IR 05000324/2019011

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams) Inspection Report 05000324/2019011 and 05000325/2019011
ML19289B887
Person / Time
Site: Brunswick  Duke energy icon.png
Issue date: 10/16/2019
From: James Baptist
NRC/RGN-II
To: Krakuszeski J
Duke Energy Progress
Archer L
References
IR 2019011
Download: ML19289B887 (21)


Text

ber 16, 2019

SUBJECT:

BRUNSWICK STEAM ELECTRIC PLANT - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000324/2019011 AND 05000325/2019011

Dear Mr. Krakuszeski:

On September 13, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Brunswick Steam Electric Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Brunswick.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Brunswick. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Docket Nos. 05000324 and 05000325 License Nos. DPR-62 and DPR-71

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000324 and 05000325 License Numbers: DPR-62 and DPR-71 Report Numbers: 05000324/2019011 and 05000325/2019011 Enterprise Identifier: I-2019-011-0007 Licensee: Duke Energy Progress, LLC Facility: Brunswick Steam Electric Plant Location: Southport, NC Inspection Dates: August 19, 2019 to September 13, 2019 Inspectors: C. Franklin, Reactor Inspector J. Montgomery, Senior Reactor Inspector G. Ottenberg, Senior Reactor Inspector M. Riley, Reactor Inspector C. Baron, Mechanical Contractor G. Nicely, Electrical Contractor Approved By: James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Brunswick Steam Electric Plant in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations Failure to Properly Size and Evaluate the Acceptability of MOV Thermal Overloads Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green None (NPP) 71111.21M Systems NCV 05000324,05000325/2019011-01 Closed The team identified a Green finding and associated Non-cited Violation (NCV) of Title 10 of the Code of Federal Regulations Part 50 (10 CFR 50), Appendix B, Criterion III, "Design Control," for the licensee's failure to translate design basis MOV requirements into sufficient procedural guidance to size and evaluate motor-operated valve (MOV) thermal overloads (TOLs) properly. Specifically, the licensee's procedure for sizing and evaluating TOLs, EGR-NGGC-0106, AC and DC Overcurrent Protection and Coordination Revision 5, did not incorporate guidance to properly size or evaluate the MOV TOLs during all design basis conditions.

Failure to Follow Calculation Control Process Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [H.3] - Change 71111.21M Systems NCV 05000324,05000325/2019011-02 Management Closed The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Title 10 of the Code of Federal Regulations Part 50 (10 CFR 50), Appendix B, Criterion V,

"Instructions, Procedures and Drawings," for the licensee's failure to follow their AD-EG-ALL-1117, Design Analyses and Calculations, procedure. Specifically, procedure AD-EG-ALL-1117, section 4.2, required the verifier to identify that the design inputs were accurate and complete, however, the licensee did not identify all design inputs for calculations 0BNP-TR-006, "MOV Design Basis Information GL89-10 & GL 96-05," and BNP-E-8.013/BNP-E-8.014,

"Motor Torque Analysis for AC MOVs." As a result, the licensee failed to update the affected calculations following motor-operated valve (MOV) testing or maintenance, the results of which could change the results of the calculations.

Additional Tracking Items None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (4 Samples)

(1) E4 Bus - Division II Emergency Switchgear
  • Material condition and configuration review performed during a visual non-intrusive inspection to assess material condition, the presence of hazards, and consistency of installed equipment with design documentation and analyses
  • Normal, abnormal, and emergency operating procedures
  • Breaker Maintenance effectiveness; Procedures for preventive maintenance, inspection, and testing to compare maintenance practices against industry and vendor guidance
  • Component health reports, corrective maintenance records, and corrective action history
  • Coordination and interface with the transmission system operator for plant voltage requirements and notification set points
  • Electrical calculations:(Load flow, bus loading and voltage drop, Degraded and loss of voltage protection, Protective relay and breaker settings and coordination, Short circuit and breaker duty analysis)
(2) Motor-Operated Valve (MOV) 2-E11-F007B - RHR Minimum Flow Bypass Valve to the Suppression Pool (Electrical Interfaces)
  • Calculations: (Motor Torque Determination, MOV Protection Thermal Overload Sizing and Evaluations, MOV motive and control power, available torque calculations)
  • Adherence to vendor and industry maintenance and technical updates
  • Material condition and configuration review performed during a visual non-intrusive inspection to assess material condition, the presence of hazards, and consistency of installed equipment with design documentation and analyses
(3) Unit 2 125V DC Distribution Panel 4-B
  • Material condition and configuration reviewed performed during a visual non-intrusive inspection to assess material condition, the presence of hazards, and consistency of installed equipment with design documentation and analyses
  • Procedures for maintenance and testing of breakers to compare practices against industry guidance
  • Component health reports and corrective action history
  • Calculations: (Bus loading and voltage drop, short circuit analysis, breaker coordination study)
  • Surveillance testing of battery power supply attributes inspected (e.g.,

maximum available fault current)

(4) Unit 1 Reactor Core Isolation Cooling (RCIC) Pump, E51-C001
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Equipment/environmental controls and qualification
  • Design calculations
  • Surveillance testing and recent test results
  • System and component level performance monitoring
  • Equipment protection from fire, flood, and water intrusion or spray
(1) Unit 1 Air-Operated Valve (AOV) 1-CAC-V216 - Hardened Wetwell Vent Line Isolation Valve
  • Material condition and configuration review performed during a visual non-intrusive inspection to assess material condition, the presence of hazards, and consistency of installed equipment with design documentation and analyses
  • Normal, abnormal and emergency operating procedures
  • Maintenance effectiveness; Procedures for preventive maintenance, inspection, and testing to compare maintenance practices against industry and vendor guidance.
  • Component health reports, corrective maintenance records, and corrective action history
  • Calculations: (actuator output capability and margins, air supply and control power, required design basis capability, uncertainty assumptions)

Modification Review - Permanent Mods (IP Section 02.03) (4 Samples)

(1) EC 406293, Evaluation of Instrument Uncertainty Calculations not for Limiting Safety System Settings or Automatic Protective Functions
(2) EC 298197, Acceptability of Shaft to Bowl Bearing Clearance and Impeller Wear Ring Clearance for 2C CSW PUMP 2-SW-2C-CONV-PMP
(3) EC 412996, Replace the 1-E11-F048B-MO (1B RHR HX BYPASS VLV) with an Aluminum Rotor Motor
(4) EC 407321, Evaluation Of DC Load Profile And Battery Voltages Following The Restoration Of DC Battery Chargers To The DC System During A DBA (LOOP/LOCA)

Review of Operating Experience Issues (IP Section 02.06) (2 Samples)

(1) NRC Regulatory Issue Summary (RIS) 2011-12, Rev. 1, Adequacy of Station Electric Distribution System Voltages
(2) NRC Information Notice 2013-17, Significant Plant Transient Induced by Safety-Related Direct Current Bus Maintenance at Power

INSPECTION RESULTS

Failure to Properly Size and Evaluate the Acceptability of MOV Thermal Overloads Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green None (NPP) 71111.21M Systems NCV 05000324,05000325/2019011-01 Closed The team identified a Green finding and associated Non-cited Violation (NCV) of Title 10 of the Code of Federal Regulations Part 50 (10 CFR 50), Appendix B, Criterion III, "Design Control," for the licensee's failure to translate design basis MOV requirements into sufficient procedural guidance to size and evaluate motor-operated valve (MOV) thermal overloads (TOLs) properly. Specifically, the licensee's procedure for sizing and evaluating TOLs, EGR-NGGC-0106, AC and DC Overcurrent Protection and Coordination Revision 5, did not incorporate guidance to properly size or evaluate the MOV TOLs during all design basis conditions.

Description:

TOLs are installed to protect MOV actuator motors from failure due to heating caused by prolonged exposure to high current. The TOLs trip to interrupt the current to the MOV motor, which prevents the valve from moving. In nuclear power plant applications, the criterion for establishing an MOV TOL trip set point should be for the valve to complete its safety function (e.g., drive the valve to its proper position to mitigate the effects of an accident) rather than to protect the motor from destructive heating. MOVs may be required to operate at the beginning of an accident when other large motors are also starting, which could result in bus voltage dropping low enough to stall the MOV until voltage recovers. If these voltage dips occur while power to the MOV is being supplied from the offsite power source, and voltage doesnt recover quickly (generally within 5 seconds), then the MOV may continue to stall until the degraded voltage protection system time delay relay (described in TS 3.3.8.1) actuates. This causes the plant to disconnect from the offsite power source, and switch to the emergency diesel generators. During this time, the stalled MOVs could be experiencing high currents and generating excessive heat within both the actuator motor and the TOL, which can cause the TOL to actuate and trip the power to the MOV if not sized adequately to operate through the event without tripping. Similarly, MOVs may also have a jogging or throttling requirement during the accident which requires multiple starts of its motor within a short period of time. These demands would add additional heat to the MOV motor and TOL, which can also cause the TOL to actuate and trip the power to the MOV.

The inspection team reviewed Attachment F, DVR and TOL Evaluation, of calculations BNP-E-8.013 and BNP-E-8.014, Motor Torque Analysis for AC Motor Operated Valves, to evaluate how the licensee confirmed that the MOV TOLs were sized appropriately for degraded grid voltage conditions concurrent with accident conditions. During the team's review of the calculations, the team discovered several errors in the calculation methodology that were non-conservative and required the licensee to re-evaluate them. The licensee captured these errors in their corrective action program as action requests (ARs) 2289038 and 2289996. Once the licensee corrected the errors in their calculation, the team discovered that the TOLs for nine MOVs had the potential to trip before the valves performed their safety function, if the MOV was taken out of its normal position and the MOV received an accident signal to reposition back to its normal safety-function position.

Upon discovering that the TOLs were undersized, the inspection team reviewed the procedural guidance in BNP Standard Procedure EGR-NGGC-0106, AC and DC Overcurrent Protection and Coordination, Revision 5, which the licensee used to size various electrical protective devices.

The team observed that section 9.3.14, Considerations for AC and DC Protective Device Selection, described that protective devices must be adequately sized for the operating scenarios under consideration, such as during starting of other loads simultaneously or during a degraded voltage condition where the inrush current of a starting motor may continue until the voltage recovers to the point at which the devices can operate. However, section 9.6, MOV Motor Circuit Protection, which the licensee used for sizing MOV TOLs specifically, did not reference or include the guidance described in subsection 9.3.14. Additionally, in section 9.6 there was no specific guidance for various scenarios required by the station MOVs design bases, including:

  • Considering a sustained degraded grid voltage and its associated 11 second maximum time delay allowed by the degraded grid voltage relay setpoints required by TS 3.3.8.1,
  • The allowances given in Generic Letter 89-10, Supplement 1, and utilized by the station MOV program to delay starting of MOVs for approximately 5 seconds during upstream motor starting which may result in stall conditions for that time,
  • Sizing TOLs for MOVs that have a jogging/throttling function post-event.
  • Establishing the trip setpoint of the TOLs with all uncertainties resolved in favor of completing the safety-related action, rather than protecting the motor.

Because of the inadequate procedural guidance, the team determined that calculation BNP-E-2.002, 480V AC Auxiliary Safety-related MOV Electrical Protection, Rev. 16, which sized the TOLs for MOVs, did not ensure that the safety function of the MOVs would be met, as it did not account for the different operating scenarios described above. Several of the TOLs were undersized in favor of providing protection for the MOV motor, rather than ensuring the safety function would be completed. NCR 2291385 was generated to evaluate the procedural adequacy.

Corrective Actions: The licensee entered the issue into their corrective action program and evaluated the MOVs' capability to respond to accident conditions due to being in their normal required position prior to the event. The licensee further initiated plans to improve the guidance in procedures for sizing and evaluating MOV TOLs.

Corrective Action References: NCRs 02289038 and 02291385 and NTM 2289996

Performance Assessment:

Performance Deficiency: The team determined the licensee's failure to translate design basis MOV requirements into sufficient procedural guidance in EGR-NGGC-0106 to size and evaluate the MOV TOLs properly was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, nine MOVs were identified that had under-sized TOLs and had the potential to trip during an accident concurrent with a degraded voltage condition, and the improper TOL sizing challenges the capability of the MOVs during degraded grid voltage design conditions.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors evaluated the finding in accordance with the NRC Inspection Manual Chapter (IMC) 0609, Attachment 4, "Initial Characterization of Findings," issued October 7, 2016, for Mitigating Systems, and IMC 0609, Appendix A, issued June 19, 2012, and determined the finding to be of very low safety significance (Green) because finding was a design deficiency and the affected SSCs maintained their operability. Specifically, the licensee justified the MOVs would be able to perform their safety function under predicted transient voltage conditions during a design basis accident, although they would be challenged under concurrent accident and degraded voltage scenarios.

Cross-Cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, required, in part that Measures shall be established to assure that applicable regulatory requirements and the design basis, are correctly translated into specifications, drawings, procedures, and instructions. Contrary to the above, since at least the last revision to procedure EGR-NGGC-0106 in April 2016, the licensee did not assure that applicable regulatory requirements and the design bases were correctly translated into procedures. Specifically, procedure EGR-NGGC-0106 did not incorporate guidance to properly evaluate the MOV TOLs during design basis accidents concurrent with degraded grid voltage design conditions allowed by the setpoints in plant technical specifications for the degraded grid voltage relays or other different MOV operating scenarios required by the station MOVs design bases.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Follow Calculation Control Process Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [H.3] - Change 71111.21M Systems NCV 05000324,05000325/2019011-02 Management Closed The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Title 10 of the Code of Federal Regulations Part 50 (10 CFR 50), Appendix B, Criterion V, "Instructions, Procedures and Drawings," for the licensee's failure to follow their AD-EG-ALL-1117, Design Analyses and Calculations, procedure. Specifically, procedure AD-EG-ALL-1117, section 4.2, required the verifier to identify that the design inputs were accurate and complete, however, the licensee did not identify all design inputs for calculations 0BNP-TR-006, "MOV Design Basis Information GL89-10 & GL 96-05," and BNP-E-8.013/BNP-E-8.014, "Motor Torque Analysis for AC MOVs." As a result, the licensee failed to update the affected calculations following motor-operated valve (MOV) testing or maintenance, the results of which could change the results of the calculations.

Description:

The purpose of calculations BNP-E-8.013 and BNP-E-8.014 was to calculate available MOV motor torque during extreme bus voltages, and the purpose of calculation 0BNP-TR-006 was to document design basis information for Generic Letter (GL) 89-10 and GL 96-05 MOVs. Additionally, each motor-operated valve (MOV) included in the licensee's MOV program has an associated calculation that determines the margin available to operate the MOV during design basis scenarios. The individual MOV margin calculations get updated occasionally following Periodic Verification Testing (PVT) if the results of the testing indicate a change in a parameter that led to an increase or decrease in the calculated margin for the MOV. The margin calculations compare available MOV output thrust/torque to the thrust/torque required to make the valve change position. The determination of available thrust/torque is dependent on the voltage of the electrical source supplying power to the MOV motor; the determination of the required thrust/torque is dependent on mechanical properties of the valve and piping system including various parameters that add load to the valve.

The inspectors identified that calculations BNP-E-8.013, BNP-E-8.014, and 0BNP-TR-006 included assumptions based on MOV margins determined at a specific time, but they did not get revised and updated properly following results of MOV PVT that changed the assumed inputs into the calculations. Failing to update the calculations following changes to a MOV PVT margin can result in misidentifying that either the MOV will not stall (failing to begin to move or continue to change position) at all, or misidentifying the point at which an MOV has the potential of stalling during periods of transient voltages as a result of accident initiated load sequencing. This may result in failing to identify that a thermal overload (TOL) was insufficiently sized for the expected stall conditions during a degraded grid voltage condition. TOLs are included in the MOV electrical power path and can trip to interrupt the current being provided to the MOV motor to protect the motor from failure due to prolonged heating. However, if the TOL is not sized properly, the TOL could trip before the valve has moved to its required safety-function position.

4 of 0BNP-TR-006 evaluated a list of MOVs subject to electrical transient voltages during an accident to determine whether or not the MOV would stall during the transient, but had not been updated due to changes in assumed loading or other MOV adjustments since November 15, 2016. Attachment F of BNP-E-8.013/-014 evaluated the acceptability of TOLs for safety-related MOVs during a degraded voltage concurrent with an accident and used MOV margins to determine the voltage at which the MOVs may stall as input to the analysis. The team observed the MOV PVT margins assumed in the calculations had not been updated since Attachment F was added under revision 10 in 2014.

Section 5.2.7.i.(3) of procedure AD-EG-ALL-1117 required the licensee to clearly identify design inputs and associated reference sources in the body of the calculation. It also stated, "Refer to Attachment 18, Design Input Considerations, for the list of Design Input considerations." Consideration of electrical requirements and design inputs which could be invalidated by field activities were included in Attachment 18. The discovery of a parameter during PVT beyond that previously assumed, or the intentional adjustment of an MOV parameter (such as packing load adjustments) during implementation of field work on MOVs should have been considered as having the potential to impact a design input into calculations BNP-E-8.013, BNP-E-8.014, and 0BNP-TR-006. Also, sections 5.3.8 and 5.3.9, stated that the responsible Engineering Manager was to ensure documents impacted by Calculation conclusions are identified and appropriate processes are initiated to track and implement required changes." Additionally, procedure AD-EG-ALL-1117 section 4.2, required the Design Verifier to identify that the design inputs were accurate and complete.

The inspectors determined that because calculations BNP-E-8.013, BNP-E-8.014, and 0BNP-TR-006 did not identify the MOV margin calculations as providing design inputs into the calculations, they were not being updated as required. Upon discovery by the inspection team, the licensee updated the affected calculations to reflect the current MOV margins reflected by PVT results and determined the MOVs remained capable of performing their safety functions.

Corrective Actions: The licensee generated NCRs 2290331 and 2289038 and updated the affected calculations to reflect the current MOV parameters from PVT results.

Corrective Action References: NCRs 2290331 and 2289038

Performance Assessment:

Performance Deficiency: The licensee's failure to follow their AD-EG-ALL-1117, "Design Analyses and Calculations" Rev. 5 procedure was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, failing to update calculations 0BNP-TR-006 and BNP-E-8.013/8.014 following changes to MOV parameters could lead to failing to identify that a valve may stall during the predicted voltage transient or failing to identify that a TOL was insufficiently sized for the expected stall conditions during a degraded grid voltage condition.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors evaluated the finding in accordance with the NRC Inspection Manual Chapter (IMC) 0609, Attachment 4, "Initial Characterization of Findings," issued October 7, 2016, for Mitigating Systems, and IMC 0609, Appendix A, issued June 19, 2012, and determined the finding to be of very low safety significance (Green) because the finding was a deficiency affecting the design or qualification of a mitigating structure, system or component (SSC) and the SSC maintained its operability or functionality. Specifically, the licensee updated the affected calculations to reflect current MOV periodic verification testing results and determined the MOVs would be capable of performing their safety functions.

Cross-Cutting Aspect: H.3 - Change Management: Leaders use a systematic process for evaluating and implementing change so that nuclear safety remains the overriding priority. In this case, the licensee did not use their established process for implementing calculation changes.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion V, required in part, Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings. Contrary to the above, Brunswick did not accomplish an activity affecting quality in accordance with their procedure. Specifically, procedure AD-EG-ALL-1117, section 4.2, required the verifier to identify that the design inputs were accurate and complete, and the licensee did not identify all design inputs for calculations 0BNP-TR-006, BNP-E-8.013, and BNP-E-8.014.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 13, 2019, the inspectors presented the design basis assurance inspection (teams) inspection results to John A. Krakuszeski and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.21M Calculations 04KV-002 4.16kV Emergency Bus Degraded Grid Voltage Relay Rev. 4

Setpoint Calc

0B21-0199 ECCS Analysis Results Rev. 8

0B21-0199 ECCS Analysis Results Rev. 8

0BNP-TR-006 MOV Design Basis Information GL-89-10 & GL-96-05 Rev. 6

0E41-1001 High Pressure Coolant Injection System - Condensate Rev. 3

Storage Tank Level Low Uncertainty and Setpoint

Calculation (E41-LSL-N002(3) Loops)

0E41-1001 High Pressure Coolant Injection System - Condensate Rev. 3

Storage Tank Level- Low Uncertainty And Setpoint

Calculation (E41-LSL-N002(3) LOOPS)

0E51-0028 Reactor Core Isolation Cooling System - Condensate Rev. 3

Storage Tank Level - Low Uncertainty And Scaling

Calculation (E51-LSL-4463(4) LOOPS)

0EOP-WS-13.1 LPCI/RHR Vortex Limit (2 Pumps) Plus HPCI and RCIC Rev. 6

Vortex Determination

0RNA-0001 Instrument Air Nitrogen Backup System Volume Rev. 4

Requirements

27-8-E41-06F NPSH Requirements - RCIC and HPCI Rev. 1

ANP-3105NP Brunswick Units 1 and 2 LOCA Break Spectrum Analysis for Rev. 1

ATRIUM 10XM Fuel for MELLLA+ Operation

BNP-E-1.012 Safety Related AC Control Loop Voltage Analysis Rev. 9

BNP-E-2.002 480V AC Safety Related MOVs Electrical Protection Rev. 16

BNP-E-2.007 U2 480V Vital MCC Calculations Rev. 19

BNP-E-6.085 Unit 2 125/250V DC Coordination/Protection Calculation Rev. 7

BNP-E-6.093 Unit 1 125/250V DC Coordination/Protection Calculation Rev. 6

BNP-E-6.095 Unit 1 125/250V DC Coordination/Protection Calculation Rev. 7

BNP-E-6.120 125/250VDC System Battery Load Study Rev. 12

BNP-E-6.121 Electrical Analysis for Safety Related DC Circuits Rev. 10

BNP-E-7.002 AC Auxiliary Electrical Distribution System Voltage/Load Rev. 14

Flow/Fault Current Study

BNP-E-8.010 AC Coordination Study Rev. 23

Inspection Type Designation Description or Title Revision or

Procedure Date

BNP-E-8.010 AC Coordination Study Rev. 24

BNP-E-8.014 Motor Torque Analysis for AC MOVs Rev. 18

BNP-MECH-1- AOV Setup Calculation for 1-CAC-V216-AO Rev. 1

CAC-V216-AO

BNP-MECH- Differential Pressure Calcualtions for 1/2-CAC-V7-AO, -V8- Rev. 0

AOV-DP-CAC AO, -V216-AO Inboard Suppression Pool Purge Exhaust,

Outboard Suppression Pool Purge Exhaust, and Hardened

Wetwell Vent Isolation Air-Operated Valves

BNP-PSA-034, Operator Action Summary Reports Rev. 17

Appendix C

M-89-0021 HPCI/RCIC NPSH with Suction from the CST Rev. 0

SA-E51-739 Stress Analysis for RCIC Exhaust Pipe Due to Water Rev. 0

Hammer Loads

Corrective Action 02085737,

Documents 02086053,

27923-23,

2063268,

2105119,

2165651,

630621, 633538,

27745, 508592,

709200

Corrective Action AR 02287837 0CM-PVT500 dated

Documents 08/20/2019

Resulting from AR 02288218 DBAI 2019 - BNP-E-1.012 & 1.013 Not updated for 7.002 dated

Inspection Rev 14 08/22/2019

AR 02288751 NRC Identified: Typographical Error Found in UFSAR dated

08/26/2019

AR 02288836 MOV Hydraulic Lock Monitoring Program dated

08/26/2019

AR 02289038 DBAI 2019 - BNP-E-8.013 & 8.014, Att. F Errors dated

08/27/2019

AR 02289460 Revise BNP-E-7.002 Assumption 3.2.2.9 dated

08/29/2019

Inspection Type Designation Description or Title Revision or

Procedure Date

AR 02289996 Corrections to BNP-E-8.013 & BNP-E-8.014 dated

09/03/2019

AR 02290331 2019 DBAI: 0BNP-TR-006 attachment 4 not updated dated

09/04/2019

AR 02290559 Administrative Update to UFSAR Section 6.3.3.3 dated

09/05/2019

AR 02291132 2019 NRC DBAI: Conservatism in MOV motor torque dated

methodology 09/10/2019

AR 02291159 HPCI and RCIC Overspeed Evaluation Discrepancies dated

09/10/2019

AR 02291174 2019 DBAI - BNP response to IN 2013-17 did not fully eval dated

09/10/2019

AR 02291176 2019 DBAI: Replacemnt of Program MOV sprng packs not dated

timely 09/10/2019

AR 02291385 2019 NRC DBAI - Procedure Corrections - EGR-NGGC- dated

0106 & 0101 09/11/2019

AR 02291396 2019 DBAI IST Program Document Issue dated

09/11/2019

AR 02291577 DBAI 2019 - BNP-E-8.013 & 8.014, Table G Errors dated

09/12/2019

Drawings 0-FP-84314 8" Class 300 Wafer A31A Valve Assemby and Bettis N721- Rev. B

SR80 Fail Close Actuator

1-FP-05887, Auto Depressurization System Elementary Diagram Unit 1 Rev. M

Sheet 2

D-02041 Service Water System Piping Diagram Rev. 66

D-02523 Sh. 1 Reactor Building High Pressure Coolant Injection System Rev. 59

Piping Diagram

D-02523 Sh. 2 Reactor Building High Pressure Coolant Injection System Rev. 53

Piping Diagram

D-02529 Sh. 1 Reactor Building Reactor Core Isolation Cooling System Rev. 64

Piping Diagram

D-02529 Sh. 2 Reactor Building Reactor Core Isolation Cooling System Rev. 46

Piping Diagram

D-02537 Reactor Building Service Water System Piping Diagram Rev. 99

Inspection Type Designation Description or Title Revision or

Procedure Date

D-70029 Reactor Building Instrument Air Supply System Piping Rev. C

Diagram

F-03000 Main One Line Diagram 230KV and 24KV Systems Rev. 40

F-03002 4160V System Switchgear One Line Diagram Rev. 33

F-03003 4160V Emergency System Switchgear E3 & E4 One Line Rev. 19

Diagram

F-03026 Emergency Key One Line Diagram Rev. 13

F-03050 480V MCC 2XB One Line Diagram Rev. 94

FSP-27059 Reactor Building, Unit 1 Hardened Wetwell Vent Piping Rev. 2

LL-03024, Sht. 7 125-250 Volt DC System Control Building Distribution Panel Rev. 28

4B - "H24"

LL-90046 CAC System Hardened Wetwell Vent Valve V216 Control Rev. 1

Wiring Diagram

Engineering 400921 Long Term Division II Load Management

Changes 407321 Evaluation Of DC Load Profile And Battery Voltages

Following The Restoration Of DC Battery Chargers To The

DC System During A DBA (LOOP/LOCA)

411708 Reduce Loads On 125/250 VDC Switchboard 1B-1 and 1B-2

and Revise 1st Minute Test Load in MST for 1A-1 1A-2, 1B-1

and 1B-2 Batteries

EC 276098

EC 294259 Unit 1, Phase 1 & 2, Hardened Containment Vent System Rev. 12

Upgrades in Repsonse to EA 12-109 (Mechanical)

EC 298197 Acceptability of Shaft to Bowl Bearing Clearance and Rev. 0

Impeller Wear Ring Clearance for 2C CSW Pump 2-SW-2C-

Conv-PMP

EC 299442

EC 406293 Evaluation of Instrument Uncertainty Calculations not for Rev. 0

Limiting Safety System Settings or Automatic Protective

Functions

Engineering ESR 96-00253 Service Water Pump Bearing Clearance Evaluation. 06/21/1999

Evaluations

Miscellaneous 4KV Metal Clad Switchgear Template Rev. 4

03FSAR-041 Licensing Document Change Request dated

Inspection Type Designation Description or Title Revision or

Procedure Date

1/26/04

04FSAR-017 Licensing Document Change Request dated

7/14/04

04TSB-04 Licensing Document Revision Request Rev. 0

238-044 Procurement of Product - Lubricated Service Water Pumps - Rev. 12

AL6XN

5170 System Health Report, Medium Voltage AC Distribution Q2-2019

AR 102456 Operability Determination dated

8/28/03

CPL-01 TECHNICAL SPECIFICATION REVISION REQUEST dated

DEGRADED VOLTAGE RELAYS 06/29/1982

CPL-02 ADEQUACY OF STATION ELECTRIC DISTRIBUTION dated

SYSTEMS VOLTAGES 11/23/1982

CSD-EG-BNP- BNP IST Program Plan - 5th Interval Rev. 0

20

DBD-51 DC Electrical System Dated

6/7/2017

Docket 50- Staff Positions Relative to Emergency Power Systems dated

25/50-324 06/03/1977

EC 280671 Att. O HPCI and RCIC Pump Discharge Pressure Evaluation Rev. 4

EC 412996 1-E11-F048B-MO (1B RHR HX BYPASS VLV) with an Rev. 0

Aluminum Rotor Motor

EC 46911 HPCI Function Update Rev. 0

EC 54587 Basis for the 1(2)-E41-LSL-N002 and 1(2)-E41-LSL-N003 Rev. 0

Setpoints

FP-82508 Bettis General Operating and Maintenance Instructions for Rev. D

Pneumatic Rotary Valve Actuators

FP-84867 Technical Manual for Installation, Operation and Rev. D

Maintenance of Johnston Pump Company 27CC - 2 Stage

Service Water Pumps

GD-79-3307 LESSONS LEARNED SHORT TERM REQUIREMENTS dated

2/31/1979

GD-79-612 ON- SITE EMERGENCY POWER SYSTEMS dated

03/06/1979

Inspection Type Designation Description or Title Revision or

Procedure Date

JOG-TD-01 Spring Relaxation for Air Operators Rev. 2

LAP-83-551 REQUEST FOR ADDITIONAL INFORMATION dated

ELECTRICAL DISTRIBUTION SYSTEM VOLTAGES 11/30/1983

NEDC-32973P Safety Analysis Evaluations Relative to Measurement Rev. 0

Uncertainties for the BWR/4

NLS-84-363 ELECTRICAL DISTRIBUTION SYSTEM VOLTAGES dated

08/30/1984

NLS-84-515 RESPONSE TO REQUEST FOR ADDITIONAL dated

INFORMATION: 1) ADEQUACY OF STATION ELECTRIC 01/18/1985

SYSTEM VOLTAGE 2) TECHNICAL SPECIFICATIONS OF

DEGRADED VOLTAGE RELAYS

NLS-85-321 AMENDMENT TO FACILITY OPERATING LICENSE dated

05/23/1985

NLS89072 Letter - SAFER/GESTR-LOCA Analysis dated

3/29/89

NLU-80-338 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR dated

REACTOR REGULATION SUPPORTING AMENDMENT 06/11/1980

NO. 28 TO FACILITY LICENSE NO. DPR-71 AND

AMENDMENT NO. 51 TO FACILITY LICENSE NO. DPR-62

NLU-83-70 PLANT SHIELDING MODIFICATIONS, NUREG-0737 ITEM dated

II.B.2.2 01/27/1983

NO-80-1093 ADEQUACY OF STATION ELECTRICAL DISTRIBUTION dated

SYSTEMS VOLTAGE 07/24/1980

NRC89401 Letter - SAFER/GESTR-LOCA Analysis dated 6/1/89

PMCR 2063268 Modify Existing 125VDC Panel PMs to include Breaker Dated

Testing 9/20/2016

SPEC 248-164 Specification for Procurement of Class 2 Buttery Valve and Rev. 1

Spare Parts for Hardened Wetwell Vent Containment

Isolation.

TIA 2003-05 NRC Policy Questions on Technical Specification Adequacy dated

and Related Technical Specification Operability 1/16/04

Procedures 0AOP-12.0 Loss of Uninterruptible Power Supply (UPS) Rev. 26

0AOP-39.0 Loss of DC Power Rev. 47

0AP-064 Time Critical Actions/Time Sensitive Actions Supplement Rev. 5

Inspection Type Designation Description or Title Revision or

Procedure Date

0CM-PVT500 Disassembly and Rebuild: Service Water Pump, Johnston Rev. 35

Pump Company

0ENP-646 Post Test Evaluation of AOV Diagnostics Rev. 2

0EOP-01-EDP Emergency Depressurization Rev. 6

0EOP-01-SBO-15 Primary Containment Isolation Rev. 1

0EOP-01-SEP-01 Primary Containment Venting Rev. 28

0MST-ADS41BR ADS Loop B Logic Sys Functional and Simulated Auto Rev. 3

Actuation Test

0PM-BKR-001 ITE 4KV Breaker and Compartment Checkout Rev. 54

0PM-RLY-033 Functional Testing of Thermal Overload Relays Rev. 24

0PT-10.1.1 RCIC System Operability Test Rev. 107

0PT-10.1.3 RCIC System Operability Test - Flow Rates at 150 PSIG Rev. 60

0PT-20.3 Local Leakrate Testing Rev. 86

1MST-BAT11AR 125 VDC Battery 1A-1 Service Capacity Test Rev. 8

1OP-19 High Pressure Coolant Injection System Operating Rev. 99

Procedure

1OP-24 Containment Atmosphere Control System Rev. 110

2EOP-01-RVCP Reactor Vessel Control Rev. 11

2MST-BAT11DR 125 VDC Battery 2B-2 Service Capacity Test Rev. 7

2PT-24.1-2 Service Water Pump and Discharge Rev. 86

AD-EG-ALL-1117 Design Analyses and Calculations Rev. 5

AD-EG-ALL-1431 Air Operated Valve Scope and Categorization Rev. 1

AD-EG-ALL-1432 Air Operated Valve Design Basis Review Rev. 0

AD-EG-ALL-1433 Air Operated Valve Testing Requirements Rev. 1

AD-EG-ALL-1434 Air Operated Valve Tracking and Trending Requirements Rev. 1

CAP-NGGC-0202 Operating Experience and Construction Experience Program Rev. 23

EGR-NGGC- Electrical Calculation of Motor Output Torque for AC/DC Rev. 12

0101 MOVs

EGR-NGGC- AC/DC Overcurrent Protection and Coordination Rev. 5

0106

EGR-NGGC- Air Operated Valve Reliability Program Rev. 10

205

NGG-PMB-SOV- NGG Equipment Reliability Template SOlenoid Operated Rev. 0

Inspection Type Designation Description or Title Revision or

Procedure Date

Valves (SOV)

SORMC-NUC- System Operations Reference Manual Carolinas Rev. 24

050

Work Orders 12068756-01,

2068759-11,

234502-01,

13503714-01,

24561-01,

20022842-01,

20107653-03,

20107653-04,

20123051-01,

255536-01,

20120570-01,

20120570-02,

20120570-03,

20120570-04,

20120570-08,

13522687-08,

20136720-01,

1895617-01,

20034690-01

18