une 10, 2010

SUBJECT:

NRC INSPECTION REPORT 050-00010/10-08(DNMS) - DRESDEN NUCLEAR POWER STATION UNIT 1

Dear Mr. Pardee:

On May 13, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed inspection activities at the permanently shutdown Dresden Nuclear Power Station Unit 1. The purpose of the inspection was to determine whether the decommissioning activities were conducted safely and in accordance with NRC requirements. The inspection consisted of a selective examination of procedures and representative records, and interviews with personnel. Specifically, during the on-site inspection on April 27, 2010, and an in-office review May 10 - 13, 2010, the inspectors evaluated decommissioning performance; radioactive waste treatment and effluent and environmental monitoring; safety reviews, design changes, and modifications; and corrective action items relevant to Unit 1 since August 2009. At the conclusion of the on-site inspection on April 27, 2010, the inspectors discussed the interim results with members of your staff. At the conclusion of the in-office review, a final telephone exit meeting was conducted on May 13, 2010, to discuss the final results with members of your staff.

Based on the results of this inspection, the NRC did not identify any violations.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you may have regarding this inspection.

Sincerely,

/RA/By George M. McCann Acting For/

Christine A. Lipa, Chief Materials Control, ISFSI, and Decommissioning Branch Docket No.50-010 License No. DPR-2 Enclosure:

NRC Inspection Report 050-00010/10-08(DNMS)

cc w/encl: Distribution via ListServ