IR 05000237/2021010
| ML21054A248 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 02/23/2021 |
| From: | Karla Stoedter Division of Reactor Safety III |
| To: | Rhoades D Exelon Generation Co, Exelon Nuclear |
| References | |
| IR 2021010 | |
| Download: ML21054A248 (24) | |
Text
February 23, 2021
SUBJECT:
DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000237/2021010 AND 05000249/2021010
Dear Mr. Rhoades:
On January 29, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Dresden Nuclear Power Station, Units 2 and 3 and discussed the results of this inspection with Mr. P. Karaba, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Dresden Nuclear Power Station, Units 2 and 3.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Dresden Nuclear Power Station, Units 2 and 3. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Karla K. Stoedter, Chief Engineering Branch 2 Division of Reactor Safety
Docket Nos. 05000237 and 05000249 License Nos. DPR-19 and DPR-25
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000237 and 05000249
License Numbers:
Report Numbers:
05000237/2021010 and 05000249/2021010
Enterprise Identifier: I-2021-010-0018
Licensee:
Exelon Generation Company, LLC
Facility:
Dresden Nuclear Power Station, Units 2 and 3
Location:
Morris, IL
Inspection Dates:
January 11, 2021 to January 29, 2021
Inspectors:
K. Barclay, Reactor Inspector
J. Benjamin, Senior Reactor Inspector
J. Corujo-Sandin, Senior Reactor Inspector
B. Daley, Senior Reactor Inspector
M. Holmberg, Senior Reactor Inspector
J. Park, Reactor Inspector
Approved By:
Karla K. Stoedter, Chief
Engineering Branch 2
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Dresden Nuclear Power Station, Units 2 and 3, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Missing or Inadequate Battery Surveillance Acceptance Criteria Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000237,05000249/2021010-01 Open/Closed
[P.2] -
Evaluation 71111.21M The inspectors identified a Green finding and associated Non-Cited Violation (NCV) of 10 CFR 50, Appendix B, Criterion XI, Test Control, when the licensee failed to establish acceptance criteria or account for instrument uncertainty in surveillance procedures for battery electrolyte temperature.
Additional Tracking Items
Type Issue Number Title Report Section Status URI 05000237,05000249/
2021010-02 Potential Non-Conservative DC Short-Circuit Current Values 71111.21M Open
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease (COVID-19), regional inspectors were directed to begin telework. During this time regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. In some cases, portions of an IP were completed remotely and on-site. The inspection documented below was determined that the objectives and requirements stated in the IP could be completed remotely.
REACTOR SAFETY
===71111.21M - Design Bases Assurance Inspection (Teams)
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02)
=
For each component sample, the inspectors reviewed the licensing bases including:
- (1) the Updated Final Safety Analysis Report (UFSAR);
- (2) the Technical Specification (TS);and
- (3) the Technical Requirements Manual (TRM). The inspectors reviewed a sample of operating procedures (including normal, abnormal and accident procedures) as well as the overall system/component health (including condition reports and operability evaluations, if any). The inspectors performed visual inspections of the accessible components to identify potential hazards and/or signs of degradation. Additional component specific attributes inspected are listed below.
- (1) Unit 3: 125VDC Battery (3-83125-3AH4-F1 & 3-83125-3AH4-F2)
1. Maintenance effectiveness
2. Modifications
3. Translation of vendor specifications
4. Environmental qualification
5. Mechanical design:
a. Flood protection b. Seismic c. High energy line break d. Room heat up e. Room ventilation
6. Test/inspection procedures, acceptance criteria, and recent results:
a. Performance testing b. TS surveillance c. Discharge testing d. Terminal corrosion resistance
7. Electrical design:
a. Battery sizing b. Duty cycle c. Float and equalizing voltages d. Battery loading e. Short circuit calculation f. Breakers g. Maximum allowed room temperature during normal and accident operations h. Voltage drop calculation i.
Minimum voltage j.
Hydrogen concentration calculation k. Battery life l.
Battery charger sizing m. Cable ampacity n. Ground protection o. Protective relays/breakers
- (2) Unit 3: 125VDC Distribution Panel (3A-1)
1. Mechanical design:
a. Flood protection b. Seismic c. Room heat up d. Room ventilation
2. Electrical design:
a. Short circuit calculation b. Breaker ratings c. Minimum voltage at downstream panels d. Voltage drop calculation e. Coordination calculations
3. Ground detection
4. Surveillance procedures
- (3) Unit 2: Isolation Condenser Outboard Condensate Return Valve (MOV 2-1301-3)
1. Environmental qualification
2. Protection against seismic events
3. Mechanical design:
a. Weak link analysis b. Required thrust and torque c. Pressure locking and/or thermal binding d. Maximum allowed leakage e. Maximum differential pressure
4. Test/ inspection procedures, acceptance criteria, and recent results:
a. Leakage b. In service testing c. TS required surveillance d. Leak rate testing e. Actuation test
5. Motor:
a. Voltage drop b. Control logic c. Thermal overload
- (4) Unit 2: Turbine Building Closed Cooling Water Heat Exchanger (2A)
1. Maintenance effectiveness (e.g., maintenance rule and procedures)
2. Design calculations and considerations:
a. Tube plugging limit b. Heat transfer capacity
3. Test/inspection procedures, acceptance criteria, and recent results:
a. Flowrates b. Inspection or thermal performance test
Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02) (1 Sample)
- (1) Unit 2: Isolation Condenser (2-1302)
1. As built heat exchanger for conformance with design specifications and
construction code requirements
2. Modifications
3. Protection against seismic events
4. Design calculations and considerations:
a. Shell make-up capability b. Heat transfer capacity
5. Test/inspection procedures, acceptance criteria, and recent results:
a. Inspection and thermal performance tests b. Eddy current examination of internal tube bundles
6. Impacts of thermal transients (peak stress and fatigue) during shell refill on
heat exchanger tube bundles
7. Chemistry samples - for leak detection
Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)
- (1) Engineering Change (EC) 20170124: Replace Speed Board and Install Magnetic Pickup Sensor for Emergency Diesel Generator (EDG) Unit 2
- (2) EC 405079: EPN 2/3-5203, EDG Fuel Oil Transfer Pump Motor - Determine Impact of Replacement Motor on Protective Devices/Calculations/UFSAR
- (3) EC 405449: Reconfigure the 2/3 EDG Heating, Ventilation and Air Conditioning Dampers and Related Items to Fail Open on a Loss of Instrument Air
- (4) EC 628890: Installation of Reactor Feed Pump Suction Strainers
- (5) EC 399980: Replace/Modify Angled Main Steam Isolation Valve Disc with Spherical Edges to Reduce Seat Leakage
Review of Operating Experience Issues (IP Section 02.06) (2 Samples)
- (1) Bulletin 1976-01: Boiling Water Reactor Isolation Condenser Tube Failure
- (2) Information Notice 2017-06: Battery and Battery Charger Short-Circuit Current Contributions to a Fault on the Direct Current Distribution System
INSPECTION RESULTS
Missing or Inadequate Battery Surveillance Acceptance Criteria Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000237,05000249/2021010-01 Open/Closed
[P.2] -
Evaluation 71111.21M The inspectors identified a Green finding and associated Non-Cited Violation (NCV) of 10 CFR 50, Appendix B, Criterion XI, Test Control, when the licensee failed to establish acceptance criteria or account for instrument uncertainty in surveillance procedures for battery electrolyte temperature.
Description:
The inspectors identified deficiencies with the testing procedures for the safety-related 125 VDC and 250 VDC station batteries. Specifically, the inspectors found examples were the licensee failed to:
- (1) establish acceptance criteria;
- (2) account for instrument uncertainties; and/or
- (3) account for errors when using indirect measurement methodologies in the procedures used to measure battery electrolyte temperature.
In accordance with Title 10 CFR Part 50, Appendix B, Criterion XI, Test Control, tests performed on safety-related components must incorporate the requirements and acceptance limits contained in applicable design documents. For the 125 VDC batteries, the applicable design document was calculation DRE18-0009, "Dresden Units 2 and 3, 125 VDC System
Analysis.
" This calculation establishes that 65 degrees Fahrenheit (degrees F) was used as the minimum electrolyte temperature when developing the battery sizing calculation.
Additionally, UFSAR Section 8.3.2.1.1 for the 250 VDC system and Section 8.3.2.2.1 for the 125 VDC system describe the minimum electrolyte temperature used for battery sizing as 65 degrees F.
To ensure continued compliance with design documents and regulatory requirements, the licensee periodically measured the battery electrolyte temperature using direct or indirect methods. When using an instrument to directly or indirectly measure a value, the measured value will always have an amount of uncertainty. These uncertainties need to be accounted for in an analysis or within the acceptance criteria to ensure the associated structure, system or component (SSC) remains within licensing and design bases values (i.e. greater than or equal to 65 degrees F). The licensee measured distinct battery parameters, including electrolyte temperatures, for the 125 VDC and 250 VDC station batteries on a monthly, quarterly and annual periodicity. For each of these frequencies the licensee developed and implemented specific surveillance procedures.
Monthly (every 31 days): Technical Specifications Surveillance Requirement (TSSR) 3.8.6.4 required the licensee to verify each battery pilot cell temperature is greater than or equal to minimum established design limits. The TS bases for TSSR 3.8.6.4 prescribes the minimum established design limit as 65 degrees F.
The licensee implemented procedure DOS 8300-16, "U2
- (3) Monthly Station Battery Inspection," to satisfy the monthly surveillance requirement. The inspectors found that instead of measuring battery electrolyte temperature directly to meet TSSR 3.8.6.4, the licensee measured battery room ambient temperature and verified the room temperature was greater than or equal to 65 degrees F. The licensee had not accounted for any potential instrument uncertainty or indirect measurement effects when establishing the acceptance criteria. The inspectors reviewed a sampling of quarterly and annual battery inspection procedures which required both battery electrolyte and room temperatures to be measured and found instances where the average temperature of the battery was below the measured room temperature. In one instance, the average battery temperature was 1.3 degrees F below the room temperature with one of the individual battery cells being 2.9 degrees F below the room temperature. Additionally, the inspectors reviewed the measuring and test equipment (M&TE) calibration certificate for the instrument used to measured room temperature and found the acceptance tolerance was +/- 0.54 degrees F.
Quarterly (every 92 days): Technical Requirements Manual, Section 3.8.b, "Battery Monitoring and Maintenance," specifically Surveillance Requirement TSR 3.8.b.3, directs the licensee to verify the average electrolyte temperature of representative cells is greater than 65 degrees F.
The licensee used procedure DOS 8300-17, "U2
- (3) Quarterly Station Battery Inspection," to meet this requirement. When successfully completed, this procedure was also credited as satisfying the monthly test required by TSSR 3.8.6.4. The inspectors found the licensee measured the electrolyte temperature directly for the pilot cell and six other representative battery cells during the performance of DOS 8300-17. However, this procedure failed to have explicit acceptance criteria to confirm the battery temperature remained within design limits.
Annually: IEEE Standard 450-1995, Section 4.3.3, "Yearly," directs the licensee check the specific gravity of each cell.
The licensee utilized procedure DES 8300-49, "Yearly Unit 2
- (3) Safety Related 125V and 250V Station Battery Inspection," to meet the IEEE Standard. When successfully completed, the results from this procedure were also used to satisfy the quarterly (TSR 3.8.b.3) and monthly (TSSR 3.8.6.4) surveillance requirements. The inspectors reviewed procedure DES 8300-49 and found the licensee had failed to establish acceptance criteria to confirm acceptable results for the specific pilot cell electrolyte temperature (TSSR 3.8.6.4) and account for instrument uncertainty in the acceptance criteria for verifying the average electrolyte temperature of representative cells (TSR 3.8.b.3). The inspectors reviewed the M&TE calibration certificate for the instrument that measured battery electrolyte temperature found that the acceptance tolerance was +/- 0.9 degrees F.
Since the available acceptance criteria in procedure DOS 8300-16 was equal to the design acceptance limits, the inspectors concluded the instrument uncertainties were not accounted in the surveillance procedures. No evidence was provided to the inspectors to demonstrate these uncertainties had been accounted for elsewhere. The licensee was also unable to provide information explaining why procedures DOS 8300-17 and DES 8300-49 failed to contain acceptance criteria. As a result, the inspectors were concerned the lack of acceptance criteria and the failure to account for uncertainties could result in a situation where a surveillance test was declared satisfactory when in reality the battery electrolyte temperature was below the minimum established design limit of 65 degree F assumed in the UFSAR, design calculations, TS Bases and the TRM. Battery temperatures below the minimum design limit would result in a failed TS surveillance, require the licensee to enter the associated LCO action statement, and the need to restore battery pilot cell temperature to greater than or equal to the minimum established design limit within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. If battery temperature is not able to be restored within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, the licensee must declare the battery inoperable. The inspectors reviewed past surveillance test results and did not identify any instances where the battery should have been declared inoperable.
Corrective Actions: The licensee verified that previous surveillance test results were acceptable and the batteries remained operable. The licensee also created an assignment to evaluate the implementing procedures for TSSR 3.8.6.4 and TSR 3.8.b to ensure uncertainty from instruments and indirect measurements are considered when establishing acceptance criteria.
Corrective Action References:
AR 4398651: 2021 NRC DBAI Questions for DOS 8300-16
AR 4398689: NRC DBAI 2021 - Inadequate 50.59 for DOS 8300-16 Rev 16
Performance Assessment:
Performance Deficiency: The licensees monthly, quarterly, and annual battery surveillance procedures had missing or inadequate acceptance criteria for the performance of TSSR 3.8.6.4 and TSR 3.8.b.3. Specifically, the acceptance criteria were either missing or failed to account for instrument uncertainty and/or indirect measurement effects. This was contrary to Title 10 CFR Part 50, Appendix B, Criterion XI, Test Control, and was a performance deficiency.
Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, failing to have acceptance criteria or implementing acceptance criteria without accounting for instrument uncertainty and indirect measurement effects would have the potential to result in a satisfactory test result, when in actuality the SSCs had failed the surveillance test. Since the acceptance criteria values used in one of the procedures were the same as those used in Technical Specifications, the Technical Requirements Manual, and the associated analysis used to establish the minimum design limit, this could have resulted in:
- (1) the licensee failing to enter the required TS Limiting Condition of Operation (LCO) action;
- (2) failing to declare the associated equipment inoperable;
- (3) failing to enter the TRM action; and/or
- (3) potentially place the plant in an unanalyzed configuration. This issue is similar to the guidance provided in IMC 0612, Appendix E, Example 3.g.
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors screened the issue against the Mitigating Systems Cornerstone questions and determined that the finding was of very low safety significance (Green) because it was not a design or qualification issue, did not represent a loss of probabilistic risk assessment function, and was not associated with an SSC specifically designed to mitigate an external event. The inspectors did not identify an example where the deficient procedures resulted in an actual failed surveillance test.
Cross-Cutting Aspect: P.2 - Evaluation: The organization thoroughly evaluates issues to ensure that resolutions address causes and extent of conditions commensurate with their safety significance. Specifically, the NRC identified a similar NCV in the first quarter of 2020, and the licensees extent of condition failed to identify these additional battery surveillance examples. The previous NCV also involved instrument uncertainty and was documented in NRC Inspection Report 05000237/2020001 (ADAMS Accession Number ML20133J811).
Enforcement:
Violation: Title 10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires, in part, that a test program shall be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents.
Calculation DR18-0009, revision 0, "Dresden Units 2 and 3, 125 VDC System Analysis,"
serves as the applicable design document and establishes that 65 degrees F was the minimum temperature assumed in the battery sizing calculation.
For the safety-related 125 VDC and 250 VDC station batteries: Procedure DOS 8300-16, "U2
- (3) Monthly Station Battery Inspection," revision 22, is the implementing procedure to comply with applicable design documents and TSSR 3.8.6.4. Data Sheet 1, "Monthly Battery Surveillance Data Sheet," contains acceptance criteria that ambient room temperature must be greater than or equal to 65 degrees F when battery charging current is less than or equal to 2 amperes when on a float charge. The licensee credits complying with the ambient room temperature acceptance criteria for verifying that each battery pilot cell electrolyte temperature is greater than or equal to minimum established design limits (i.e. 65 degrees F).
Procedure DOS 8300-17, "U2
- (3) Quarterly Station Battery Inspection," revision 22, is the implementing procedure to comply with applicable design documents, TSSR 3.8.6.4. and TSR 3.8.b.3. Section A, "Purpose", states in part, "this procedure contains actions to satisfy weekly AND monthly surveillance criteria." Data Sheet 2, "U2(3) 125 VDC Battery Cell Voltage, Level, and Specific Gravity Datasheet," measures the electrolyte temperature for the pilot cell and six other representative battery cells. Data Sheet 3, "U2(3) 125 VDC Battery Average Determination Datasheet," calculates the average electrolyte temperature of the pilot and representative cells.
Procedure DES 8300-49, "Yearly Unit 2
- (3) Safety Related 125V and 250V Station Battery Inspection," revision 12, is the implementing procedure to comply with applicable design documents, TSSR 3.8.6.4. and TSR 3.8.b.3. Section A, "Purpose," states in part, "this procedure contains actions to satisfy weekly, monthly and quarterly surveillance criteria."
Data Sheet 1, "U2(3) 125 VDC Battery Yearly Surveillance," records all battery cell temperatures and calculates the average electrolyte temperature. Additionally, Step I.25 (e)states, "(AC) Verify Average Cell Temp is greater than 65 degrees F (TSR 3.8.b.3)."
Contrary to the above, as of January 29, 2021, the licensee failed to assure that the testing required to demonstrate that the 125 VDC and 250 VDC batteries would perform satisfactorily in service was identified and performed in accordance with written test procedures which incorporated the requirements and acceptance limits contained in applicable design documents, as evidenced by the following examples:
1) Specifically, for procedure DOS 8300-16, revision 22, the licensee failed to account for instrument uncertainties and the effects of indirect measurements (i.e. room temperature instead of the pilot cell temperature) when establishing the acceptance criteria to ensure successful completion of these tests would ensure the associated batteries would remain operable and within the acceptance limits as determined by applicable design documents and TSSR 3.8.6.4.
2) Specifically, for procedure DOS 8300-17, revision 22, the licensee failed to establish testing acceptance criteria to ensure the batteries would remain operable and within the acceptable limits contained in applicable design documents, TSSR 3.8.6.4. and TSR 3.8.b.3.
3) Specifically, for procedure DES 8300-49, revision 12, the licensee failed to establish acceptance criteria to confirm acceptable results for the specific pilot cell electrolyte temperature, as required by TSSR 3.8.6.4; and failed to account for instrument uncertainties when verifying the average electrolyte temperature of representative cells was greater than 65 degrees F, as directed by TSR 3.8.b.3.
Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
Unresolved Item (Open)
Potential Non-Conservative DC Short-Circuit Current Values URI 05000237,05000249/2021010-02 71111.21M
Description:
During the inspectors review of calculation DRE18-0009, "Dresden Units 2 and 3, 125 VDC System Analysis," the inspectors noticed the licensee used 125 percent of the full load rating for the battery charger current contribution to the short circuit calculations. The inspectors were concerned that using 125 percent of the battery charger full load rating may be non-conservative based on NRC Information Notice (IN) 2017-06, "Battery and Battery Charger Short-Circuit Current Contributions to a Fault on the Direct Current Distribution System." Specifically, the Dresden 125 VDC battery chargers were silicon-controlled rectifier (SCR) type battery chargers and the testing described in the IN demonstrated SCR-type battery chargers produced significantly higher currents than expected. NRC IN 2017-06, stated, The testing validated that the initial fault current contribution to a downstream fault from a battery charger (specifically the SCR-type chargers vs. the CF-type) is much higher in the range of 7 to 10 times the battery charger full load ampere ratingduring the first 100 milliseconds than what is currently stated as 150 percent of battery charger full load rating in IEEE Standard 946-2004. The test results indicated that the initial short circuit contribution from the charger is not limited when connected in parallel with the battery.
The inspectors reviewed the licensees evaluation of NRC IN 2017-06 (OPXR ATI Assignment #: 4067133-02) and found the licensee did not discuss the vulnerability of SCR-type battery chargers producing higher currents or justify why the Dresden battery chargers were not susceptible to the higher current condition. The inspectors determined, based on a battery charger full load rating of 200 amperes, that the additional current contribution from a single battery charger could potentially range from 1150 to 1750 amperes.
Additionally, because the licensee parallels two battery chargers together when switching between battery chargers, the licensee models two battery chargers contributing to the total short circuit current, which could double the additional current contribution. The inspectors found that in one portion of the licensees 125 VDC distribution system the margin to exceeding the 10,000-ampere limiting fault rating of a circuit breaker may be as low as 298 amperes before any additional currents are considered. The inspectors also recognized that increasing the short-circuit current can affect the circuit breaker coordination studies and potentially change the conclusions of the licensees fire safe shutdown analyses.
Planned Closure Actions: The inspectors plan to review the licensees updated evaluation of NRC IN 2017-06, which is being tracked by AR 4398306, and determine if any performance deficiencies exist, whether the performance deficiencies are more than minor, and if a violation of NRC requirements occurred.
Licensee Actions: Based on inspectors' concerns the licensee entered the issue into their corrective action program to reopen the evaluation of NRC IN 2017-06. An action was assigned to the Engineering department to account for the potentially high fault current contribution to a downstream fault from a battery charger that is much higher-in the range of 7 to 10 times the charger full load ampere rating-during the first 100 milliseconds than what is currently stated as 150 percent in IEEE Std 946-2004. The Operations department evaluated the available information and determined the potentially affected batteries remain operable.
Corrective Action References:
AR 4398306: 2021 DBAI: OPEX IN 17-06 Evaluation Incomplete
AR 4056647: OPEX Review: IN 2017-06: Battery / Charger Short Circuits (Corporate AR)
AR 4399797: AR Generated to Determine Course of Action for 2021 DBAI: OPEX IN 17-06 Evaluation (Corporate AR)
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On January 29, 2021, the inspectors presented the design basis assurance inspection (teams) inspection results to Mr. P. Karaba, Site Vice President and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21M Calculations
004-E-032
Dresden Units 2 and 3 Thermal Overload Review
0101-0072-01
Dresden Isolation Condenser Heat Transfer Calculation
0591-156-SED-
2
ISCO Shell Side Pressure
2-016-DRN
Evaluation of Stroke Time and Actuator Capacity for DC
Motor-Operated Valves at Dresden Nuclear Station
1303-M-205/206,
Hanger
No. M-1163D-254
Pipe Support Qualification
5569-39-19-1
25 VDC Fault Currents
294-TB-05
25 VDC Battery Replacement, Trolley Beam & Rack
Design
29-TB-05
25 VDC Battery Rack Details, U-3
8188-109B-D2
Flued Head Anchor X-109B
8900-15-EO-S
Re-evaluate Anchorage Assemblies for the Isolation
Condenser
9389-68-19-1
Calculation for Voltage Adequacy of Swing Diesel Circuit
Breaker Closing Coils
9389-68-19-2
Calculation for Voltage Adequacy of Swing Diesel Circuit
Breaker Closing Coils
9389-68-19-3
Calculation for Control Voltage Adequacy of Unit 3 Diesel
Generator Circuit Breaker Closing Coils
9389-68-19-6
Calculation for Control Voltage of Unit 2 Diesel Generator
Circuit Breaker Closing Coils
9630-13-19-1
Voltage Adequacy at the Closing Coils of Ten Selected
Circuit Breakers
BSA-D-99-04
Reconstitution of Isolation Condenser Design Basis with
Respect to Decay Heat Loads and Long Term Make-up
Requirements
1b
CE-DR-003
Calculation for Allowable Limits for Stems and Discs for
Valves with Tag Nos. 2(3)-1301-3
D2-ISCO-01C
Reanalysis Per NRC Bulletin 79-14
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
D3-lSP-07
Isolation Condenser Steam Side Setpoint Flow Rates
DRE-2-1301-3
MIDACALC Results, DC Motor Operated GL96-05 Gate
Valve
DRE01-0045
Isolation Condenser Vent Piping Flow Capability
DRE02-0020
Isolation Condenser Heat Removal Capacity Test Validation
DRE03-0011
Isolation Condenser System Combined DBD and DP
Calculation
and 0A
DRE03-0025
Baseline Calculation for 125 VDC ELMS-DC Conversion to
DCSDM
2B, 3D and
4D
DRE05-0011
Hydraulic Model of Condensate, Condensate Booster, and
Feedwater Systems to Evaluate Impact of Increased
Condensate Filtration Flow
DRE18-0009
Dresden Units 2 and 3, 125 VDC System Analysis
DRE97-0005
Isolation Condenser Return Valve 2/3-1301-3 Cool Down
Rate
DRE99-0011
Isolation Condenser Make-up Pumps Hydraulic Performance 1
EMD-067683
Calculation for Isolation Condenser Vent Piping
KPA-SWC-67-
131
Stress Report Dresden Unit 2 and 3 Isolation Condenser
NED-M-MSD-72
The Seismic Thrust Limits of the Dresden Non-Mark I MOVs
SL-4500-3
Overcurrent Protective Device Overcurrent Study, 125 VDC
Systems
03/24/1989
VE-4
Dresden Unit 3 Battery Room Ventilation
07/08/1985
XCE091.0208
MOV Structural Integrity Calculation, Non-Mark I MOVs,
Dresden Units 2 & 3
Calibration
Records
0011216087
Anton Paar DMA 35 Density Meter
2/01/2020
0011267136
Anton Paar DMA 35 Density Meter
09/17/2020
0011284855
Fluke 54 II B Digital Thermometer
2/18/2020
Corrective Action
Documents
00693719
U2 IC West End Pass Plate is Bowed, with Sheared Bolts
11/02/2007
00798153
MOV 2-1301-3 Thermal Binding Review
07/18/2008
01337933
NRC Concern: 3B Standby Liquid Control Squib Valve
Temperature
03/07/2012
01685226-02
Evaluation to Determine the Tube Plugging Limit for TBCCW
Heat Exchangers
04/07/2017
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
2498753
U3 125 VDC Level III Ground
05/11/2015
04056647
OPEX Review: IN 2017-06: Battery / Charger Short Circuits
09/28/2017
04069471
MOV 2-1301-3 Stroke Length Found Shorter than
Acceptable
11/01/2017
04107306
Discrepancy Found in HPCI AOP Critical Parameters
2/23/2018
04141412
MOV 2-1301-3 As-Found Stroke Length High
05/25/2018
04144225
Isolation Condenser 2-1301-3 Valve Troubleshooting
06/04/2018
292887
D2R26 - Results of ISCO Shell Internals Inspection Results
10/30/2019
297715
U2 Isolation Condenser Tritium is Above Goal
11/15/2019
04310460
2B TBCCW HX Has Reached Tube Plugging Limit
01/15/2020
04354304
U2 ISO Condenser West End Bell Leak
07/02/2020
04357922
U2 ISO Cond Press Reading High on PI 2-1340-3
07/20/2020
Corrective Action
Documents
Resulting from
Inspection
04396236
21 DBAI - NRC Identified Discrepancy in Calc on ISCO
01/15/2021
04396770
21 DBAI - Incorrect Code Reference in Piping Analysis
01/19/2021
04397127
21 DBAI - Inapplicable Information in EQ Binder EQ-74D
01/21/2021
04397286
21 DBAI Non Conservative Calculation Fault 125 VDC
system
01/21/2021
04398108
IST 10-Year Plan Valve Test Table Not Updated
01/26/2021
04398306
21 DBAI: OPEX IN 17-06 Evaluation Incomplete
01/27/2021
04398651
21 NRC DBAI Questions for DOS 8300-16
01/28/2021
04398660
21 DBAI: UFSAR Section 8.3.2.2.1 Update
01/28/2021
04398682
21 DBAI: Calculation 004-E-032 Justification Needed
01/28/2021
04398689
NRC DBAI 2021 - Inadequate 50.59 for DOS 8300-16
Rev 16
01/28/2021
04399797
OPEX IN 17-06 Evaluation Review
2/02/2021
Drawings
Schematic Diagram Primary CNMT Isolation System
Isolation Condenser VLV - Outboard MOV 1301-3 Control
Key Diagram 4169 Switchgears 31, 32, 33, 34
S
Key Diagram Turbine Building 125 VDC Main Bus
Distribution Panels
Z
Schematic Diagram Turbine Building 125 VDC Main Bus 3 &
3A
S
Wiring Diagram Turbine Building 125V VDC Main Bus
M
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Distribution Panel
66-2-5636C1
Isolation Condenser
66-2-5636D1
Isolation Condenser - Shell Details
66-2-5637D1
Isolation Condenser - Tube Bundle Assembly
D-14297
Tee Strainer Assembly
ISI-201
Inservice Inspection Class II Isolation Condenser Piping
H
ISI-307
Inservice Inspection Class III Isolation Condenser and Vent
Piping
C
M-16
Diagram of Condensate Booster Piping
AQ
M-609C
Piping Plan Reactor Feed Pump Suction Line Condensate
Booster Piping
A
Engineering
Changes
0000358092
Unit 2 Isolation Condenser East End Tube Bundle Heat
Shield Installation - Gap Dimension
0000368127
U2 Isolation Condenser Water Box Repairs
0000399980
Replace/Modify Angled MSIV Disc with Spherical Edges to
Reduce Seat Leakage
0000405079
EPN 2/3 5203, EDG Fuel Oil Transfer Pump Motor.
Determine Impact of Replacement Motor on Protective
Devices/Calculations/UFSAR
0000405887
Replace Speed Board and Install Magnetic Pickup Sensor
for Emergency Diesel Generator (EDG) Unit 2
0, 1 and 2
0000620232
Load Profile for the Unit 3 125 VDC Main Battery Modified
Performance Test (DES 8300-19) Supersedes EC 401226
0000628890
Installation of a Reactor Feed Pump (RFP) Suction Strainer
2-3404-A, 2-3404-B, 2-3404-C
Engineering
Evaluations
0000363440
Isolation Condenser Tube Plugging Criteria
0000372073
Unit 2 Isolation Condenser Valve 2-1301-3 Opening Setting
Adjustment
0000372144
Preliminary Results of U2 ISCO Heat Capacity Test
09/13/2008
0000382128
Isolation Condenser Eddy Current Testing Tube Plugging
Criteria
0000399268
Preliminary Results of U2 ISCO Heat Capacity Test
09/13/2014
0000405702
Isolation Condenser Make-up Pump DOS 1300-05
Evaluation
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
0000617372
LLRT Scope Reduction
0000624559
MOV Program Risk Ranking and Scoping Document
(2018 PRA)
0000628678
Isolation Condenser Make-up Pump DOS 1300-05
Evaluation Dresden
0001493789
00001376-01, COM D2 3RFL, COM MOV Electrical Insp &
Diagnostic Test 2-1301-3, E: 2-1301-3, MOVA, L05
11/27/2017
EE-017002-15
GNB Battery Short Circuit Ratings: Justification for Short
Circuit Ratings
Pressure Locking and Thermal Binding Susceptibility
Evaluation for Dresden Station
Miscellaneous
50.59 Applicability Review and Coversheet for DTP 47,
Rev. 20
10/27/2017
Inservice Testing (IST) Program Plan
Isolation Condenser System Health Report
U2 Daily Operator Surveillance Log
01/25/2021
Report - Master Lee, Eddy Current Examination Final
Report - ISO Condenser EPN: 2-1302-West
11/2017
Report - Master Lee, Eddy Current Examination Final
Report - ISO Condenser EPN: 2-1302-East
11/2015
Form N-1 Manufacturers Data Report for Nuclear Vessels,
Heat Exchanger 66-2-5637
2/31/1967
Letter from Commonwealth Edison to USNRC, Dresden
Station Units 1, 2, and 3 Response to IE Bulleting No. 76-01
03/17/1976
Letter from Commonwealth Edison to USNRC, Dresden
Station Units 1, 2, and 3 Emergency/Isolation Condenser
Information (Record of Phone Call)
03/03/1976
Letter from Exelon to USNRC, Dresden Nuclear Power
Station Unit 2 Completion of Isolation Condenser Tube
Bundle Integrity Testing; Response to NRC IE Bulleting
76-01
03/05/1998
TBCCW System Health Report
AC/DC Distribution - Engage Health System Health Report
11/2020
Engage Health System Health Reports (DIS - AC/DC
NA
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Distribution)
04067133-02
Level 3 OPEX Evaluation: IN 2017-06
01/31/2018
2019-009-002
CFR 50.59 Evaluation - Installation of a Reactor Feed
Pump Suction Strainer 2-3404-A, 2-3404-B, 2-3404-C
2019-129
CFR 50.59 Screening-Installation of a Reactor Feed
Pump Suction Strainer 2-3404-A, 2-3404-B, 2-3404-C
205-92017
GE Specification - Instruction Book for Isolation Condenser
for Dresden
2/26/1968
2A TBCCW/EPN
2-3802-A
Eddy Current Examination Final Report
05/07/2017
2B TBCCW/EPN
2-3802-B
Eddy Current Examination Final Report
01/15/2020
CHRON# 188292
Test Report: GNB NCX-21 Series Cell Short Circuit Tests
05/06/1992
D03-8303A1-2-
P06
Screening Evaluation Work Sheet (SEWS) for 125 VDC / TB
Main Bus #3A-1
and 1
DR-MISC-14
Motor-Operated Valve Program Risk Ranking Input - PRA
Model Revision DR217B
DR-PSA-005.05
Electric Power (EP) System Notebook
DR-PSA-005.09
Instrument/Service and Pumpback Air (IA/SA/PBA) System
Notebook
DR-PSA-005.10
Isolation Condenser (IC) System Notebook
DR-PSA-005.20
Probabilistic Risk Assessment - Turbine Building Closed
Cooling Water (TBCCW) System Notebook
DRE-19-002
Surveillance Test Interval (STI) Evaluation Form - DOS
1300-01 Isolation Condenser Five Year Heat Removal
Capability Test
10/31/2019
DRE-2-1301-3
(DRE-2)
MIDACALC Results for 2-1301-3 DC Motor Operated
GL96-05 Gate Valve
EQ Binder
No. EQ-74D
Limitorque SMB Valve Actuators Located Outside Drywell
PNL-10719
Report - Pre-Phase 1 Aging Assessment of the BWR
Isolation Condenser System
08/1995
RRP 3-14-023
ASME Section XI Repair/Replacement Plan for WO 1617486-23
03/06/2014
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
RRP 3-16-024
ASME Section XI Repair/Replacement Plan for WO 1617486-28
05/02/2016
Section 35.40
Specifications Nuclear Class 1E Flooded Batteries NCN* -
03/2010
Section 93.10
GNB Flooded Classic Installation and Operation Manual
Section 4
08/2014
NDE Reports
Hydrostatic Test Certificate, ISLIP Flow Controls Inc,
Drawing D-14297
10/22/2019
Procedures
04932057
D3 QTR TSNC 125 VDC Sta Batt Surv
09/12/2019
CY-DR-120-160
Isolation Condenser
DAN 902(3) B-4
Isolation Condenser Valves Off Normal
DAN 902(3) H-2
Isolation Condenser Line Break (Group 5 Isolation)
DAN 902(3)-3 B-3 Isolation Condenser Vent Radiation High
DAN 902(3)-3
C-4
Isolation Condenser Temperature High
DAN 902(3)-3
D-4
Isolation Condenser Level Hi-Lo
DAN 902(3)-4
Isolation Condenser Channel A-B Initiation
DAN 902(3)-8
C-9
U2 125 VDC Battery Ground U3 125 VDC Battery Ground
DAN 902(3)-8
D-10
25 VDC Power Failure
DAN 923-1
U2 or U3 TBCCW Temp High
DAN 923-1 D-2
U2 or U3 TBCCW Press Low
DGA-12
DGA-13
Loss of 125 VDC Battery Chargers with Simultaneous Loss
of Auxiliary Electrical Power
DOA 0010-01
Dresden Lock and Dam Failure
DOA 1300-01
Isolation Condenser Tube Leak
DOA 3800-01
Loss of Turbine Building Closed Cooling Water
DOA 6900-03
Failure of Unit 3 125 VDC Power Supply
DOA 6900-03
Failure of Unit 3 125 VDC Power Supply
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
DOA 6900-T1
Unit 2 and Unit 3 125 VDC Battery System Detailed Load
List
DOA 6900-T2
Unit 2 and Unit 3 125 VDC Battery System
DOP 1300-01
Standby Operation of the Isolation Condenser System
DOP 1300-02
Automatic Operation of the Isolation Condenser
DOP 1300-03
Manual Operation of the Isolation Condenser
DOP 6900-02
25 VDC Electrical System
DOP 6900-07
25 VDC Ground Detection - Unit 3
DOP 8300-06
Unit 2 (3) Supplemental Battery Information
DOS 1300-01
Isolation Condenser Heat Removal Capacity Test
DOS 1300-05
Isolation Condenser Make-Up Pump Capacity Test
DOS 8300-16
Unit 2 (3) Monthly Station Battery Inspection
DOS 8300-17
Unit 2 (3) Quarterly Station Battery Inspection
DTP 09
Leak Detection and Reduction Program
ML-NDE-017
Eddy Current Examination of Non-Ferromagnetic Heat
Exchanger Tubing
Operator Response Time Program
OP-DR-102-106
Operator Response Time Program at Dresden
Operating Experience Program
Processing of Level 3 OPEX Evaluations
Self-Assessments 4385641
FASA: NRC DBAI Preparation
2/17/2020
SRPT 04323578-
Self-Assessment Report
Work Orders
00884517
D2 5RFL COM Isolation CDSR Insp/Eddy Current East
11/12/2015
01096660-24
D2 5RFL Com Isolation CDSR Insp/Eddy Current West
10/19/2017
01650222
D3 5Y TSNC 125 VDC STA Batt Modified Performance Test
04/28/2018
01703750-01
Isolation Condenser Heat Removal Test
09/13/2014
01705165-01
B Iso Condenser Make-Up Pump Capacity Test
04/07/2016
01712364-01
A Iso Condenser Make-up Pump Capacity Test
05/31/2016
01939575
Replace EDG Speed Board & Install Magnetic Pickup
Sensor U2
2/13/2016
04700713-01
D2 PRE/RFL Reg Iso Cond Leak Det & Reduction Program
10/28/2019
04716683-01
D2 QTR/CSD TS (IST) Cold Shutdown Valve Testing
11/12/2019
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Surveillance
04718571-01
D2 24M TS Isolation Condenser Auto-Actuation
11/13/2019
04753909-01
05/25/2018
04787291
D3 AN TSNC 125 VDC Main Station Batt Surv
03/14/2019
04899165
D3 QTR TSNC 125 VDC Sta Batt Surv
06/13/2019
04900547
D3 AN TSNC 125 VDC Main Station Batt Surv
03/05/2020
04945098-07
Installation of 2A Reactor Feed Pump (RFP) Suction Strainer 11/06/2019
04945098-08
Installation of 2A Reactor Feed Pump (RFP) Suction Strainer 11/03/2019
04945098-11
Installation of 2A Reactor Feed Pump (RFP) Suction Strainer 11/16/2019
04945098-15
Installation of 2A Reactor Feed Pump (RFP) Suction Strainer 11/07/2019
04945098-23
Installation of 2A Reactor Feed Pump (RFP) Suction Strainer 11/05/2019
05023261-01
Fatigue and Transient Monitoring Program
08/13/2020
05108899
D3 1M TSNC 125 VDC Station Battery Insp
01/20/2021
05113940
D3 WK TSNC 125 VDC Battery Surv
01/13/2021