SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - EMERGENCY PREPAREDNESS BIENNIAL EXERCISE INSPECTION REPORT 05000237/2021501 AND 05000249/2021501
Dear Mr. Rhoades:
On July 23, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Dresden Nuclear Power Station, Units 2 and 3. On July 22, 2021, the NRC inspectors discussed the results of this inspection with Mr. P. Boyle, Plant Manager and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Patricia J. Pelke, Chief Operations Branch Division of Reactor Safety Docket Nos. 05000237 and 05000249 License Nos. DPR-19 and DPR-25
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000237 and 05000249
License Numbers:
Report Numbers:
05000237/2021501 and 05000249/2021501
Enterprise Identifier:
I-2021-501-0016
Licensee:
Exelon Generation Co., LLC
Facility:
Dresden Nuclear Power Station, Units 2 and 3
Location:
Morris, IL
Inspection Dates:
July 19, 2021 to July 23, 2021
Inspectors:
D. Chyu, Reactor Engineer
M. Garza, Emergency Preparedness Inspector
G. Hansen, Senior Emergency Preparedness Inspector
G. Roach, Senior Operations Engineer
Approved By:
Patricia J. Pelke, Chief
Operations Branch
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an emergency preparedness biennial exercise inspection at Dresden Nuclear Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71114.01 - Exercise Evaluation
Inspection Review (IP Section 02.01-02.11) (1 Sample)
- (1) The inspectors evaluated the Biennial Emergency Plan Exercise on July 20, 2021.
The exercise scenario simulated an event at the Dresden Station that initiated with the declaration and notification of an Alert in response to abnormal plant conditions.
The scenario conditions simulated the escalation of the significance of the event requiring the declaration and notification of a Site Area Emergency. The Site Area Emergency was the highest classification level reached, as planned, during the exercise.
71114.08 - Exercise Evaluation Scenario Review
Inspection Review (IP Section 02.01 - 02.04) (1 Sample)
- (1) The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan exercise on June 16,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12)===
- (1) January 1, 2020 through March 31, 2021 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
- (1) January 1, 2020 through March 31, 2021 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
- (1) January 1, 2020 through March 31,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On July 22, 2021, the inspectors presented the emergency preparedness biennial exercise inspection results to Mr. P. Boyle, Plant Manager and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
DR-EP-2019-PEX-OSC-FAILED-DCS
07/10/2019
2Q19 EP FAD Issues (DC Failure, Scenario Control, etc)
07/19/2019
DR-EP-2019-NRC-MCR-FAILED-DCS
07/31/2019
DR-EP-2019-NRC-TSC-FAILED-DCS
07/31/2019
DR-EP-2019-NRC-OSC-FAILED-DCS
07/31/2019
Dresden EP OYE Sim Unsat DCs, Sat with Comments, &
Comments
10/05/2020
Dresden EP OYE TSC DCs Sat with Comments and Other
Comments
10/05/2020
Corrective Action
Documents
Objective Failure D.1 During Full PI Drill
10/08/2020
Drill Critique Reports
07/01/2019 -
07/01/2021
Radiological Emergency Plan Annex for Dresden Station
Addendum 3
Emergency Action Levels for Dresden Station
Emergency Classification and Protective Action
Recommendations
Control Room Operations
TSC Activation and Operation
Operations Support Center Activation and Operation
Emergency Operations Facility Activation and Operation
EP-AA-113-F-19
Dresden Assembly, Accountability and Evacuation
Guidelines
D
Miscellaneous
NOTIFICATIONS
Miscellaneous
Dresden NRC Graded Exercise 60-Day NRC Submittal
NRC Performance Indicator Data, Emergency Preparedness
- Alert and Notification System Reliability
01/01/2020 -
03/31/2021
NRC Performance Indicator Data, Emergency Preparedness
- Drill/Exercise Performance
01/01/2020 -
03/31/2021
71151
Miscellaneous
NRC Performance Indicator Data, Emergency Preparedness
- ERO Drill Participation
01/01/2020 -
03/31/2021