IR 05000237/2022004
| ML23041A043 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 02/10/2023 |
| From: | Robert Ruiz NRC/RGN-III/DORS/RPB1 |
| To: | Rhoades D Constellation Energy Generation |
| References | |
| IR 2022004, IR 2022002 | |
| Download: ML23041A043 (1) | |
Text
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3-INTEGRATED INSPECTION REPORT 05000237/2022004, 05000249/2022004 AND 07200037/2022002
Dear David Rhoades:
On December 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Dresden Nuclear Power Station, Units 2 and 3. On January 12, 2023, the NRC inspectors discussed the results of this inspection with P. Boyle, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
February 10, 2023 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000237, 05000249 and 07200037 License Nos. DPR19 and DPR25
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000237, 05000249, and 07200037
License Numbers:
Report Numbers:
05000237/2022004, 05000249/2022004, and 07200037/2022002
Enterprise Identifier:
I2022004-0048 and I-2022-002-0700
Licensee:
Constellation Energy Generation, LLC
Facility:
Dresden Nuclear Power Station, Units 2 and 3
Location:
Morris, IL
Inspection Dates:
October 01, 2022 to December 31, 2022
Inspectors:
Z. Coffman, Resident Inspector
A. Demeter, Project Engineer
G. Edwards, Health Physicist
G. Hansen, Senior Emergency Preparedness Inspector
C. Hunt, Senior Resident Inspector
A. Nguyen, Senior Resident Inspector
J. Park, Reactor Inspector
M. Porfirio, Illinois Emergency Management Agency
P. Smagacz, Resident Inspector
C. St. Peters, Resident Inspector
J. Steffes, Senior Resident Inspector
Approved By:
Robert Ruiz, Chief
Reactor Projects Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Dresden Nuclear Power Station,
Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
Type Issue Number Title Report Section Status LER 05000237/2022001-00 LER 2022001-00 for Dresden Nuclear Power Station, Unit 2, Reactor Scram due to Turbine Trip on High Reactor Water Level Caused by Feedwater Regulating Valve Failure 71153 Closed LER 05000237/2022001-01 LER 2022001-01 for Dresden Nuclear Power Station, Unit 2, Reactor Scram due to Turbine Trip on High Reactor Water Level Caused by Feedwater Regulating Valve Failure 71153 Closed
PLANT STATUS
Unit 2 began the inspection period at rated thermal power. On December 10, 2022, reactor power was lowered to 58 percent to perform routine control rod drive scram time testing, control rod sequence exchange, main turbine surveillances and feedwater regulating valve maintenance. The unit was returned to full power on December 11, 2022, and remained at or near full power for the remainder of the inspection period.
Unit 3 began the inspection period in coast down to prepare for refueling outage D3R27. On October 31, 2022, the unit was shut down to commence D3R27. The unit was synchronized to the grid on November 18, 2022, and ascended to full power shortly thereafter. On November 29, 2022, reactor power was lowered to 65 percent to perform maintenance on the 3B condensate/condensate booster pump seal leak. Reactor power was further lowered to 50 percent to monitor the 3A, 3C and 3D condensate/condensate booster pumps and rod pattern adjustment. Following repair to the 3B condensate/condensate booster pump the unit was returned to full power on December 2, 2022, and remained at or near full power for the remained of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, apendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 3 shutdown cooling system on November 1, 2022 (2)4 kilovolt electrical crossties during D3R27 on November 7-10, 2022
- (3) Unit 3 spent fuel pool cooling system and alternate decay heat removal alignment during D3R27 on November 7-9, 2022
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Fire Zone (FZ) 1.1.1.1, Unit 3 torus basement elevation 476' and torus catwalk, November 3, 2022
- (2) FZ 6.2, Unit 2/3 computer room and auxiliary electrical room elevation 517' on November 4, 2022
- (3) FZ 8.2.5E, Unit 3 high pressure heaters, elevation 517', FZ 8.2.5 D, Unit 3 low pressure heater bay, elevation 517', and FZ 8.2.6 D, Unit 3 low pressure heater bays, elevation 538' on November 2-4, 2022
71111.07A - Heat Exchanger/Sink Performance
Annual Review (IP Section 03.01) (1 Sample)
The inspectors evaluated readiness and performance of:
- (1) Unit 3 'B' low pressure coolant injection (LPCI)/containment cooling service water (CCSW) heat exchanger
71111.08G - Inservice Inspection Activities (BWR)
BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding
Activities (IP Section 03.01)
- (1) The inspectors verified that the reactor coolant system boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from October 31, 2022-November 18, 2022:
03.01.a - Nondestructive Examination and Welding Activities.
1. Ultrasonic testing (UT) of component IDs 3/2/1302A12/127 and -8, Cat. RA,
item R1.16
2. UT of component ID 3/1/RPV SHELL/3SC4D-VERT, Cat. BA, item B1.12
3. UT of component ID access hole cover welds at 155° and 335°
4. Magnetic particle exam of component 3/2/150120/2012, Cat. CB,
item C2.31
5. NDE report 7480332222-EB3RPVID for component ID 3/1/RPV
SHELL/3SC4B-VERT with relevant indication accepted for continued service
6. Weld repair of 3B LPCI heat exchanger support component under
work order (WO) 488633602, weld No. 1, 1A, 11, and 11A
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 3 shutdown and startup for D3R27 on October 31 and November 17, 2022.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated licensed crew performance in the simulator on October 18, 2022.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (2 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
- (1) Compressed air due to repeated failures of the Unit 2 and Unit 3 instrument air compressors
- (2) High pressure injection system
Quality Control (IP Section 03.02) (1 Sample)
The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:
- (1) Safety related service water
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Unit 3 refueling outage, D3R27, yellow work windows for lowered inventory conditions on November 1 and November 12, 2022
- (2) Unit 3 refueling outage, D3R27, planned and emergent elevated risk activities on October 31-November 18, 2022
- (3) Unit 3 condensate booster pump 3B emergent work due to seal degradation on November 28-December 2, 2022
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (8 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Unit 3 high pressure coolant injection leak detection temperature switch 32372-A found broken on November 2, 2022
- (2) Unit 3 high pressure coolant injection steam chest and turbine control valve NDE indications identified on November 4, 2022
- (3) Unit 3 incorrect fuse found in Bus 39 UV circuitry, on November 4, 2022
- (4) Unit 3 125 V DC grounds
- (5) Bypassing Unit 3 mechanical vacuum pump trips (6)
===30220-44, recirculation loop sample line isolation air-operated valve, failed its local leak rate test on November 13, 2022
- (7) Unit 3 hotwell basement flood seal missing bolts on November 7, 2022
- (8) Unit 3 low pressure coolant injection loop I coolant injection inboard isolation MOV, 31501-22A, thrust unacceptable for asleft maximum, on November 15, 2022
71111.18 - Plant Modifications
Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03)===
- (1) The inspectors verified the site SAMG were updated in accordance with the BWR generic sever accident technical guidelines and validated in accordance with NEI 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents, Revision 1.
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:
- (1) Unit 3 1000 psi system leakage test/hydrostatic test per WO 5126822
- (2) DOS 700027, local leak rate testing of Unit 2
- (3) reactor vessel water level instrumentation system valves, following work on valve 30299-98A, on November 15, 2022
- (3) DOS 030015, control rod scram time testing, November 13, 2022
- (4) Non-destructive examination and pressure test of 31501-26A, low pressure coolant loop injection valve, after repairs during D3R27 per WO 1183382
- (5) DOS 150012, CCWS loop flow verification, per WO 5022790 and WO 4830134
- (6) DES 830020, Unit 3 250-volt station battery modified performance test, per WO 5260976
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated Unit 3 refueling outage, D3R27, activities from October 31 to November 18, 2022.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:
Surveillance Tests (other) (IP Section 03.01) (3 Samples)
- (1) DOS 660004, bus undervoltage and emergency core cooling system integrated functional test for Unit 3 diesel generator, on November 6, 2022
- (2) DTS 160007, Unit 2(3) primary containment integrated leak rate test on November 15, 2022
- (3) DIS 050020, reactor mode switch (start, hot standby, shutdown, and refuel, positions) logic system functional test, on November 16, 2022
Inservice Testing (IP Section 03.01) (1 Sample)
- (1) DOS 710003 seat leakage testing of valves 2 (3)-029997A(B), 2 (3)-029998A(B), 2 (3)-029999A(B) and 2 (3)-0299100A(B), on November 3, 2022
Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)
- (1) DOS 700001, local leak rate test of main steam isolation valves (dry tests), and DOS
===700002, local leak rate test of main steam isolation valves (wet test), on October 31-November 1, 2022
71114.04 - Emergency Action Level and Emergency Plan Changes
Inspection Review (IP Section 02.0102.03)===
- (1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes:
Evaluation No. 2158, Emergency Action Levels for Dresden Station, November 20, 2021 This evaluation does not constitute NRC approval.
RADIATION SAFETY
71124.01 - Radiological Hazard Assessment and Exposure Controls
Radiological Hazard Assessment (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazard.
Instructions to Workers (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazard.
Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)
The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:
- (1) Workers exiting the RCA at the Unit 3 drywell equipment hatch during a refueling outage
- (2) Workers exiting the RCA from the refuel floor during a refueling outage
Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)
The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:
- (1) Unit 3 turbine building moisture separator activities (inspection, repair, maintenance as applicable)
- (2) Unit 3 main steam line crossover piping inspections
- (3) Main condenser repair activities
- (4) Unit 3 turbine building feedwater systems maintenance High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)
The inspectors evaluated licensee controls of the following high radiation areas and very high radiation areas:
- (1) Unit 3 drywell main steam isolation valves areas
- (2) Unit 3 reactor building equipment drain tank room
- (3) Unit 3 reactor vessel head platform Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
- (1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.
71124.03 - InPlant Airborne Radioactivity Control and Mitigation
Temporary Ventilation Systems (IP Section 03.02) (1 Sample)
The inspectors evaluated the configuration of the following temporary ventilation systems:
- (1) Temporary HEPA ventilation systems used on the refuel floor during refueling activities.
OTHER ACTIVITIES-BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===
- (1) Unit 2 (October 1, 2021 through September 30, 2022)
- (2) Unit 3 (October 1, 2021 through September 30, 2022)
BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)
- (1) Unit 2 (October 1, 2021 through October 31, 2022)
- (2) Unit 3 (October 1, 2021 through October 31, 2022)
OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)
- (1) October 1, 2021 through October 31, 2022 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
- (1) October 1, 2021 through October 31, 2022
71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Evaluation of and corrective actions associated with the Unit 2 2A feedwater regulating valve failing open and subsequent scram under AR 4510475
71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)
- (1) The inspectors reviewed the licensees corrective action program for potential adverse trends in work planning and execution that might be indicative of a more significant safety issue.
71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)
The inspectors evaluated the following licensee event reports (LERs):
- (1) LER 237/2022001-01, Reactor Scram due to Turbine Trip on High Reactor Water Level caused by Feedwater Regulating Valve Failure (ADAMS Accession No. ML22304A228). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements. The inspectors reviewed the updated LER submittal. The previous LER submittal was also reviewed in this inspection report.
OTHER ACTIVITIES
-TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
60853 - OnSite Fabrication of Components and Construction on an ISFSI OnSite Fabrication of Components and Construction on an ISFSI
- (1) The inspectors evaluated the licensees Independent Spent Fuel Storage Installation (ISFSI) pad expansion activities from July 2022 to November 2022. Throughout construction, the inspectors evaluated the following:
Preparation of the subsurface, formwork, and type and condition of reinforcing steel
The materials used were consistent with the design and procurement specifications
Aggregates were tested for potential reactivity
Design changes, modifications, and non-conformance reports
Qualifications of individuals performing quality assurance (QA) functions including non-destructive evaluations
QA oversight
American Concrete Institute (ACI) and American Society for Testing and Materials (ASTM) concrete sample test results, including verifying compressive strength tests met design specifications The inspectors were onsite on September 12 and 15, 2022, and observed the following during construction:
Placement of reinforcing steel was consistent with design requirements
Concrete placement was consistent with ACI standards
Concrete testing was consistent with ASTM and ACI standards
Overall pad dimensions were consistent with the design documents
INSPECTION RESULTS
Observation: Failure of 2A Feedwater Regulating Valve 71152A On July 12, 2022, the 2A feedwater regulating valve (FWRV), a non-safety related valve, failed to the full-open position. The 2B reactor feed pump (RFP) tripped on low suction pressure, followed by the 2A and 2C RFPs tripping due to high reactor level. This caused a high reactor water level turbine trip, and subsequently Unit 2 received an automatic reactor Scram. The licensee replaced the 2A FWRV Joucomatic solenoid valve and returned to full power.
The inspectors reviewed the licensee's root cause report and supporting failure analysis report from a third party to determine the cause of the FWRV failing full-open. The licensee determined that the root cause was the 2A FWRV pilot valve assembly did not operate as demanded by the feedwater control system due to manufacturing byproduct inside the pilot valve that was introduced during the manufacturing process.
The third-party vendor concluded a piece of plastic migrated from another location within the pilot valve and settled on the seat surface of the movable pilot plunger. This resulted in the movable pilot plunger not full seating against the fixed seat. The failure mode was identified as the pilot valve not seating in a deenergized state. The piece of plastic was believed to be the same plastic used to manufacture the body components, and likely left over from the manufacturing process.
The site developed corrective actions to have incoming Joucomatic solenoid valves with specific identification related to the failure inspected by a second-or third-party vendor and certified to be free of foreign material. The site also reclassified the FWRV as a single-point vulnerability.
The inspectors did not identify any findings or violations associated with their review.
Observation: Maintenance Preparation and Execution Trend Review 71152S The inspectors performed a semiannual review of issues entered into the corrective action program (CAP) and a cognitive review of plant observations over the period of July 1, 2022, to December 31, 2022, to identify any potential trends that might indicate the existence of a more significant safety issue. In the second half of 2022, the licensee and NRC identified a rise in the number of work processes that were not accomplished first time with quality or resulted in multiple instances to fix issues. The first example was the main power transformer lovoltage bushing sensors not being installed during the work window due to a fitment issue that went undiscovered until work execution. Following issue review, the inspectors concluded due to work complications on the main power transformer and additional outage, delayed work bushing sensor replacement was removed from the outage scope to the next Unit 3 refueling outage incurring 2 more years of wear and tear.
On September 15, 2022, the licensee entered DOA 740001, Failure of the Stator Coolant System, for the failure of the motor cooling fan which resulted in overheating and ultimately the failure of the stator water cooling (SWC) pump motor. The inspectors noted, as documented in condition report (CR) 04522803, 3B Stator Water Cooling Pump Trip.
Entered DOA 7400-01, that the licensee had previously extended the maintenance frequency of the SWC pump motors and that the motors failed during the extended maintenance window. Following 3B SWC pump motor replacement the licensee documented in CR 04538065, Elevated Temperatures on 3B SWC, on November 19, 2022, further elevated temperature issues associated with the motor inboard bearing which resulted in another motor replacement. On December 1, 2022, post maintenance testing of the replaced 3B SWC pump motor revealed elevated temperatures on the pump to motor coupling. The inspectors noted that licensee evaluation suggested that side loading of the bearing was most likely the cause of the increased temperatures following maintenance. The inspectors noted that in an approximate three-month period the licensee had documented four separate condition reports associated with the 3B SWC pump.
Inspector review also noted condition reports associated with the scram air header. In CR 04535612, 3B Scram Air Header Filter Air Leak, the inspectors noted that post maintenance system inspection noted air leaks on the inlet and outlet piping connections to the 3B scram air header filter housing. Licensee assessment resulted in the issue being scoped into the ongoing refueling outage for Unit 3 for resolution. The licensee further documented in CR 04538075, 3B Scram Air Header Filter Air Leak, that the air leak appeared to be from a spot where the Oring was protruding from the flange on the side of the filter. Isolation of the air leak using inlet and outlet valves did not arrest the leak but slowed it, so it did not represent a challenge system function.
Finally, in conversation with plant management the inspectors discussed the previously noted issues and ongoing efforts by the licensee to address equipment reliability. The inspectors noted that challenges in work process preparation and execution could also present challenges to, and hamper efforts to broadly address and improve equipment reliability. The inspectors did not identify any findings or violations associated with the inspection activities.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On January 12, 2023, the inspectors presented the integrated inspection results to P. Boyle, Site Vice President, and other members of the licensee staff.
On November 15, 2022, the inspectors presented the radiation protection inspection results to P. Boyle, Site Vice President, and other members of the licensee staff.
On November 18, 2022, the inspectors presented the inservice inspection results to D. Avery, Acting Regulatory Assurance Manager, and other members of the licensee staff.
On November 28, 2022, the inspectors presented the emergency action level and emergency plan changes inspection results to A. Clements and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
Resulting from
Inspection
04522444
NRC Final Rebar Inspection Prior to ISFSI Pad Concrete
Pour
09/14/2022
B2287 Sheet 1
South ISFSI Pad General Notes
B2287 Sheet 2
South ISFSI Pad Geotechnical Notes
Drawings
B2287 Sheet 3
South ISFSI Pad Plan, Sections, and Details
Engineering
Changes
South ISFSI Expansion Pad
9411106
Concrete Inspection Report-Mud Mat for ISFSI
08/18/2022
9411125
Concrete Inspection Report-North & South ISFSI Pad
10/13/2022
9411130
Concrete Inspection Report-Middle ISFSI Pad
10/21/2022
D2018001
Concrete Construction Specification for South ISFSI Pad,
Construction Pad, Turning Pad/Apron, and Heavy Haul Path
08/22/2022
D3000
Dresden ISFSI Concrete Mix Report
03/14/2022
G22.112
Plate Load Test Data Report
07/15/2022
60853
Miscellaneous
PO# 341479
Certified Mill Test Report
04/22/2022
Corrective Action
Documents
4534445
Leak Identified on PI 31407-C, 3C Shutdown Cooling Pump
Discharge
11/03/2022
Drawings
2E2328
Emergency Power System
O
Engineering
Evaluations
637324
Alternate Decay Heat Removal (ADHR) Qualification for
D3R27
DOP 1000M1/E1
Unit 3 Shutdown Cooling Checklist
DOP 1900M1
Unit 3 Fuel Pool Cooling System Checklist
DOP 650008
Bus 241 to Bus 341 Tie Breaker Operation
Procedures
DOP 650030
Bus 231 to Bus 331 Tie Breaker Operation
Corrective Action
Documents
Resulting from
Inspection
4534891
NRC ID: Housekeeping/Hot Work Issues
11/04/2022
Fire Plans
FZ 1.1.1.1
Unit 3 Torus Basement Elevation 476' and Torus Catwalk
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
FZ 6.2
Unit 2/3 Computer Room and Auxiliary Electrical Room
Elevation 517'
FZ 8.2.5C
Unit 2/3 EHC Reservoir Area, Elevation 517'
FZ 8.2.5D
Unit 3 Low Pressure Heater Bay, Elevation 517'
FZ 8.2.5E
Unit 3 High Pressure Heaters/Steam Line, Elevation 517'
FZ 8.2.6D
Unit 3 Low Pressure Heater Bays, Elevation 538'
Procedures
OPAA201004
Fire Prevention for Hot Work
NDE Reports
3B LPCI Heat Exchanger Eddy Current Examination Final
Report
11/01/2022
2635334
Shroud Weld Inspection Does Not Meet BWRVIP Criteria
03/03/2016
4381004
FM Identified in RPV
10/30/2020
4445276
Previously Identified Leak on ASME Class 2 Valve
31501-11A
09/08/2021
4491094
D3R27 IVVI Emergent OPEX-Access Hole Cover Inspection
04/07/2022
4494861
Deviation from BWRVIP Inspection U2/3 Core Shroud Vert
04/22/2022
4534671
D3R27 M1192D260 VT3 IWF Support Cold Setting OOT
11/03/2022
Corrective Action
Documents
4535096
IVVI D3R27 Indications in Access Hole Covers
11/06/2022
21307
Technical Justification to Support Deviation from BWRVIP
Inspection Guidance for Dresden Station Unit 2 and Unit 3
Core Shroud Vertical Welds
637904
Technical Evaluation of the Dresden Unit-3 Access Hole
Cover 155°
Engineering
Evaluations
637945
Technical Evaluation of Dresden Unit-3 Access Hole Cover
335°
Miscellaneous
BWRVIP180
BWR Vessel and Internals Project - Access Hole Cover
Inspection and Flaw Evaluation Guidelines
7480332222-
EB3RPVID for
3SC4B
UT Report for Component No. 3/1/RPV
SHELL/3SC4B-VERT
11/06/2022
NDE Reports
7480332222-
EB3RPVID for
UT Report for Component No. 3/1/RPV
SHELL/3SC4D-VERT
11/05/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
3SC4D
CNF-AHC01
Indication Results for Access Hole Cover at 155°
CNF-AHC02
Indication Results for Access Hole Cover at 335°
CNF-AHC03
Weld Crown Measurements for the Access Hole Cover at
335°
Magnetic Particle Examination Report for Component
No. 3/2/150120/2012
11/04/2022
UT Report for Component No. 3/2/1302A12/127
11/08/2022
UT Report for Component No. 3/2/1302B12/128
11/08/2022
EPRI-DMW-
PA1
Procedure for Manual Phased Array Ultrasonic Examination
ERAA335003
Magnetic Particle (MT) Examination
ERDR3311001
Dresden Reactor Pressure Vessel and Internals Program
Bases Document
GEH-UT562
Procedure for Phased Array Ultrasonic Examination of
Access Hole Cover Welds
GEH-UT737
Procedure for the Examination of Reactor Pressure Vessel
Welds from the Inside Surface with the ZScan UT System in
Accordance with Appendix VIII
Procedures
WPS 11-GTSM-
ASME Welding Procedure Specification Record
Work Orders
488633602
Repair Identified Deficiencies on U3 B LPCI HX Support
11/04/2020
DGP 0101
Unit Startup
204
Procedures
DGP 0201
Unit Shutdown
176
4465461
U2 CCSW Division 1 Thru Wall Leak
2/08/2021
4513848
Bar Rack Plugging DOA Entries
07/30/2022
4519442
Unexpected Alarm 9231 U3A IAC Trip
08/29/2022
24121
2B Instrument Air Compressor Fails to Load/Unexpected
21 E6 Alarm
09/22/2022
4534701
2A IAC Trending
11/04/2022
4535921
3A IAC Trip on High Temp
11/09/2022
Corrective Action
Documents
4537312
Unit 3 High Pressure Coolant Injection Room Cooler Motor
11/16/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Vibration Increase
4540539
Maintenance Rule High Safety System Maintenance Rule
Functional Failure Were Not Screened in a Timely Manner
2/02/2022
4542415
Unit 3 High Pressure Coolant Injection Room Cooler Motor
Vibration Increase
2/13/2022
Engineering
Changes
635679
Code Repair of a Through Wall Leak on CCSW
Line 21510-16"-D
High Pressure Injection System Health Report
2/20/2022
Compressed Air System Health Report
2/02/2022
SR Service Water System Health Report
2/13/2022
Miscellaneous
NOAA10
Quality Assurance Topical Report (QATR)
4830134
CM Replace Division 1 CCSW Piping 517 TB to RBDT
Room EC 624725
11/12/2022
22790
CM Replace Division 1 CCSW Piping 517 to RBEDT Room
11/12/2022
211916
MM Repair the CCSW Pipe per EC 635679
2/10/2021
Work Orders
211916
MM EWP Remove Paint/Prep Pipe for NDE of 2nd Leak
2/09/2021
24978
Unit 3 ESS Current Low per DOS 680001
11/05/2022
4539461
3B Condensate Pump Seal Degraded
11/28/2022
Corrective Action
Documents
4539818
Unexpected Load Drop
11/30/2022
Engineering
Changes
637260
MR90 Temporary 250VDC Power to Bus 383250-3A/B
D3R27 Shutdown Safety Analysis
Miscellaneous
Various Protected Pathway Schemes During D3R27
10/31/2022 -
11/18/2022
DOA 650001
4kV Bus Failure
DOP 380001
Essential Service System
DOP 670014
Bus 39 Outage
OPAA108117
Protected Equipment Program
Procedures
OUDR1041001
Shutdown Risk Management Contingency Plans
MIDACALC Results DRE31501-22A (DRE3) AC Motor
Operated GL9605 Gate Valve
Calculations
CEDR027
Weak Link Analysis for Dresden Unit 2 & 3 Mark-I MOVs
2B
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
(MO2(3)-150122A(B))
04534040
HPCI Leak Detection Temperature Switch Found Broken
11/01/2022
1135936
NDE Indications Discovered in HPCI Control Valve #4
11/05/2010
4534722
Incorrect Fuse Found in Bus 39 UV Relay Circuitry
11/04/2022
4534843
D3R27 NDE LR VT3 Exam Identified Recordable
Indications
11/04/2022
4535038
U3 Sporadic Alarms
11/05/2022
4535195
Missing Bolts U3 Hotwell Basement Flood Seals
11/07/2022
4535761
345kV BT 910 and 1011 Breakers Tripped Open
11/09/2022
4536021
Unit 3 HPCI Turbine Control Valve Inspection
11/10/2022
4536615
Unit 3 HPCI Turbine Control Valve Adjustment
11/12/2022
4536679
220-44 LLRT Results
11/13/2022
Corrective Action
Documents
4537098
D3R27 MO 31501-22A WR for Contingent Stem Nut Work
11/15/2022
B527
Turbine Building Foundation Sections DD and FF
06/20/1966
B533
Turbine Building Foundation Section
FL19 Sheets 1
and 2
Flood Barrier Turbine Building
FL20
Flood Barrier Turbine Building Section 20
05/26/1995
M284
Turbine Building Ventilation Misc. Plans and Sections
07/21/1967
Drawings
M357, Sheet 2
Diagram of Nuclear Boiler & Reactor Recirculation Piping
BT
637989
D3R27 125 VDC Ground Evaluation
Engineering
Changes
637993
PCTCC for Bypassing Mechanical Vacuum Pump Trips
Unit 3 HPCI Control Valve Seat 4 Crack Indications
ECR 456524
Multiple Recordable Indications Identified Inside HPCI
Steam Chest
11/06/2022
Engineering
Evaluations
ECR 456583
Indication on U3 HPCI Control Valve 3 Seat
11/10/2022
CCAA206
Fuse Control
Procedures
DAN 902(3)-3 C7
HPCI Auto Isolation Initiated
DIS 230007
High Pressure Coolant Injection Area Temperature Switch
Calibration
DOP 540010
Condenser Vacuum Pump Startup
ERAA450
Structures Monitoring
Procedures
OPAA108101
Control of Equipment and System Status
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Work Orders
Work Request to Replace the Missing Bolts on the U3
Hotwell Basement Flood Seals
11/07/2022
4534079
Evidence of Packing Leak on 32301-4 Valve
11/01/2022
4536760
Body to Bonnet Leak on 38941-705 SDC to HRSS XCV
11/14/2022
4536774
D3R27 RCPB Class 1 and Class 2 System Leakage Test
Results
11/14/2022
4536866
Rod H15 Scram Time Did Not Meet TS Requirements
11/14/2022
4536880
Rod R6 Scram Time Did Not Meet TS Requirements
11/14/2022
4536908
Scram Timing Results
11/14/2022
4536929
U3 CRD G13 Stuck at Overtravel In
11/14/2022
4536931
U3 CRD H5 Stuck at Overtravel In
11/14/2022
Corrective Action
Documents
4537035
Control Rod M08 Scram Time Data Not Found
11/15/2022
NDE Reports
2186
D3R27 Class 1 & Class 2 System Leakage Test
11/14/2022
DES 830020
Unit 3 250 Volt Station Battery Modified Performance Test
DOS 030014
Control Rod Drive Scram Testing at Power
DOS 030015
Control Rod Drive Scram Timing Test During Hydro
DOS 700027
Local Leak Rate Testing of Unit 2 (3) Reactor Vessel Water
Level Instrumentation System (RVWLIS) Valves
Procedures
OPDR300101
Average Scram Time Determination
4830134
OPD PMTT Perform DOS 150012 CCSW Flow Verification
for Division 1
11/16/2022
22790
OPD PMT Perform DOS 150012 CCSW Flow Verification
for Division 2
11/16/2022
Work Orders
26822
D3 Refueling TS (ISI) 1000psi Reactor Vessel System
Leakage Test/Hydrostatic Test
11/15/2022
4535057
Foreign Material Recovered from 3B Feedwater Regulating
Valve Cage
11/05/2022
Corrective Action
Documents
4536522
CMO Review of 3A RR Motor Bridge and Megger
Unacceptable
11/12/2022
DRMODE4
TS 3.0.4.b Evaluation-Mode Change with Division 2 CCSW
Out of Service
CCSW 16" Pipe Replacement
Engineering
Evaluations
D3R27 Spent Fuel Pool Cooling Evaluation During
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Transition to ADHR Dresden Station Unit 3
ECR 456634
Determine Minimum Acceptable Resistance to Ground
Reading for Cabling from ASD Trailers
11/11/2022
Miscellaneous
D3R27 Shutdown Safety Analysis
DFP 080007
Fuel Movements during Refueling Operations
DGP 01S1
Start-up Checklist
106
DGP 01S5
Mode 3 to Mode 2 Restart Checklist
DGP 0401
Fuel Moves and Refueling
DOP 020104
Reactor Pressure Vessel Water Inventory Control
MAAA716008-
1008
Reactor Services Refuel Floor FME Plan
MAAA716021
Rigging and Lifting Program
Procedures
OUDR104
Shutdown Safety Management Program
22790
Replace Division 2 CCSW Piping 517' to RBEDT Room per
11/02/2022
Work Orders
5119099
Bridge and Megger Recirculation Pump Motor, 30202-A
11/12/2022
4533563
203-1D MSIV Slow to Close (Hot)
10/31/2022
4533856
Severe Packing Leak from 30220-90A
11/01/2022
4533867
Inboard MSIV 30203-1B Exceeded Technical Specification
LLRT Limit
11/01/2022
4533874
203-1A MSIV LLRT Unfavorable Performance
11/01/2022
4533878
203-2A MSIV LLRT Unfavorable Performance
11/01/2022
4533881
203-2D MSIV LLRT Unfavorable Performance
11/01/2022
4534189
D3R27 IST Seat Leakage Test Exceeded <3 ml/hr (AC)
11/02/2022
4534966
590111B Did Not Initially Pick Up During DIS 050020, Ch B
11/05/2022
4535103
TR32 to Bus 34 Breaker Cubicle Contacts Malfunctioned
During DOS 660004
11/06/2022
4535342
Need WR Created for IR 4534966
11/07/2022
4536998
ILRT Drywell Temperature Sensor T12 Failed
11/15/2022
4537140
Local Leakage During D3R27 ILRT
11/15/2022
Corrective Action
Documents
4537218
Packing Leak on U3 LPCI A Pump Suction Valve from CST
11/15/2022
Procedures
DIS 050020
Reactor Mode Switch (Start, Hot Standby, Shutdown, and
Refuel, Positions) Logic System Functional Test
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
DOS 660004
Bus Undervoltage and ECCS Integrated Functional Test for
Unit 3 Diesel Generator
DOS 700001
Local Leak Rate Test of Main Steam Isolation Valves
(Dry Tests)
DOS 700002
Local Leak Rate Test of Main Steam Isolation Valves
(Wet Test)
DOS 710003
Seat Leakage Testing of Valves 2 (3)-029997A(B),
(3)-029998A(B), 2 (3)-029999A(B) and
(3)-0299100A(B)
DTS 160007
Dresden Integrated Leakage Rate Test
Work Orders
4850420
EM Burnish Reactor Mode Switch Contacts 88C(B)
11/11/2022
Miscellaneous
Q 2158
Emergency Action Levels for Dresden Station
11/20/2021
EPAA1004,
Addendum 3
Emergency Action Levels for Dresden Station
Procedures
EPAA1004,
Addendum 3
Emergency Action Levels for Dresden Station
DR0322-00816
D3R27 TB Feedwater Systems Maintenance
ALARA Plans
DR0322-00901
D3R27 Reactor Disassembly/Reassembly and Related
Activities
Miscellaneous
RPAA302,
Alpha Area Level Assessment
20
NISP-RP002
Radiation and Contamination Surveys
RPAA302
Determination of Alpha Levels and Monitoring
Procedures
RPAA4011003
Contamination Control Best Practice Application
22181001
11/04/2022
Radiation
Surveys
22181049
11/05/2022
DR0322-00509
D3R27 DW Main Steam Isolation Valve (MSIV) Activities
DR0322-00510
D3R27 DW Main Steam ERV, SRV, Target Rock VLVs
DR0322-00802
D3R27 TB Main Condenser Activities
DR0322-00807
D3R27 TB Moisture Separator Activities
DR0322-00808
D3R27 TB Valve Maintenance (Excluding XArea)
Radiation Work
Permits (RWPs)
DR0322-00810
D3R27 TB Water Box Maintenance Activities
Self-Assessments PIAA1261001-
F01
10/29/2022
ALARA Plans
DR0322-00906
D3R27 Cavity Decon
Monthly Data Elements for NRC Radiological Effluent
Technical Specifications/Offsite Dose Calculation Manual
Radiological Effluent Occurrences (RETS/ODCM)
Radiological Effluent Occurrences Sample
(10/01/2021-10/31/2022)
10/01/2021 -
10/31/2022
Monthly Data Elements for NRC Reactor Coolant System
(RCS) Specific Activity (10/01/2021-10/31/2022)
10/01/2021 -
10/31/2022
Monthly Data Elements for NRC Occupational Exposure
Control Effectiveness Sample (10/01/2021-10/31/2022)
10/01/2021 -
10/31/2022
71151
Miscellaneous
Data Validation Package for Safety System Functional
Failure Performance Indicator, Unit 2 and Unit 3
10/01/2021
09/30/2022
Corrective Action
Documents
4510475
2A FRV Failed Open
07/12/2022
Procedures
PIAA1251001
Root Cause Investigation Report Template
6