|
---|
Category:Inspection Plan
MONTHYEARIR 05000324/20230052023-08-23023 August 2023 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2023005 and 05000325/2023005) IR 05000324/20220062023-03-0101 March 2023 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 NRC Inspection Reports 05000324/2022006 and 05000325/2022006 ML22307A1762022-11-0707 November 2022 Notification of an NRC Fire Protection Team Inspection (FPTI) IR 05000324/20220052022-08-24024 August 2022 Updated Inspection Plan for Brunswick Steam Electric Plant (Report 05000324/2022005 and 05000325/2022005) ML22192A0862022-07-12012 July 2022 RQ Inspection Notification Letter ML22119A1352022-05-0909 May 2022 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000325/2022403; 05000324/2022403 IR 05000324/20210062022-03-0202 March 2022 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 (Reports No. 05000324/2021006 and 05000325/2021006) IR 05000324/20210052021-08-26026 August 2021 Updated Inspection Plan for Brunswick Steam Electric Plant (Report 05000324/2021005 and 05000325/2021005) ML21113A0762021-04-23023 April 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 IR 05000324/20200062021-03-0303 March 2021 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Reports 05000325/2020006 and 05000324/2020006 ML20310A3342020-11-0505 November 2020 Emergency Preparedness Exercise Inspection Request for Information IR 05000324/20200052020-08-24024 August 2020 Updated Inspection Plan for Brunswick Steam Electric Plant Units 1 and 2, NRC Inspection Report 05000325/2020005 and 05000324/2020005 ML20198M5742020-07-16016 July 2020 Requalification Program Inspection - Brunswick Steam Electric Plant IR 05000324/20190062020-03-0303 March 2020 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Reports 05000325/2019006 and 05000324/2019006 ML19296A7712019-10-23023 October 2019 Notification of an NRC Fire Protection Team Inspection - NRC Inspection Report 05000324/2020010 and 05000325/2020010) and Request for Information IR 05000324/20180062019-03-0404 March 2019 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2018006 and 05000324/2018006 ML18352B0192018-12-18018 December 2018 U2 ISI 2019001 RFI Notification IR 05000324/20180052018-08-23023 August 2018 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2, NRC Report 05000325/2018005 and 05000324/2018005 IR 05000324/20170062018-02-28028 February 2018 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Reports 05000325/2017006 and 05000324/2017006, 05000325/2017402 and 05000324/2017402, 05000325/2017501 and 05000324/2017501 ML18026A6242018-01-25025 January 2018 U1 ISI 2018001 RFI Bcc IR 05000324/20170052017-08-28028 August 2017 Updated Inspection Plan NRC Inspection Report 05000325/2017005 and 05000324/2017005 ML17153A0712017-06-0101 June 2017 Notification of Inspection and Request for Information ML17115A4742017-04-17017 April 2017 Emergency Preparedness Inspection and Request for Information IR 05000324/20160062017-03-0101 March 2017 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 & 2 - NRC Inspection Report 05000325/2016006 and 05000324/2016006 ML17021A0032017-01-20020 January 2017 Notification of Inspection and Request for Information IR 05000324/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2016005 and 05000324/2016005 ML16027A1652016-01-27027 January 2016 Notification of Inspection and Request for Information IR 05000324/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2015005 and 05000324/2015005 ML15085A1392015-03-26026 March 2015 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000324/20140012015-03-0404 March 2015 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2014001 and 05000324/2014001 IR 05000324/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Brunswick, Units 1 & 2, Inspection Report 05000325/2014006 and 05000324/2014006 IR 05000324/20130012014-03-0404 March 2014 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 - NRC Inspection Report 05000325/2013001 and 05000324/2013001 ML13254A0402013-09-10010 September 2013 Notification of Inspection and Request for Information ML13246A0592013-09-0303 September 2013 Mid Cycle Assessment Letter ML13123A3252013-05-0101 May 2013 Emergency Preparedness Inspection and Request for Information ML13080A3912013-03-21021 March 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000324/20120012013-03-0404 March 2013 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 & 2, (IR 05000325-12-001 and 05000324-12-001,) on 02/13/2013, ML12304A0702012-10-30030 October 2012 Requalification Program Inspection ML12248A1812012-09-0404 September 2012 Mid Cycle Assessment Letter Brunswuck 2012 ML1206504102012-03-0505 March 2012 EOC Report 22 ML1124401522011-09-0101 September 2011 Report 22 Inspection/Activity Plan ML1106304362011-03-0404 March 2011 EOC Report 22, Inspection/Activity Plan, 03/01/2011 - 06/30/2012 ML1006210102010-03-0303 March 2010 Report 22 - 2010001 ML1006210132010-03-0303 March 2010 ISFSI Report 22 - 2010-001 ML0924405252009-09-0101 September 2009 Report 22, Inspection/Activity Plan 09/01/2009 - 12/31/2010 ML0906303602009-03-0404 March 2009 Report 22 Inspection/Activity Plan 03/01/2009 - 06/30/2010 ML0824609822008-09-0202 September 2008 Report 22. Inspection/Activity Plan, 09/01/2008 - 12/31/2009 IR 05000324/20080012008-03-0303 March 2008 Annual Assessment Letter (NRC Inspection Report 05000325/2008001 and 05000324/2008001) ML0724306612007-08-31031 August 2007 Inspection Plan Report 22, for 09/01/2007 - 03/31/2009 2023-08-23
[Table view] Category:Letter
MONTHYEARIR 05000324/20230112023-12-26026 December 2023 NRC Fire Protection Team Inspection - FPTI Report 05000324/2023011 and 05000325/2023011 IR 05000324/20234022023-12-14014 December 2023 Security Baseline Inspection Report 05000324-2023402 and 05000325-2023402 ML23297A0262023-11-27027 November 2023 Proposed Alternatives to ASME Code Section XI Subsection IWE Requirements for Torus Metallic Liner Inspections ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230032023-11-0101 November 2023 Integrated Inspection Report 05000324/2023003 and 05000325/2023003 IR 05000324/20230102023-10-17017 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000324/2023010 and 05000325/2023010 IR 05000325/20234012023-10-16016 October 2023 Security Baseline Inspection Report 05000324 and 05000325 2023401 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000324/20230052023-08-23023 August 2023 Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2 (Report 05000324/2023005 and 05000325/2023005) IR 05000324/20230022023-08-0404 August 2023 Integrated Inspection Report 05000324/2023002 and 05000325/2023002 ML23201A2042023-07-28028 July 2023 Summary of Regulatory Audit in Support of Alternative Request RA-22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20243012023-07-25025 July 2023 Notification of Licensed Operator Initial Examination 05000325/2024301 and 05000324/2024301 ML23212B2682023-07-25025 July 2023 Notification of Licensed Operator Initial Examination 05000325/2024301 and 05000324/2024301 ML23146A0012023-05-24024 May 2023 EN 56538 - Engine Systems Inc and Brunswick ML23212A9502023-05-24024 May 2023 Engine Systems, Inc., Part 21 Report Re Woodward EGB-35P Governor/Actuator with Foreign Material ML23130A3902023-05-12012 May 2023 Regulatory Audit Plan in Support of Alternative Request RA 22-0308 for Inservice Inspection of the Torus Metallic Liner IR 05000324/20230012023-05-10010 May 2023 Integrated Inspection Report 05000324 2023001 and 05000325 2023001 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000324/20220042023-04-0404 April 2023 Reissue - Brunswick Steam Electric Plant - Integrated Inspection Report 05000324/2022004 and 05000325/022004 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000324/20220062023-03-0101 March 2023 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 NRC Inspection Reports 05000324/2022006 and 05000325/2022006 ML23033A5252023-02-0808 February 2023 Integrated Inspection Report 05000324/2022004 and 05000325/2022004 IR 05000324/20223012023-02-0303 February 2023 NRC Operator License Examination Report 05000325/2022301 and 05000324/2022301 IR 05000324/20224022022-11-23023 November 2022 Security Baseline Inspection Report 05000324 2022402 and 05000325 2022402 ML22332A0132022-11-23023 November 2022 Operator Licensing Written Examination Approval 05000325/2022301 and 05000324/2022301 ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000324/20224032022-11-10010 November 2022 Cyber Security Inspection Report 05000324/2022403 and 05000325/2022403 ML22307A1762022-11-0707 November 2022 Notification of an NRC Fire Protection Team Inspection (FPTI) IR 05000324/20220032022-11-0707 November 2022 Integrated Inspection Report 05000324/2022003 and 05000325/2022003 ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports IR 05000324/20220052022-08-24024 August 2022 Updated Inspection Plan for Brunswick Steam Electric Plant (Report 05000324/2022005 and 05000325/2022005) ML22230D0692022-08-22022 August 2022 Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai-ichi Accident IR 05000324/20220022022-08-0505 August 2022 Integrated Inspection Report 05000324/2022002 and 05000325/2022002 IR 05000324/20220102022-06-27027 June 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000324 2022010 and 05000325 2022010 ML22028A1742022-05-12012 May 2022 Issuance of Amendment Nos. 309 and 337 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-580, Revision 1 IR 05000324/20220012022-05-10010 May 2022 Integrated Inspection Report 05000324/2022001 and 05000325/2022001 ML22119A1352022-05-0909 May 2022 Information Request for the Cyber-Security Baseline Security Inspection, Notification to Perform Inspection 05000325/2022403; 05000324/2022403 ML22082A2682022-05-0202 May 2022 Issuance of Amendment Nos. 308 and 336 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2 ML22102A0502022-04-11011 April 2022 301 Corporate Notification Letter IR 05000324/20224012022-03-16016 March 2022 Security Baseline Inspection Report 05000324/2022401 and 05000325/2022401 ML22054A2152022-03-0808 March 2022 Correction to Amendments to Revise Standby Liquid Control System Boron Solution Storage Tank Volume Technical Specifications IR 05000324/20210062022-03-0202 March 2022 Annual Assessment Letter for Brunswick Steam Electric Plant, Units 1 and 2 (Reports No. 05000324/2021006 and 05000325/2021006) IR 05000324/20210042022-02-14014 February 2022 Integrated Inspection Report 05000324/2021004 and 05000325/2021004 ML22035A1262022-02-0909 February 2022 Withdrawal of Exemption Request from the Requirements of 10 CFR Part 50, Appendix E, Section IV.F.2.d (EPID L-2021-LLE-0055 (COVID-19)) ML21354A5032022-01-24024 January 2022 Requested Exemption from 10 CFR 50, Appendix E, Section IV.F.2.D Not Required (EPID L-2021-LLE-0055 (COVID-19)) ML22018A1842022-01-18018 January 2022 Notification of Brunswick Steam Electric Plant, Units 1 & 2 - Design Bases Assurance Inspection - U.S. Nuclear Regulatory Inspection Report 05000324/2022010 and 05000325/2022010 ML21348A7192021-12-21021 December 2021 Regulatory Audit Summary Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times 2023-09-25
[Table view] |
Text
SUBJECT:
UPDATED INSPECTION PLAN FOR BRUNSWICK STEAM ELECTRIC PLANT (REPORT 05000324/2022005 AND 05000325/2022005)
Dear Mr. Krakuszeski:
The enclosed inspection plan lists the inspections scheduled through June 30, 2024 for the Brunswick Steam Electric Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
Beginning on January 1, 2023, the engineering inspection frequency will transition from a triennial (3-year) to a quadrennial (4-year) cycle. The new engineering inspection program will consist of a Comprehensive Engineering Team Inspection (CETI)1and three Focused Engineering Inspections (FEIs) that will be performed in each quadrennial cycle. For the cycle beginning in 2023, the FEIs will be: Fire Protection Team Inspection, Commercial Grade Dedication and an engineering inspection that reviews age-related degradation and management2.
In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities to return to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and as discussed in our November 2, 2021 memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission.
1Aspects of the Design Basis Assurance Inspection (DBAI), Evaluations of Changes, Tests, & Experiments, and Heat Sink inspections will be included in the CETI inspection. Attached Report 22 will reference DBAI procedure until the CETI procedure is made publicly available. Previously scheduled Evaluation of Changes, Tests, & Experiments and Heat Sink inspections have been cancelled and removed from Report 22.
2The age-related degradation and management procedure is under development and will be publicly available by the end of calendar year 2022. For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
The NRC will also perform inspections under Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal.
Additionally, during this period the NRC will schedule an additional inspection per a revised version Temporary Instruction 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01) for any sites who elect to implement the guidance of the Industry Initiative on Open Phase Condition, Revision 3 (ML19163A176), which included an option for relying on annunciation and operator manual actions instead of automatic protective features to isolate a power supply affected by an open phase condition. Licensees will be individually notified when the NRC schedules these inspections. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 404-997-4547 with any questions you have regarding this letter.
Sincerely, Signed by Fannon, Matthew on 08/24/22 Matthew S. Fannon, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos. 05000324 and 05000325 License Nos. DPR-62 and DPR-71 Enclosure:
Brunswick Inspection/Activity Plan (09/01/2022 - 06/30/2024)
cc Distribution: via ListServ
ML22236A528 X SUNSI Review X Non-Sensitive X Publicly Available Sensitive Non-Publicly Available OFFICE RII/DRP RII/DRP NAME A. Wilson M. Fannon DATE 8/25/2022 8/24/2022
Site Inspection Activity Plan Brunswick 09/01/2022 - 06/30/2024 Unit Start End Activity CAC Title Staff Count BRUNSWICK REQUAL INSPECTION 2 1,2 9/12/2022 9/16/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance CYBER SECURITY INSPECTION 4 1,2 9/19/2022 9/23/2022 IP 71130.10 000741 Cybersecurity SECURITY BASELINE INSPECTION 3 1,2 10/31/2022 11/4/2022 IP 71130.02 000734 Access Control 1,2 10/31/2022 11/4/2022 IP 71130.05 000737 Protective Strategy Evaluation 1,2 10/31/2022 11/4/2022 IP 71130.09 001656 Security Plan Changes 1,2 10/31/2022 11/4/2022 IP 71151 001338 Performance Indicator Verification BRUNSWICK INITIAL LICENSE EXAM 5 1,2 10/31/2022 11/4/2022 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1,2 12/5/2022 12/16/2022 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
1,2 1/9/2023 1/20/2023 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
FIRE PROTECTION TEAM INSPECTION 4 1,2 1/30/2023 2/3/2023 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
1,2 2/13/2023 2/17/2023 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
TARGET SET INSPECTION 1 1,2 1/30/2023 2/3/2023 IP 71130.14 000743 Review of Power Reactor Target Sets UNIT 2 IN-SERVICE INSPECTION 1 2 4/3/2023 4/7/2023 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
RP OCCUPATIONAL RADIATION SAFETY BASELINE INSPECTION 3 1,2 4/3/2023 4/7/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 4/3/2023 4/7/2023 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 4/3/2023 4/7/2023 IP 71124.04 000728 Occupational Dose Assessment 1,2 4/3/2023 4/7/2023 IP 71124.05 000729 Radiation Monitoring Instrumentation 1,2 4/3/2023 4/7/2023 IP 71151 000746 Performance Indicator Verification 1,2 5/15/2023 5/19/2023 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 5/15/2023 5/19/2023 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 5/15/2023 5/19/2023 IP 71124.04 000728 Occupational Dose Assessment 1,2 5/15/2023 5/19/2023 IP 71124.05 000729 Radiation Monitoring Instrumentation 1,2 5/15/2023 5/19/2023 IP 71151 000746 Performance Indicator Verification PROBLEM IDENTIFICATION & RESOLUTION 4 1,2 8/28/2023 9/1/2023 IP 71152B 000747 Problem Identification and Resolution Prepared on 8/23/2022 6:52:55 AM 1 of 3
Site Inspection Activity Plan 1,2 9/11/2023 9/15/2023 IP 71152B 000747 Problem Identification and Resolution EMERGENCY PREPAREDNESS PROGRAM INSPECTION 2 1,2 9/25/2023 9/29/2023 IP 71114.02 000717 Alert and Notification System Testing 1,2 9/25/2023 9/29/2023 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 9/25/2023 9/29/2023 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 9/25/2023 9/29/2023 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 9/25/2023 9/29/2023 IP 71151 001397 Performance Indicator Verification SECURITY BASELINE INSPECTION 3 1,2 10/2/2023 10/6/2023 IP 71130.02 000734 Access Control 1,2 10/2/2023 10/6/2023 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1,2 10/2/2023 10/6/2023 IP 71130.07 000739 Security Training 1,2 10/2/2023 10/6/2023 IP 71130.09 001656 Security Plan Changes 1,2 10/2/2023 10/6/2023 IP 71151 001338 Performance Indicator Verification POST-APPROVAL LICENSE RENEWAL PHASE 4 4 1,2 11/13/2023 11/17/2023 IP 71003 000687 Post-Approval Site Inspection for License Renewal BRUNSWICK INITIAL EXAM 5 1,2 1/7/2024 1/12/2024 OV 000956 FB-OR-ONSITE VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1,2 2/11/2024 2/24/2024 EXAD 000500 FB-OR-INITIAL LICENSE EXAM ADMINISTRATION (EXAD)
UNIT 1 IN-SERVICE INSPECTION 1 1 3/4/2024 3/8/2024 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
RP RAD SAFETY OCCUPATIONAL AND TRANSPORTATION BASELINE INSPECTION 2 1,2 3/4/2024 3/8/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 3/4/2024 3/8/2024 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation 1,2 3/4/2024 3/8/2024 IP 71151 000746 Performance Indicator Verification FOCUSED ENGINEERING INSPECTIONS (CGD) 3 1,2 3/25/2024 3/29/2024 IP 71111.21N.03 001808 Commercial Grade Dedication 1,2 4/8/2024 4/12/2024 IP 71111.21N.03 001808 Commercial Grade Dedication CYBER SECURITY INSPECTION 4 1,2 5/6/2024 5/10/2024 IP 71130.10 000741 Cybersecurity RP RAD SAFETY PUBLIC BASELINE INSPECTION 2 1,2 5/13/2024 5/17/2024 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1,2 5/13/2024 5/17/2024 IP 71124.07 000731 Radiological Environmental Monitoring Program 1,2 5/13/2024 5/17/2024 IP 71151 000746 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - BRU 5 1,2 5/13/2024 5/17/2024 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1,2 6/3/2024 6/7/2024 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Prepared on 8/23/2022 6:52:55 AM 2 of 3
Site Inspection Activity Plan MATERIAL CONTROL AND ACCOUNTING 1 1,2 6/3/2024 6/7/2024 IP 71130.11 000742 Material Control and Accounting (MC&A)
Prepared on 8/23/2022 6:52:55 AM 3 of 3