IR 05000237/2022011

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000237/2022011 and 05000249/2022011
ML22101A240
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 04/12/2022
From: Karla Stoedter
NRC/RGN-III/DRS/EB2
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2022011
Download: ML22101A240 (10)


Text

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000237/2022011 AND 05000249/2022011

Dear Mr. Rhoades:

On April 1, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Dresden Nuclear Power Station, Units 2 and 3 and discussed the results of this inspection with Mr. P. Boyle, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Karla K. Stoedter, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 05000237 and 05000249 License Nos. DPR-19 and DPR-25

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000237 and 05000249

License Numbers:

DPR-19 and DPR-25

Report Numbers:

05000237/2022011 and 05000249/2022011

Enterprise Identifier:

I-2022-011-0037

Licensee:

Constellation Energy Generation, LLC

Facility:

Dresden Nuclear Power Station, Units 2 and 3

Location:

Morris, IL

Inspection Dates:

March 14, 2022 to April 01, 2022

Inspectors:

J. Benjamin, Senior Reactor Inspector

B. Jose, Senior Reactor Inspector

A. Shaikh, Senior Reactor Inspector

Approved By:

Karla K. Stoedter, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Dresden Nuclear Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

The inspectors reviewed the valves listed below to determine the following:

a.

Whether the sampled power-operated valves (POVs) are being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases.

b.

Whether the sampled POVs are capable of performing their design-basis functions.

c.

Whether testing of the sampled POVs is adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions.

d.

Material condition of the valve including a review of maintenance activities and a walkdown of the valve (if accessible).

(1) Air Operated Valve (AOV) 3-1601-60: Unit 3 Torus Vent Valve
(2) Squib 3-1106 A: Unit 3 Standby Liquid Control System Squib Valve
(3) Motor Operated Valve (MOV) 3-1501-10: Unit 3 High Pressure Coolant Injection (HPCI) System Test Return to Condensate Storage Tank
(4) MOV 2-1501-38A: Unit 2 Low Pressure Coolant Injection Test Injection Isolation Valve
(5) MOV 2-2301-3: Unit 2 HPCI Turbine Steam Supply Valve
(6) AOV 2-1599-61: Unit 2 Torus to Hotwell Containment Isolation Valve
(7) MOV 2-1201-1: Unit 2 Reactor Water Clean-Up System Inlet Isolation Valve
(8) Main Steam Isolation Valve 2-0302-1D: Unit 2 Inboard Main Steam Isolation Valve
(9) MOV 2-1301-3: Unit 2 Isolation Condenser Isolation Valve
(10) AOV 2-0302-158B: Unit 2 Scram Discharge Volume Drain Valve
(11) AOV-3 1601-23: Unit 3 Drywell Vent Valve

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On April 1, 2022, the inspectors presented the design basis assurance inspection (programs) inspection results to Mr. P. Boyle, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-1301-3

Midacalc Results DRE-2-1301-3

2-1501-38A

MIDACALC Results MOV 2-1501-38A

AOV-MEDP-

DRE-02-001

Inboard Main Steam Isolation Valve

DRE 02-0038

MOV Alternating Current (AC) Motor Terminal Voltage

Calculation

DRE 03-0015

HPCI MOV Design Basis Document and Differential

Pressure Calculation

0A

DRE 03-0100

Reactor Water Cleanup System Combined DBD and DP

Calculation

000

DRE 16-0040

Seismic Qualification of AVCO Air Pilot Valves

DRE-15-0046

Hardened Containment Vent System (HCVS) Vent Line

Sizing, Unit 3

DRE-3-2301-10

MIDACALC Results, DC MOV Generic Letter (GL) 96-05

Globe Valve 3-2301-10

DRE00-0061

Main Steam Isolation Valves Capability Margin Calculation

0A

DRE01-0066

Dresden Units 2 and 3 Standby Liquid Control (SLC)

Discharge Piping Pressure Drop

DRE03-0013

LPCI Differential Pressure (DP) Calculation

DRE98-0031

Unit 2 Reactor Building Motor Control Centers (MCCs),

Thermal Overload (TOL) Heater Sizing

Calculations

Pratt Order # DD-

664 (Pratty

Original Order #

N-3410-2)

18" 2FII Dimensional Data for Commonwealth Edison

Dresden Plant PO 00013597

07/18/2000

AR 03988159

2-2301-3 Unit 2 HPCI Turbine Steam Supply MOV Did Not

Open

03/22/2017

AR 03991760

2-2301-3 Weak Link Calculation Revision Required for

Disc and Stem

03/30/2017

AR 04074741

2-2301-3 Failed to Close During DIS 2300-05

11/14/2017

AR 04191433

3-1601-60 Failed Pressure Decay Test in DOS1600-28

11/04/2018

71111.21N.02

Corrective Action

Documents

AR 04193082

3-1601-60-SV, Unit 3 Instrument Air Supply Solenoid

11/08/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Valve Leak

2E-2441

Schematic Diagram Low Pressure Coolant Injection

(LPCI) / Containment Cooling System MOVs 2-1501-18A,

18B, 38A and 38B

AG

2E-3512

Schematic Diagram, Primary Containment Isolation

System (PCIS) Drywell and Torus Vent and Purge

Isolation Control

X

2E-3512A

Schematic Diagram Atmospheric Control Inboard and

Outboard Valves

E

2E-3529

Schematic Diagram HPCI Steam Main Pumps and

Condensate Valves

AL

2553-2

" Gate Valve Actuator Operated

09/15/2006

706-4069-007

Assembly (MT1) 3A Line 8.00 Bore (G) 1.38 Rod Dia. NC

2/20/2011

B-397

Checkered Steel Floor Plate Details

06/30/1967

CBO7805

Sub-Assembly of Anti-Rotation Pilot Valve for List 653

MSIV Assembly

01/06/2017

H-29529

900 LB 18-8 MO Stainless Steel Gate Valves Sheet 1

A

M-12

Diagram of Main Steam Piping

F

M-28

Diagram of Isolation Condenser Piping

LR

M-34 Sheet 1

Diagram of Control Rod Drive Hydraulic Piping

AN

M-34 Sheet 2

Diagram of Control Rod Drive Hydraulic Piping

Z

M-356

Diagram of Pressure Suppression Piping

CZ

M-356

Diagram of Pressure Suppression Piping

CZ

Drawings

M-374

Diagram of High Pressure Coolant Injection (HPCI) Piping

CY

Engineering

Changes

401069

Hardened Containment Vent System Modification as

Required by NRC Order EA-13-109

IST-DRE-BDOC-

V-18

Inservice Test (IST) Basis Document, Valve 2-1501-38A

03/01/2019

IST-DRE-BDOC-

V-21

IST Basis Document for Valve 3-1601-60

Engineering

Evaluations

IST-DRE-BDOC-

V-31

IST Basis Document Valve 3-1106A

03/01/2019

MPR-2524-A

Joint Owners Group Programs Summary Report

Miscellaneous

OTC-371

Vendor Thrust Analysis, Required and Maximum for

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Valves 1501-38A and B

DOP 1100-02

Injection of SLC

DOP 1300-01

Standby Operation of the Isolation Condenser

DOP 1300-02

Automatic Operation of the Isolation Condenser

DOP 1300-03

Manual Operation of the Isolation Condenser

DOP 1600-01

Normal Pressure Control of the Drywell or Torus

DOP 1600-03

Unit 2 Quarterly Valve Timing

DOS 0040-07

Verification of Remote Position Indication for Valves

DOS 0040-07

Verification of Remote Position Indication for Valves

DOS 0250-02

Full Closure Timing and Exercising of Main Steam

Isolation Valves

DOS 1100-03

SLC Injection Test

DOS 12600-18

Cold Shutdown Valve Testing

DOS 1600-03

Unit 2 Quarterly Valve Timing

DOS 1600-18

Main Steam Isolation Valve-Safe Closure Test

DOS 2300-01

HPCI Valve Operability and Timing

DOS 7000-01

Local Leak Rate Testing of Main Steam Isolation Valves

DOS-1600-28

Air Operated Valve Fail Safe and Accumulator Integrity

Test

DOS-2300-01

High Pressure Coolant Injection Valve Operability and

Timing

ER-AA-116

Motor Operated Valve Program

ER-AA-302

Motor Operated Valve Program Engineering Procedure

ER-AA-302-1001

MOV Rising Stem Motor Operated Valve Thrust and

Torque Sizing and Setup

ER-AA-302-1009

Final Joint Owners Group MOV Periodic Verification

Program Implementation

ER-AA-410

Air Operated Valve Program Implementing Procedure

ER-AA-410-1000

Air Operated Valve Cattegorization

ER-AA-410-1002

Air Operated Valve Testing Requirements

Procedures

MA-AA-743-310

Diagnostic Testing and Evaluation of Air Operated Valves

Work Orders

00339085

Dresden 2, 10 Year MOV Diagnostic and Limitorque

Surveillance 2-1501-38A

01/06/2011

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

00597794

4th Refuel Replace Actuator on Valve 3-1601-60

09/06/2006

00692782

Year Preventive Maintenance (PM) Lube/Inspection

Limitorque Valve Actuator 3-2301-10

06/16/2016

00743475

Year Standby Liquid Squib Valve A, Replace

Connector

2/12/2007

00769761

Year Motor Operated Valve (MOV) Diagnostic and

Limitorque Surveillance 3-2301-10

03/18/2018

00976072

Dresden 3, 48 Month Standby Liquid Control System

Manually Initiate to Inject Demineralized Water

11/17/2010

01312947

In-Body Seat Found Damaged During Inspection

10/29/2015

01422808

Year Valve Lube Stem Threads Only 3-2301-10

03/20/2016

01803711

Technical Specifications Local Leak Rate Test Valve

3-1601-60

2/09/2016

04710348

Reactor Water Cleanup System MOV Operability and IST

Timing

11/15/2019

04849925

3-1601-60 Failed Pressure Decay Test in DOS 1600-28

11/16/2018

04877777

Month Air Operated Valve(AOV) Accumulator Integrity

Test 3-1601-60

11/02/2020

04981359

Cold Shutdown Valve Testing Surveillance

05/13/2021

05131603

TS Unit 3 Quarterly Valve Stroke Timing 1601-60

06/04/2021

05135479

AOV 1599-61 QTR TS Valve Timing (IST)

06/12/2021

05161497

AOV 1599-61 QTR TS Valve Timing (IST)

09/24/2021