IR 05000324/2019005

From kanterella
Jump to navigation Jump to search
Updated Inspection Plan for Brunswick Steam Electric Plant, Units 1 and 2, NRC Report 05000325/2019005 and 05000324/2019005
ML19239A013
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 08/27/2019
From: Bradley Davis
NRC/RGN-II, Division Reactor Projects II
To: William Gideon
Duke Energy Progress
Reeder D
References
IR 2019005
Download: ML19239A013 (6)


Text

ust 27, 2019

SUBJECT:

UPDATED INSPECTION PLAN FOR BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2, NRC REPORT 05000325/2019005 AND 05000324/2019005

Dear Mr. Gideon:

The enclosed inspection plan lists the inspections scheduled through June 30, 2021 for Brunswick Steam Electric Plant, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

The following planned infrequent inspection will be conducted at your facility during the period:

2515/TI 194, Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities In Electric Power Systems; and Inspection Procedure 95001, Supplemental Inspection Response to Action Matrix Column 2 Inputs. These are included in the enclosed inspection plan.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at 404-997-4428 with any questions you have regarding this letter.

Sincerely,

/RA/

Bradley J. Davis, Chief Reactor Projects Branch 4 Division of Reactor Projects Docket Nos.: 50-325, 50-324 License Nos.: DPR-71, DPR-62 Enclosure:

Inspection Plan cc w/ encl: Distribution via ListServ SUBJECT: UPDATED INSPECTION PLAN FOR BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2, NRC REPORT 05000325/2019005 AND 05000324/2019005 DISTRIBUTION:

M. Kowal, RII S. Price, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMBrunswick Resource ROPassessment Resource ADAMS Accession Number: ML19239A013 OFFICE RII:DRP RII:DRP RII:DRP NAME JDodson DJackson BDavis DATE 8/22/2019 8/22/2019 8/22/2019 OFFICIAL AGENCY RECORD

Enclosure

3