NRR E-mail Capture - Results of Acceptance Review - FENOC Fleet - Request for Approval of Request for Approval of Lrradiated Fuel Management Plans, EPID L-2019-LRO-0016
ML19161A213
Person / Time
Site: Beaver Valley, Davis Besse, Perry
Issue date: 06/06/2019
From: Bhalchandra Vaidya
Plant Licensing Branch III
To: Lashley P, Lentz T
FirstEnergy Nuclear Operating Co
References
L-2019-LRO-0016
Download: ML19161A213 (3)


Text

NRR-DRMAPEm Resource From: Vaidya, Bhalchandra Sent: Thursday, June 6, 2019 10:17 AM To: Lentz, Thomas A. (Licensing; Lashley, Phil H.

Cc: Regner, Lisa; Miller, Fred; Harwell, Shawn

Subject:

Results of Acceptance Review - FENOC FLEET - Request for Approval of Request for Approval of lrradiated Fuel Management Plans, EPID L-2019-LRO-0016

SUBJECT:

FENOC FLEET - Request for Approval of lrradiated Fuel Management Plans EPID L-2019-LRO-0016 Beaver Valley Power Station, Unit Nos. 1 and 2 Docket No. 50-334, License No. DPR-66 Docket No. 50-412, License No. NPF-73 Davis-Besse Nuclear Power Station, Unit No. 1 Docket No. 50-346, License No. NPF-3 Perry Nuclear Power Plant, Unit No. 1 Docket No. 50-440, License No. NPF-58 By letter dated March 15, 2019, FirstEnergy Nuclear Operating Company (FENOC, LICENSEE) submitted a request to NRC for approval of the FENOC Irradiated Fuel Management Plans pursuant to 10 CFR 50.54(bb).

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 180 hours7.5 days <br />1.071 weeks <br />0.247 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is March 2020. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities.

1

If you have any questions, please contact me.

Bhalchandra K. Vaidya Licensing Project Manager NRC/NRR/DORL/LPL3 (301)-415-3308 (O) bhalchandra.vaidya@nrc.gov 2

Hearing Identifier: NRR_DRMA Email Number: 37 Mail Envelope Properties (DM6PR09MB2601408EEEA18AD9EE9EC7AE8D170)

Subject:

Results of Acceptance Review - FENOC FLEET - Request for Approval of Request for Approval of lrradiated Fuel Management Plans, EPID L-2019-LRO-0016 Sent Date: 6/6/2019 10:16:40 AM Received Date: 6/6/2019 10:16:00 AM From: Vaidya, Bhalchandra Created By: Bhalchandra.Vaidya@nrc.gov Recipients:

"Regner, Lisa" <Lisa.Regner@nrc.gov>

Tracking Status: None "Miller, Fred" <Fred.Miller@nrc.gov>

Tracking Status: None "Harwell, Shawn" <Shawn.Harwell@nrc.gov>

Tracking Status: None "Lentz, Thomas A. (Licensing" <talentz@firstenergycorp.com>

Tracking Status: None "Lashley, Phil H." <phlashley@firstenergycorp.com>

Tracking Status: None Post Office: DM6PR09MB2601.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3012 6/6/2019 10:16:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: