ML20342A283

From kanterella
Jump to navigation Jump to search
NRC Inspection Report 05000237/2020090 and 05000249/2020090
ML20342A283
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 12/07/2020
From: David Curtis
NRC/RGN-III
To: Bryan Hanson
Exelon Generation Co
Shared Package
ML20353A400 List:
References
EA-20-053, EA-20-120 IR 2020090
Download: ML20342A283 (4)


See also: IR 05000237/2020090

Text

December 7, 2020

EA-20-053

EA-20-120

Mr. Bryan C. Hanson

Senior VP, Exelon Generation Co., LLC

President and CNO, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 - NRC INSPECTION

REPORT 05000237/2020090 AND 05000249/2020090

Dear Mr. Hanson:

This letter refers to the triennial heat sink inspection conducted from February 10, 2020, to

March 31, 2020, (Inspection Report Nos. 05000237/2020001 and 05000249/2020001) and from

April 1, 2020, to April 24, 2020, (Inspection Report Nos. 05000237/2020012 and

05000249/2020012) at Dresden Nuclear Power Station, Units 2 and 3. The purpose of the

inspection was to monitor licensee performance in accordance with the Reactor Oversight

Process. The results of this inspection were discussed with Mr. P. Karaba, Site Vice President

and other members of your staff on April 24, 2020. The inspection reports provided above can

be found in the NRCs Agencywide Document Access and Management System (ADAMS) at

Accession Nos. ML20133J811 and ML20140A181, respectively. ADAMS is accessible from the

NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

The NRC has determined the apparent violation described in Inspection Report 05000237/2020012; 05000249/2020012 (AV 05000237,05000249/2020012-012) is a Severity

Level IV violation of NRC requirements. The NRC concluded this violation was best

characterized as a Severity Level IV violation based upon example 6.1.d.2 of the Enforcement

Policy dated January 15, 2020, because the violation resulted in a condition which was

previously evaluated as having very low safety significance (i.e., Green) as discussed in the

subject inspection report. Because you initiated condition reports demonstrating objective

evidence of plans to restore compliance, the violation is being treated as a Non-Cited Violation

(NCV) consistent with Section 2.3.2 of the Enforcement Policy. The Enforcement Policy is

included on the NRCs Web site at (http://www.nrc.gov/about-

nrc/regulatory/enforcement/enforce-pol.html).

In the letter transmitting Inspection Report 2020012, we provided Exelon with the opportunity to

address the apparent violation identified in the report by either attending a pre-decisional

enforcement conference or by providing a written response before we made our final

enforcement decision. Although Exelon provided a response to the apparent violation in a letter

B. Hanson

2

dated July 2, 2020, "Response to Apparent Violation in NRC Inspection Report 05000237/2020012 and 05000249/2020012; EA-20-053," (ML20184A260) the NRC did not use

the information in the letter to make its final enforcement decision. As stated above, the NRC

made its final enforcement decision solely based upon example 6.1.d.2 of the Enforcement

Policy.

However, while reviewing the information submitted by Exelon, the NRC identified that

10 CFR 50.59 Evaluation 2020-02-001, Update to UFSAR Section 9.2.5.3.1, DOA 0010-01,

and DTS 4450-04, Revision 1, did not consider the plants original design and licensing basis: a

loss of the dam due to a seismic event coincident with a loss of offsite power (LOOP).

Region III inspectors reviewed the design and licensing basis of the facility and consulted with

the Division of Reactor Oversight in the Office of Nuclear Reactor Regulation to determine a

seismically induced dam failure coincident with a LOOP was originally part of the design and

licensing basis for Dresden Station. The NRC will follow up on this issue of concern using either

Inspection Procedure 92702, Follow-up on Traditional Enforcement Actions Including

Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, and Alternative

Dispute Resolution Confirmatory Orders, or another baseline inspection effort.

If you contest the violation or the severity of the violation documented in this inspection report,

you should provide a response within 30 days of the date of this inspection report, with the basis

for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,

Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director,

Office of Enforcement; and the NRC Resident Inspector at Dresden Nuclear Power Station,

Units 2 and 3.

This letter, its enclosure, and your response, if you choose to provide one, will be made

available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at

the NRC Public Document Room in accordance with Title 10 of the Code of Federal

Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding. To the extent

possible, your response should not include any personal privacy or proprietary information so

that it can be made available to the Public without redaction.

Sincerely,

David Curtis, Deputy Director

Division of Reactor Safety

Docket Nos. 05000237 and 05000249

License Nos. DPR-19 and DPR-25

Enclosure:

As stated

cc w/ encl: Distribution via LISTSERV

David Curtis

Digitally signed by David

Curtis

Date: 2020.12.07 14:11:07

-06'00'

ML20342A283

Package: ML20353A400

NCP-2020-010: ML20342A287

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

OFFICE RIII

RIII

RIII

RIII

NAME

LRodriguez:mb LR

Non-Concur

KStoedter via e-mail

JCameron via e-mail

DCurtis

DATE

11/4/2020

11/5/2020

11/5/2020

12/7/2020

Enclosure

DOCUMENTS REVIEWED

Type

Designation

Description or Title

Revision or

Date

Calculations

DRE16-0011

Required Ultimate Heat Sink (UHS) Capacity

1

Corrective Action

Documents

Resulting from

Inspection

AR 4343358

2020 UHS Inspection - 50.59 Apparent Violation

05/19/2020

Drawings

M-194

Outdoor Piping

U

Drawings

M-355

Diagram of Service Water Piping

SQ

Drawings

M-52

Circulating Water Piping Plan

K

Drawings

M-53

Circulating Water Piping Sections

K

Engineering

Changes

631940

Determination of the Volume of Water Contained in Piping

Between the Condenser and the Circ Pumps for a Loss of

Dam Event

0

Engineering

Changes

DFL 12-007

UFSAR Change 12-007

0

Engineering

Evaluations

2012-0067

UFSAR Changes Related to Loss of Dam

0

Engineering

Evaluations

2020-02-001

Update to UFSAR Section 9.2.5.3.1, DOA 0010-01, and DTS

4450-04

1

Miscellaneous

SVPLTR 20-0037

Response to Apparent Violation in NRC Inspection Report 05000237/2020012 and 05000249/2020012; EA-20-053

07/02/2020

Procedures

DGA-12

Loss of Offsite Power

80

Procedures

DOA 0010-01

Dresden Lock and Dam Failure

37

Procedures

DOP 1300-03

Manual Operation of the Isolation Condenser

38

Procedures

DTS 4450-04

Dresden Credited Ultimate Heat Sink Bathymetric

Surveillance for Intake and Discharge Canals

2