MONTHYEARML24017A2392024-01-17017 January 2024 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Valve Testing Frequency Alternative VR-9 ML23226A0742023-08-14014 August 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Remove the Table of Contents from the Technical Specifications ML23180A2322023-06-29029 June 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Revise Technical Specifications Consistent with TSTF-276-A, Revision 2 ML23129A3122023-05-0909 May 2023 NRR E-mail Capture - Beaver Valley Unit 2 - Verbal Authorization of Alternative Request, 2-TYP-4-RV-06 ML23128A1612023-05-0808 May 2023 NRR E-mail Capture - Comanche Peak Nuclear Power Plant, Units 1 and 2, Beaver Valley Power Station, Unit Nos. 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, and Perry Nuclear Power Plant, Unit No. 1 - Acceptance of Requested Licensing ML23125A1602023-05-0505 May 2023 NRR E-mail Capture - Correction to Beaver Valley - RAI Regarding Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23125A1462023-05-0505 May 2023 NRR E-mail Capture - Beaver Valley - RAI Regarding Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23122A0342023-05-0202 May 2023 NRR E-mail Capture - Beaver Valley - Request for Additional Information Regarding Unit 1 - 180 Day Steam Generator Tube Inspection Report ML23095A3442023-04-0505 April 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Licensing Action Request Regarding Irradiated Fuel Management Plan ML23089A1252023-03-30030 March 2023 NRR E-mail Capture - Beaver Valley Upcoming Steam Generator Tube Inservice Inspection ML23086B9862023-03-27027 March 2023 NRR E-mail Capture - Davis-Besse, Unit No. 1 - Acceptance Review Results for Davis-Besse, Unit No. 1 - Proposed Alternative Request RP-5 ML23079A1202023-03-20020 March 2023 NRR E-mail Capture - Acceptance Review for Beaver Valley 1 & 2 Exemption from Specific Provisions in 10 CFR 50 Appendix H ML23065A0782023-03-0303 March 2023 Final RAIs Regarding the Beaver Valley Emergency LAR (EPID L-2023-LLA-002) - Email ML23033A0322023-02-0101 February 2023 NRR E-mail Capture - Request for Additional Information for Davis-Besse's 2022 Steam Generator Inspection Report (L-2022-LRO-0115) ML23010A2892023-01-10010 January 2023 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment Regarding Revising the Methodology Used for Flood Hazard Analysis ML22341A0322022-11-30030 November 2022 10 CFR Part 21 Notification from Curtiss-Wright Nuclear Division for Qualtech Np Supplied Eaton TRM5 Timing Relays ML22321A2392022-11-17017 November 2022 NRR E-mail Capture - (External_Sender) Beaver Valley Power Station, Units 1&2 - Clarification on LAR to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML22312A5912022-11-0808 November 2022 NRR E-mail Capture - Beaver Valley Power Station, Units 1&2 - Request for Additional Information LAR to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML22273A1132022-09-30030 September 2022 NRR E-mail Capture - Acceptance of Requested Licensing Action to Add Full Spectrum LOCA Methodology to COLR ML22266A1102022-09-23023 September 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding July 21, 2022, Request for Withholding Information from Public Disclosure ML22277A5122022-09-19019 September 2022 NRR E-mail Capture - (External_Sender) Eh Response to Corrected SE Associated with Beaver Valley Amendments 315 and 205 Changes to the EPP ML22241A0362022-08-29029 August 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of License Amendment Request to Adopt TSTF-541, Revision 2 ML22238A2812022-08-25025 August 2022 Request for Additional Information for Beaver Valley Unit 2 - 2R22 Steam Generator 180 Day Report ML22202A4642022-06-29029 June 2022 Emergency Plan Safety Evaluation ML22178A1322022-06-24024 June 2022 Request for Additional Information for Beaver Valley Unit 2 Steam Generator Inspection Report - Fall 2021 Refueling Outage ML22173A0402022-06-21021 June 2022 NRR E-mail Capture - Acceptance of Requested Licensing Action Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML22167A1002022-06-16016 June 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Delay in Issuance of License Amendment and Exemptions Regarding Revising the Methodology Used for Flood Hazard Analysis (EPIDs No.L-2021-LLA-0067, L-2021-LLE-0022, L-2021-LLE-0023) ML22164A8572022-06-13013 June 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Emergency Plan ML22147A0392022-05-27027 May 2022 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Pennsylvania Regarding a Beaver Valley, Units 1 & 2 Amendment - Revise TS 3.3.5, Loss of Power (LOP) Diesel Generator (DG) Start and Separation Instrumentation ML22136A2122022-05-16016 May 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-063 ML22129A0122022-05-0606 May 2022 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Pennsylvania Regarding a Beaver Valley Power Station, Unit 2 Amendment - Correct TS 3.1.7 Change Made by TSTF-547 ML22123A0232022-05-0202 May 2022 NRR E-mail Capture - Acceptance of Requested Licensing Action for Beaver Valley Power Station, Units 1 and 2 - Adoption of TSTF-501, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML22118A6862022-04-28028 April 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Alternative to Extend the Steam Generator Weld Inspection Interval ML22112A1092022-04-22022 April 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Design Basis for the Shield Building ML22153A5212022-04-15015 April 2022 Email Error in Energy Harbor Submittal and Associated SE for Beaver Valley 1 & 2 - Containment Isolation Valve Relief Request ML22101A0122022-04-0808 April 2022 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Pennsylvania Regarding a Beaver Valley Power Station, Units 1 and 2 Amendment - Revise Technical Specification 5.6.3, Core Operating Limits Report (COLR) ML22090A1692022-03-30030 March 2022 Re_ Action Tracking Item 2022 SST - 335 - Tom Gurdziel, E-mail Re_ Event Number 55734 at Davis Besse, a Matter of Interpretation ML22089A2452022-03-30030 March 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-12 ML22087A1302022-03-28028 March 2022 NRR E-mail Capture - (External_Sender) NRC Notification to the State of Pennsylvania Regarding a Beaver Valley Power Station, Units 1 and 2 Amendment - Adopt TSTF-577 ML22080A2512022-03-18018 March 2022 NRR E-mail Capture - (External_Sender) ASME OM Code Case OMN-27, Alternative Requirements for Testing Category a Valves (Non- Piv/Civ) ML22068A1822022-03-0909 March 2022 NRR E-mail Capture - Beaver Valley Power Station, Units 1 & 2 - Request for Additional Information for License Amendment Request to Revise Technical Specification 3.3.5 ML22055B0382022-02-24024 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Upcoming Steam Generator Tube Inservice Inspection ML22055A0872022-02-23023 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Relief Request RP-3 ML22045A4962022-02-14014 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of License Amendment Request to Revise the Emergency Plan ML22040A1832022-02-0707 February 2022 LTR-22-0033 Tom Gurdziel, E-mail Event Number 55734 at Davis Besse, a Matter of Interpretation ML22034A9472022-02-0303 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Revised Review Estimates for Proposed Alternative to Extend the Steam Generator Weld Inspection Interval ML22033A0632022-02-0101 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Acceptance of License Amendment Request to Revise the Design Basis for the Shield Building Containment Structure ML22020A0722022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Alternative Requests Regarding VR-10 and VR-11 Inservice Valve Testing ML22020A0712022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Alternative VR-12 ML22020A0702022-01-18018 January 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Acceptance of Proposed Inservice Inspection Alternative IR-063 2024-01-17
[Table view] |
Text
From: Lentz, Thomas A (EH) <talentz@firstenergycorp.com>
Sent: Thursday, February 27, 2020 11:53 AM To: Wall, Scott Cc: Salgado, Nancy; Vaidya, Bhalchandra; Hamilton, David B (EH); Joyce, Brendan; Stenger, Daniel F.; Desai, Sachin; david.repka3@gmail.com; lbeckerman@akingump.com; Benyak, Darin M (EH); Emley, James E (EH)
Subject:
[External_Sender] Completion of License Transfer for the Beaver Valley, Davis-Besse and Perry Nuclear Units Scott:
This message is to inform the NRC that the actions required to complete the transfer of the Beaver Valley, Davis-Besse and Perry nuclear units have been completed today, effective immediately.
Consistent with the NRCs approval order dated December 2, 2019 (Order), the direct transfers of the operating authority for the facilities from FirstEnergy Nuclear Operating Company (FENOC) to Energy Harbor Nuclear Corp., and the ownership of the facilities from FirstEnergy Nuclear Generation, LLC (FENGen) to Energy Harbor Nuclear Generation LLC, were completed. The indirect transfer of ownership of the facilities from FirstEnergy Corp./FirstEnergy Solutions Corp. to Energy Harbor Corp. as the ultimate parent company was also completed. It is requested that the NRC issue the conforming license amendments consistent with the Order.
Energy Harbor Nuclear Corp. adopts and endorses the outstanding commitments, licensing actions, applications and similar items on the dockets submitted by FENOC on the behalf of the licensees.
Energy Harbor Nuclear Corp. requests NRC continuation of the regulatory reviews and actions on these items.
Any questions, please call.
Tom Thomas Lentz Energy Harbor Nuclear Corporation Manager, Nuclear Licensing & Regulatory Affairs 341 White Pond Drive Akron, Ohio 44320 talentz@firstenergycorp.com Work: (330) 315-6810 Mobile: (440) 666-8499 The information contained in this message is intended only for the personal and confidential use of the recipient(s) named above. If the reader of this message is not the intended recipient or an agent responsible for delivering it to the intended recipient, you are hereby notified that you have received this document in error and that any review, dissemination, distribution, or copying of this message is strictly prohibited. If you have received this communication in error, please notify us immediately, and delete the original message.