nuclear Power Plant that were required by an NRC Order.

Subsequently, FENOC withdrew this request. In its letter of withdrawal, FENOC indicated that they see value in the continuance of the independent assessments as the assessments provide external perspectives that will further assist Davis-Besse in achieving top industry performance.

A copy of FENOCs withdrawal letter was forwarded by the NRCs Office of Congressional Affairs (OCA) to your office.

As you requested in your letter, the OCA staff contacted the subcommittees staff director, Mr. Jaron Bourke. OCA looks forward to working with him to schedule a briefing on NRCs current work if that would be helpful to you and your colleagues.

Sincerely,

/RA/

Luis A. Reyes Executive Director for Operations DISTRIBUTION: G20070202/LTR-070203 R07-0064 PUBLIC RidsNrrDorlLpl3-2 S. Sands, NRR EDO Reading File RidsNrrDirsIrib J. Caldwell, RIII RidsOcaMailCenter RidsEdoMailCenter G. Grant, RIII RidsNrrRgn3MailCenter RidsNrrOd M. Satorius, RIII RidsNrrDorl RidsNrrAdro G. Shear, RIII RidsOgcRp R. Gibbs, NRR K. OBrien, RIII LPL3-2 Reading File T. Bloomer, EDO E. Duncan, RIII RidsOpaMail R. Schmidt, OCA J. Rutkowski, RIII RidsNrrWpcMail DOCUMENT NAME:C:\FileNet\ML071020513.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy ML071010595 OFFICE RIII/DRP NRR OCA RIII NAME EDuncan*:sls RGibbs by email* RSchmidt by email MSatorius*

DATE 04/11/07 04/11/07 04/12/07 04/11/07 OFFICE RIII OCA EDO NAME JCaldwell RSchmidt LReyes DATE 04/12/07 04/17/07 04/18/07 OFFICIAL RECORD COPY